GDI PREVENTIVE MAINTENANCE INSTRUCTION Date: 15/04/10 Rev: 0

Maximo Ref. MPM-861-01-46 SFI Code 861-01


Equip.
AC Generator
Description
Manufacturer Caterpillar Equip. Location Engine Room

Model SR-4

MAINTENANCE SPECIFICATIONS

Frequency 36000 Hourly Estimated Duration 50 Hours

Criticality 5 Area Authority Chief Electrician

Class Structure 1358 Failure Code EGMD

Craft Chief Electrician No. of Craft 1

SAFETY NOTES

• Complete required Permit-To-Work (PTW).


• Lockout / Tag-out Permit required.
• Review / Complete Job-Safety-Analysis (JSA).
• Inform Area authority if work is carried out on critical equipment for ongoing
operation.
• Do not wear jewellery when working around rotating or Electrical machinery.
• Wear all proper safety equipment.

JOB PLAN INSTRUCTION


It is not uncommon to exchange the generator with a “spare” set instead of completing this
planned maintenance routine onboard. Ensure when dispatching the generator for
1
overhaul/service that the vendor utilised is approved by the OEM of the generator. If this routine
is to be completed onboard it is to be performed by a GDI approved vendor.
2 Dismantle generator including rotor removal.
Clean generator windings using clean, dry and oil free compressed air with electrical solvent or
3
de-greaser and high pressure hot water wash dependent on severity of contamination.
4 Dry windings to acceptable resistance levels.

5 Remove bearings.
Measure shaft bearing surfaces, endbell bearing wells and housings for roundness and proper
6
size.
7 Install new replacement bearings and pack with grease.