Question. 1
You test the various options that SAP S/4HANA offers for
stock transfers between two different plants within the same
company code. Which special features do stock transport orders
have? Note: There are 2 correct answers to this question.

A. You can optionally post the goods issue from inspection


stock in the supplying plant.

B. The material on the road is managed in the stock in transit


of the receiving plant.

C. If necessary, you can post the goods receipt to blocked stock


in the receiving plant.

D. The material on the road is part of the valuated stock of the


shipping plant.

Answers B C

Question. 2
How do you proceed if you want to create purchasing info
records for consumable materials without material master
records?

A. You specify a special info category.


B. You specify the relationship between a material type and a
supplier.

C. You must first create material master records.

D. You specify the relationship between a material group and a


supplier.

Answers D

Question. 3
Which of the following occurs when you park a supplier invoice
related to a purchase order? Note: There are 2 correct answers to
this question.

A. The purchase order history is updated.

B. An MM invoice document is created.

C. G/L accounts are updated.

D. An FI invoice is posted and blocked for payment.

Answers A B

Question. 4
At which of the following organizational levels must you
maintain a business partner master record for a supplier? Note:
There are 3 correct answers to this question.

A. Client

B. Purchasing organization

C. Plant

D. Purchasing group

E. Company code

Answers A B E

Question. 5
You want to use automatic conversion of purchase requisitions
into purchase orders for some raw materials. What are the
prerequisites? Note: There are 3 correct answers to this question.

A. The Automatic Purchase Order indicator is set in the plant-


specific purchasing data of the material master record.

B. The Automatic Purchase Order indicator is set in the


purchasing data of the business partner master record.

C. A source of supply containing valid conditions is assigned


to the purchase requisition.

D. A contract with plant-specific conditions exists for the


material and the vendor.
E. A plant-specific source list entry exists for the material.

Answers A C E

Question. 6
When using a classic release procedure, for which of the
following documents must you use classification? Note: There
are 2 correct answers to this question.

A. Outline agreements

B. Requests for quotation

C. JIT delivery schedules

D. Purchase requisitions

Answers B D

Question. 7
Your MRP run detects a shortage of 2000 pieces for a certain
material for which a quota arrangement is active. Each of your
two suppliers can only supply 1000 pieces at once. What must
you maintain to have MRP generate a procurement proposal for
1000 pieces for each supplier? Note: There are 2 correct answers to
this question.
A. Assign the indicator for quota splitting to the used lot-
sizing procedure.

B. Assign a rounding profile in the material master record of


the planned material.

C. Set a maximum quota quantity in the quota arrangement


item for each supplier.

D. Set a maximum lot size in the quota arrangement item and


activate the 1x checkbox.

Answers C D

Question. 8
In your project, you need to make sure that consignment
purchase orders utilize a different number range than other
purchase orders. What must you do?

A. Customize a new document type, assign a new number


range object, and assign the item category for consignment to
this type.

B. Customize a new document type, assign a new number


range, and assign the item category for consignment only to
this type.

C. Customize a new item category for this purpose and assign a


new number range to it.
D. Customize a new item category for this purpose and
deactivate the standard one.

Answers B

Question. 9
Which SAP Fiori design principle has the goal of having one
type of user, one use case, and a maximum of three screens for
each application?

A. Simple

B. Role-based

C. Responsive

D. Instant value

Answers A

Question. 10
You regularly purchase non-stock materials. What must you
set up to allow the system to automatically propose specific
accounts for these materials?

A. Assign transaction keys to the material groups of these


materials.
B. Assign transaction keys to the account assignment
categories used.

C. Assign valuation classes to the material groups of these


materials.

D. Assign valuation classes to the account assignment


categories used.

Answers C

Question. 11
Your purchasing department wants to monitor overdue purchase
orders. What are the prerequisites for issuing delivery reminders
for a purchase order? Note: There are 3 correct answers to this
question.

A. Maintain reminder periods in the purchase order item.

B. Maintain a confirmation control key in the supplier master.

C. Maintain purchasing value keys in the purchase order item.

D. Output the purchase order.

E. Set message determination in Customizing and maintain


message records.

