You are on page 1of 2

LAPORAN HARIAN HSE

Project : PETROCHINA JABUNG INTERNATIONAL LIMITED

Weather Date & Time

6:00 Cerah 9:00 Cerah 12:00 Cerah 15:00 Cerah 30 Okt 2022
8:00 Cerah 11:00 Cerah 14:00 Cerah 18:00 Cerah 06:00-18:00 WIB

LOCATION ACTIVITIES
Meeting Koordinasi KPI
Update Daily Report
Betara - Geragai

MAN POWER TOTAL HOURS OVERTIME REMARKS


Projerct Manager 1 12
Admin 6 72
HSE 2 24
Field Coordinator 2 24
S.R.O 1 12
Security 228 2736
TOTAL TODAY 240 2880 0 0
TOTAL PROJECT PREVIOUS TODAY CUMMULATIVE
SAFE MAN HOURS 0 2880 2880
HSE INFORMATION
1 ACCIDENT/INCIDENT
1.1. Fatalities = 1.7. Light vehicle =
1.2. LTI's = 1.8. Fire =
1.3. Medical Treatment Incident (MTI) = 1.9. Environmental =
1.4 First Aid =
1.5 Nearmiss = 24
1.6 Equipment =

2 EQUIPMENT
No TYPE TOTAL WORKING HOURS REMARKS
1
2
3
4
5
LAPORAN HARIAN HSE

Project : PETROCHINA JABUNG INTERNATIONAL LIMITED

Weather Date & Time

6:00 Cerah 9:00 Cerah 12:00 Cerah 15:00 Cerah 30 Okt 2022
8:00 Cerah 11:00 Cerah 14:00 Cerah 18:00 Cerah 06:00-18:00 WIB

LOCATION ACTIVITIES
Meeting Koordinasi KPI
Update Daily Report
Betara - Geragai

TOTAL
3 OTHERS
No TYPE TOTAL REMARKS
1
2
3
4

Prepared by, Approved by,

Alvadika Y / Arsonsyah P / Indra G Asnawi Sanjaya


HSE Project Manager