You are on page 1of 160

1 Introduction – protect and survive

2 Basic construction guidelines

3 Design of Concertainer structures

4 Fill selection and characteristics

5 Preconfigured structures

6 Improvised structures

7 Maintenance and repair

8 Product technical information

9 Trial information

10 Packing and shipping

11 Conversion tables

12 Contacts
1
Introduction –
protect and
survive
Introduction – protect and survive 1.01

HESCO® Concertainer® has Delivered flat-packed on standard


been a key component in timber skids or pallets, units
providing Force Protection since can be joined and extended
the 1991 Gulf War. using the provided joining pins
and filled using minimal
Concertainer units are used manpower and commonly
extensively in the protection of available equipment.
personnel, vehicles, equipment
and facilities in military, Concertainer units can be
peacekeeping, humanitarian installed in various configurations
and civilian operations. to provide effective and
economical structures, tailored
They are used by all major to the specific threat and level
HESCO Construction Guide for Engineers

military organisations around of protection required. Protective


the world, including the UK structures will normally be
MOD and the US Military. designed to protect against
ballistic penetration of direct fire
It is a prefabricated, multi- projectiles, shaped charge
cellular system, made of warheads and fragmentation.
Alu-Zinc coated steel welded
mesh and lined with non-woven
polypropylene geotextile.
Introduction – protect and survive 1.02

Protection is afforded by the fill In constructing protective


material of the structure as a structures, consideration must

HESCO Construction Guide for Engineers


consequence of its mass and be given to normal structural
physical properties, allied with design parameters.
the proven dynamic properties
of Concertainer units. The information included in this
guide is given in good faith,
Users must be aware that the however local conditions may
protection afforded may vary affect the performance of
with different fill materials, and structures. HESCO Bastion Limited
may be further varied by cannot be held responsible for
moisture content. This guide will failures of structures beyond the
provide general guidance, with existing material warranty against
an emphasis on the design and manufacturing defects.
construction practices
applicable to structures built As with any structure,
from Concertainer units. More maintenance may be required
detailed reference material may to ensure continued effective
be required for information on long-term service.
weapon-effects data and
comparison of fill material. HESCO Bastion Ltd can provide
design, training, supervisory
and consultancy services.
Introduction – protect and survive 1.03

A 10m long wall can be built


from a Mil® 1 Concertainer unit
by two men with suitable
material-handling equipment,
in less than 20 minutes.
An equivalent wall of 1,500
HESCO Construction Guide for Engineers

sandbags would take 10 men


seven hours to build.
Introduction – protect and survive 1.04
The Mil range

HESCO Construction Guide for Engineers


Introduction – protect and survive 1.05
Using this manual
Warning
This guide was published in
2010; it replaces all previous Statements presented in
this style warn of the danger
versions of the HESCO
of a particular action or lack
Construction Guide for Engineers of action. These statements
and the HESCO Bastion should be followed, as
Technical Information booklet. failure to do so could result
in injury or death.
Amendments to this guide will
be issued from time to time.
Please see the next page for
instructions. Safety
HESCO Construction Guide for Engineers

Statements presented in
This guide includes statements this style advise certain
on safety issues and information actions or approaches to
tasks. Failure to follow the
on correct procedure. Examples
advice could result in a
of how these statements failure of the product
appear and what they constitute and/or danger to users.
are shown to the right.

Note: Statements that provide


general information about an
issue or that draw attention to
a point of detail are presented
in this style, as emboldened
text preceded by ‘Note:’.
Introduction – protect and survive 1.06
Amendments

Amendments to this guide will


be posted at:

www.hesco.com/amends

Please ensure that once


amendments are incorporated
into this document they are
recorded as such in the table
below.

HESCO Construction Guide for Engineers


Amendment record

Amendment number By whom amended Date of insertion


Introduction – protect and survive 1.07

Notes
5mm
HESCO Construction Guide for Engineers
2
Basic
construction
guidelines
Basic construction guidelines 2.01
Health and safety - A minimum number of persons
Task commanders must ensure should be employed when
that all relevant and practical carrying out tasks at height.
health and safety precautions are
- Keep good site organisation.
taken. The main risks to health
and safety during the building of - Ensure personnel only lift the
Concertainer structures, in weight that they are safely
addition to any tactical risks able to.
that may be present, are:
- Provide a properly briefed and
competent banksman for the
- working at height.
loading equipment. He is to
- personnel working in close ensure correct employment of
HESCO Construction Guide for Engineers

proximity to plant equipment. the loading equipment, correct


placement of the fill material
- manual handling injuries, back
and that working areas for the
strain, cut hands etc.
loading equipment are free
- risk of injuries from the elements, from personnel.
cold or heat injuries.
All personnel should be fully
- collision between personnel briefed on the task, including:
and loading equipment/
- safe methods of work.
crushing injury.
- safety around moving loading
Simple precautions should be equipment.
taken to ensure a safe build,
- manual handling techniques.
such as:
- work positions when working
- Only qualified and properly
above ground level.
trained equipment operators
should operate the loading
Site supervisors must ensure
equipment, when used.
that they have sufficient control
- Ladders, when used, should measures in place to protect
be secured at the top and their personnel from the risks
bottom and be fit for purpose. that may be present on the site.
Basic construction guidelines 2.02
Basic equipment
There is little need for special
tools when building structures
and walls from Concertainer
units. The following list shows
basic items which are either
required or are useful:

- shovels (must have)

- multi-tool (desirable)

- tape measure (desirable)

HESCO Construction Guide for Engineers


- string line (desirable)

- small jemmy bar (desirable)

- bolt croppers (desirable)

- knife (must have, supplied on


pallet)
Basic construction guidelines 2.03
General Warning
A Concertainer unit is a simple
product that is used to create Structures built in a hasty
manner due to operational
effective and economical
circumstances must be
protective structures. The routinely inspected to ensure
guidelines contained in this that they are structurally
publication will refer to “normal” sound and do not present a
conditions of expected use in hazard to those working or
living around them.
operational situations.

The tactical and operational a number of simple steps are


situation may however dictate followed during the construction:
that speed of build is more
HESCO Construction Guide for Engineers

important than properly prepared - firm level foundations


foundations and the use of a
- adequate drainage
carefully selected fill. In this case
the life of the structure may be - use of appropriate fill
reduced. The use of a poor fill
- Concertainer units laid out,
material may require the
line and level checked
structure to be wider to ensure
that it provides the level of - correct joining of units
protection required.
- tucking in geotextile flaps

Once erected the service life of - bottom centre of the units


structures built from Concertainer pulled out after the first
units depends upon how well they 150mm of fill is placed
were built, local environmental
- fill material placed in layers
conditions and the maintenance
of 150mm max depth for first
regime implemented.
layer and 300mm max for
subsequent layers
The building of Concertainer walls
is a relatively simplistic operation. - fill material is spread and
However, to get the best from compacted before placing
the material it is imperative that further layers
Basic construction guidelines 2.04
Site considerations, An improved foundation may be
foundations and drainage required when:
The location where the
structure will be built will - the planned structure is large.
normally be dictated by
- the structure is to be in place
operational requirements in
for more than six months.
response to the nature of the
threat and the position of - the soil to be built on is weak
assets to be protected. and is unlikely to support the
weight of the wall to be built.
In most cases site preparation will
be required. The level will depend The strength of the ground can
on local conditions, wall design be confirmed by using a cone

HESCO Construction Guide for Engineers


and/or time that the wall is penetrometer to ascertain the
expected to be in service. CBR1.

The most basic requirement is 1


CBR, or California Bearing
a relatively level surface with a Ratio – measure of the ground’s
base of sufficient strength to ability to support loads.
support the structure. Where
ground preparation is required
the minimum procedure would
be to strip all organic or topsoil
material and replace with a
granular fill material.
Basic construction guidelines 2.05

For long walls, the inherent


flexibility of Concertainer units
will allow the structure to
conform to moderate ground
contours.
HESCO Construction Guide for Engineers
Basic construction guidelines 2.06
Foundations - Line the trench with a
Local conditions may vary, but geotextile (minimum weight
a basic foundation for those 200 g/m2) or preferably a
without the resources to design Geogrid1.
one can be constructed, as
- Backfill the trench in layers
shown in Figure 1.
with coarse graded fill and
compact well.
- Excavate a trench 0.5m (1'8")
deep, extending at least 0.5m
(1'8") beyond the footprint of
the structure all around.

HESCO Construction Guide for Engineers


0.5m
(1'8")
| |
|

0.5m (1'8")
|

Base Fill Geogrid

Figure 1 Diagram showing improved foundation layout

1
Geogrid – adds strength to
a weak subgrade and will
enable it to support much
heavier loads.
Basic construction guidelines 2.07
Drainage weakened by excessive moisture.
HESCO Concertainer units form The issue of drainage should
a very effective dam so care not be ignored.
must be taken to ensure that
drainage is provided where Culvert pipes can be placed
required. Correct drainage will through the units to allow water
also ensure the base that the to be passed from one side
wall is built on will retain its of a wall to the other in a
strength and will not be controlled manner (see Figure 2).
HESCO Construction Guide for Engineers

HESCO Wall

Ground level

Culvert pipe fitted with welded


mesh (optional)

Culvert pipe bedding


Figure 2
Basic construction guidelines 2.08
Basic construction techniques - Pull the unit out to its full
Whether the structure is a length. Check it is in the
simple, single-course wall or a correct position (Figure 5).
more complex structure, basic
- Adjust the outer walls of the
construction techniques are still
unit so that they are parallel.
the same:
- Make any joints or extensions
- layout required before filling the unit
(see Joining).
- joining

- forming corners and curves Note: A number of Concertainer


units can be split into two
- filling
segments whilst still on the

HESCO Construction Guide for Engineers


pallet. This is achieved by
Layout removing the orange tagged
pins. This facilitates easier man
- Units are delivered to site, handling of the units.
flat-packed on pallets.

- Units are lifted off the pallet


Safety
and placed in the desired
location. Ensure all personnel are
properly briefed on the
- Concertainer unit placed on correct method of lifting
the ground horizontally with and carrying weight.
the arrow pointing away from Persons should only lift
and carry the weight that
the desired direction the wall
they feel comfortable with.
is to be erected (Figure 3).

- Two men each grasp the end


panel and together move in
the desired direction. The unit
will concertina from the horizon-
tal to the vertical and become
self supporting (Figure 4).
Basic construction guidelines 2.09 Basic construction guidelines 2.10
Figure 3 Joining vertically
Place the unit in the stacked units
desired location Joining is achieved using the
supplied hog rings.

- Fill the bottom unit to within


approximately 100mm (4")
from the top (Figure 10).

- Place the upper units and


pull out (Figure 11).
Figure 10
Figure 4
Pull up and out Suggested positions for hog rings

HESCO Construction Guide for Engineers


Figure 5
Pull out and check position

Figure 11

Note: Hog rings should be fitted every 150 – 200mm (6 – 8")


approximately. This would require two hog rings per Mil 2 side panel
and four per Mil 1 side panel.
Basic construction guidelines
Joining Figure 9
Most walls will require
Concertainer units to be joined
end to end. This is achieved by
using the supplied joining pins.

- Butt together the units to be


joined and overlap and
interlock the coils on each
butted corner (Figure 6).
Figure 6 Butt together and
- Insert the supplied joining pin
overlap coils
through the overlapped coils,
HESCO Construction Guide for Engineers

ensuring that it connects the


coils fully and that it is fully
inserted (Figure 7).

Note: The joining operation must


be carried out prior to placing
fill in any of the cells to be joined. Pull out panel centres around 100mm (4")
Care should be taken to ensure after fill placement (see page 2.14)
that units are horizontally
aligned before joining.
Figure 7 Place joining pins
Before filling, ensure all
geotextile flaps at the base of
the unit are tucked in (Figure 8).