Answers A D E
Question. 12
You want to manually post an initial entry of stock for a
material in SAP S/4HANA. You should be able to enter both a
quantity and an amount. How do you proceed? Note: There are 2
correct answers to this question.

A. On the SAP Fiori launchpad, use the Post Goods Movement


app.

B. On the SAP Fiori launchpad, use the Manage Stock app.

C. On the SAP Fiori launchpad, use the Post Goods Receipt


without Reference app.

D. In the SAP GUI, use transaction MIGO.

Answers C D

Question. 13
An incoming invoice shows a variance when compared to the
expected quantity or amount. How can you record this invoice?
Note: There are 2 correct answers to this question.
A. Enter the actual invoice values, use the reduction function,
and post. The system creates a credit memo in addition to the
actual invoice.

B. Enter the actual invoice values, use the reduction function,


and post. The system creates an invoice with the reduced values.

C. Enter the actual invoice values and post. The system creates
an invoice with the actual values and might block it for
payment.

D. Enter the actual invoice values. You must then park the
invoice because posting is NOT allowed.

Answers A D

Question. 14
Which of the following prerequisites must be met for the system
to check the shelf life of materials at goods receipt? Note: There
are 3 correct answers to this question.

A. The shelf life expiration date check is activated for the


material type in Customizing.

B. The shelf life expiration date check is activated for the plant
in Customizing.

C. The shelf life expiration date check is activated for the


movement type in Customizing.
D. Batch management is active for the material in the plant.

E. The purchase order item contains the remaining shelf life.

Answers A C E

Question. 15
Which of the following elements can be generated by material
requirements planning (MRP)? Note: There are 3 correct
answers to this question.

A. Production order

B. Delivery schedule line

C. Purchase order

D. Planned order

E. Purchase requisition

Answers B D E

Question. 16
For which type of blocked invoices can you use the automatic
release function of the Release Blocked Invoices app?

A. Invoices blocked because of an excessive amount


B. Invoices blocked manually

C. Invoices blocked stochastically

D. Invoices blocked due to variances

Answers D

Question. 17
How can you personalize the Procurement Overview app? Note:
There are 3 correct answers to this question.

A. Filter the content of a card.

B. Extend the set with a new card.

C. Change the position of the cards.

D. Change the set of cards.

E. Hide an existing card

Answers A C E

Question. 18
Which of the following tasks does the system perform during
reorder point planning? Note: There are 3 correct answers to this
question.

A. Recalculate the replenishment lead time for materials with


automatic reorder point planning.

B. Check, in the planning file entries, whether a material must


be included in the planning run.

C. Perform backward scheduling to determine the availability


dates of purchase requisitions.

D. Carry out a lot-size calculation for every material with net


requirements.

E. Carry out a net requirement calculation for every material


included in the planning run.

Answers A C D

Question. 19
You want to set up account determination so that several
material types are grouped on the same accounts. What must
you do?

A. Assign the same valuation grouping code to the material


types.

B. Assign the same account modification to the material types.


C. Assign the same valuation class to the material types.

D. Assign the same account category reference to the material


types.

Answers D

Question. 20
What are some key features of goods-receipt-based (GR-based)
invoice verification? Note: There are 3 correct answers to this
question.

A. An invoice item is automatically generated for each goods


receipt.

B. As a prerequisite, the indicator for GR-based invoice


verification is set in the purchase order item.

C. Each invoice item is assigned to a goods receipt item.

D. After posting, you can reassign invoices from one goods


receipt to another.

E. A goods receipt must be posted prior to the invoice.

Answers B C E
Question. 21
Goods from a supplier arrive at your warehouse. However, you do
NOT want these goods to be part of your inventory yet. What is
the procedure for recording the conditional goods receipt (GR)?

A. Post a goods receipt to valuated GR blocked stock.

B. Post a goods receipt to non-valuated GR blocked stock.

C. Select the blocked stock stock type when posting the goods
receipt.

D. Make a note in the purchase order and wait until the


conditions for accepting the delivery are met.

