442139580
Q1: Solutions;
1)
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 7 + 4(4) + 1
𝐴= = =4
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 2 + 4(2) + 2
𝐵= = =2
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 8 + 4(5) + 2
𝐶= = =5
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 5 + 4(4) + 3
𝐷= = =4
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 8 + 4(6) + 4
𝐸= = =6
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 6 + 4(0) + 4
𝐹= = = 1.66̅
6 6
𝑡𝑃 + 4(𝑡𝑀) + 𝑡𝑂 9 + 4(6) + 3
𝐺= = =6
6 6
3) The Expected time to complete the project is :21 Weeks.
4) The Critical Paths is :A, C, E and G.
5) The Float of Activity F is :11 Weeks.
6) The Float of Activity C is :11 Weeks, Because it's in the Critical Path.
Q2: Solutions; 1)