If a single tier is required, filling


can start after all units in a
run are aligned and joined.
Compacting must be undertaken,
as shown in Figure 9, for every
300mm (1') lift of fill. See p. 2.14 Spread and compact
for the correct approach to filling. Figure 8 Tuck in flaps at base each layer of fill
Basic construction guidelines 2.10
Joining vertically
stacked units
Joining is achieved using the
supplied hog rings.

- Fill the bottom unit to within


approximately 100mm (4")
from the top (Figure 10).

- Place the upper units and


pull out (Figure 11).
Figure 10

Suggested positions for hog rings

HESCO Construction Guide for Engineers

Figure 11

Note: Hog rings should be fitted every 150 – 200mm (6 – 8")


approximately. This would require two hog rings per Mil 2 side panel
and four per Mil 1 side panel.
Basic construction guidelines 2.11

Figure 12 Figure 13
HESCO Construction Guide for Engineers

Figure 14 Figure 15

- Line up the upper cells with - Tuck the welded mesh of the
the lower ones (Figure 12). upper unit into the lower. Fit
and rotate a hog ring enclosing
- Locate the top welded mesh
the top strut of the lower cell
strut under the stapled
and bottom strut of the upper
geotextile of the lower cell.
cell (Figure 14).
Make a small, horizontal cut
under it and a vertical cut up - Tuck any geotextile from the
through the geotextile with upper unit into the lower prior
the supplied knife (Figure 13). to filling (Figure 15).
Basic construction guidelines 2.12
Corners and curves
There are various methods of
making corners and curves with
Concertainer units.

Where a curve is required, pull


out the centre coils on each cell
until you achieve the desired
curve – see Figures 16 and 17.

Note: Only pull the centre Figure 16


coils outward when creating
curved sections of wall;

HESCO Construction Guide for Engineers


pushing the centre coils
inward creates a wall section
with less than the minimum
protective thickness.

Figure 17 Pulling out the centre coils to create curved walls


Basic construction guidelines 2.13
Alternatively, for angled corners,
fold in one complete side panel
and secure by overlapping the
coils and inserting a joining pin
(Figure 18).

Note: This method is only


applicable to units with a
split side panel, such
as the Mil 1.
HESCO Construction Guide for Engineers

Figure 18 Folding the centre coil in to create a 45 degree corner

Where a right angled corner is


required, join two units at 90
degrees by meshing the coils
and inserting the joining pins, as
previously described (Figure 19).

Figure 19
Basic construction guidelines 2.14
Filling It is important that the unit is
The filling of a basic Concertainer checked for correct position,
wall should be commenced with line and level prior to filling. The
placing no more than 150mm diagram assumes that the
(6") of material in the order loading equipment will straddle
shown in the diagram below. two cells at once.

Note: It is important that the


bottom centre of each cell is
pulled out after the first layer of
material has been placed and
spread, as shown at the
bottom of the diagram. 150mm

HESCO Construction Guide for Engineers


max.

End cells

End cells

On longer walls
centre cells next

Place 150mm (6")


of fill in all others Pulling out
bottom
centre
Basic construction guidelines 2.15
Once the centre coils are pulled Walls which will have another
outward subsequent layers of unit placed on top should be
fill should be placed in depths filled to approximately 100mm
no greater than 300mm. Fill must (4") of the top of the unit. This
be spread inside each cell and allows for the subsequent
then manually compacted by foot joining of the units and ensures
(see page 2.09). Placement of that the geotextile flap at the
this layer should start at the cell base of the unit forms a seal.
indicated in diagram A below
and then continue along the full Units should be filled to the top
length of the wall. Once 300mm when they will form the top
(12") has been placed in the full layer or where subsequent
length, filling should recommence layers to be built on top form a
HESCO Construction Guide for Engineers

from the very end cell, as pyramid. See Building Higher


shown in diagram B. Walls, later in this section.

Note: No cell should


ever contain more
than 300mm (12") of
material than its
neighbour. Failure to
comply will result in
deformation of
Concertainer walls.

Note: Stand-alone
walls which will not
be subjected to a
subsequent load need
not be compacted.
Basic construction guidelines 2.16
Further construction normally be at the centre coil
techniques if one is fitted. The coil must
be opened at the top and
Dividing and shortening bottom to facilitate its removal.
It is likely when building walls
- Remove the coil by unscrewing,
and structures that the
counter-clockwise, completely
Concertainer unit may have to
(Figure 21). Repeat on the
be shortened. Units are easily
opposite side.
modified to suit this requirement.
The majority of units arrive on site - Cut the geotextile. Leave a
with the in-built ability to be split 150mm (6") overlap if
into two. This is achieved by incorporating into a wall (see
removing the orange tagged pins, page 2.18).

HESCO Construction Guide for Engineers


as described earlier. With the
- Separate the shortened
Mil 1 unit, for example, this will
segments (Figure 22).
result in two segments: one of
four cells and the other of five. - The coil can then be re-
inserted to secure the loose
Segments can be further side panels if required;
shortened simply by folding in alternatively, the loose ends
the end cells and securing by can simply be incorporated
overlapping the coils and fitting into the wall.
pins. This can reduce the
segment length by either one Note: If available, bolt croppers
or two cell lengths. A unit can can be used to cut the welded
be further shortened using the mesh to speed the above
procedure below: operation.

- Erect the unit as shown on Note: All of the above methods


page 2.09, but do not fill. result in the loss of a cell.

- Open the coil hinges by Shortening the EPW 1 unit can


bending at the desired location be achieved by removing the pin
of the cut (Figure 20), this will securing the side panels.
Basic construction guidelines 2.17

Figure 20 Figure 21

Note: Whenever possible


HESCO Construction Guide for Engineers

the end of a segment


that has been split
should be incorporated
into the wall.

Figure 22
Basic construction guidelines 2.18
Half segments The EPW 1 unit is split by remov-
Walls built up to existing ing the pins at the centre of the
structures may not fit exactly, side panel and then refastening
therefore it may be necessary to the half cell to the end of the
split an end segment in half or unit. To add half a cell, remove
add an extra half segment to half a cell from a spare unit and
the end to fill the gap (see fix it to the end of the unit in use.
Figure 23).
Figure 23
- To shorten a segment by half,
unwind the two centre coil
hinges from the end cell of
the unit.

HESCO Construction Guide for Engineers


- Cut the geotextile, leaving a
150mm (6") overlap, as
shown. Fold in the two panels
still attached to the unit and
secure using hog rings.

- Rewind the hinges, butt the


three loose panels up to the
end panel of the unit.

- Fasten using joining pins.

To add a half segment to the end


of a unit, remove a half segment
from a spare unit and fit it to the
unit to be lengthened by following
the last two steps above.

Note: This method is only


applicable to units with a
split side panel, as shown.
Basic construction guidelines 2.19
Thicker walls
Thick walls are formed by
placing units side by side.
Any width of wall can be
constructed using this
method.

- Secure the adjacent units at


the ends using joining pins
(see Figure 24).

- Cut away a small section of


geotextile to expose the top
HESCO Construction Guide for Engineers

welded mesh strut of each


side panel to be joined
(Figure 25).

- Place a hog ring around the Figure 24


struts and twist the ring to
ensure it encloses both struts
(Figure 26). Repeat the process
for further hog ring connections
along the run (Figure 24).

Figure 25 Figure 26
Basic construction guidelines 2.20
Building higher walls
The building of higher walls will
normally require a pyramid type
structure to be formed. This is by
far the best means of creating a
competent high structure.

- Make sure the ground is level


and firm before proceeding to
build a tall wall. Figure 27

- Deploy lower units and fill


completely to the top

HESCO Construction Guide for Engineers


(Figure 27).

- Place and join the units for


the second layer and fill them
completely (Figure 28).

- Place and join the units for


the third layer and fill them
completely (Figure 29).

Figure 28
Note: There is very little vertical
joining required on a structure
of this type.

Examples of pyramid type walls


and possible use are shown on
page 2.21.

Figure 29
Basic construction guidelines 2.21

Mil 1 – 2 1. Mil 1 and Mil 5 on top. Protective


Typical perimeter wall. wall around accommodation units.
HESCO Construction Guide for Engineers

Mil 3 – 2 1. Mil 3 – 3 2 1.
ECP or perimeter wall. Perimeter wall.

Mil 1 – 3 2 1. Mil 7, 8 and 9.


Perimeter wall. Aircraft revetment kit.
Basic construction guidelines 2.22
Building multistorey - Lay out, join and fill the lower
vertical walls unit to around 100mm (4")
Multistorey vertical walls are from the top.
sometimes required for a
- Place and join the upper unit
number of reasons, such as:
using the hog rings.

- the desire to present a - Ensure the welded mesh from


vertical wall on the hostile the upper unit is inside the
side. mesh of the lower unit.

- a high wall being required,


Warning
but a very small footprint
available to build on. Wall height should not

HESCO Construction Guide for Engineers


exceed two times the base
width. Failure to comply
The main rule regarding the with this requirement may
building of these walls is that result in an unstable and
the height of the wall must dangerous structure.
never exceed 2 x the width of
the base. For example, a wall
with a 1m (3'3") wide base
Warning
should not exceed 2m (6'6")
high. Mil 1, Mil 1.9, EPW 1, Mil 7
and Mil 10 should not be
stacked vertically.
The sequence for building a
multistorey vertical wall is as
previously described in this
section:
Basic construction guidelines 2.23 Basic construction guidelines 2.24
Increased stability of Construction planning basics In the main, large rocks or
thinner walls stones should be avoided as
Due to a number of factors you Fill material during a large blast they may
may be required to build a tall, The fill material used in building present a secondary
thin wall. In order to increase Concertainer walls has a fragmentation risk. However,
the stability of thinner defence significant bearing on the walls’ large rocks have been used
walls, various alternative layouts protective qualities. Generally, where the threat has been
can be used, as shown. the ideal fill is a sand/gravel mix. accurately defined and there is
This offers good construction no risk from secondary
For example, if a Mil 2 wall, characteristics, but, more fragmentation.
three storeys high, is adopted, importantly, offers a high degree
then the wall should be laterally of protection, with little Table 1 provides a brief outline
braced by intersecting walls or incidence of secondary of potential fill materials.

HESCO Construction Guide for Engineers


in-built stiffeners at no more fragmentation.
than 3.6m (11'10") centres. Table 2 provides a guide to
Fine material such as silt and quantities of fill required per
clay do not offer the same unit. It is a guide only and
protection and may, indeed, actual figures will depend on
require the wall to be wider. type of fill, construction methods
They are also not reliable and control, amount of loss etc.
construction materials.
Fill material is discussed in
Large clumps of earth should more detail in Section 4.
be avoided, as these may
damage the unit, as can Note: The figures in Table 2
large stones. account for expansion of the
|

unit, compaction of the fill and


loss of fill.
")
'10
(11
m
3.6
um
xim
Ma
|
Basic construction guidelines
Increased stability is important if The stability of the walls can be
you believe the wall may be further increased by the use of
struck face on by a hostile “anchor sections” in the
vehicle or the wall is close to alignment where space permits.
where personnel live or work.

3rd cell is folded in to create right angle


HESCO Construction Guide for Engineers

Mil 5 units in ‘zig-zag’ formation Mil 5 units joined at right angles

Anchor unit increases


wall stability

Mil 5 units in ‘lozenge’ formation Mil 5 units joined at right angles


Basic construction guidelines 2.24
Construction planning basics In the main, large rocks or
stones should be avoided as
Fill material during a large blast they may
The fill material used in building present a secondary
Concertainer walls has a fragmentation risk. However,
significant bearing on the walls’ large rocks have been used
protective qualities. Generally, where the threat has been
the ideal fill is a sand/gravel mix. accurately defined and there is
This offers good construction no risk from secondary
characteristics, but, more fragmentation.
importantly, offers a high degree
of protection, with little Table 1 provides a brief outline
incidence of secondary of potential fill materials.

