You are on page 1of 13

EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

EPC/TURNKEY CONTRACT,
LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENTS

Oleh :
Sarwono Hardjomuljadi
sarwonohm2@yahoo.co.id
Civil Engineering Department,Faculty of Engineering, University of Mercu Buana
Jakarta, Indonesia

Abstract : The most important thing before starting the construction project is deciding the
type of contract will be used for the project’s implementation. In order to get the proper
decision, the understanding on various conditions of contracts are required. In Indonesia
there are many project using the so called “modified” FIDIC Conditions of Contract for
EPC/Turnkey Project, but with the incorrect understanding on the reasons of using
EPC/Turnkey Contract, so instead of solving the problem it may caused bigger problems in
practice, many problems raised during the execution due to such incorrect understanding of
the spirit of EPC/Turnkey Contract. Most of Employers, in this case the government
institution or state owned enterprises in Indonesia, choose the EPC/Turnkey Contract with
minimum understanding of the essence of the EPC/Turnkey Contract. Their reasons of
choosing the EPC/Turnkey Contract was the “tied schedule” and the “higher certainty of
cost”. FIDIC EPC/Turnkey Contract based on the discussion in this paper, instead of fit the
Employer’s need only, the EPC/Turnkey Contract still give chance to the contractor to
submit their claim (Clause 20) and even the price is fixed, payment could be made once the
claim is accepted (Sub-Clause 17.4) means that additional to the contract price can be done.
One of the important noteworthy thing is that if there is additional cost it should be “added
to the contract price”, while in the conventional contract it should be “included in the
contract price”, so the final price will be the same (Sub-Clause 14.1).

Keyword: EPC/Turnkey Contract, tied schedule, higher certainty of cost, added, included.

MATERIALS AND DISCUSSION contractor’s advantages. This


1.General misperception makes them hesitate to
The claims and disputes occurred in use the FIDIC Conditions of Contract
the construction of State Electricity for Construction and move to FIDIC
Corporation’s coal power plants in Conditions of Contract EPC/Turnkey
Indonesia were mostly due to the lack Project which is in their opinion will
of deeper understanding on the spirit be more fix in term of contract price.
of EPC/Turnkey Contract as the Most of decision makers in Indonesia
conditions of contract to be used and State Electricity Corporation (PLN)
were not due to the use of certain have only a little or even no
conditions of contract itself. However, knowledge on the spirit of FIDIC
many Indonesian higher ranking EPC/Turnkey Contract. That is why
officials think that the use of they choose to develop coal power
standardized conditions of contract plant in Indonesia by using their own
such as FIDIC Conditions of Contract standard conditions of contract which
in this case the FIDIC CC for is actually the modified FIDIC
Construction is the main causal factor Conditions of Contract for
of the claim and using the such FIDIC EPC/Turnkey Project.
Conditions of Contract is more the