Answers A

Question. 22
Which of the following are characteristics of the Hold function
for purchase orders? Note: There are 2 correct answers to this
question.

A. It triggers a workflow to request completion of the document.

B. It is supported for blanket purchase orders.

C. It disables follow-on activities.

D. It allows any kind of error in a document.


Answers A C

Question. 23
What is the effect of setting the Freeze Book Inventory indicator
in a physical inventory document header?

A. The book inventory is determined and fixed in the physical


inventory document at the beginning of the count.

B. The system blocks all inventory management units of the


physical inventory document for procurement.

C. The book inventory is determined and fixed in the physical


inventory document at the time of the difference posting.

D. The system blocks all inventory management units of the


physical inventory document for goods movements.

Answers A

Question. 24
Which field can you use to prevent a discontinued material from
being procured?

A. Special procurement type

B. Control code

C. Material status
D. Authorization group

Answers C

Question. 25
Which of the following are possible personalization options of the
SAP Fiori launchpad? Note: There are 2 correct answers to this
question.

A. Settings for language and region

B. Selection of the design theme

C. Selection of an SAP Fiori catalog

D. Selection of tile size

Answers A B

Question. 26
You send newly created purchase orders to a supplier via EDI,
whereas quantity or price changes are to be transmitted by e-
mail. What prerequisites must be met if you are using the
condition technique for message determination? Note: There are
3 correct answers to this question.
A. The Price and Quantity fields are relevant for printout
changes.

B. The condition record contains the Price and Quantity fields.

C. The dispatch time related to the change message needs to be


set to 1 (send with periodically scheduled job).

D. The New Message Determination Process for Change


Messages indicator is flagged in Customizing.

E. You use different message types for the print operations New
and Change.

Answers E

Question. 27
When creating a scheduling agreement, which field controls the
creation of a scheduling agreement with release documentation?

A. JIT Indicator

B. Creation Profile

C. Agreement Type

D. Item Category

Answers C
Question. 28
What can you control with a document type in purchasing?
Note: There are 3 correct answers to this question.

A. Number range

B. Linkage to material groups

C. Allowed account assignment categories

D. Field selection

E. Allowed item categories

Answers A D E

Question. 29
You are receiving deliveries for a valuated material. Which
documents are created when you post a goods receipt? Note: There
are 2 correct answers to this question.

A. Physical inventory document

B. Material document

C. Accounting document

D. Invoice document

Answers B C
Question. 30
Which options are available for the automatic posting of
unplanned delivery costs when creating an invoice with
purchase order reference? Note: There are 2 correct answers to this
question.

A. The costs can be posted to a separate account.

B. The system determines a freight clearing account for posting


the costs.

C. The costs are posted automatically in a separate invoice.

D. The costs can be distributed among the invoice items.

Answers A D

Question. 31
Which item category must you use for subcontracting?

A. Item Category K

B. Item Category L

C. Item Category D

D. Item Category W
Answers B

Question. 32
Which of the following are features of the Delivery Completed
indicator in a purchase order (PO) item? Note: There are 2 correct
answers to this question.

A. You can set the indicator manually when entering a goods


receipt for your PO item.

B. The indicator is always set automatically if the quantity


received is within the underdelivery tolerance.

C. If you set the indicator, the PO item is NO longer relevant for


material requirements planning.

D. If you set the indicator, NO further goods receipt may be


posted for the PO item.

Answers A C

Question. 33
Which of the following actions can an end user perform with
filtered report results in an SAP Fiori app? Note: There are 3
correct answers to this question.
A. Schedule as a background job.

B. Save as a new tile on the SAP Fiori launchpad.

C. Share on SAP Jam.

D. Send via e-mail.

E. Save as a CDS view.

Answers B C D

Question. 34
Which of the following can you control with the confirmation
control key? Note: There are 2 correct answers to this question.

A. The sequence of required confirmations

B. Default reminder levels for outstanding confirmations

C. The document type for the goods receipt

D. Whether a confirmation is a prerequisite for a goods receipt

Answers A D

Question. 35
Which of the following are prerequisites for flexible workflows
for purchase order approval? Note: There are 3 correct answers to
this question.

