Professional Documents
Culture Documents
Unbundled Services
Lee Willis’, John Finney2, and Greg Ramon3
October 1996 17
Cost of Power cost the transmission
Though not part of operator must allocate
delivery services per se, to customers if provid-
the cost of the power ing this service.
itself was computed
on a nodal basis for Generation Reserve
two reasons. First, Reliable and secure
some ancillary ser- operation of a power
vices (losses, reserves, system requires that
regulation) depend both spinning and
on power production stand-by generation
resources; inclusion of be available t o cover
production cost in the reasonable contingen-
computations clarifies cies. Requirements to
procedures needed to make reserves available
optimize overall cost, also place con-
as well as unbundle straints on transmission
and allocate costs. Sec- capability. Computation
ond, several deregulat- of reserve is rather
ed electric pricing straightforward, but its
mechanisms (for exam- allocation on a nodal
ple, the location-based Figure 3. Costing analysis identifying a line (red) whose capacity basis is tricky, because
limit forces an out-of-meritre-dispatch of generation in order to
pricing system) define t h e potential failure
accommodate a requested increase of 100 MW in an ongoing
the cost of transmis- transaction and showing power flow results (as opposed to of many generators
sion service between cost results as in Figure 2) for the recommended system state at different locations
two points in a system to accommodate the congestion. may be covered by the
as the net difference in same reserve.
the total price (power plus delivery) between those two
points. Capital Recovery and Network Operation
Two costs not included in the transmission cost analysis
Losses are the capital recovery cost of the system equipment
Movement of power through a transmission grid creates and the charges for the transmission system operator’s
losses, which must be made up by appropriate genera- services of scheduling, controlling and dispatching the
tion and for which movement of power (transmission) system. Computation and allocation of these costs are
must also be allocated. The cost of losses is a considered straightforward (see For Further Reading).
substantial element of the delivery cost. The costs vary Both can be computed as off-line tables, and used in allo-
with loading, flow pattern, location, and distance. cating costs to transmission system users on an access
or standard-fee basis.
Reactive Support
Reactive losses and voltage support in a power system Congestion Cost
must be accommodated in order both to provide transmis- Perhaps the most technically interesting variable operat-
sion of power and to assure system operation. Reactive ing cost associated with transmission service, and an
losses provided by generation are a mandatory service issue expected to become critical under open access, is
within FERC ruling 888 (the utility must offer to provide the congestion cost associated with equipment and
them, and the customer must buy them from the utility). security constraints. Assuming that a power system is
operating at the most economic and secure state possi-
Load Following ble for a given pattern of generation and loading, the
Tracking variations in load and maintaining system fre- request for an additional transaction (movement of
quency requires availability and control of generation, a power from one location to another) can sometimes only
October 1996 19
(including identification fast enough to be
of adjustments need- useful for both
ed t o accommodate offline planning
congestion) as well a s and online control-
the unbundled transmis- room evaluation.
sion services costs The basic algo-
at all nodes in the sys- rithm seems satis-
tem model. factory as a trans-
mission services
Provision for costing engine.
Secure Operation In addition, test-case
Security of operation for application indicates
a power system general- that a transmission sys-
ly requires that the sys- tem’s cost behavior is
tem be maintained in Figure 5. The transmission access costing program uses an opti- often quite unlike its
states that satisfy post- mal power flow a s the core of the computational engine. electrical behavior, t o
contingency constraints the point that is often
for the loss of any of its major components. The p r c and counter-intuitive (largely because planner’s and opera-
post-processor optimal power flow shown in Figure 6 tor’s intuition is based upon past experience with only
does not consider such constraints on operation. At electrical behavior). In general, cost of providing trans-
present, these are accommodated by transferring the mission services does rise as load and wheeling dis-
system s t a t e computed by a security-constrained tances are increased, as one would expect. However, the
OPF, along with its computed transfer limits FTC), from
the EPRI TRACE program, a s the base case for the
program (Figure 7). Use of the “starting case” and
maximum transfer limits from the TRACE program
permits application of the costing engine in a framework
likely t o respect security constraints, and identifies
which transactions can be accommodated a s
firm contracts and which only as nonfirm because of
security considerations.
While the costing analysis and t h e TTC-security
analysis both utilize optimal power flow algorithms, the
two applications use far different reformulations of the
OPF, and there are no present plans to combine the two
into one program. The partitioning into the costing
and TTC/ATC-security components also has advantages
of solution modularity, development autonomy,
and integration flexibility.
Figure 7. Provision for constraints on operation to assure Costing Analysis: A Part of the Future
secure operation within, for instance the NERC first-contingency In an open access power industry, analysis of costs
guidelines, is provided by interface to security constrained OPF and cost flow will become as routine and as sophis-
analysis such a s the EPRI TRACE (used for security constrained ticated as analysis of electrical performance is at the
analysis in all the authors research to date). present. In fact, profit-motivated utilities very likely
will need cost-analysis methods whose quality,
highest costs in a system are often not on the most high- auditability, and defendability exceeds programs used
ly loaded lines; costs do not always increase substantial- today. Experience with the prototype transmission
ly as loadings approach transfer limits; contingencies do access pricing program has shown that effective
not always increase costs by substantial margins; and transmission access costing software can be developed,
shedding significant load after a contingency hardly and that the approach described in this article is a
reduces costs. Overall, neither cost nor electrical perfor- sound method.
mance is better behaved or easier to analyze; they are
just different. For Further Reading
J. Finney, H. Othman, and W. Rutz, “EvaluatingTransmission Con-
Reduction of Large System Models straints in System Planning,” presented at the 1996 IEEE PES Sum-
One concern raised by research to date is the legitimacy mer Meeting and to appear in IEEE Transactions on Power Systems.
G. Ramon et al, Interconnected Operation of Transmission
for costing purposes of reduced models of large power Systems, North American Electric Reliability Council, Princeton,
systems. For example, since cost behavior of transmis- NJ, 1996.
sion networks appears t o be quite different than B.F. Wollenberg, A.J. Wood, Power Generation, Operation,
electrical behavior, it is natural to question whether and Control,Wiley Interscience, New York, 1995.
E.R. Tufte, The Visual Display o f Quantitative Information,
a 4,000-bus model of a 20,000 bus system, reduced Graphics Press, Cheshire, Connecticut, 1983.
on the basis of traditional electrical equivalencing
criteria, will be a valid model for cost analysis and
pricing purposes. Therefore, the current development Biographies
Lee Williis is manager of T&DTechnology for ABB Systems Control
goal is to increase the dimension of the transmission in Cary, North Carolina. A Fellow of the IEEE, he is vicechair of the
cost analysis program to 20,000 buses, alleviating the PES Power System EngineeringCommittee.
problem for a majority of cases and minimizing the John Fmey is a senior engineer in at the ABB Transmission
potential for error due to this cause for very large pools. Technology Institute in Raleigh, North Carolina. He has BS and PhD
degrees in electrical engineering from Georgia Tech.
However, the whole issue of reduction guidelines for Greg Ramon is director of Engineering for Tampa Electric Com-
cost-behavior analysis is something that needs to pany. A registered engineer in Florida, he is chair of the NERC Task
be examined further. Force on Interconnected Operations Services.
October 1996 21