11 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

(i) of the Works which the


2. FIDIC GCC for EPC/Turnkey Contractor is required to execute,
Project and FIDIC GCC for or
Construction. (ii) for the purposes of Clause 12
Clauses related to the [Measurement and Evaluation];
difference between EPC and and
(Conditions of Contract for
Construction Contract are as follows:
Construction-1999 and MDB
2.1. The Contract Price Harmonised Edition-2006)
Sub-Clause 14.1 The Contract Price
(Silver Book) The above clauses show that the
Unless otherwise stated in the
“spirit” of EPC Contract (Silver Book)
Particular Conditions:
(a) payment of the Works shall be is a fixed “lump sum” contract price,
made on the basis of the lump sum while the Construction Contract (Red
Contract Price, subject to Book) is a “dynamic” contract price.
adjustments in accordance with
the Contract; and 2.2. Consequences of Employer
(b) the Contractor shall pay all taxes, Risks (Silver Book)
duties and fees required to be paid Sub-Clause 17.4 Consequences of
by him under the Contract, and the Employer Risks
Contract Price shall not be If the Contractor suffers delay and/or
adjusted for any of these costs, incurs Cost from rectifying this lost or
except as stated in Sub-Clause 13.7 damage, the Contractor shall give a
[Adjustments for Changes in further notice to the Employer and
Legislation]. shall be entitled subject to Sub Clause
(Conditions of Contract for 20.1 [Contractor’s Claim]
EPC/Turnkey Projects -1999) (a) an extension of time for any such
delay, if completion is or will be
Sub-Clause 14.1 The Contract Price delayed, under Sub clause 8.4
(Red Book) [Extension of Time for
(a) the Contract Price shall be agreed Completion]; and
or determined under Sub-Clause (b) payment of any such Cost, which
12.3 [Evaluation] and be subject to “shall be added to” the Contract
adjustment in accordance with the Price.
Contract. (Conditions of Contract for
(b) the Contractor shall pay all taxes, EPC/Turnkey Project-1999)
duties and fees required to be paid
by him under the Contract and the
Contract Price shall not be Sub-Clause 17.4 Consequences of
adjusted for any of these costs Employer Risks (Red Book)
except as stated in Sub-Clause 13.7 If the Contractor suffers delay and/or
[Adjustment for Changes in incurs Cost from rectifying this lost or
Legislation]; damage, the Contractor shall give a
(c) any quantities which may be set further notice to the Employer and
out in the Bill of Quantities or shall be entitled subject to Sub Clause
other Schedules are estimated 20.1 [Contractor’s Claim]
quantities and are not to be taken (a) an extension of time for any such
as the actual and correct delay, if completion is or will be
quantities: delayed, under Sub clause 8.4

12 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

[Extension of Time for Works, or (iii) it will have an adverse


Completion]; and impact on the achievement of the
(b) payment of any such Cost, which Performance Guarantees. Upon
“shall be included in” the Contract receiving this notice, the Employer
Price, in the case of sub-paragraph shall cancel, confirm or vary the
(f) and (g) of Sub-Clause 17.3 instruction.
[Employer’s Risk], reasonable (Conditions of Contract for
profit on the Cost shall also be EPC/Turnkey Project-1999).
included.
(Conditions of Contract for Sub-Clause 13.1 Right to Vary (Red
Construction-1999 and MDB Book)
Harmonised Edition-2006) Variations may be initiated by the
Employer at any time prior to issuing
The above sub-clause shows that the the taking Over Certificate for the
Contract Price in FIDIC CC for Works, either by an instruction or by
EPC/Turnkey Contract is “fixed request for the contractor to submit a
proposal.
contract price”, means that in case
there are some works necessary to be The Contractor shall execute and be
done on completing the Work, such bound by each Variation, unless the
cost “shall be added to the contract Contractor promptly gives notice to
price” and not “shall be included in the the Employer stating (with supporting
Contract Price” as for the cost of particulars) that the Contractor
additional work in the FIDIC CC for cannot readily obtain the Goods
required for the Variation. Upon
Construction. It means that both
receiving this notice, the Employer
Conditions of Contract allow the shall cancel, confirm or vary the
additional contract price, only the way instruction.
to include that additional in the Each Variation may include:
contract price is treated in different (a) changes in the quantities of any
way. item of work included in the
Contract (however, such change
2.3. Right to Vary 9 (Silver Book) do not necessarily constitute a
Sub-Clause 13.1 Right to Vary Variation),
Variations may be initiated by the (b) changes to the quality and other
Employer at any time prior to issuing characteristics of any item of
the taking Over Certificate for the work,
Works, either by an instruction or by (c) changes to the level, positions
request for the contractor to submit a and/or dimension of any parts
proposal. A Variation shall not of the Works,
comprise the omission of any work (d) omission of any work unless it is
which is to be carried out by others. to be carried out by others,
(e) any additional works, Plant,
The Contractor shall execute and be Materials or services necessary
bound by each Variation, unless the for the Permanent Works,
Contractor promptly gives notice to including any associate Test on
the Employer stating (with supporting Completion, boreholes and other
particulars) that (i) the Contractor testing and exploratory work or,
cannot readily obtain the Goods (f) changes to the sequence or
required for the Variation, (ii) it will timing of the execution of the
reduce the safety or suitability of the Works.