A. Deactivate the classic release procedure for purchase orders in


customizing.

B. Activate the flexible workflow for purchase orders in


customizing.

C. Define the recipients for the flexible workflow in the Manage


Workflows for Purchase Orders SAP Fiori app.

D. Set up the preconditions for the flexible workflow in the


Manage Workflows for Purchase Orders SAP Fiori app.

E. Create a class with flexible workflow characteristics for


purchase orders.

Answers B C D

Question. 36
What do you need to do if you want MRP Live to create planned
orders for externally procured materials?

A. Implement BAdI PPH_MRP_SOURCING_BADI =>


SOS_DET_ADJUST.

B. Change the procurement type of the material.

C. Set the MRP indicator in the source list of the material to


"Not relevant for planning".
D. Set the appropriate plant-specific material status.

Answers A

Question. 37
For which of the following scenarios could you implement a
stock determination strategy for a material in inventory
management? Note: There are 3 correct answers to this question.

A. Your material is stored at various storage locations in your


plant. You want to withdraw from the storage location with the
highest stock first.

B. Your material is stored in different plants. You want to


withdraw from the plant with the lowest stock first.

C. You use split valuation to separate internally produced and


externally procured quantities. Internally produced quantities
should be withdrawn first.

D. You have both vendor consignment stock and own stock for
the material. You want to withdraw your own stock first.

E. You have both quality inspection stock and unrestricted-use


stock for the material. You want to withdraw unrestricted-use
stock first.

Answers A C D
Question. 38
What needs to be configured and assigned if pricing conditions
in purchase orders should only be visible to certain users?

A. User parameter EVO

B. User parameter EFB

C. Field selection key for the activity category

D. Field selection key for the transaction

Answers B

Question. 39
Which of the following parameters should you consider when
determining the manual reorder point for a material? Note: There
are 3 correct answers to this question.

A. Safety stock

B. Checking group for availability check

C. Expected daily requirements

D. Lot-sizing procedure

E. Replenishment lead time


Answers A C E

Question. 40
Production planning and product costing are to be implemented
in your company. Which organizational level must you choose
for stock valuation?

A. Company code

B. Business area

C. Plant

D. Controlling area

Answers C

Question. 41
For which type of contracts can you use item category Material
Group (W)?

A. Sales contracts

B. Service contracts

C. Quantity contracts

D. Value contracts
Answers D

Question. 42
You have ordered a stock material that is valuated with a
standard price. The price in the purchase order (PO) is higher
than the standard price of the material. Which accounts are
updated at goods receipt? Note: There are 3 correct answers to this
question.

A. GR/IR

B. Stock

C. Price differences

D. Material consumption

E. Inventory differences

Answers A B C

Question. 43
Your company uses the classic release procedure for purchase
orders. What are some characteristics of a release procedure for
purchase orders? Note: There are 2 correct answers to this
question.
A. The release or rejection of a purchase order is only possible at
header level.

B. The output of purchase orders is NOT possible before approval.

C. Release procedures for purchase orders are possible without


classification.

D. The release or rejection of a purchase order is only possible at


line item level.

Answers A C

Question. 44
In your company, invoice verification clerks post a cash
discount amount using the posting net method. How do they
trigger the posting method?

A. By choosing an appropriate payment method

B. By changing the payment terms

C. By using an appropriate document type

D. By creating an extra invoice item for the cash discount


amount

Answers B
Question. 45
You have several company codes and plants in your SAP
S/4HANA system. You set the valuation level to plant. How can
you minimize the effort involved in account determination?

A. You can group plants assigned to company codes that have


the same chart of accounts by using the account grouping code.

B. You can group plants assigned to company codes that have


different charts of accounts by using the account grouping
code.

C. You can group plants assigned to company codes that have


different charts of accounts by using the valuation grouping
code.

D. You can group plants assigned to company codes that have


the same chart of accounts by using the valuation grouping
code.

Answers D

Question. 46
In which situation can you have open items in the GR/IR
clearing account?

