Professional Documents
Culture Documents
2 AssessmentReport7April2021
2 AssessmentReport7April2021
2 Project Description
The location of Makulapnit Mini Hydropower Project (MHP) is shown in Figure 1. The
project will be located approximately within 50 m downstream from the outlet of the
Makulapnit Reservoir, where it will utilize the stored water from the reservoir for
power generation.
The hydropower scheme has a conventional layout. It will exploit a gross head of 70
m by diverting the water from the Makulapnit Reservoir into a steel pipeline and
conveying that water to steel penstock and then to a powerhouse located
approximately 700 m downstream. The installed capacity of the project is 500 kW
and the estimated annual energy generation is about 2.10 GWh. The general layout
of the scheme is shown in Figure 2.
The main structures of the scheme are:
Concrete overflow weir, 5–m high by 37-m long, with 1.5 m by 1.5 m opening
sluiceway with wheeled vertical gate on its right;
Gated reinforced concrete side intake with 1 m by 1 m inlet opening
connected to the headrace steel pipe;
Steel pipe, approximately 700 – m long, with an inside diameter of 700 mm;
Surge tank, to absorb sudden rises of pressure, as well as to quickly provide
extra water during a brief drop in pressure;
Steel penstock, approximately 130 – m long, with an inside diameter of 700
mm, bifurcated to provide the needed discharges for the turbine units;
Surface powerhouse accommodating two (2) units of horizontal shaft Turgo
Turbines and its associated equipment;
Outdoor switchyard feeding into the 13.8 kV distribution lines; and
Access road, connecting the concrete overflow weir area to the existing road,
via the powerhouse area.
3 Hydrology
Rainfall
There are four recognized climate types i.e., I, II, III and IV in the country, and these
are based on the distribution of rainfall. Marinduque belongs to type III, having no
very pronounced maximum rain period with a dry season lasting only from one (1) to
three (3) months, either during the period from December to February or from March
to May.
Rainfall stations with available daily data are installed in many parts of the island and
being managed by the Advanced Science and Technology Institute (ASTI) under the
Department of Science and Technology (DOST). DOST-ASTI’s Philsensors website
can be easily accessed to secure daily rainfall data. Another rainfall station with
available monthly data is found. This station is located in Boac and the data can be
accessed thru the website of World Weather Information Service (WWIS) under the
World Meteorological Organization.
The rainfall data from WWIS was adopted in the estimate of inflows, since it has a
longer and complete monthly rainfall data, 2009 to 2020. Data secured from some of
the rainfall stations in Philsensors website were used for validation/checking.
Shown on Table 2 are the monthly rainfall data gathered from WWIS website. Figure
3 shows the average monthly rainfall data, which vary between 56 mm to 209 mm.
The recorded highest monthly rainfall was 440 mm and it was in the month of
December in 2010.
Estimated Inflows at the Proposed Dam Site
The monthly inflows at the proposed dam site were estimated using the formula
below:
Imo = Rmo x DAsite / (86.4 x Dmo)
Where:
Imo = Monthly inflow for a particular month, cms
Rmo = Monthly rainfall depth for a particular month, mm
DAsite = Drainage area at the proposed dam site, km2
Dmo = Number of days for that month
The flow duration curve of the estimated monthly inflows is shown in Figure 4.
Design Flood
The design flood (Peak Discharge) adopted has a return period of 100 years. This
was based from the previous studies conducted in 2017 for small hydro projects in
q = C x DA
Where:
q = Specific Discharge (m3/sec/km2)
C = Creager”s Constant, as tabulated below
DA = Drainage Area (km2)
Creager’s Constants
Region RETURN PERIOD
2-Year 5-Year 10-Year 25-Year 50-Year 100-Year
Luzon 15.66 17.48 18.91 21.51 23.83 25.37
Visayas 6.12 7.77 9.36 11.89 14.52 17.47
Mindanao 8.02 9.15 10.06 11.60 12.80 14.00
Peak discharges in m3/sec at various return periods were computed by multiplying
the specific discharge by the drainage area. Tabulated below is the result of the
computation:
RETURN PERIOD
2-Year 5-Year 10-Year 25-Year 50-Year 100-Year
Specific 11.88 13.26 14.35 16.32 18.08 19.25
Discharge,
m3/sec/km2
Peak Discharge, 140.54 156.87 169.70 193.03 213.85 227.67
m3/sec
Figure 5 shows the peak discharges at various return periods.
