Date : 22-03-2022
❖ On 23-03-2022 Scaffolding alteration for shell side ‘4’number of baffle spotted area
window cutting purpose.
❖ On 23-03-2022 Baffle Spotted area insulation removed upto 17:00 Hrs
BAFFLE SPOTTED AREA:
Date: 23-03-2022
Date: 24-02-2022
4th BAFFLE INSIDE VIEW:
Date: 24-03-2022
3rd BAFFLE INSIDE VIEW:
Date:24-03-2022
❖ On 25-02-2022 3rd and 4th Baffle window cut down
❖ On 25-02-2022 All baffles and Shell Bottom manhole inside accumulated sludge
cleaned.
❖ On 25-02-2022 Tubes cutting work started from bottom to 4th Baffle inside tubes (22
number of 2m lengthy tubes cut down.)
2nd BAFFLE INSIDE VIEW:
Date:25-02-2022
Date:25-02-2022
Date: 25-03-2022
3rd BAFFLE:
2nd BAFFLE:
1st BAFFLE:
Date: 25-03-2022
Date:25-03-2022
CUTTED TUBES:
HARD SCALE FORMED ON TUBE INNER SURFACE
Date: 25-03-2022
❖ On 26-03-2022, 49 Tubes (2m Lengthy tubes) removed, so far 77 tubes removed. (from bottom to 4th Baffle
segment)
❖ On 26-03-2022, Top Tubesheet area grinding work being done.
❖ On 27-03-2022, 200 Tubes (2m Lengthy tubes) removed, so far 277 tubes removed. (from bottom to 4th Baffle
segment)
❖ On 27-03-2022, Top Tubesheet area grinding work being done.
❖ On 28-03-2022, 67 tubes (2m Lengthy tubes) removed, so far 344 tubes removed. (from bottom to 4th Baffle
segment)
❖ On 28-03-2022, Top Tubesheet area grinding work being done.
BOTTOM TO 4TH BAFFLE TUBES REMOVED SEGMENT VIEW:
❖ On 28-03-2022, 30 Tubes (2m Lengthy tubes) removed, so far 30 tubes removed. (From Top to 4th Baffle
segment)
❖ On 29-03-2022, 37 Tubes (2m Lengthy tubes) removed, so far 67 tubes removed. (From Top to 4th Baffle
segment)
❖ On 29-03-2022, Top Tubesheet area grinding work being done.
❖ On 30-03-2022, 277 Tubes (2m Lengthy tubes) removed, so far 344 tubes removed. (From Top to 4th Baffle
segment)
TOP TUBESHEET TO 4TH BAFFLE SEGMENT TUBES REMOVED SEGMENT VIEW:
Date: 29-03-2022
❖ On 30-03-2022, 154 Tubes (2m Lengthy tubes) removed, so far 154 tubes removed. (From 4th Baffle to 3rd
Baffle segment)
❖ On 30-03-2022, Bottom Tubesheet Area grinding work being done.
1ST BAFFLE TO 2ND BAFFLE SEGMENT TUBES REMOVED SEGMENT VIEW:
Date: 31-03-2022
❖ On 30-03-2022, 114 Tubes (2m Lengthy tubes) removed, so far 114 tubes removed. (From 1st Baffle to 2nd
Baffle segment)
❖ On 31-03-2022, 230 Tubes (2m Lengthy tubes) removed, so far 344 tubes removed. (From 1st Baffle to 2nd
Baffle segment)
❖ On 31-03-2022, 344 Tubes (2m Lengthy tubes) removed, so far 344 tubes removed. (From 2nd Baffle to 3rd
Baffle segment)
❖ On 01-04-2022, 344 Tubes (2m Lengthy tubes) removed, so far 344 tubes removed. (From 3rd Baffle to 4th
Baffle segment)
❖ On 01-04-2022, Bottom Tubesheet Grinding being done.
❖ On 02-04-2022, Top and Bottom Tubesheet Grinding being done.
❖ On 03-04-2022, Top and Bottom Tubesheet Grinding being done.
❖ On 04-04-2022, Top and Bottom Tubesheet Grinding being done and all baffle plates cleaning done.
❖ On 05-04-2022, Top and Bottom Tubesheet Grinding completed.
Date:05-02-2022
ALL BAFFLE PLATES CLEANING:
Date: 04-04-2022
Date:04-04-2022
❖ On 05-04-2022, Bottom Tubesheet Chamfering completed
❖ On 06-04-2022, Top Tubesheet Chamfering completed
TOP AND BOTTOM TUBESHEET CHAMFERING:
CHAMFERING/
V-SHAPED
GROOVE
Date:06-04-2022
❖ On 07-04-2022, Bottom Tubesheet Internal Diameter(51.35mm) of Bore checked by Bore Dial Gauge by
inspection Department.
❖ On 08-04-2022, Top Tubesheet Internal Diameter(51.35mm) of Bore checked by Bore Dial Gauge by
inspection Department.
❖ On 08-04-2022, After getting clearance from Inspection Department, Tubes insertion started by manual
lifting.
❖ 10 metres height Scaffolding Erected from top dish for tube lifting purpose.
❖ Total scaffolding height erected from Bottom end to top 24 metres.
Date: 14-04-2022
❖ On 14-04-2022, 6mm tube projection checked for Top and Bottom Tubesheet as per OEM Drawing by
inspection department and then clearance given for TIG Welding.
❖ On 14-04-2022, Bottom Tubesheet 138 Tubes, so far 138 Tubes TIG welding completed.
❖ On 15-04-2022, Bottom Tubesheet 94 Tubes, so far 232 Tubes TIG welding completed.
❖ On 16-04-2022, Bottom Tubesheet 112 Tubes, so far 344 Tubes TIG welding completed.
❖ On 17-04-2022, Top Tubesheet 150 Tubes, so far 150 Tubes TIG welding completed.
❖ On 18-04-2022, Top Tubesheet 160 Tubes, so far 310 Tubes TIG welding completed.
❖ On 19-04-2022, Top Tubesheet 34 Tubes, so far 344 Tubes TIG welding completed.
TIG WELDING:
TOP TUBESHEET AREA TIG WELDED TUBES:
Date:18-04-2022
Dye Penetrant Test:
Date: 19-04-2022
❖ On 19-04-2022, Dye Penetrant Test Checked for TIG Welded Tubes by inspection department and then
clearance given for Flaring.
❖ On 20-04-2022, Doom welding and flaring Done for top and bottom tubes.
❖ On 21-04-2022, All cut open baffle area windows welded back.
NEW TUBES INSIDE VIEW:
NEWLY INSTALLED ATA-2022 CHE TUBE INLET DUCT CATCH POT :
STIFFNER PLATE
OBSERVATIONS AFTER ATA-2022:
DATA OF CHE TUBE PRESSURE DROP AFTER ATA-2021
DESIGN DP : 230 mmwc
PRESSURE DROP
DATE (mmwc) LOAD(RPM)
18-07-2021 700 6700
22-07-2021 720 6500
26-07-2021 750 6900
15-08-2021 815 6900
19-07-2021 830 6900
25-08-2021 870 6900
13-09-2021 890 6900
26-09-2021 890 6900
03-10-2021 900 6900
10-10-2021 930 6500
18-10-2021 950 6800
24-10-2021 930 6500
21-11-2021 950 6500
12-12-2021 1050 6900
21-12-2021 1120 6500