13 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

(Conditions of Contract for consequently will delay the


Construction-1999 and MDB collecting of the revenue.
Harmonised Edition-2006)
2. No design available at that time.
It could be seen that the spirit of FIDIC
Conditions of Contract for
By using the EPC/Turnkey Contract,
EPC/Turnkey Project (Silver Book) is
the Employer thought that they
fixed price providing that there is no
already shift the risks to the
change, in the form of instruction or
contractor side, but EPC/Turnkey
approval in the construction drawings
Contract with too limited information
and/or the method of working
or too simple basic design would
proposed by the contractor when they
create many problems in the course of
aubmit the revised drawing for
the work.
implementing the activities, it should
The condition might be worsen since
be understood that in both, FIDIC
most of conditions of contract for
Conditions of Contract for
public sector and private sector
Construction (Red Book) of FIDIC
construction work in Indonesia was
Conditions of Contract for
“tailor-made” and was not
EPC/Turnkey Project (Silver), there is
standardized. Instead of controlling
possibility of changes in most
the contract price, a modified
activities or part of the works.
EPC/Turnkey Contract would create
As an illustration, once the employer
more problems and finally everything
paid to the contractor for the
became uncontrollable. A “tailor
additional volume for example the pile
made” contract by deleting and
foundation, it means the employer
replacing some clauses in the FIDIC
indirectly agreed that a variation to
Conditions of Contract for
the work was instructed, whereas in
EPC/Turnkey Project by newly made
EPC/Turnkey Contract, there should
clauses for the employer’s sake was
not be an additional to the Contract
mostly than none creating the
Price without changing order to the
disputes in the future since the
scope of work or design change.
contractor would obviously try to
In the implementation, the approval
minimize the loss.
on construction working drawing
With such misunderstanding, the
menas the instruction to proceed the
owner, in this case the Indonesia State
work, since without such approval the
Electricity Corporation constructed
work is not allowed to be started.
their coal power plant projects using
3. EPC/Turnkey Contract for power the modified FIDIC Conditions of
plants in Indonesia Contract for EPC/Turnkey Project,
The reasons of using EPC/Turnkey mostly by deleting the clauses of the
Contract for most projects in employer’s obligation and attaching
Indonesia are: unit prices in the civil works part
1. Time constraint to complete the without any remarks.
project on time since the delay in
completion may affect the
operation of the premises and
14 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

Table 1 Coal Power Plant Projects using EPC/Turnkey Contract in Indonesia


(Java Island)

CAPACITY ORIGINAL CONTRACT


NO PROJECT NAME REMARK
(MW) USD IDR
1 REMBANG CPP, 2 X 315 353,793,444 2,565,638,698,812 Claim for
CENTRAL JAVA additional
pile
foundation
for
construction
jetty.
2 LABUAN CPP, 2 X 300 373,427,613 1,538,121,618,046 Claim/ for
BANTEN additional
length of
break water
and jetty.
3 INDRAMAYU 3 X 330 766,407,863 1,647,300,023,978 Potential
CPP, WEST JAVA claim for
delay of L/C
opening
(EOT).
4 PAITON CPP, 1 X 660 428,127,137 777,293,309,275
EAST JAVA
5 SURALAYA CPP, 1 X 625 367,903,081 951,677,973,128 Claim for
BANTEN additional
work for
coal yard
and coal
handling.
6 PACITAN CPP, 2 X 315 379,469,024 1,353,549,015,500
EAST JAVA
7 PELABUHAN 3 X 350 623,683,413 2,425,583,521,260 Potential
RATU CPP, claim for
WEST JAVA delay of L/C
opening
(EOT).
8 TELUK NAGA 3 X 315 588,789,989 2,079,145,339,700 Claim for
(LONTAR) CPP, project
BANTEN safety and
damage
about
incident
with local
people.
9 TANJUNG 2 X 350 480,776,540 1,495,162,036,192 Potential
AWAR-AWAR Claim for
CPP, EAST JAVA additional
length of

15 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

pile
foundation
for jetty
construction
10 ADIPALA 1 X 660 605,296,555 2,446,311,697,151 Potential
CILACAP CPP, Claim for
CENTRAL JAVA additional
length of
pile
foundation
for jetty
construction