HESCO Construction Guide for Engineers


fragmentation.
Table 2 provides a guide to
Fine material such as silt and quantities of fill required per
clay do not offer the same unit. It is a guide only and
protection and may, indeed, actual figures will depend on
require the wall to be wider. type of fill, construction methods
They are also not reliable and control, amount of loss etc.
construction materials.
Fill material is discussed in
Large clumps of earth should more detail in Section 4.
be avoided, as these may
damage the unit, as can Note: The figures in Table 2
large stones. account for expansion of the
unit, compaction of the fill and
loss of fill.
Basic construction guidelines 2.25
Table 1 – brief outline of fill materials

Very good Good Poor Do not use

Well graded Sand Fluid solids Large rocks


sand and gravel (i.e. snow)
Concrete Naturally Clay Large clumps
occurring soils of earth or soil
Organic
materials

Table 2 – fill material requirement per unit


HESCO Construction Guide for Engineers

Unit Type Unit Length No. of Cells Material Material


Per Unit Per Unit
Mil 1 10m 9 Cells 22m3 29yd3

Mil 1.9 3.3m 3 Cells 13m3 17yd3


Load Bearing

Mil 2 1.22m 2 Cells 0.5m3 0.6yd3

Mil 3 10m 10 Cells 13m3 16yd3

Mil 4 10m 10 Cells 20m3 26yd3

Mil 5 3.05m 5 Cells 1.2m3 2yd3

Mil 6 3.05m 5 Cells 4m3 5.6yd3

Mil 7 27.74m 13 Cells 190m3 248yd3

Mil 8 10m 9 Cells 25m3 33yd3

Mil 9 9.14m 12 Cells 9m3 12yd3

Mil 10 30.5m 9 Cells 66m3 87yd3

EPW 1 33m 30 Cells 103m3 135yd3


Basic construction guidelines 2.26
Manpower The above figures equate to
A crew of four to six is ideal to around one minute per cubic
support a mechanical loading metre (1.35yd3) of fill material to
shovel during filling operations. be placed.
The crew-members’ tasks are:
On the rare occasions when
- unpacking of materials and manual filling is required, it will
laying out of units. take four men around 14
minutes to fill one cell of a Mil 1
- joining units.
unit. As height increases then
- spreading and compacting fill an allowance must be made for
material. additional time.

HESCO Construction Guide for Engineers


- pulling out the bottom centres
This equates to one man
of cells.
placing approximately two cubic
- the direction of loading metres per hour. This does not
equipment. account for those persons
required to carry the fill to him.
Construction Time
Given ideal conditions, a basic
linear construction of a 10m
(32'10") length of Mil 1 will take
approximately 20 minutes using
one loading shovel and 4 men.
This will include removal of the
unit from the pallet, layout and
placement of the unit, and filling.

The above figure is with fill


material close by to the site of
use and with a wheeled loading
shovel with a bucket capacity
somewhere in the region of
1 – 2m3 (1.35 – 2.7yd3).
Basic construction guidelines 2.27
Plant The selected equipment must
Many different types of be able to raise the fill to the
equipment may be used for required height and place it with
placing the fill material. sufficient accuracy for efficiency,
safety and economy.
The type of equipment selected
will depend on a number of
factors, not least:

- the type of equipment


available.

- the space available to


HESCO Construction Guide for Engineers

manoeuvre.

- the height that the fill must be


lifted to.
For lower levels, wheeled front-
- the type of terrain.
end loaders are ideal, especially
- the distance that the fill must those fitted with 4:1 buckets.
be hauled. This also includes skid steer
loaders.
- the type of Concertainer unit
being filled.

Safety
Only qualified and properly trained equipment operators
should operate the loading equipment. Also, provide a properly
briefed and competent banksman for the loading equipment.
He is to ensure correct employment of the loading equipment,
correct placement of the fill material and that working areas for
the loading equipment are free from personnel.
Basic construction guidelines 2.28

For higher levels, excavators, Telehandler/shooting boom type


particularly those with loading equipment has proved
articulated or clamshell buckets, to be very effective and versatile

HESCO Construction Guide for Engineers


are effective. when loading Concertainer units.

Concrete skips, or elevated conveyor-type equipment have proved


successful for filling very high structures.
Basic construction guidelines 2.29
Removal A safe system of work must be
There may be a requirement to adopted and followed and
remove Concertainer protective should include the practices
structures. This operation is described below:
often undertaken using heavy
earthmoving plant to topple the - Working at height should be
walls and rip the welded mesh minimised.
away from the fill material. While
- When cutting the welded
this method works, it results in a
mesh always cut from the
mass of welded mesh that is very
bottom up.
difficult to handle and dispose of.
The following pages, describe two - Wear gloves and protective
alternative methods for removal. eye wear when handling cut
HESCO Construction Guide for Engineers

and removed welded mesh.

Warning - Competent banksmen to be


appointed to manage
Any demolition work can
be dangerous. It is earthmoving equipment and
imperative that a safe to ensure the operating area
system of work is adopted is kept clear of personnel.
and followed, as described
on this page. - Ensure dump trucks are
supervised whilst reversing.

- When an electric angle


The following risks may be
grinder or disk cutter is used
present during demolition work:
it should be supplied with
- working at height site-safe electricity.

- premature collapse of
structure

- manual handling injuries

- collisions between
earthmoving plant and
pedestrians
Basic construction guidelines 2.30
Removal – method 1
This method uses earthmoving
equipment fitted with a
demolition grab, grapple
attachment, orange peel grab
or timber grab attachment.
Orange peel
- Identify and remove all material
and equipment from the area
that is not to be disposed of.

- Cut all hog rings by bolt


croppers, angle grinder or

HESCO Construction Guide for Engineers


abrasive cutting tool.
Clamshell Demolition grab
- Cut all units into two-cell
lengths by bolt croppers or - Work in a methodical and
angle grinder. logical manner removing
two-cell segments, but
- Ensure all personnel are ensuring that remaining cells
removed from the area prior do not become buried in
to using the grab or grapple. dislodged fill.
- Remove each two-cell length - Surplus fill material may be
at a time with the demolition removed from the area by
equipment. As the segment is means of a loading shovel
removed it should be shaken once the grapple has
to remove as much of the fill progressed a sufficient
as possible. distance.
- The removed welded mesh - The above process should
should be stockpiled at the continue until the site is
site for later removal or placed cleared.
immediately into a dump truck
or skip for transportation to
Note: The welded mesh can be
the disposal area.
recycled where facilities exist.
Basic construction guidelines 2.31
Removal – method 2
This method involves removing
the welded mesh by hand and
is only suitable for low walls.

- Identify and remove all


material and equipment that
is not to be disposed of.

- Use bolt croppers or an angle - Remove all accessible panels


grinder to cut off all hog rings. on a cell, as described in the
previous step. The welded
mesh of the diaphragm wall
HESCO Construction Guide for Engineers

(between each cell’s geotextile)


should be removed as and
when it becomes free.
Do not cut the geotextile.

Direction of cut

- Beginning at the bottom, cut


the welded mesh all the way
up both sides adjacent to the - Use earthmoving equipment
corner coils. Then cut the to remove the fill (this will still
welded mesh across the top be contained in the geotextile).
just under the stapled flap. The removal of the fill, where
Continue cutting until the possible, should be carried
welded mesh panel can be out cell by cell.
removed.
- Continue until the site is
cleared.
Basic construction guidelines 2.32
Removal – method 3

Removal of EPW 1 units for


reuse or disposal
Identify and remove all material
and equipment that is not to be
disposed of. This method
involves extracting the removable
pins from the centre of one The plain end of the Y-shaped
side panel, splitting each cell. strap is fed around the cell then
MHE will be required to remove joined to the ratchet strap, which
the pins. is then hooked onto the far
corner coil of the cell adjacent to

HESCO Construction Guide for Engineers


the one being removed. Tighten
the straps, using the ratchet,
without distorting the coils.
Ensure only the pin on the
opposite panel to the ratchet
mechanism is removed. After
removing this pin, release the
ratchet strap, upon which the
cell will swing open to release
the fill material. All personnel
The ratcheted cell-removal must stand clear at this point.
straps must be fitted to each
cell, in turn, prior to pin
removal. The hooks on the ends
of the Y-shaped strap are
attached to the corner coil of
the cell to be removed, 1/3rd
from the top and bottom, on
the same side as the pin
selected to be removed, as
shown above.
Basic construction guidelines 2.33
Bulldoze the released fill material
away from the wall. Continue
this process until the wall
has been completely
removed. Remove the
EPW material, and clean,
inspect and repair any
damaged panels, as required.
Reassemble and re-palletise
the units ready for transportation
or storage.

Plan view of strap arrangement for removal of EPW 1 unit


HESCO Construction Guide for Engineers

Ratchet release Strap


operator Ratchet

EPW 1 unit
Pin to be removed
Safety
The ratchet must be on
the side opposite the pin
which is to be removed.
All other personnel to
stand clear before the
ratchet’s release.

Note: It is important the area around the cell to be split is free from
obstruction. This allows the cell to be opened freely.
Basic construction guidelines 2.34
In many instances HESCO
Concertainer units may be
delivered to site in RAID®
configuration.

RAID has been designed to


reduce the logistics burden of
supporting force-protection
missions on expeditionary
operations. In some cases
double the length of wall can be Concertainer units provided in
carried inside one RAID shipping RAID configuration using a
container than can be carried specially modified and

HESCO Construction Guide for Engineers


when units are transported configured 20ft container.
using conventional methods,
such as the units laid onto This arrangement allows the
timber pallets and then loaded easy splitting of the unit if a
into a normal 20ft ISO container. shorter length is required or,
indeed, breaks and corners are
The Concertainer units arrive required.
on site stood vertically inside a
specially modified and configured The deployment of the
20ft container. Concertainer unit from the RAID
Container can be achieved
The concertainer unit carried using two methods or a
inside the container is a combination of each.
continuous length for Mil 7 and
Mil 10 types and two continuous The first method is to use the
lengths in the case of a RAID 1 container as a storage unit.
unit. The units are made up of The container is opened up, the
five cell segments; each unit pulled out by hand and
segment is joined to the next by each five cell segment split from
means of two joining pins. the next. The segments can
Basic construction guidelines 2.35
then be placed onto a pallet or required for the construction of
into the bucket of an earthmoving walls using Concertainer units,
tractor for carriage to their the use of RAID can reduce this
place of use. This process to as little as two.
continues until the required
amount of Concertainer unit has Detailed instructions on how to
been removed. The remainder use the system are provided
of the unit is left on board for with each container.
future use and the container
resecured. The container complies with all
normal ISO standards with
The second method is achieved regard to transportation,
by pulling out the first 2 – 3 cells stacking and shipping.
HESCO Construction Guide for Engineers

of the unit, anchoring those


cells and then proceeding to Further explanation on all these
pull the container forward using topics can be found on the
a suitably sized vehicle, such as HESCO Training DVD. If you
an earthmoving tractor or require a copy, free of charge,
armoured vehicle. As the please email:
container moves forward the
unit is pulled out from the back technical@hesco.com
of the container against its own
weight. Splitting of the unit, to
allow the forming of breaks and
corners in the wall, is carried
out as previously described.