6 Economic Analysis
An essential element in evaluating the economic benefit of a project is the definition
of the alternative to the project, the “without project” scenario. The “without project”
scenario would be that no hydropower project. This means that the existing units of
Diesel Power Plant in Boac will continue to operate until its retirement.
For the case of “with project” scenario, our proposed mini hydro project will be
implemented. The total cost for construction and operation & maintenance of our
proposed mini hydro project should be proven lesser than the total cost for the
operation & maintenance (less salary and wages), fuel consumption and
replacement of the equivalent capacity of the Boac DPP.
Non-Traded Goods
Local Component
The annual operation & maintenance cost is estimated at PHP 3.64 million. This
includes the salary and wages for the three (3) operators, three (3) security guards
and one (1) janitor. Converted to economic values by deducting all the taxes, the
annual economic O&M amounts to PHP 3.38 million.
Replacement cost of PHP 15.75 mil for the electro-mechanical equipment with an
economic life of 12 years have been included in the economic analysis. The total
economic replacement value amounts to PHP 18.90 million.
Thermal Alternative
Normally, the economic benefit shall be the cost of installing and operating the
thermal alternative, happens to be the diesel power plant in our case. Since there is
enough capacity in the area, the economic benefit will be derived mostly from the
costs of operating and maintaining the Boac DPP. Economic benefit from installing a
new diesel power plant, with equivalent capacity, is scheduled on the latter part of
the economic life of our mini hydro project, where some of the existing units of the
Boac DPP are scheduled to be retired.
The difference of the net flow of the DPP and our Mini Hydro Project is the cost
savings and this will be the net benefit of our proposed project.
The DPP shall have an equivalent capacity of our MHP. Based on the on-going
project of NPC, the project cost of a DPP per kW is around PHP 77,020.00. The
economic value is PHP 67,777.60 per kW.
Cost-Benefit Analysis
The cost and benefit streams have been estimated for a 25-year period. The residual
value after 25 years was assumed to be zero. All costs used for the analysis are in
2021 values.
The result of the analysis shows that the proposed project is economically viable,
having an estimated economic Internal Rate of Return (IRR) of 13.33% which is
above the 10% hurdle rate as prescribed by the National Economic and
Development Authority (NEDA), economic Net Present Value (NPV) of PHP 24.22
million and a Benefit-Cost (B-C) ratio of 1.21.
Table 6 shows the cost and benefit streams.
Sensitivity Analysis
Economic sensitivity analysis was conducted using the NEDA-ICC prescribed
sensitivity runs i.e., 10% decrease in benefits, 10% increase in costs and 10%
decrease in benefits and 10% increase in costs. Result of the sensitivity runs is
presented below:
Cases NPV, mil PHP IRR, % B-C Ratio
Base case 24.22 13.33 1.21
10% decrease in 10.35 11.46 1.09
Benefits
10% increase in 15.55 11.98 1.12
Costs
10% decrease in 1.69 10.22 1.01
Benefits and 10%
increase in Costs
7 Financial Analysis
This section presents the results of the financial analysis undertaken to determine
the financial viability of our proposed project. In particular, the following aspects have
been taken into consideration:
Cost associated with the proposed development program which includes the
development costs and the operating costs;
A 25-year project period;
Price term is in current 2021 level; and
Construction period of two years.
Project Investment Cost
The project investment cost components are the direct (construction costs) and
indirect costs (project engineering services, land acquisition and contingencies).
These amounts, as mentioned above, are expressed in 2021 price level.
Tabulated below is the summary of the investment cost while the detailed breakdown
of the cost estimates is presented in Table 3.
Description Amount, PHP
Direct Cost 93,499,700.00
Indirect Cost 17,297,444.00
Total Project Cost 110,797,144.00
A replacement cost of PHP 15.75 million for the electro-mechanical equipment with
an economic life of 12 years have been included in the financial analysis.
Operating Expenses
The bases of operating expenses for the project are the following:
An annual operation & maintenance cost amounting to PHP 3.64 million. This
includes the salary and wages for the three (3) operators, three (3) security
guards and one (1) janitor. An amount of PHP 2 million is also included for the
annual maintenance and other operating expenses;
A local tax of 1% of gross sales as per EPIRA, Rule 29 of the IRR;
Financial Benefits to Host Communities as per ER 1-94, amounting to PHP
0.01 per kWh of the electricity sales;