Table 2 Coal Power Plant Projects using EPC/Turnkey Contract in Indonesia


(Sumatera Island)

N PROJECT CAPACIT ORIGINAL CONTRACT


REMARK
O NAME Y (MW) USD IDR
1 NAGAN 2 X 110 160,910,505 795,022,169,563 Potential
RAYA CPP, Claim for
NANGROE additional
ACEH length of
DARUSSALA pile
M foundatio
n.
2 PANGKALAN 2 X 220 270,819,993,7 1,010,461,264,161,2 Potential
SUSU CPP, 3 5 Claim for
NORTH additional
SUMATERA length of
pile
foundatio
n.
3 BENGKALIS 2 X 10 10,911,169,50 171,444,999,913
CPP, RIAU
4 SELAT 2X7 12,001,083 144,098,063,800
PANJANG
CPP, RIAU
5 TANJUNG 2X7 8,251,281,50 92,170,796,317,50 Potential
BALAI claim
KARIMUN (change
CPP jetty
KEPULAUAN design).
RIAU
6 LAMPUNG 2 X 100 154,273,163 595,100,000,000 Potential
CPP, Claim for
LAMPUNG additional
length of
pile
foundatio
n.

16 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

7 SUMATERA 2 X 112 179,024,152 673,609,315,309 Potential


BARAT CPP, Claim for
WEST additional
SUMATERA length of
pile
foundatio
n.
8 No.3 2 X 30 29,700,000 410,138,467,860
BANGKA
BELITUNG
CPP,
PANGKAL
PINANG,
BANGKA
9 No 4 2 X 16,5 30,933,801,8 184,008,788,665,5
BANGKA
BELITUNG
CPP,
BELITUNG
10 LABUHAN Claim for
ANGIN CPP, additional
NORTH length of
SUMATERA pile
foundatio
n.

The above tables show that problem most of Standard General Conditions
occurred in most of the project was of Contract. The spirit of clause
similar, i.e. claim on the additional related to “Unforeseeable Physical
cost due to the “unforeseeable Conditions” requires the contractor to
physical condition” (contractor’s observe the site condition from time to
opinion) where it was only the less time so he is able to find that condition
significant additional volume that timely
should actually be considered by the As an illustration, the length of the pile
Contractor before submitting the bid foundation was 5 meter based on the
(employer’s opinion). Most of the design (Contractor’s own design, but
claim was caused by additional length based on the information given by the
of the foundation, which actually employer at the time of tender and/or
being done based on the approved pre bid conference), but in the
working drawing prepare by the implementation, the length of the pile
Contractor and approved by the foundation have to be constructed 10
Employer. meter deep. In the contractor’s
“Unforeseeable physical conditions” is opinion this could be classified as UPC,
the contractor’s favorite clause: because their expectation while
The term ”Unforeseeable Physical signing the EPC Contract was exactly 5
Conditions (UPC)” and the like, is a meter.
contractual term specifically used in

17 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

Additional volume: There were two The Contractor had the schedule of
arguable opinions. The lawyer’s rates and prices attached to the
opinion saying that the additional contract, so in order to avoid further
length of the pile foundation in the failure, the Employer instructed the
above illustration was due to Contractor to use the former
something unforeseeable might be Employer’s design. The final price of
correct. Another opinion saying that it the pier then became even higher than
was just a less significant additional the original price of the pier with the
volume might be also correct, but no length of X meter
matter what it was, there was no
doubt that as the contract was signed Case 2:
it meant that it was understood and In the construction of a Coal Power
agreed by both parties as stipulated in Plant Q, the foundation was originally
the Sub-Clause 4.12 Unforeseeable designed using pile foundation with a
Difficulties of the FIDIC CC certain depth, say X meter, but during
EPC/Turnkey Project. the execution of the work the hard
rock was found deeper, say Y meter
Case 1: where Y > X.
In the implementation of In the contract, there was schedule of
EPC/Turnkey Contract for a Coal rates and prices attached to the
Power Plant Project P, the Contractor contract for foundation works. It
was responsible to construct the pier meant that the payment for this work
for unloading the coal. would be based on such unit price.
Based on the original design, the This showed that the Employer did
length of the pier was X meter but not fully understand the spirit of an
based on the supporting data of the EPC/Turnkey Contract which was
sea level, Contractor A in his bid actually a Lump Sum Fixed Price
proposed to reduce the pier length Contract as they also included Unit
into Y meter, where Y < X meter which Price work in the Contract.
was then agreed by the Employer. Due The final Contract Price increased
to that, the bid price submitted by since the substantive principle of an
Contractor A was lower than the other EPC/Turnkey Contract had been
contractors. abandoned due to the lack of
After the price and technical understanding on EPC/Turnkey
evaluation, Contractor A was then Contract.
appointed as the Contractor for the FIDIC Conditions of Contract is an
Coal Power Plant Project P to conduct engineered conditions of contract
the design, engineering, procurement required by the international lending
and construction works including the institution, unfortunately there is a
pier. During the construction, the misperception in the employer side
actual sea water level was lower than that the use of FIDIC Conditions of
predicted by the contractor when Contract facilitates the contractor in
preparing the design. The ship was submitting their claims which used to
consequently unable to unload and create disputes. In the writer’s opinion
the coal supply would be disrupted. the spirit of equality between