The use of RAID can reduce


much of the work which is
undertaken on the site of the
force-protection operation.
Whereas a section of four to
eight soldiers is normally
5mm

Notes
Basic construction guidelines
2.36

HESCO Construction Guide for Engineers


3
Design of
Concertainer
structures
Design of Concertainer structures 3.01
General means of creating stand-off will
It is possible to design and be required. This can be in the
construct walls that give form of Concertainer unit walls,
complete protection from ditches, fences, portable
weapons and threats such as barriers and earth bunds.
small arms fire, cannon rounds,
RPG, mortars and shrapnel and Concertainer units provide a
fragmentation from larger types proven, rapidly erected means
of shells or bombs. It is not, of creating barriers to enforce
though, possible to build a stand-off.
structure to totally protect
against the effects of blast from Another main aim of constructing
larger explosive devices. defence walls is to provide
HESCO Construction Guide for Engineers

However, the construction of a close-in ballistic protection for


competent defence wall may personnel and assets. In the
substantially reduce the blast simplest terms for ballistic
effects. For instance, the walls protection, the wall must extend
of a building immediately behind to interrupt the line-of-sight
a Concertainer unit wall may be from the firing position of the
subjected to a blast pressure potential attacker to all areas of
significantly lower than it would the target.
have been otherwise.
To provide some blast
One of the main aims in protection, the wall must be
constructing defence walls is to sufficiently high, long and
put distance between the target separated from the target to
and the potential site of charge attempt to deflect the blast
initiation. The creation of wave over and around it, whilst
“stand-off” is by far the best also protecting against
means of defence and in its penetration from fragments and
best form will negate the need shrapnel. It is generally accepted
for any walls at all. This ideal that a blast wall should be as
situation will unfortunately rarely high as possible but a minimum
be the case, so some other of 3 metres (9'10").
Design of Concertainer structures 3.02
The blast wave will re-form at a number of configurations that
some distance on the other have been proven through use,
side of the defence wall but it as well as some guidelines as to
will, of course, have reduced in configurations that should be
intensity due to the extra avoided. This section of the
distance it has had to travel. Construction Guide will provide a
number of proven configurations
Concertainer unit structures as well as guidelines for the
provide protection against the design of larger walls.
effects of weapons by
optimising the mass and Whilst it is possible to build
characteristics of the fill structures of virtually any height,
material. Field guides to force experience has led to the

HESCO Construction Guide for Engineers


protection normally provide conclusion that walls higher
guidance for the design of than 4.92m (16') require special
structures in terms of the care in their design and use of
thickness of various materials specialised equipment, which
required against defined threats. may not be readily available.
This will generally suffice for
operational structures. For very large or complex
structures, competent
For many applications a single engineering advice should be
course of the appropriate size sought as this guide does not
of HESCO Concertainer is the contain sufficient information
most effective solution in for such walls.
providing a protective structure.
For higher walls, stacking of
units is generally the solution.

A wide variety of stacking


configurations is possible,
particularly as the heights
increase. Experience has led to
Design of Concertainer structures 3.03
Design procedure Expected threat
The basic design parameters This will be a key determinant
required in the design of a in establishing the minimum
wall are: thickness and/or height
required for the wall. This may
- the threat expected and what
range from limited small arms
aspects you want the wall to
fire through mortar bombs right
mitigate against
up to very large VBIED. The use
- topography of vehicles to break through the
defence wall should also not be
- fill material available
overlooked. With regard to
- size, shape, layout and value attack, the desired mitigating
of the target to be protected effects which you wish the wall
HESCO Construction Guide for Engineers

to achieve should also not be


- type of Concertainer unit
overlooked. For instance, do
available (this may be dictated
you want the wall to:
by those already in theatre)

- available space to build on - disrupt the blast wave?

- interrupt primary
fragmentation from the
weapon?

- catch secondary
fragmentation?

- not break up and create


significant secondary
fragmentation?

- mitigate risk?

- eliminate risk?
Design of Concertainer structures 3.04
Topography Fill material
The lay of the land (topography) The fill material available will
may have a direct impact on influence the thickness of
the wall design. In simplistic the wall.
terms, if your base or asset that
you must protect is on the top Use of locally available fill is the
of a hill then theoretically the usual method for defences built
wall need not be as high to in the field. In this case an ideal
enable it to interrupt both line of fill material may not be
sight and direct line of fire. immediately available. This may
require an increase in width of
Conversely, if the camp is on flat, the wall to achieve the same
level ground or is, indeed, in a protective qualities.

HESCO Construction Guide for Engineers


depression, then walls will have
to be much higher to achieve the Good fill material must be used
same effect. when building structures with
an expected longer service life.

Safety
Care should be taken with
structure design when
using a poor fill material.
Use of poor fill may lead to
instability of the structure.
Design of Concertainer structures 3.05
Target to be protected Footprint available to build on
The target will dictate the plan The height to which the wall can
of the structure and the be built will sometimes be dictated
required height in a number by how much space you have
of ways. available for the wall’s base width.
A wall, for instance, that has a
- The layout of the targets. base width of 2m (6'6") should
This may be complex such not be more than 4m (13') high.
as attempting to provide
protection to existing
buildings, or may be much Safety
more straightforward in the
The height of a wall should
case of an ammunition
HESCO Construction Guide for Engineers

not exceed two times the


compound. base width. For instance,
a wall with a base width
- The size of the target. Length, of 1.5m cannot be taller
depth and height. than 3m.

- The position of the target in


relation to the attacker or
potential site of initiation of a
device. In some cases where
the target is well back from
the possible site of initiation
then multiple walls may be
required to provide the best
protection.
Design of Concertainer structures 3.06
Selection of wall configuration Heights of all other defensive
The following pages show structures must be decided
typical structure configurations upon by taking into account the
designed to protect against target to be protected,
clearly defined threats. It should topography and likely location
be noted that every situation is of the attacker. For example, a
unique, therefore the examples soldier who requires protection
shown are intended only as but must still be able to fire
a guide. over his Mil 1 unit protective
structure will only require the
Concertainer units are grouped structure to be one unit high;
with units of a similar width. whereas if you require complete
protection then it must be at

HESCO Construction Guide for Engineers


An example of the end of the least two units high.
structure is given against each
of the specified threats. In many When constructing higher
cases a more substantial structures the height should not
structure is required where the exceed two times the base width.
fill material is deemed to be
poor: clay, snow etc. A Mil 7 unit cannot be stacked
directly on top of another Mil 7
The heights of the suggested unit. To gain extra height when
structures are for illustration using Mil 7, either a pyramid
purposes only. However, the formation of Mil 7 can be used,
heights for air delivered bombs or smaller units should be
and VBIED walls should be used on top of the base Mil 7.
regarded as the minimum This rule also applies to Mil 1,
required. This is due to the Mil 1.9, Mil 6, Mil 10 and
likelihood of a large charge size. EPW 1 units.
Design of Concertainer structures 3.07
The tables on the following pages Note:
show the structures required to
provide protection against RPG7
specific threats. Each table has A 1m thick wall filled with
been derived from extensive good quality rock fill will
testing and trials by DERA (UK provide protection from a
MOD) and other leading testing RPG 7 warhead. However,
agencies worldwide. walls filled with all other fill
materials will require a wall of
The inclusion of these tables in at least 1.2m to provide
this document does not protection.
suggest that these structures
give guaranteed protection from Artillery
HESCO Construction Guide for Engineers

the threats specified. A 1m thick wall filled with


very good/good fill will
Further guidance on the use of provide protection from the
these tables can be sought effects of a close-in detonation
from HESCO Bastion Ltd. of a 155mm artillery round,
but the wall will burst if
subjected to a direct hit.
Safety
Air delivered bombs
A Mil 7 unit cannot be
stacked directly on top of Users must be aware that
another Mil 7 unit. To gain fragments from air delivered
extra height when using weapons may pass through
Mil 7 either a pyramid the very top layer of the wall
formation of Mil 7 can be
when filled with poor fill
used or smaller units
should be used on top of material.
the base Mil 7. This rule
also applies to Mil 1,
Mil 1.9, Mil 6, Mil 10 and
EPW 1 units.
Design of Concertainer structures 3.08

Mil 1 H 1.37m (4'6") W 1.06m (3'6")


EPW 1 H 2.1m (7') W 1.06m (3'6")
Mil 1.9 Load Bearing H 2.74m (9') W 1.06m (3'6")
Threat Very Good Fill/Good Fill Poor Fill
Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.09

Mil 1 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs

Configuration not applicable for EPW 1 and Mil 1.9 Load Bearing unit

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices

Configuration not applicable for EPW 1 and Mil 1.9 Load Bearing unit
Design of Concertainer structures 3.10

Mil 2 H 0.61m (2') W 0.61m (2')


Mil 5 H 0.61m (2') W 0.61m (2')
Mil 6 H 1.68m (5'6") W 0.61m (2')
Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.11

Mil 2 and Mil 5 (continued)


Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

Configuration not applicable for Mil 6 unit

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices

Configuration not applicable for Mil 6 unit


Design of Concertainer structures 3.12

Mil 3 H 1.0m (3'3") W 1.0m (3'3")


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.13

Mil 3 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.14

Mil 4 H 1.0m (3'3") W 1.5m (5')


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.15

Mil 4 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.16

Mil 7 H 2.21m (7'3") W 2.13m (7')


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.17

Mil 7 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery and
Mortars
(over 82mm)
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.18

Mil 8 H 1.37m (4'6") W 1.22m (4')


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.19

Mil 8 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.20

Mil 9 H 1.0m (3'3") W 0.76m (2'6")


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.21

Mil 9 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.22

Mil 10 H 2.21m (7'3") W 1.52m (5')


Threat Very Good Fill/Good Fill Poor Fill

Small arms
Single shot

Burst

HESCO Construction Guide for Engineers


Cannon
HE Volley

AP Volley

RPG7

Grenade
Design of Concertainer structures 3.23

Mil 10 (continued)
Threat Very Good Fill/Good Fill Poor Fill
Mortars
(up to 120mm)
For mortars larger
than 120mm use
Artillery table

Artillery
Up to 155mm in
contact
HESCO Construction Guide for Engineers

Air delivered
bombs
Designs will give
a high level of
protection against
bombs of up to
2000lbs.

VBIED*

*Vehicle Borne
Improvised
Explosive
Devices
Design of Concertainer structures 3.24
Selection of the pyramid 4.57m (15') wall with a base
configuration width of 2.13m (7'), and a
Once the three parameters and minimum thickness of 0.76m
the design table are analysed, (2'6"). This provides excellent
the length of the wall, its height resistance to ballistic and
and its minimum thickness will fragmentation penetration.
be known. Once the height and
minimum width of the structure
is decided upon, a configuration
can be designed.

For high walls the most


structurally sound design will be

HESCO Construction Guide for Engineers


based on a pyramid configuration.
The uppermost tier must be the
minimum thickness required to
defeat the specified threat.
Upper tiers should not be
higher than the lower tiers and Mil 7, 8 and 9.
ideally should be shouldered in Aircraft revetment kit.
by 300 – 600mm (1' – 2').

Typical pyramid structures Warning


A pyramid of one Mil 1 stacked The height of the wall must
on a base of two Mil 1 has not exceed two times the
become very common, base width. A Mil 1 unit
particularly for perimeter should not be stacked
directly on top of another.
protection. This again provides
This wall may become
good resistance to ballistic and unstable and collapse
fragmentation penetration. causing serious injury or
loss of life.
Designed specifically for aircraft
revetments, a pyramid of Mil 9,
on a Mil 8, on a Mil 7 creates a
Design of Concertainer structures 3.25

Mil7/Mil 1 perimeter wall Mil 7 wall post attack


HESCO Construction Guide for Engineers

Entry control point Mil 7, 8 and 9 aircraft revetment


Design of Concertainer structures 3.26

When using larger units in a


single course, a substantial
wall can be created very
quickly. This provides excellent
resistance to ballistic and
fragmentation penetration.

