% Manpower 2018
DESCRIPTION COST
Weight Loading 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
INTERIOR & EXTERIOR PAINTING WORKS MAY JUNE JULY AUGUST SEPTEMBER
1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun 26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep
Preliminaries 852,698.13 9.09%
To Walls
Basement 27,936.15 0.30% 3 14
Ground Floor 660,821.38 7.05% 4 21
1st Floor 199,294.43 2.12% 3 7
2nd Floor 166,717.24 1.78% 3 14
3rd Floor 186,309.75 1.99% 3 14
4th Floor 391,948.55 4.18% 5 21
4th Floor Trap room 518,562.67 5.53% 4 21
5th Floor 948,466.29 10.11% 6 14
6th Floor 382,964.52 4.08% 3 14
7th Floor 243,696.97 2.60% 3 14
8th Floor 286,450.30 3.05% 3 14
9th Floor 315,256.07 3.36% 3 14
10th Floor 71,564.69 0.76% 2 14
To Steel Doors
Painting to Steel Door 591,292.80 6.30% 2 110
Painting to Steel Door Jamb 440,600.00 4.70% 2 110
Submitted by:
Melchor Ansus
Project in-Charge