18 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

employer and contractor should not since once the contract is signed then
allow such misperception. The clause Sub-Clause 4.12(b) becomes valid.
allowing the contractor to submit The decision makers think that the
claim and the clause of Unforeseeable UPC clauses are the main causal factor
Physical Conditions and the like are of claims and therefore suggest that
the entry gate for the contractor to the clauses to be eliminated, whereas
recover their loss. the existence of clauses emphasizing
adjustment of the contract price
4. Unforeseeable Conditions and/or extension of time if
The term ”Unforeseeable Physical unexpected circumstances occurred
Conditions (UPC)” and the like, is a would reduce the contingency costs or
contractual term specifically used in hidden risk taking into account by the
most of Standard General Conditions contractor in his tender calculation.
of Contract. The spirit of clause Those clauses are based on the
related to “Unforeseeable Physical assumption that if the contractor
Conditions” requires the contractor to obtains adjustment of the contract
observe the site condition from time to price and/or extension of time when
time so he is able to find that condition encountering the Unforeseeable
timely. Physical Conditions (UPC), the
contractor should not consider the
Sub-Clause 4.12 Unforeseeable risk allocation in their tender price.
Difficulties Since the risks allocated by every
Except as otherwise stated in the contractor vary largely, it will be
Contract: easier in evaluating the submitted
(a) the Contractor shall be deemed tender if the risk allocations are not
to have obtained all necessary included and therefore the price
information as to risks, submitted will be a realistic one.
contingencies and other The hesitation to allow the UPC
circumstances which may Clauses makes the EPC/Turnkey
influence or affect the Works; Contract the employer’s first choice,
(b) by signing the Contract , the considering that all risks will be fully
Contractor accepts total shifted to the contractor. There is a
responsibility for having
tendency in Indonesia using the
foreseen all difficulties and costs
of successfully completing the EPC/Turnkey Contract instead of the
Works; and Conventional Construction Contract.
(c) the Contract Price shall not be Example clauses related to
adjusted to take account of any Unforeseeable Physical Conditions
unforeseen difficulties or costs. from some General Conditions of
(Conditions of Contract for Contract are as follows:
EPC/Turnkey Project-1999)
Clause 12.2. Not Foreseeable
In Clause 4.12 of Conditions of Physical Obstruction or Conditions.
Contract for EPC/Turnkey Project- If however, during the execution of
1999, it is clear that principally no the Works the Contractor encounters
“unforeseen conditions” is allowed physical obstruction or physical