A. When there is a price difference between purchase order and


invoice receipt for a purchase order item.
B. When there is a quantity difference between invoice and
purchase order item.

C. When there is a difference between the invoice price and the


valuation price of the material.

D. When there is a quantity difference between goods receipt


and invoice receipt for a purchase order item.

Answers B

Question. 47
You are interested in the percentage of shopping cart items that
require manual changes to either the purchase order or the
purchase requisition after initial creation and approval. What
key performance indicator (KPI) provides this information?

A. Purchase Requisition-to-Order Cycle Time

B. Purchase Requisition Item Changes

C. Purchase Requisition High Touch Rate

D. Purchase Requisition Low Touch Rate

Answers B
Question. 48
How does the system derive the company code when you post a
goods movement in a plant?

A. The system determines the company code from your default


settings.

B. When you enter a plant, the system uniquely determines the


company code, since a plant can only belong to one company
code.

C. When you enter a plant, the system uniquely finds a


purchasing organization and then a company code, since each
purchasing organization is assigned to a single company code.

D. When you enter a movement type, the system uniquely


finds a company code, since a movement type is only valid for a
single combination of plant and company code.

Answers B

Question. 49
You want to post scrap expenses to a special account. Which
characteristics can you use to influence the behavior of the
account determination? Note: There are 2 correct answers to this
question.

A. Movement type
B. Stock type

C. Plant

D. Storage location

Answers A D

Question. 50
What are some SAP Smart Business key performance
indicators (KPIs) available for contracts? Note: There are 3
correct answers to this question.

A. Value contract consumption

B. Conditions by contract

C. Unused contracts

D. Contract release orders

E. Contract leakage

Answers A C E
Question. 51
You want to prevent a specific material from being ordered from
a specific supplier. What must you do?

A. Create an entry in the source list with a blocking indicator.

B. Create a blocking entry in the purchasing info record.

C. Create a quota arrangement entry with a quantity of zero.

D. Create a blocking entry in the supplier master record.

Answers A

Question. 52
Which of the following business partner roles are required to
execute a procurement process? Note: There are 2 correct answers
to this question.

A. Contact Person on purchasing organization level

B. FI Vendor on company code level

C. Supplier on purchasing organization level

D. Supplier on purchasing group level

Answers B C
Question. 53
Supplier A should automatically be proposed as the primary
source for a specific material. What options do you have? Note:
There are 2 correct answers to this question.

A. Use the Regular Supplier indicator in the info record.

B. Use a source list and mark the supplier as fixed.

C. Set the Regular Supplier indicator in the business partner


master record.

D. Enter the supplier as the primary source in the material


master record.

Answers A B

Question. 54
Which of the following activities is a prerequisite to enable
partner role determination in purchasing documents?

A. Assign a partner role to relevant purchasing document types.

B. Assign a partner schema to relevant arrangement types.

C. Assign a partner schema to relevant account groups.


D. Assign a partner schema to relevant purchasing document
types.

Answers D

Question. 55
Which of the following are features of a scheduling agreement?
Note: There are 3 correct answers to this question.

A. A scheduling agreement can be used for a consignment


process.

B. Item category M (Material Unknown) can be used in a


scheduling agreement.

C. A material master record is optional in a scheduling


agreement item.

D. Scheduling agreement delivery schedule lines can only be


created manually.

E. A scheduling agreement item is always plant-specific.

Answers A C E
Question. 56
In which of the following business transactions will you get an
error message if automatic account determination has been set
up incorrectly? Note: There are 3 correct answers to this question.

A. Posting of a material price change

B. Goods issue of a valuated material

C. Goods receipt of consignment stock

D. Goods receipt of a valuated material

E. Stock transfer from a storage location to another storage


location

Answers A B D

Question. 57
You want to create a purchase order with reference to a purchase
requisition. What controls the linkage between the line item of
your purchase order and the purchase requisition?

A. Document type

B. Document category

C. Account assignment category

D. Item category
Answers A

Question. 58
What are some key features of the SAP Smart Business key
performance indicator (KPI) tiles used for purchasing
analytics? Note: There are 2 correct answers to this question.

