You are on page 1of 5

Cost Estimation & Specifications

Quantity survey
Openings
Plaster
Space Title

Perimeter

Skerting
Cornice
Ceiling

Finish
Space

Walls
Floor

Code
Area
No.
Code

subtract 2.3*4 =9.2


S-1 Class 8 35 32 32 32 64 68 23
S-2 corridor 1 59 59 25 25 80 86 20
S-3 corridor 1 53 53 16 16 80 86 16
S-4 Roof 205.6 195.6 196 25 116.3 116 84

Exterior
W-1 2 54 54 50 54
wall
Exterior
W-2 2 184 184 180 184
wall
Exterior
W-3 2 13 13 9 13
wall

Exterior
W-4 2 18 18 14 18
wall

Total Floor material


1- Porcelain Matt 30 x 30 cm
MATERIALS UNIT Q U A N.
CEEAMIC m² 57.75
WHITE CEMENT Kg 0.22
SAND m³ 1.1
CEMENT Kg 104.5
Total Wall material
1- Cementic Plaster
2- Cementic Plaster + Washable Paint
3- Artificial Stone Plaster
MATERIALS UNIT Q U A N.
CERAMIC m² 12.6
WHITE CEMENT Kg 12
SAND m² 0.3
CEMENT Kg 108

Total Ceiling material


1- Gypsum False Ceiling + Plastic Paint
MATERIALS UNIT Q U A N.
CEMENT Kg 330
GYPSUM Kg 0.264
SAND m² 0.726

Total Skerting material


1- Porcelain Skerting 8 Cm Height
MATERIALS UNIT Q U A N.
CONC. TILES m` 47.25
WHITE CEMENT Kg 0.045
SAND m² 1.125
CEMENT Kg 405