Alderstone Template Cutover Plan

A Production cutover requires detailed planning and careful coordination of multiple actors.
This document is intended as a template to support the planning of a Production cutover and the Emulated cutov
which should be performed prior to the real Production cutover.
This spreasheet allows you to specify FIXED times for the start of a sequence of activities and then dependencie
between activities.
The start and end times of an activity will be calculated based on the end time of the proceeding task and the
duration.
The ID of the preceeding task is shown int he PRE column, you may add multiple predecessors seperated by a com
the end time of the last ID in the list will be used for calculation.
The start times of fixed activities are shown with an underline, and we recommend you use this for milestones on
For example, the Data Migration Commences tasks is delayed to 8am to align with resource availability.
All Tasks muct have a unique ID.
Create a new row by copying and pasting an existing row, so that the hidden formulas are carried through.
This template provides a sequence of actions which may or may not be appropriate for your project. Please conta
your Alderstone Support Representative if you need help planning your Remedy upgrade.
ID Activity PRE Type

PRE005 Copy 7.6 Production Overnight backup to File system on 9.1 PRE000 Preparation
Server
PRE007 Restore 7.6 Production database Overnight backup into <Source PRE005 Preparation
Database> database on 9.1 database server
PRE008 Check Recover Model for Source ( <Source Database> ) and PRE007 Preparation
Target Databases (ARSsytem)
PRE030 Migrate all SLA data from 7.6 to 9.1 PRE008 Preparation
PRE040 Build SLA targets on 9.1 PRE008 Preparation
PRE090 Configure and validate CMT Data Migration for Production PRE030 Preparation
Cutover
M10 Pre-Tasks Complete Milestone
D10 Cutover Go/No-Go Decision M10 Decision
B10 Open Bridge for Cutover Bridge
M20 Outage Commences Milestone
SH10 Shutdown <Integration> Integration M20 Shutdown
SH20 Redirect Production 7.6 URL To System Down page SH10 Preparation
SH40 Shutdown ARS 7.6 Production AR Server SH20 Shutdown
SH50 Confirm all 7.6 Production database connections are closed SH40 Shutdown
SH60 Redirect Production 9.1 URL To System Down page SH10 Preparation
SH70 Shutdown ARS 9.1 Production AR Servers SH60 Shutdown
SH80 Confirm all 9.1 Production database connections are closed SH70 Shutdown
SH90 Stop Availability Group on 9.1 production SH80 Cutover
CUT010 Backup 7.6 Production database SH50 Cutover
CUT015 Copy 7.6 Production Overnight backup to Arsystems _PRD_76 CUT010 Preparation
database on 9.1 Server
CUT020 Restore7.6 Production database backup into <Source Database> CUT015 Cutover
database on 9.1 database server
CUT030 Execute SQL Script to add CMT DB user privileges on <Source CUT020 Cutover
Database>
CUT035 Cutover Migration of Audit Log Data CUT030 Cutover
M30 Data Migration Commences CUT030 Milestone
CUT040 Execute Pre-Migration Scripts M30 Cutover
CUT050 Export Phase 2 Companies from <Source Database> CUT040 Data Migration
CUT060 Import Phase 2 Companies into Arsystem CUT050 Data Migration
CUT070 Run Post Migration SQL CUT060 Data Migration
CUT120 Backup 9.1 Production database CUT070 Cutover
CUT130 Start all 9.1 ARS Servers in Loud Mode CUT120 Cutover
D20 Testing Go - No Go Decision CUT130 Decision
M40 Ready to Start Testing D20 Milestone
T10 9.1 Post-migration testing M40 Testing
T15 Validate <Integration> on 9.1 Production M40 Testing
T20 9.1 Testing Review Meeting T10 Meeting
D30 Go Live Go/No-Go decision T20 Decision
M60 Go Live Authorised D30 Milestone
CUT200 Stop 9.1 Production ARS Servers M60 Cutover
CUT210 Restore 9.1 Production Database from backup CUT200 Cutover
CUT225 Restart Availability Group on 9.1 production CUT210 Cutover
CUT220 Start all 9.1 ARS Servers in Loud Mode CUT210 Cutover
M70 9.1 Production Available to Users CUT220 Milestone
CUT225 Redirect <Integration> Production traffic to 9.1 Production & M70 Cutover
Validate
CUT230 Initiate FTS Index rebuild in 9.1 Production M70 Post-cutover
CUT240 Start 9.1 Email Service & Validate Outgoing mail M70 Cutover
CUT250 Validate 9.1 Production Service CUT240 Cutover
M90 7.6 Production System OFF CUT250 Milestone
CUT400 Notify outage end M90 Cutover
PC10 Validate FTS Rebuild on 9.1 Complete Successfully M90 Post-cutover
B50 Close Bridge CUT400 Bridge
M100 All Cutover Actions Complete B50 Milestone
Duration Start Time End Time Person
(mins)
150 2:00 PM 26-Jul 4:30 PM 26-Jul John Doe

40 4:30 PM 26-Jul 5:10 PM 26-Jul John Doe

5 5:10 PM 26-Jul 5:15 PM 26-Jul John Doe

20 5:15 PM 26-Jul 5:35 PM 26-Jul John Doe


120 5:15 PM 26-Jul 7:15 PM 26-Jul John Doe
30 5:35 PM 26-Jul 6:05 PM 26-Jul John Doe