A. Each tile represents a set of actionable cards.

B. Chart snippets on a tile are updated after each start of the


evaluation.

C. The tiles show key information that is updated in real time.

D. Numbers on the tiles can have different colors for different


alert thresholds.

Answers C D

Question. 59
What must you consider when defining purchasing
organizations? Note: There are 2 correct answers to this
question.

A. Each purchasing organization has its own supplier master


data.
B. Each purchasing organization has its own info records.

C. Each purchasing organization has its own material master


data.

D. Each purchasing organization has its own purchasing


groups.

Answers A B

Question. 60
You want to procure material from another plant. What
purchasing instrument would you use?

A. Warehouse transfer request

B. Warehouse transfer order

C. Standard purchase order

D. Stock transport order

Answers D

Question. 61
Which of the following are features of a subcontracting
procurement process? Note: There are 3 correct answers to this
question.

A. You can assign a subcontracting order item to an account.

B. You must create a subcontracting info record before you can


order a material by subcontracting.

C. You can maintain components to be provided in a bill of


material.

D. You can have subcontracting purchase requisitions created


by MRP.

E. You can post a non-valuated goods receipt for a


subcontracting order item.

Answers A B C

Question. 62
Which organizational assignment is mandatory for external
procurement?

A. Plant - Purchasing Group

B. Company Code - Purchasing Organization

C. Plant - Purchasing Organization

D. Reference Purchasing Organization - Purchasing


Organization
Answers C

Question. 63
A supplier delivers material to your warehouse; however, you are
only obliged to pay the supplier once you have withdrawn the
stock. Which procurement process would you implement for this
purpose?

A. Standard

B. Third-party

C. Consignment

D. Stock transfer

Answers C

Question. 64
You procure finished goods from a supplier. The supplier
manufactures the product using components shipped from your
company. Which process do you use for this scenario?

A. Subcontracting

B. External processing
C. Standard procurement

D. Third-party procurement

Answers A

Question. 65
At what level do you maintain the purchasing group in the
material master?

A. Purchasing organization

B. Plant

C. Company code

D. Client

Answers A C D

Question. 66
What logic does the system use during PO creation to propose a
valid price when using an info record? Note: There are 2 correct
answers to this question.

A. The system always proposes the price from the last purchase
order whose number was copied into the info record.
B. The system always proposes the price stored at purchasing
organization level, if available.

C. If a valid plant-specific price exists, it is proposed when a


purchase order is created for the corresponding plant.

D. If there are NO valid conditions maintained in the info


record, the system can propose the price from the last purchase
order.

Answers C D

Question. 67
Your company uses the classic release procedure for purchasing
documents. For which configuration object must approvers have
the appropriate authorization?

A. Release indicator

B. Release group

C. Release strategy

D. Release code

Answers D
Question. 68
You procure some materials exclusively by consignment. You
want material requirements planning (MRP) to create
consignment purchase requisitions assigned to a supplier,
instead of normal purchase requisitions for these materials.
What must you do for each of these materials? Note: There are 2
correct answers to this question.

A. Maintain a default storage location for external procurement


in the material master record.

B. Create at least one source of supply for consignment.

C. Set a special procurement type for consignment in the


material master record.

D. Set a special MRP group for consignment in the material


master record.

Answers B C

Question. 69
How does SAP Fiori achieve the role-based design principle? Note:
There are 2 correct answers to this question.

A. Complex transactions are split into several apps that


correspond to a user's role.
B. End users get all the information and functions they need
for their daily work.

C. Navigation, personalization, and application configuration


are limited to ensure consistency across user roles.

D. The application interface adapts to the size and device used


by the user.

Answers A C

Question. 70
You are entering a supplier invoice for a purchase order that has
been delivered. What information can you use as a reference to
post the invoice? Note: There are 3 correct answers to this
question.

A. Purchase order number

B. Purchase requisition number

C. Delivery note number

D. Material document number

E. Bill of lading number

Answers A C E
Question. 71
In the standard system, a controllable system message is shown
when a user creates a purchase order with a delivery date in the
past. What must you configure to allow such purchase orders to
only be created by authorized users?

