Professional Documents
Culture Documents
• Planning
• Scheduling
• How it is to be performed?
Planning Requires:
• Ability to visualize discrete work
elements
• Intimate knowledge of
construction methods
• Establishing interdependencies
Project Planning
Project Code
provides the
framework Superintendent
Schedule Engr.
Is a well-‐defined scope Each work package has Each package has to Each package may vary It must be identifiable
of work that usually to be different from have start and end date in size, but must be a in a numerical
terminates in a other packages as well as a unique measurable and accounting system
deliverable product budget. controllable unit of (coding systems) in
work to be performed order to permit the
capture of both
budgeted & actual
performance
information
WBS Uses
Uses Scope
of
WBS: Costs
Schedule
Responsibility
The detail of a work package.
Beam 1
Column 3 Column 4
Column 1 Column 2
Question
B3
C5 S2
B2
S1
C6
B1
C3 C4
C1 C2
Planning
Key Elements:
• Generate Work Breakdown Structure (WBS)
& Activity List.
• Estimate Activity Duration/Cost.
• Determine job logic (sequential
relationships among activities).
• Draw graphic presentation in a network
diagram.
Project Scheduling
• Breaking down the scope of work into manageable portions; namely its
activities.
• Estimating each activity duration
• Establishing sequence relationships among activities.
• Finding the earliest and latest possible times for
• the execution of each activity.
• Looking up the project’s critical sequence of activities.
• Reviewing, optimizing, communicating, updating, and in general, using the…
Schedule.
Example
Slab Beam 2
Beam 1
Column 3
Column 4
Column 2
Column 1