19 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

conditions, other than climatic making of reasonable


conditions on the Site, which enquiries; and
obstruction or conditions were, in his c) the site and its near surrounds
opinion, not foreseeable by an (Standards Australia: General
experienced contractor, the Conditions of Contract AS 4000-1997,
Contractor shall forthwith give notice amendment 3-2005)
thereof to the Engineer.................,”
(FIDIC General Conditions of Contract Clause 5.2 Adverse Physical
for Works of Civil Engineering 4th Condition
Edition, 1987, amended 1992) If the Contractor shall encounter
adverse physical conditions (other
Clause 4.12 Unforeseeable than weather conditions or effects due
Physical Conditions to weather conditions on the Site) in
In this Sub-Clause “physical the course of carrying out sub-surface
conditions” means natural physical works, which adverse physical
conditions and man made and other conditions could not have been
physical obstructions and pollutants, reasonably foreseen by an
which the Contractor encounters at experienced contractor and the
the Site when executing the Works, Contractor is of the opinion that
including sub-surface and additional cost will be
hydrological conditions but excluding incurred………….”
climatic conditions. (Building and Construction Authority
If the Contractor encounters adverse of Singapore: Public Sector Standard
physical conditions which he Conditions of Contract for Construction
considers to have been Unforeseeable, Works 5th Edition, 2006)
the Contractor shall give notice to the
Engineer as soon as practicable. Clause 4.3.4 Claims for Concealed
(FIDIC General Conditions of Contract or Unknown Conditions
for Construction, 1st Edition 1999 and If conditions are encountered at the
MDB Harmonised Edition 2006) site which are (1) subsurface or
otherwise concealed physical
Clause 12.1 Latent Conditions condition which differ materially from
Latent conditions are: those indicated in the Contract
Physical conditions on the Site and its Document or (2) unknown physical
near surrounds, including artificial conditions of an unusual nature,
things but excluding weather which differ materially from those
conditions, which differ materially ordinarily found to exist and generally
from the physical conditions which recognized as inherent in construction
should reasonably have been activities of the character provided for
anticipated by a competent Contractor in the Contract Document …………..”
at the time of the Contractor’s tender, (American Institute of Architect:
if the Contractor has inspected: General Conditions of the Contract for
a) all written information made Construction A201-1997)
available by the principal to
the contractor for the purpose There are “unforeseen conditions” in
of tendering many contracts with their own
b) all information influencing the definition respectively, but for the
risk allocation in the
EPC/Turnkey, Sub-Clause 4.12 is
Contractor’s tender and
reasonably obtainable by the bound. So no claim on the
unforeseeable physical conditions are

20 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

allowed. But, the contractor still delayed, under Sub clause 8.4
possible to receive additional payment [Extension of Time for Completion];
if there are instruction and/or and payment of any such Cost, which
approval on the variations proposed “shall be added to” the Contract Price.
by the contractor. FIDIC Conditions of Contract for
It should be noted that the contract EPC/Turnkey Project could be
price while using the EPC/Turnkey categorized as the fair conditions of
Contract might be higher than using contract not only for the contractor
the Construction Contract, but in case but also for the employer. On choosing
that the allocation of time and cost are the EPC/Turnkey Contract, employer
limited EPC Contract might be the should realize that since there are
best. Another reason for using EPC in more risks allocated to the Contractor,
Indonesia is the certainty of cost the contractor will require more data
which is better than the uncertain cost on site conditions site including sub-
with huge additional cost and in order surface condition and need more time
not to be suspected especially by the to study the risks before submitting
Anti Corruption Committee, the the tender.
government super body to fight Learning from the experiences in
against the corruption. Indonesia the use of “tailor made”
By using EPC Contract the chance to EPC/Turnkey Contract by modifying
submit the claim is very limited. Once several clauses should be avoided, but
the contractor signed the contract it should be mandatory of using the
means they accept any site conditions original version of FIDIC Condition of
and the Contract Price shall not be Contract EPC/Turnkey Project along
adjusted to take account of any with the translation from the English
unforeseen difficulties or costs. version to Bahasa Indonesia which is
Eventhough there is no adjustment to published under FIDIC license as the
the Contract Price in the Conditions of supporting tools to deeply understand
Contract EPC/Turnkey Project, there the spirit of FIDIC Conditions of
is still chance for the contractor to Contract for EPC/Turnkey Project.
submit claim in accordance to Clause Another advantage for the employer
20 and by the existence of Sub-Clause by using the EPC/Turnkey Contract is
13.1 Right to Vary, where mentioned that the owner only needs to put in
variations may be initiated by the minimum efforts in his project as the
Employer at any time prior to issuing cost is already known at the beginning
the Taking Over Certificate for the of the project. Market cost fluctuation
Works, either by an instruction or by has an important influence to the
request for the contractor to submit a contractor side as there is no price
proposal and Sub-Clause 17.4 escalation clause in an EPC Contract.
Consequences of Employer Risks That is why the contractor has to pay
where mentioned that that the attention to the currency exchange
contractor shall be entitled subject to and price variation of materials and
Sub Clause 20.1 [Contractor’s Claim], labor in the market. All variations in
for an extension of time for any such cost are considered as the contractor’s
delay, if completion is or will be risks since by an EPC Contract means