A. Copy the system message to a new version, set it as a


warning message, and assign the version with user parameter
MSV to the non-authorized users.

B. Copy the system message to a new version, set it as a


warning message, and assign the version with user parameter
MSV to the authorized users.

C. Copy the system message to a new version, set it as an error


message, and assign the version with user parameter MSV to the
authorized users.

D. Copy the system message to a new version, set it as an error


message, and assign the version with user parameter MSV to the
non-authorized users.

Answers B

Question. 72
Which purchasing organization assignments can you make in
Customizing for the enterprise structure? Note: There are 3
correct answers to this question.

A. One purchasing organization to one company code

B. Several purchasing organizations to one purchasing group

C. One purchasing organization to several company codes

D. Several purchasing organizations to one company code

E. One purchasing organization to several plants across


company codes

Answers A D E

Question. 73
Your purchasing department is working with scheduling
agreements. What can you do using release creation profiles?
Note: There are 3 correct answers to this question.

A. You can control the periodicity of release creation using


release creation profiles.

B. You can create plant-specific release creation profiles in


Customizing.

C. You can enter a release creation profile in the material master


data.
D. You can assign a specific confirmation control key to a
release creation profile.

E. You can enter a release creation profile in the master data of a


supplier.

Answers A B E

Question. 74
You are posting a goods receipt without a corresponding purchase
order (PO) in the system. Which of the following are
prerequisites for automatic generation of the PO at the time of
goods receipt? Note: There are 3 correct answers to this question.

A. Automatic purchase order generation is activated for the


movement type in Customizing.

B. The goods receipt to be posted is intended for consumption.

C. A valid purchasing info record must exist for the material


and supplier combination.

D. A central purchasing organization is assigned to the plant


in Customizing.

E. The delivered material is a valuated stock material.

Answers A D
Question. 75
Which of the following options are available to block an invoice
for payment? Note: There are 3 correct answers to this question.

A. Set up automatic blocking based on user authorization.

B. Set plant-specific tolerance limits for automatic blocking.

C. Set up random automatic blocking.

D. Set a manual payment block at invoice header level.

E. Set up automatic blocking based on the amount.

Answers A D E

Question. 76
You want to collectively convert assigned purchase requisitions
into purchase orders. How can you do this? Note: There are 3
correct answers to this question.

A. Use the assignment list.

B. Use the source list.

C. Use the document overview in the Create Purchase Order app


(ME21N).
D. Run material requirements planning (MRP).

E. Run the automatic generation of purchase orders.

Answers A C E

Question. 77
You have several valid purchasing info records for one specific
material available in your system. What is the system behavior
when you manually create a purchase requisition?

A. The system will choose the most recent info record.

B. The system will list all valid records and the user needs to
select one.

C. The system will choose the info record with the lowest price.

D. The system will choose the info record from the last purchase
order.

Answers B

Question. 78
Which lot-sizing procedures are suitable for reorder point
planning? Note: There are 3 correct answers to this question.
A. Monthly lot size

B. Daily lot size

C. Replenish to maximum stock level

D. Lot-for-lot order quantity

E. Fixed order quantity

Answers C D E

Question. 79
How can you prevent a release order from being created in excess
of the target quantity of a quantity contract?

A. You must implement a BAdI to check the target quantity in


the contract release order and prevent release if the quantity
exceeds it.

B. If the order quantity exceeds the target quantity, a warning


message is issued. You can set this as an error message in
Customizing to prevent release.

C. If the order quantity exceeds the target quantity, a dialog


box opens. You can use a special authorization to control whether
the user may order the excess quantity.

D. The system prevents exceeding the target quantity in a


release order. NO additional action is required from you.

Answers B
Question. 80
You want to implement split valuation functionality. What
must you do? Note: There are 2 correct answers to this question.

A. Customize valuation categories and valuation types.

B. Assign valuation types to stock types.

C. Add valuation types to all open purchase order items.

D. Create additional accounting data for the relevant materials.

E. None

F. None

G. None

H. None

I. None

J. None

Answers A D