6:00 PM 26-Jul 6:00 PM 26-Jul


30 1:00 PM 29-Jul 1:30 PM 29-Jul Change Approval Board
15 5:45 PM 29-Jul 6:00 PM 29-Jul John Doe
6:00 PM 29-Jul 6:00 PM 29-Jul
10 6:00 PM 29-Jul 6:10 PM 29-Jul John Doe
15 6:10 PM 29-Jul 6:25 PM 29-Jul John Doe
15 6:25 PM 29-Jul 6:40 PM 29-Jul John Doe
15 6:40 PM 29-Jul 6:55 PM 29-Jul John Doe
15 6:10 PM 29-Jul 6:25 PM 29-Jul John Doe
15 6:25 PM 29-Jul 6:40 PM 29-Jul John Doe
15 6:40 PM 29-Jul 6:55 PM 29-Jul John Doe
10 6:55 PM 29-Jul 7:05 PM 29-Jul John Doe
20 6:55 PM 29-Jul 7:15 PM 29-Jul John Doe
150 7:15 PM 29-Jul 9:45 PM 29-Jul John Doe

40 9:45 PM 29-Jul 10:25 PM 29-Jul John Doe

5 10:25 PM 29-Jul 10:30 PM 29-Jul John Doe

120 10:30 PM 29-Jul 12:30 AM 30-Jul John Doe


8:00 AM 30-Jul 8:00 AM 30-Jul
10 8:00 AM 30-Jul 8:10 AM 30-Jul John Doe
90 8:10 AM 30-Jul 9:40 AM 30-Jul John Doe
60 9:40 AM 30-Jul 10:40 AM 30-Jul John Doe
20 10:40 AM 30-Jul 11:00 AM 30-Jul John Doe
20 11:00 AM 30-Jul 11:20 AM 30-Jul John Doe
25 11:20 AM 30-Jul 11:45 AM 30-Jul John Doe
15 11:45 AM 30-Jul 12:00 PM 30-Jul Change Approval Board
12:00 PM 30-Jul 12:00 PM 30-Jul
120 12:00 PM 30-Jul 2:00 PM 30-Jul John Doe
10 12:00 PM 30-Jul 12:10 PM 30-Jul John Doe
20 2:00 PM 30-Jul 2:20 PM 30-Jul John Doe
10 2:20 PM 30-Jul 2:30 PM 30-Jul Change Approval Board
2:30 PM 30-Jul 2:30 PM 30-Jul
20 2:30 PM 30-Jul 2:50 PM 30-Jul John Doe
30 2:50 PM 30-Jul 3:20 PM 30-Jul John Doe
60 3:20 PM 30-Jul 4:20 PM 30-Jul John Doe
20 3:20 PM 30-Jul 3:40 PM 30-Jul John Doe
3:40 PM 30-Jul 3:40 PM 30-Jul
30 3:40 PM 30-Jul 4:10 PM 30-Jul John Doe

15 3:40 PM 30-Jul 3:55 PM 30-Jul John Doe


20 3:40 PM 30-Jul 4:00 PM 30-Jul John Doe
20 4:00 PM 30-Jul 4:20 PM 30-Jul John Doe
4:20 PM 30-Jul 4:20 PM 30-Jul
15 4:20 PM 30-Jul 4:35 PM 30-Jul John Doe
30 4:20 PM 30-Jul 4:50 PM 30-Jul John Doe
15 4:35 PM 30-Jul 4:50 PM 30-Jul John Doe
4:50 PM 30-Jul 4:50 PM 30-Jul
Details Actual_Duration Actual_Start

Ensure Simple logging rather than Full Logging


Actual_Finish Status

Scheduled

Scheduled

Scheduled

Scheduled
Scheduled
Scheduled

Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled

Scheduled

Scheduled

Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled

Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
ID Activity PRE Type

D30 Go Live Go/No-Go decision T20 Decision


M60 Go Live Authorised D30 Milestone
RB10 Stop 9.1 Production ARS Servers M60 Rollback
RB20 Restart ARS 7.6 Production AR Servers M60 Rollback
RB30 Restart ARS 7.6 Production Mid Tier Servers RB20 Rollback
RB40 Redirect Production 7.6 URL To Mid Tiers RB30 Rollback
RB50 Validate 7.6 Production is live RB40 Rollback
M70 Rollback complete RB50 Milestone
Duration Start_(BST) End_(BST) Person Details Actual_Durati
(mins) on
10 2:20 PM 30-Jul 2:30 PM 30-Jul Change Approval Board
### 2:30 PM 30-Jul
20 2:30 PM 30-Jul 2:50 PM 30-Jul John Doe
25 2:30 PM 30-Jul 2:55 PM 30-Jul John Doe
15 2:55 PM 30-Jul 3:10 PM 30-Jul John Doe
15 3:10 PM 30-Jul 3:25 PM 30-Jul John Doe
15 3:25 PM 30-Jul 3:40 PM 30-Jul John Doe
### 3:40 PM 30-Jul
Actual_Start Actual_Finish Status

Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled
Scheduled