21 | K o n s t r u k s i a
Jurnal Konstruksia | Volume 6 Nomer 2 | April 2015

that both parties have committed a References


fixed price and it will be free from 1. American Institute of Architect:
variation of the market prices. It “General Conditions of the
should be considered an arrangement Contract for Construction A201”,
of a re-agreement between the 1997
2. Building and Construction
contractor and the suppliers in order
Authority of Singapore: “Public
to protect the contractor’s Sector Standard Conditions of
performance. Contract for Construction Work”
The Employer should rember that the 5th Edition, 2006
Conditions of Contract for 3. Bunni, Nael G., “The FIDIC Forms
EPC/Turnkey Projects are not suitable of Contract”, Blackwell Publishing,
for use in the following circumstances: 3rd Edition, 2008
4. Chow, Kok Fong, ”Construction
o If there is insufficient time or
Contracts Dictionary”, Sweet &
information for tenderers to scrutinise Maxwell Asia, 1st Edition,
and check the Employer's Singapore, 2006
Requirements or for them to carry out 5. FIDIC, “General Conditions of
their designs, risk assessment studies Contract for Civil Engineering
and estimating (taking particular Works”, 4th Edition, Geneva, 1987,
amended 1992
account of Sub-Clauses 4.12 and 5.1).
6. FIDIC, “General Conditions of
o If construction will involve Contract for Construction”, 1st
substantial work underground or Edition, Geneva, 1999
work in other areas which tenderers 7. FIDIC, “General Conditions of
cannot inspect. Contract for EPC/Turnkey Project,
o If the Employer intends to supervise 1st Edition, Geneva, 1999
8. FIDIC, “General Conditions of
closely or control the Contractor's
Contract for Construction, MDB
work, or to review most of the
Harmonised Edition, 1st Edition,
construction drawings. Geneva, 2006
o If the amount of each interim 9. Garner, Bryan A., “Black’s Law
payment is to be determined by an Dictionary”, Thomson West, St.
official or other intermediary Paul , 2004
10. Hardjomuljadi, Sarwono, “Pre
CONCLUSION Contract Strategy for Minimizing
Construction Claims Impact on
1. Both FIDIC CC for EPC/Turnkey and Hydro Electric Power Plant
FIDIC CC for Construction allowed the Projects in Indonesia” ,
additional contract price. Tarumanagara University, Jakarta,
2. FIDIC CC for EPC/Turnkey not 2009
suitable for underground works 11. Hardjomuljadi, Sarwono, “The
3. In FIDIC CC for EPC/Turnkey the Metamorphosis of FIDIC GCC
issuance of construction working Clauses and the Main Causal
drawings mean the instruction, so if Factors of Construction Claims in
there are differences from the original Indonesia”, Paper Presented at
drawings, it could be classified as FIDIC Asia-Pacific Contract Users’
variation order. Conference, Hong Kong, 29-30
June 2009
12. Hardjomuljadi, Sarwono;
Abdulkadir, Ariono and Takei,

22 | K o n s t r u k s i a
EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENT (Sarwono)

Masaru, “Construction Claim 14. Martin, Elizabeth A. and Law,


Strategy based on FIDIC Jonathan, “Dictionary of Law”,
Conditions of Contract”, ISBN:979- Oxford University Press, New
97749-2-6, Polagrade, Jakarta, York, 2007
2006. 15. Standards Australia: “General
13. Indonesia State Electricity Conditions of Contract AS 4000-
Corporation, Projects 1997”, amendment 3-2005
Information, 2010

23 | K o n s t r u k s i a

You might also like