HESCO Construction Guide for Engineers


It also provides a substantial
physical barrier.
Design of Concertainer structures 3.27
Vehicle barriers shorter distance, a more
Concertainer units can be used substantial wall should be built.
in a number of configurations to A wall of 2 cells backed up by
form very effective vehicle 2 cells has been shown to stop
control barricades. These walls the same vehicle in a little
range from single cells used over 5m (16'5").
merely to slow and channel
traffic to walls designed and built The complete exclusion of a
to completely exclude vehicles vehicle from an area such as a
from entry to certain areas. camp, airfield, port or essential
services processing area may
Concertainer units have been require a much more substantial
tested by various agencies as a wall. This will typically be a
HESCO Construction Guide for Engineers

vehicle barricade. The use that single storey wall of double


the barricade is to be put to will thickness or a wall in a 2:1
dictate its design. configuration built from Mil 1
units or 2:2 Mil 3 structure.
A common structure built for a Similar configurations to these
short term vehicle check point have been tested in the US.
is a 2-cell Mil 1 wall. This is The tests were conducted to
used to form a serpentine or K12 standards, which is one of
chicane and is used only to the highest classifications that
channel and slow the vehicles. can be awarded in the US for
It is most commonly used vehicle barriers. The Mil 1 and
along with additional 2-cell Mil 3 unit have been awarded
sections. K12 Certification.

A single 2-cell Mil 1 structure These configurations will prevent


has been shown to stop a a cargo-carrying goods vehicle
cargo-carrying goods vehicle travelling in excess of 45mph
travelling in excess of 35mph (72.4kph) from bursting through
(56kph) in around 10 metres into the protected or controlled
(32'7") (Figure 1). Where you area (Figures 2 and 3).
wish to stop the vehicle in a
Design of Concertainer structures 3.28
Larger walls have been built and Further details on vehicle
tested to prevent much larger barriers can be provided on
vehicles entering areas. Vehicles request.
as large as 65,000lb (29.48
tonnes) travelling at 50mph
(80kph) have been stopped.

HESCO Construction Guide for Engineers


Figure 1

Figure 2 Figure 3
Design of Concertainer structures 3.29
Notes
5mm
HESCO Construction Guide for Engineers
4
Fill selection and
characteristics
Fill selection and characteristics 4.01
Selection of fill material Clumps can also damage the
The protective properties of unit during the filling process,
defence walls built from as can large stones and rocks.
Concertainer units are Large rocks or stones should
substantially defined by the be avoided as they may
characteristics of the infill become secondary fragmentation
material. Generally, the ideal fill in the event of a large blast.
is a sand/gravel mix. Offering a
high degree of protection with The table on the following
little incidence of secondary pages provides a brief outline
fragmentation, a sand/gravel on potential fill materials.
mix is easily handled. Fine
material such as silt and clay
HESCO Construction Guide for Engineers

makes filling more difficult, as


they do not flow easily from the
buckets of the loading shovels
and, in fact, may tend to clump
causing voids in the structure.
Fill selection and characteristics 4.02 Fill selection and characteristics 4.03
Characteristics of fill material

Fill Material Construction/Structural Stability Blast Protection Ballistic Protection

Concrete Generally excellent. Foundation Generally good unless blast Generally likely to provide the
Structural Concrete required for long-term stability. results in catastrophic failure of highest level of protection of
Lean Concrete the structure resulting in all the materials in this table.
Ground Impregnated dangerous secondary effects.
Aggregates

Crushed Rock Generally very good with suitable Generally good. Care should be Generally good. Unlikely to
Type 1 – Scalping foundation. Stability can be taken to avoid inclusion of large supersede concrete materials,
affected by moisture variations rocks which may form damaging but generally better than clays.
within the fill material. secondary projectiles.

Gravel, Sand Generally very good with suitable Generally good. Minimal Similar to crushed rock.
foundation. Stability can be contribution to secondary
affected by moisture variations projectile threat.
within the fill material.

Clay Generally only suitable for short-term Generally not as good as the Generally significantly inferior to
construction. The moisture content of materials above. materials above. The moisture content
the material may significantly influence of the material may significantly
performance (increased moisture = affect performance (increased
decreased performance). moisture = decreased performance).

Organic Matter Generally unsuitable and should only be Generally not as good as the Generally inferior to the materials
Peat used when alternative material materials above. above.
Top Soil unavailable.

Other Materials Only suitable for short-term applications Variable depending on the Variable depending on the
Ice Concrete (ice bound unless in a permanently cold nature and quality of material. nature/quality of fill.
Aggregate) environment.
Snow
Fill selection and characteristics 4.04
Selection of fill material In addition to wet fill having a
(continued) lower protection factor, if heavily
The selection of a poor fill saturated the resultant
material may be the only hydrostatic pressures can cause
realistic option given operational large and potentially damaging
or economic considerations; lateral forces to be generated. It
in this event, trade-offs in is recommended for structures
protective capability or service above 3m (9'10") high that fill
life will have to be considered. material be selected to contain
For example, the use of poor a maximum of 10% fines
fill may require a wall of greater (material passing a #200 or
thickness to achieve the desired 75mµ sieve).
level of protection.

HESCO Construction Guide for Engineers


Capping the exposed fill or
As important to the above are otherwise protecting against
changes to the moisture saturation is therefore highly
content of the fill material or recommended for large
foundation material after structures, particularly those
construction. This may that will be in service for an
adversely affect the protection extended period.
offered by the wall or its stability
and long-term durability. Note: Fine grained soils are
those which have more than
These effects may be prevented 35% by weight of a particle
by careful selection of fill material, size smaller than 0.06mm.
good compaction and protection These are a problem and
against the ingress of water. should always be avoided.

The geotextile used in HESCO


Concertainer is designed to be
permeable to water. This allows
for drainage of the fill material,
should water enter.
Fill selection and characteristics 4.05
Soil and rock in more detail 10m. In most cases once
This guide talks generally about treated (e.g. compacted) it will
soil and rock in a number of be capable of supporting light
areas, particularly with regard to engineering structures, such as
its protective capabilities. This Concertainer walls.
small section goes on to
elaborate a little on the iii) Rock
information already provided. Rocks are a mixture of minerals
This will enable the HESCO user which are generally high
to have a better understanding of strength. They derive this
the foundation and fill material. strength from grains of material
which are cemented together or
The term soil is used for from a mixture of interlocking
HESCO Construction Guide for Engineers

different material types: topsoil, crystals. Bed rock and crushed


soil and rock. These can be rock are very good at supporting
broadly defined as follows: engineering structures.

i) Topsoil The person responsible for the


Topsoil is the material which is construction of HESCO
a mixture of plant material and structures has an interest in
weathered mineral debris. It is these materials, since he must
generally in a layer between make decisions based on the
150 – 300mm (6-12") thick and material he is dealing with.
is not capable of supporting
engineering structures. Topsoil
Does this material need to be
ii) Soil removed prior to construction?
Soil is the generic term for What depth is it? Therefore,
loose geological deposits which how much good soil must he
are the result of the breakdown import to reinforce the
of rock. It can be excavated foundation?
without having to rip or blast
the deposits. It will not normally
be found in layers thicker than
Fill selection and characteristics 4.06
Soil Soil classification
Can the local soil be used to The materials which form soils
form the foundations and can it are divided into groups. Each
also be used as the fill material group contains only soil which
for the HESCO cells? What type is likely to perform or react in a
of soil is it? Does the standard similar manner to the other soils
thickness of the HESCO wall in the same group. This makes
have to be increased due to the it much easier for the engineer
local soil being of a particularly to predict what the soil group
poor quality? Is the soil going to will do when incorporated into
become unstable when subjected an engineering structure. This
to variations in moisture content? guide will very briefly explain
how to classify soils. The

HESCO Construction Guide for Engineers


Rock guidance should not be used if
Given the demands in a tactical designing other types of long-
theatre for construction materials, term or permanent structures.
it is unlikely that there will be
sufficient stocks of crushed rock Soils are first of all divided into
readily available for use in the two groups: coarse-grained and
construction of HESCO walls. fine-grained soils. Coarse-
Therefore, the person grained soils are those with
responsible for planning the particles above 0.06mm in size,
task must make an assessment forming at least 65% by weight
as to which material to use, of all the material present in the
based on the logistic effort sample. This material is then
required. Large rocks can be further sub divided into gravels
used in the construction of the (particle size 2 – 60mm) and
foundations but are not suitable sands (particle size 0.06 –
for filling Concertainer units, 2mm). The material type is
unless it is first to be crushed to normally decided upon by
a size not exceeding 50mm. laboratory testing. This entails
drying samples and then
passing them through a series
of sieves. Soils which have a
Fill selection and characteristics 4.07
similar weight of material structures. This material is
retained on each sieve are said extremely sensitive to changes
to be “well graded”; those that in moisture content. A change in
have the majority of the material moisture content can lead to a
retained on either one, two or dramatic change in the materials
three sieves are termed either ability to stand up. A foundation
“single size”, “poorly graded” or from this material, which may
“gap graded”. The single size have been thought to be sound,
would have all the particles can easily collapse with an
retained on only one sieve. increase in moisture content,
and Concertainer units filled
A well-graded material is by far with this type of material have
the best for the construction of been known to fail dramatically.
HESCO Construction Guide for Engineers

long term structures, since this


has the most efficient means of The following details a procedure
achieving mechanical interlock. that can be used to determine
The single size, poorly or gap the quantity of fines in a sample
graded material may still be of material being considered
useful when working with for use.
Concertainer units, and could be
used in the construction of the i) Take a sample
foundations or as a fill material. - Take a representative sample
of the material that you are
The particle size of 0.06mm is proposing to use.
about the smallest size that can
- Estimate the volume.
normally be seen by the human
eye. Particles below this size ii) Separate the gravel
are either clay or silt, neither of - Remove all particles larger
which is conducive to good than 2mm from the sample.
construction. It is highly
- Make an estimate of the
recommended that materials
volume that you have removed
with a fines content of more
in percentage terms against
than 10% should be avoided
the complete sample, eg 15%.
when building long term HESCO
Fill selection and characteristics 4.08
iii) Sedimentation test construction this initial settlement
- Break up a sample of the soil is taken up by compaction.
without gravel and place it in
a glass container to a depth Each soil or rock has a different
of around 25mm. capability with regards to GBC
and CBR. The GBC of an
- Add water to a depth of
igneous rock is very high and is
130mm and shake it well.
likely to be in the region of
- Allow the sample to settle for 1960KN, with weak clay only
30 seconds and then being able to withstand around
measure the depth of the 40KN.
settled material.
The moisture content at the

HESCO Construction Guide for Engineers


- The proportion that has
time of sampling will have a
settled is sand (0.06mm) and
huge influence on the results
that which is still in suspension
gained on the weaker soil types,
is fines (clay or silt).
such as sand containing more
If at this point you believe that than 10% fines. The wetter the
the proposed material has more soil is, the lower the reading.
than 10% fines then you should However, do not rely on a high
regard it as not suitable for use reading from a dry, weak soil
as a fill material for a long-term type as this soil will almost
structure. Nor should it be used certainly become wet at
for foundation work. sometime during the life of the
structure, and it will then lose
Ground Bearing Capacity strength. This may lead to a
(GBC) and California Bearing collapse of the structure.
Ratio (CBR)
A rock or soil which is subjected The GBC of soils with little or
to a bearing load within its no stones can be estimated by
capabilities should not show signs means of a cone penetrometer;
of indentation or collapse after its this equipment is available
initial settlement period. During within various engineer units in
Fill selection and characteristics 4.09
the military and is used by
some civilian organisations.
It will provide a CBR reading
which can then be roughly
translated into a GBC.

The following table very roughly


transfers CBR into GBC; it
should not be used for
technical engineering designs.
The table also attempts to
provide guidance as to what
CBR and GBC is likely to be
HESCO Construction Guide for Engineers

required to support a given


structure.

