Energy Fiji Limited

Project Cost Estimate

Scheme No: SG06-19 Quotation Date: 11-Oct-19

Customer Name: JOHN Scheme Name: SUPPLY TO JOHN LAING OF MATOVO, SIGATOKA.

Remarks:

Code Description Quantity Unit Cost Line Total


B-PA-18A 1P 11KV T/OFF WITH FUSE/LINK 1 833.51 833.51

B-PA-13A 1P 11KV TERM DOUBLE XARM 1 264.75 264.75

B-PA-14A 1P 11KV THROUGH STRAIN 1 491.8 491.8

I03965 HELIUM CONDUCTOR-7/3. 75MM AAAC 200 1.37 273.34

I05464 11M CONCRETE POLES 2 1,173.02 2,346.04

B-PA-57A SINGLE POLE RURAL TYPE STD 1 2,280.46 2,280.46

I04361 5kVA Pole-M Transformer 1 1,906.7 1,906.7

I02100 2A HT EXPULSION FUSE FAST 2 9.91 19.81

I01998 35A HRC FUSE 35KO7 BRUSH 1 5.45 5.45

B-PG-LIN Lines Construction Team 3 720.27 2,160.81

B-PG-OHC O&M Team (Overhead) 2 505.44 1,010.88

B-PG-INS Electrical Inspection Team 1 156.78 156.78

RIVERSTONE River Stone 1 80 80

CART Internal Cartage 10 100 1,000

EQUIP Equipment Hire 15 100 1,500

B-PA-58 GROUND STAY 1 216.45 216.45

B-PA-59 FLY STAY 1 1,240.36 1,240.36

R0001 Engirng dsgn DrawgsGIS 8 100 800

R0002 Pwrline Rte SVY/WL ACQ 8 100 800

R0006 Construction Mangmt/Suprvsn 15 100 1,500

R0010 Inventory Management 1 100 100

VEGETATION_HEAVY Vegetation Management Heavy 2 380 760

___________

Total Price: $19,747.15

Markup Amount of 0.00% : $0.00

Vat Amount (9.0% :) $1,777.24

Total Value Incl VAT : $21,524.39

Customer Contribution (100%): $21,524.39

End of Quote