Required CBR ratings for Concertainer Structures

CBR (%) Approx Typical Concertainer Structure


GBC (t/m2)
1 1.9 Single storey Mil 3

2 3.5 Single storey Mil 1

4 6 1:1 Mil 8 or single storey Mil 7

5 7.5 3:2:1 Mil 1 or Mil 7 Aircraft Revetment Kit

7 10 20ft or 40ft Bunker Kit

11 14 Single EOPS
Fill selection and characteristics 4.10
Notes
5mm

HESCO Construction Guide for Engineers


5
Preconfigured
structures
Preconfigured structures 5.01
General Concertainer units and the
In addition to the standard required additional components
Concertainer units, HESCO tailored to create protective
Bastion Ltd provides several structures quickly and efficiently.
specialised products designed
to meet a number of
requirements identified by
operational users. A variety of
off-the-shelf sets has been
configured which include
HESCO Construction Guide for Engineers

HESCO Accommodation Bunker (HAB)


Preconfigured structures 5.02
Guard post/Sangar The interior space is 1.22m (4')
The components of this set by 1.8m (6'), with 1.98m (6'6")
provide a small emplacement of headroom. The complete set
with 0.61m (2') thick walls and is delivered on a single pallet
0.45m (1'6") of overhead cover. weighing 375kg (826lb).
Embrasure (firing/observation Detailed instructions for the
port) forms are included in the assembly of the guard post are
set, as are roof joists and supplied with the set.
waterproof roofing material.

HESCO Construction Guide for Engineers

Guard Post Kit


Preconfigured structures 5.03
Personnel and material bunkers highly recommended that an
Bunker sets have been escape hatch be provided by
developed to utilise 40ft and cutting a hole in the other end
20ft ISO containers. Walls are from the container doors.
constructed using reinforced Mil 1
sections of preconfigured Sea containers are not provided
lengths providing a wall with the sets. Detailed instructions
thickness of 1.09m. The roof for the assembly of the bunker
design provides 0.61m (2') of are included with the kit.
overhead cover. Material
bunkers provide access from The Concertainer units used for
one end of the bunker, while the lower layers of the walls are
personnel bunkers provide specially designed for this
HESCO Construction Guide for Engineers

access from both ends. application and therefore have


a higher bearing capacity than
For personnel bunkers using a a standard unit.
standard sea container, it is

20' Bunker Kit


Preconfigured structures 5.04
Containerised bunker kit Note: Although ISO containers
A containerised kit has been are not absolutely necessary
developed which offers an when building bunkers, they
effective means of transporting do provide enhanced
all the components required to protection, by acting as a
construct a bunker. The spall liner. If properly
specially modified ISO container ventilated, they provide
has a fully opening side, excellent environmental
facilitating rapid deployment of protection to the occupants.
all components. The container
also comes complete with a
prefabricated personnel door
and a rear escape hatch, both

HESCO Construction Guide for Engineers


of which can be opened from
the inside.

A single container can carry the


component parts for an
additional two bunkers (this
does not include the sea
containers for the additional
two bunkers).
HESCO Construction Guide for Engineers Preconfigured structures 5.05

Containerised Bunker Kit


Preconfigured structures 5.06
HESCO Accommodation A comprehensive tool kit is also
Bunker (HAB) provided to ensure that those
HAB has been developed by constructing the bunker have
HESCO Bastion Ltd as a result such tools as string lines, tape
of the ever increasing threat to measures and spirit levels.
deployed personnel from
indirect fire weapons. Two bunkers can be built in two
days by one section of soldiers
The bunker is designed to provide assisted by a loading shovel.
safe living accommodation for The bunker can be fitted out for
up to eight persons, giving each air conditioning, heating and
person a space of around 2m other services by using the
(6'6") square. There is up to factory formed aperture placed

HESCO Construction Guide for Engineers


2.16m (7') of headroom inside at one end.
the bunker.
A HAB has a footprint of 12.4m
HAB will provide protection (40'8") long and 6.2m (20'4")
from weapons systems up to wide and an overall height of
and including large mortar around 3.5m.
rounds. It has side walls formed
from Mil 6 Concertainer units If a larger accommodation unit
and a specifically engineered is required then HAB can be
roof structure to combat the joined end to end to form a
effects of indirect fire weapons. longer unit.

It is provided in kit form and is Hab is also used for Forward


delivered in wooden crates. Aid Posts, dining facilities,
These crates hold all the command posts and welfare
components for the bunker and, facilities.
indeed, form part of the structure
themselves. Everything required
is provided in the kit apart from
the fill material.
HESCO Construction Guide for Engineers Preconfigured structures 5.07

HESCO Accomodation Bunker (HAB)

HAB interior
Preconfigured structures 5.08
Extended Overhead the local market; they can
Protection System (EOPS) though be purchased from
HESCO Bastion Ltd have HESCO Bastion Ltd, if required.
developed a system designated
as the “EOPS”. This system The system can also be
provides side and overhead adapted to provide overhead
protection for extended widths. protection for more than one
One cabin that can be protected cabin under a common roof.
typically measures in excess of This system of having a number
7m (22'11") wide. EOPS will give of containers under one
protection from munitions common roof is ideal where a
detonating in contact with the large linked structure is required
roof with explosive payloads in such as a field hospital, large

HESCO Construction Guide for Engineers


excess of 20kg (it will not provide command post or dining facility.
protection against munitions
fitted with a delay fuse). Further guidance and advice on
the construction of EOPS can
The EOPS typically takes two be obtained from HESCO
and a half days to construct Bastion Ltd on application.
and is formed from a number of
component parts. The parts that Note: The container system
are supplied by HESCO Bastion being used must comply with
Ltd are the Concertainer units ISO standards with regard to
and the specially manufactured load bearing.
weight bearing locating cups
which transfer the roof load
onto the container structure.

It is expected that the users will


procure the remainder of the
components consisting of steel
sheet piles, sheet steel etc from
HESCO Construction Guide for Engineers Preconfigured structures 5.09

Extended Overhead Protection System (EOPS)

EOPS locating cup


Preconfigured structures 5.10
HESCO Lightweight Bunker Each roof is 5m (16'4") long when
Roof (HLBR) built and can be easily extended
HLBR has been developed by by the addition of further kits.
HESCO Bastion Ltd to provide The roof kit is supplied in one
a lightweight protective roof wooden crate and can be
solution in those areas under assembled by four men in less
threat from IDF weapons. than five hours. Like the HAB,
the roof kit is supplied with a
The HLBR is designed to be comprehensive tool kit.
built on existing walls, be they
HESCO, concrete, brick or block Other preconfigured
work. The minimum requirements structures
of the walls are that they must In addition to those sets

HESCO Construction Guide for Engineers


not be more than 3.3m (10'10") developed and configured by
apart, must have a minimum HESCO Bastion, several
bearing area of 0.2m (8") and preconfigured sets have been
must be capable of supporting developed by, for example,
the weight of the completed Engineer Research and
roof – approximately 25 tonnes Development Centre for the
(55,000lb). The HLBR is US Army. These kits are generally
designed to provide protection similar to those developed by
from large mortar rounds and HESCO Bastion Ltd.
has been tested accordingly.
HESCO Construction Guide for Engineers

5mm Notes
Preconfigured structures
5.11
6
Improvised
structures
Improvised structures 6.01

The regular shape of described earlier, and the


Concertainer units and the application of appropriate
ability to easily join units using guidelines, such as those
the provided joining pins included in current military
enable the rapid construction doctrine and training publications,
of many different structures. will result in effective and safe
When designing, care must be structures. The US Army field
exercised in creating a structure manual FM 5-103 Survivability
that is sound. For operational gives design guidelines, for
survivability, the adherence to example.
good construction practices,
HESCO Construction Guide for Engineers

Improvised guard post


Improvised structures 6.02

Technical information
appertaining to roof structure
design etc can be provided by
HESCO Bastion Ltd on
application.

HESCO Construction Guide for Engineers


Security position

Improvised bunker
HESCO Construction Guide for Engineers

5mm Notes
Improvised structures
6.03
7
Maintenance
and repair
Maintenance and repair 7.01

Repair procedure (1)


Repairs to Concertainer
structures may be required as
a result of attack or accidental (2)
mechanical damage. There are
a number of repair techniques
available, with the technique
adopted depending on the
nature and extent of the damage.
In the majority of cases once (4)
repairs have been carried out
the wall will once again be as
(5) (6) (3)
competent as it was before the
HESCO Construction Guide for Engineers

damage occurred.

In general, material required for


repair consists of:

- welded mesh panels (1)

- coils (2)
Repairs may range from minor
- pins (3) repair of torn geotextile to
the repair or replacement of
- geotextile (4)
complete sections of wall.
- hog rings (5) The modular design of the
Concertainer units allows all
- multi-tool (6)
of these repairs to be
completed in an economical
Alternately repair material can and efficient manner.
be gained by cannibalising
parts from unused units.
Maintenance and repair 7.02

Minor repair
It is very rare for a complete unit
or cell to require replacement,
but more common for an
exterior panel to have suffered
some damage. This can be
repaired by the application of
a repair panel or a small section
of panel if cannibalising
materials from unused units.
Typical damage caused by
Measure the size of repair patch a rocket.
required (Figure 1) and decide

HESCO Construction Guide for Engineers


whether to apply a patch over - Secure the left side to the
the damaged area, or apply a existing wall by means of a
complete panel. coil coiled through the patch
and the existing cell panel
For a small patch (Figure 3).

- Cut an oversize patch from - Place the cut geotextile


the repair panel or behind the welded mesh
cannibalised unit. patch ensuring the 150mm (6")
overlap is folded within the
- Cut two coils to the patch’s
welded mesh patch (Figure 4).
depth (Figure 2).
- Close the welded mesh patch
- Cut a geotextile patch. Leave
over the area of repair, then
a generous overlap – 150mm
wind in the right-hand coil
(6") all round is generally
(Figure 5).
sufficient (Figure 2).
- Refill or top up the fill in the
- Place the welded mesh patch
unit, as necessary.
over the damaged area.
Maintenance procedure 7.03

Figure 1 Figure 2
HESCO Construction Guide for Engineers

Figure 3 Figure 4

Figure 5
Maintenance and repair 7.04

For a complete panel


Obtain a full size panel to the
correct size, two coils, two
joining pins and a piece of
geotextile 150mm (6") larger on
all sides (Figure 6).

- Fit coils to both sides of the


repair panel (Figure 6).

- Interlink the coil on one side


with the coil of the existing unit
Figure 6
and fit a joining pin (Figure 7).

HESCO Construction Guide for Engineers


- Place the geotextile patch on
inside of the repair panel and
fold in the 150mm (6") overlap
(Figure 8).

- Close the repair panel tight.


Interlink the coil on the
opposite side and fit a pin
(Figure 9).

- Refill the unit to complete the


repair (Figure 10).

Note: It may be necessary to


fit additional coils to increase Figure 7
the length of the repair panel
to enable the coils to be
overlapped and a joining pin
to be fitted.
Maintenance and repair 7.05

Figure 8 Figure 9
HESCO Construction Guide for Engineers

Figure 10
Maintenance and repair 7.06

Complete replacement - Place new cells (Figure 13).


The complete replacement of - Insert joining pins and fit hog
cells will only normally be rings to secure the new units
required when a substantial (Figure 14).
amount of damage has been
incurred. - Place fill and compact in the
normal manner (Figure 15).
- Cut away damaged panels
(Figure 11). Note: Additional coils may
be required (see note on
- Remove all loose fill
page 7.04).
(Figure 12).

HESCO Construction Guide for Engineers

Figure 11
Maintenance and repair 7.07

Figure 12 Figure 13
HESCO Construction Guide for Engineers

Figure 15

Figure 14
Maintenance and repair 7.08

Reinforcement
In this technique, new cells are
established alongside the
damaged section (Figure 16).
Where damage has been
incurred in the upper layers of a
multi-layer structure, it may be
necessary to build a buttress
(Figure 17). This is a quick and
efficient repair method but relies
on the availability of ground to
increase the size of the
structure’s footprint.

HESCO Construction Guide for Engineers


Figure 16

Figure 17
Maintenance and repair 7.09

Capping Protection against ultraviolet


For structures which are radiation
expected to have a long service The geotextile used in HESCO
life, are in wind-affected areas Concertainer is susceptible to
or are adjacent to aircraft the effects of UV radiation after
operating surfaces, it is a period of prolonged exposure.
important that loss of fill
material is prevented. This can The manufacturer of the
be achieved by a number of geotextile has carried out a raft
means: of development work. This has
resulted in a geotextile that has
- Fill material should be shaped a design life of five years, with
and sufficiently compacted to no planned maintenance
HESCO Construction Guide for Engineers

allow moisture to run off. required for the first two years.

- The structure can be covered


One of the problems with trying
by tarpaulins or other
to predict the effects of UV is
waterproof membranes.
that it varies considerably from
- A lean mix concrete or region to region and can, in fact,
cement bound material can differ within the same region.
be used as the final layer. There are, of course, a number
of other issues which affect the
- Where fine sand has been
severity of any degradation that
used as the bulk fill and is
may occur:
susceptible to being blown
out by the wind, then a slightly
- fill material used in the cells
coarser aggregate can be
used to cap the cells. - orientation of the units to
the sun

- the level of fill within the unit


Maintenance and repair 7.10

General advice How to protect


Our advice to all users of HESCO There a number of ways to
Concertainer units is that if you protect the geotextile from the
believe the material is to be in effects of UV radiation
service for more than two years generated by the sun:
then you should apply a
protective layer. This is the - the application of a protective
same principle as applying coating, such as UV CAM,
termite treatment to a timber cement slurry or paint
home in the USA.
- covering the structure with a
sacrificial layer of material
Protection can be applied at the
two year point, this alleviates - the planting of foliage to

HESCO Construction Guide for Engineers


the problem of trying to predict provide shade
how long the base or mission
- the use of specialist HESCO
will last when carrying out the
units which do not have an
initial build.
exposed geotextile face

Application of protective
coatings
The application of a protective
coating, such as UV CAM,
cement slurry or, indeed, paint
(water-based emulsion), is likely
to extend the life span of the
geotextile to 10 years or more.
With maintenance, the life is
likely to be much longer.

A sprayer such as a stucco gun


(texture gun) connected to a
7.5 cu ft/m compressor is ideal
Maintenance and repair 7.11

for the application of UV Cam,


cement slurry or paint. UV Cam,
cement slurry or paint can also
be applied by brush or roller.

UV CAM is supplied in 25 litre


drums. One litre will cover 5m2
(5.98yd2). It can be sourced
direct from HESCO Bastion Ltd.

Cement slurry is simply a


mixture of cement powder and
water. It is mixed to a strength
HESCO Construction Guide for Engineers

of approximately 1:1 but this


can be adjusted to suit
whatever application method is
being used. Sand can also be
added if desired. The unit to be
coated is often wetted prior to
the application of the slurry; this
prevents the slurry from drying
out too quickly.
5mm

Notes
Maintenance and repair
7.12

HESCO Construction Guide for Engineers


8
Product
technical
information
Product technical information 8.01

General
The design of the Concertainer
unit is available in a variety of
differing sizes. The range of
sizes provides the force
protection engineer with
flexibility, allowing him to more
easily tailor the wall to provide
the optimum solution for a wide
range of protective requirements.

The following pages provide


basic product specifications to
HESCO Construction Guide for Engineers

be read in conjunction with the


tables at the end of this section.
Product technical information 8.02

Mil 1

Height Width Length Unit Code Stock Number


1.37m 1.06m 10m Mil1B* 5680-99-835-7866
(4'6") (3'6") (32') Mil1G* 5680-99-001-9396
*B=Beige G=Green

HESCO Construction Guide for Engineers


9 cells (1x5, 1x4)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information

EPW 1

Height Width Length Unit Code Stock Number


2.1m 1.06m 33m EPW1B Pending
(7') (3'6") (108') EPW1G Pending
HESCO Construction Guide for Engineers

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
30 cells (6x5) and flood-protection barriers. The EPW 1 is designed specifically for
rapid erection, reducing exposure of the construction force to hostile fire.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.03 Product technical information 8.04

Mil 1.9 Load Bearing Unit Mil 2

Height Width Length Unit Code Stock Number Height Width Length Unit Code Stock Number
2.74m 1.06m 3.18m Mil1.9B Pending 0.61m 0.61m 1.22m Mil2B 5680-99-968-1764
(9') (3'6") (10'6") Mil1.9G Pending (2') (2') (4') Mil2G 5680-99-001-9397

HESCO Construction Guide for Engineers


3 cells (1x3) 2 cells (1x2)

A geotextile-lined unit designed specifically for load-bearing applications.


The unit is suitable for filling with earth, sand, gravel, crushed rock
and other granular materials. The unit fulfils a wide range of uses, A geotextile-lined unit for general use as an earth-filled gabion. The unit
including the construction of protective walls and barriers, soil-retaining is suitable for filling with earth, sand, gravel, crushed rock and other
and load-bearing structures. The Mil 1.9 Load Bearing Unit is designed to granular materials. The unit fulfils a wide range of uses, including the
support a load of 4,000lb per linear foot (5 tonnes per metre). It is therefore construction of protective walls and barriers, soil-retaining structures
ideal for use in the construction of structures involving overhead loads. and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2. All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal. All dimensions nominal.


Product technical information 8.04

Mil 2

Height Width Length Unit Code Stock Number


0.61m 0.61m 1.22m Mil2B 5680-99-968-1764
(2') (2') (4') Mil2G 5680-99-001-9397

HESCO Construction Guide for Engineers


2 cells (1x2)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.05

Mil 3

Height Width Length Unit Code Stock Number


1.0m 1.0m 10m Mil3B 5680-99-001-9392
(3'3") (3'3") (32') Mil3G 5680-99-001-9398
HESCO Construction Guide for Engineers

10 cells (2x5)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.06

Mil 4

Height Width Length Unit Code Stock Number


1.0m 1.5m 10m Mil4B 5680-99-001-9393
(3'3") (5') (32') Mil4G 5680-99-001-9399

HESCO Construction Guide for Engineers


10 cells (2x5)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.07

Mil 5

Height Width Length Unit Code Stock Number


0.61m 0.61m 3.05m Mil5B 5680-99-001-9394
(2') (2') (10') Mil5G 5680-99-001-9400
HESCO Construction Guide for Engineers

5 cells (1x5)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.08

Mil 6

Height Width Length Unit Code Stock Number


1.68m 0.61m 3.05m Mil6B Pending
(5'6") (2') (10') Mil6G Pending

HESCO Construction Guide for Engineers


5 cells (1x5)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers. An ideal unit for protective structures around
tented or other soft-skinned accommodation.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information

Mil 7

Height Width Length Unit Code Stock Number


2.21m 2.13m 27.74m Mil7B 5680-99-169-0183
(7'3") (7') (90') Mil7G 5680-99-126-3716
HESCO Construction Guide for Engineers

13 cells (1x5, 2x4)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.09 Product technical information 8.10

Mil 8 Mil 9

Height Width Length Unit Code Stock Number Height Width Length Unit Code Stock Number
1.37m 1.22m 10m Mil 8B 5680-99-335-4902 1.0m 0.76m 9.14m Mil 9B 5680-99-563-5949
(4'6") (4') (32') Mil 8G 5680-99-517-3281 (3'3") (2'6") (30') Mil 9G 5680-99-052-0506

HESCO Construction Guide for Engineers


12 cells (2x6)
9 cells (1x5, 1x4)

A geotextile-lined unit for general use as an earth-filled gabion. The unit A geotextile-lined unit for general use as an earth-filled gabion. The unit
is suitable for filling with earth, sand, gravel, crushed rock and other is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers. and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2. All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal. All dimensions nominal.


Product technical information 8.10

Mil 9

Height Width Length Unit Code Stock Number


1.0m 0.76m 9.14m Mil 9B 5680-99-563-5949
(3'3") (2'6") (30') Mil 9G 5680-99-052-0506

HESCO Construction Guide for Engineers


12 cells (2x6)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information

Mil 10

Height Width Length Unit Code Stock Number


2.21m 1.52m 30.5m Mil 10B 5680-99-391-0852
(7'3") (5') (95') Mil 10G 5680-99-770-0326
HESCO Construction Guide for Engineers

20 cells (4x5)

A geotextile-lined unit for general use as an earth-filled gabion. The unit


is suitable for filling with earth, sand, gravel, crushed rock and other
granular materials. The unit fulfils a wide range of uses, including the
construction of protective walls and barriers, soil-retaining structures
and flood-protection barriers.

All wires conform to BS 1052. Alu-Zinc coatings are to BS / EN 10244 - 2.

All dimensions nominal.


Product technical information 8.11 Product technical information 8.12

Training units The table below gives technical


HESCO Mil 1, and Mil 3 units data for the geotextile used in
are ideal for training purposes. all HESCO Concertainer
products.
These standard units have
pinned joints on each of the Geotextile technical data
side walls. This allows the filled Property Test Method Typical Value MARV
units to be split by extracting Physical
successive pins, allowing the fill Mass/Unit Area ASTM D5261 220 g/m2 203 g/m2
material to fall away. Thickness ASTM D5199 1.45 mm 1.04 mm
Mechanical
The pins are then replaced, Grab Tensile Strength (md)1 ASTM D4632 756 N 580 N
Grab Tensile Strength (cd)2 ASTM D4632 890 N 710 N
reassembling the units for

HESCO Construction Guide for Engineers


Grab Elongation (md) ASTM D4632 65% 50%
re-use. It is recommended that Grab Elongation (cd) ASTM D4632 70% 50%
a single sized sand gravel is Wide Width Tensile
Strength (md) ASTM D4595 13 kN/m 8 kN/m
used as a fill material. Wide Width Tensile
Strength (cd) ASTM D4595 16 kN/m 12 kN/m
Wide Width Elongation (md) ASTM D4595 50% 35%
Wide Width Elongation (cd) ASTM D4595 50% 35%
Static (CBR) Puncture ASTM D6241 2447 N 2000 N
Hydraulic
Apparent Opening Size (AOS)3 ASTM D4751 0.15 mm 0.21 mm
Permittivity ASTM D4491 2.00 sec-1 1.30 sec-1
Permeability ASTM D4491 0.40 cm/sec 0.24 cm/sec
Water Flow Rate ASTM D4491 6111 l/min/m2 4075 l/min/m2
1
md = machine direction. 2 cd = cross direction.
3
For AOS, smaller numbers are more desirable. The MARV in this case indicates Maximum Average Roll Value.

The values given above are indicative and correspond to average results obtained in our suppliers' laboratories
and in testing institutes. The right is reserved to make changes without notice at any time.
Product technical information 8.12

The table below gives technical


data for the geotextile used in
all HESCO Concertainer
products.

Geotextile technical data


Property Test Method Typical Value MARV

Physical
Mass/Unit Area ASTM D5261 220 g/m2 203 g/m2
Thickness ASTM D5199 1.45 mm 1.04 mm
Mechanical
Grab Tensile Strength (md)1 ASTM D4632 756 N 580 N
Grab Tensile Strength (cd)2 ASTM D4632 890 N 710 N

HESCO Construction Guide for Engineers


Grab Elongation (md) ASTM D4632 65% 50%
Grab Elongation (cd) ASTM D4632 70% 50%
Wide Width Tensile
Strength (md) ASTM D4595 13 kN/m 8 kN/m
Wide Width Tensile
Strength (cd) ASTM D4595 16 kN/m 12 kN/m
Wide Width Elongation (md) ASTM D4595 50% 35%
Wide Width Elongation (cd) ASTM D4595 50% 35%
Static (CBR) Puncture ASTM D6241 2447 N 2000 N
Hydraulic
Apparent Opening Size (AOS)3 ASTM D4751 0.15 mm 0.21 mm
Permittivity ASTM D4491 2.00 sec-1 1.30 sec-1
Permeability ASTM D4491 0.40 cm/sec 0.24 cm/sec
Water Flow Rate ASTM D4491 6111 l/min/m2 4075 l/min/m2
1
md = machine direction. 2 cd = cross direction.
3
For AOS, smaller numbers are more desirable. The MARV in this case indicates Maximum Average Roll Value.

The values given above are indicative and correspond to average results obtained in our suppliers' laboratories
and in testing institutes. The right is reserved to make changes without notice at any time.
Product technical information 8.13

The table below gives technical Note: All wires conform to


data for the welded mesh used BS 1052. Alu-Zinc coatings
in all HESCO Concertainer are to BS/EN 10244-2.
products.

Welded mesh technical data


Property 3" x 3" x 4mm wire 3" x 3" x 5mm wire

Steel 0.10% Carbon Max 0.10% Carbon Max


Properties Mild Steel Mild Steel
(6.50mm base rod) (5.50mm base rod)

Coating Weight Zinc / Aluminium Zinc / Aluminium


(g/m2) 145 min 145 min

Wire Tensile 540 – 770 540 – 770


HESCO Construction Guide for Engineers

(N/mm2)

Mesh Tensile 70% of Wire tensile 70% of Wire tensile


(N/mm2)

Tolerance
Wire (un-coated) 3.89 / 3.91mm 4.9 / 4.92mm
Wire (coated) 3.92 / 4.00mm 4.92 / 5.00mm
Panel +/- 3mm on length +/- 3mm on length
+/- 3mm on width +/- 3mm on width
+/- 2mm on mesh spacing +/- 2mm on mesh spacing

Panel 39” x 39” +/- 3mm max 87” x 42” +/- 6mm max
Squareness 54” x 21” +/- 3mm max 87” x 60” +/- 6mm max
54” x 42” +/- 5mm max 87” x 30” +/- 6mm max
24” x 24” +/- 3mm max 87” x 84” +/- 8mm max
66” x 24” +/- 3mm max

Panel Flatness 39” x 39” +/- 12mm max 25mm max


54” x 21” +/- 12mm max
54” x 42” +/- 16mm max
24” x 24” +/- 12mm max
66” x 24” +/- 12mm max

Elongation Approx 5% Approx 5%

The values given above are indicative and correspond to average results obtained in our suppliers' laboratories
and in testing institutes. The right is reserved to make changes without notice at any time.
5mm

Notes
Product technical information
8.14

HESCO Construction Guide for Engineers


9
Trial
information
Trial information 9.01

General Aim
Concertainer units have The aim of this section is to
undergone a huge array of summarise some of the testing
testing worldwide. This testing carried out on Concertainer units,
has been conducted by world- from the early 1990s to date.
leading test authorities in the
field of blast mitigation, Limitations
containment of blast effects The majority of test information
and force protection. is owned by Military Authorities
and in the case of the British
Weapon systems tested against MOD is still subject to the
HESCO units include: Official Secrets Act. Therefore,
some critical data has been
HESCO Construction Guide for Engineers

- small arms (5.56 – 14.5mm AP) omitted to allow a wider


circulation of this document.
- cannon (20 – 40mm including
Further information may be
HE, AP and long rod)
obtained on application.
- shaped charges (RPG 7 and
RPG 18) Testing
The Concertainer unit was first
- grenades
introduced to the British military
- mortars (81, 82 and 120mm) in 1991; it was then subjected
to testing against a wide range
- artillery (122, 152 and 155mm)
of small arms munitions. These
- air delivered bombs tests were conducted by the
(US Mk 82) Defence Research Agency (DRA)
Fortifications section, (UK MOD
- conventional plastic and
research agency) and by the
home made explosive bare
British Army Infantry Trials
charges, including vehicle
Team. DRA Fortifications is now
borne improvised explosive
part of QinetiQ.
devices

- fuel air explosives


Trial information 9.02

Weapons used were: Concertainer Mil 1 Units were


also tested against .50"
- shotgun
machine gun fired in bursts of
- 7.62mm, single shot and 3 – 5 rounds. The cells were
general-purpose machine gun sand filled and no rounds
penetrated.
- 0.5" Amour piercing AP,
Soviet 12.7 and 14.5 mm AP
The Mil 1 unit was also tested
- Rarden 30mm long rod against:
penetrator cannon
- 81mm mortar
The above tests were against
- 155mm HE artillery shell
Concertainer Mil 2 units filled

HESCO Construction Guide for Engineers


with a good quality fill material. - simulated 120mm HESH
None of the rounds achieved round in direct contact
complete penetration of the
Concertainer units. The Mil 2 In 1993 HESCO, in conjunction
unit at 600mm (2') thick is the with the UK MOD, developed a
smallest unit manufactured collective protection system
by HESCO. (COLPRO). This was designed
to provide protection from
close-in detonation of 155mm
artillery shells fitted with super-
quick fuses. The COLPRO
system is made up of a 20ft
ISO container protected by
Concertainer Mil 1 units. Steel
sheet piles, Concertainer Mil 2
units, and 600mm (2') of soil fill
provide overhead protection.
This test proved that the
COLPRO system would prevent
serious casualties even when
Trial information 9.03

the structure was subjected to minor damage. The second test


a detonation in contact. This was an Mk 82 bomb, at fairly
system has subsequently been short stand-off; this resulted in
used extensively around the superficial damage. The wall
world to provide mortar, bomb was not breached. The third
and artillery type shelters. Shells and last test was over seven
fitted with a delay fuse will cause tonnes of C4 explosive to
casualties with a direct hit. simulate a large VBIED.

1995 saw the US military at Concertainer units were one


Fort Leonard Wood test of three wall systems tested.
Concertainer units against Concertainer units fared the
155mm artillery shells close into best of the three, generating
HESCO Construction Guide for Engineers

the target of a Concertainer Mil 3. no significant secondary


Damage was judged “superficial”. fragmentation. They also far
outshone the other systems
1997 saw a substantial amount when a cost benefit analysis
of testing take place in the US, was carried out.
UK and Germany.
The German MOD tested
The UK tested the system Concertainer units along with
against RPG7. Gravel-filled other gabion systems in 1997.
Concertainer Mil 1 units will Weapons systems used were
prevent penetration of RPG7 similar to previous testing. The
rounds, but may allow the tail results achieved were also
fin to pass through. At least similar to those achieved
1.8m of poor fill material is elsewhere. The system was also
required to defeat RPG7. attacked, in a trial, by anti-tank
grenades and 82mm mortar in
Concertainer units were tested contact. The resulting damage
in the US at Wright Laboratories, was judged as “not significant”.
Tyndall. This testing was against
235lbs of ANFO, this resulted in
Trial information 9.04

The Dutch Trials Agency, TNO with gravel. A medium sized


has also conducted trials using truck travelling in excess of
Concertainer units. These 40mph was crashed into the
originated with the Dutch barrier. The vehicle was
testing the COLPRO system, stopped within approximately
achieving similar results as the 11m (36'). The 2nd was against
UK. The Dutch have also trialled four cells with gravel. The same
Concertainer units for type of vehicle at the same
ammunition storage separation speed was used. On this
walls. The test consisted of occasion it was stopped within
5011kg of explosives contained 6m (19'8") and was extensively
within artillery shells in a 20ft damaged. HESCO had long
ISO container. Live detonators held the belief that the system

HESCO Construction Guide for Engineers


were stored within Container would be effective against
units adjacent to the donor vehicles but had never had it
charge. The explosive charge tested. These tests confirmed
was initiated, which resulted in our confidence in the system for
severe damage to the adjacent this application.
container units but no
sympathetic detonation of the A similar test has been
acceptor charge occurred. This conducted in the USA by Air
has resulted in the Quantity- Force, Force Protection Battle
Distances being reduced. Labs – on this occasion, a
similar-sized vehicle, travelling
Concertainer units were tested at approx 50mph. The barrier
in June 2004 as a vehicle was 10m (32') in length with a
barrier. The Transport Research double thickness wall of
Laboratory conducted this testing Concertainer Mil 1 units on the
at the request of the UK security base and a single Mil 1 unit on
services. Two tests were carried top. This resulted in the vehicle
out, the first with two cells of being stopped in a very short
Concertainer Mil 1 units filled distance.
Trial information 9.05

Further testing of the ability cased charges of C4. All the


of Concertainer units to stop charges were placed on the
vehicles was carried out in roof and ranged from 2kg to
December 2004 by the Texas 30kg. Only the largest charge
Transportation Institute. This caused any damage to the
testing was carried out to K12 structure. Pressures measured
standards. This was the US inside the protected area were
standard for crash barrier well below the level which is
testing. The units tested were perceived to be the threshold
the smaller flood-mitigation units. for eardrum damage.
This has resulted in HESCO
being awarded K12 Certification The HESCO Accommodation
for a variety of its units. Bunker (HAB) has been tested
HESCO Construction Guide for Engineers

against indirect fire weapons.


December 2005 saw further The bunker provides protection
testing of Concertainer units as from fragmentation and blast
a vehicle barrier, this time effects from small, medium and
against a 65,000lb truck large mortars. Similar testing
travelling at 50mph. This has has been conducted on the
resulted in HESCO being HLBR.
awarded H50 certification.

Testing of Concertainer units


has been carried out by firing
107mm rockets and 120mm
mortars into a Concertainer
wall. Mortar rounds have also
been statically detonated in
contact with the HESCO walls.

The Extended Overhead


Protection System (EOPS) has
been tested against contact
Trial information 9.06

Conclusion
The above is a quick summary
of some of the main testing
which has taken place over the
last 15 years, to which we have
been privy. It can be seen from
the above that the system has
been comprehensively tested
and continues to be so.

This level and variety of testing


demonstrates the pedigree of
the system and the number of

HESCO Construction Guide for Engineers


different protective uses it can
be put to.
HESCO Construction Guide for Engineers

5mm Notes
Trial information
9.07
10
Packing and
shipping
Packing and shipping 10.01

Optimum packing for Many HESCO units when


transportation packaged accordingly are
While many packaging options capable of being air delivered
are available, experience has by dropping by parachute. The
led to the following optimum HAB is also capable of being air
shipping configurations, based delivered.
on stacking of units on timber
skids or pallets. Generally these The delivery of a number of
pallets are then loaded into types of unit in RAID configuration
shipping containers, loaded on provides a reduction in the
trailers or airlift pallets, as logistics burden of supporting
appropriate. Units may be force-protection operations.
loaded in bulk into containers,
HESCO Construction Guide for Engineers

which would provide for a


greater capacity. However,
loading and unloading would be
more difficult, so the practice is
therefore not recommended.
Packing and shipping 10.02

Flat-packed individual units dimensions and weights

Unit Height Width Length Weight

Mil 1 0.25m 1.07m 1.37m 148.5kg


(10") (42") (54") (327lb)
EPW 1 0.75m 1.07m 2.1m 840kg
(30") (42") (82") (1851lb)
Mil 1.9 0.10m 2.18m 2.74m 198kg
Load (4") (85") (107") (437lb)
Bearing
Mil 2 0.05m 0.61m 0.61m 10kg
(2") (24") (24") (22lb)

HESCO Construction Guide for Engineers


Mil 3 0.2m 1.0m 1.0m 105kg
(8") (39") (39") (231lb)
Mil 4 0.2m 2.49m 1.0m 160kg
(8") (98") (39") (352lb)
Mil 5 0.11m 0.61m 0.61m 23kg
(4.5") (24") (24") (51lb)
Mil 6 0.22m 0.61m 1.68m 46kg
(8.5") (24") (66") (101lb)
Mil 7 0.72m 2.23m 2.23m 950kg
(28") (91") (91") (2090lb)
Mil 8 0.25m 1.22m 1.37m 155kg
(10") (48") (54") (341lb)
Mil 9 0.3m 0.76m 1.0m 99kg
(12") (30") (39") (218lb)
Mil 10 0.79m 1.66m 2.25m 1050kg
(31") (65") (88") (2310lb)
Packing and shipping 10.03

Palletised unit dimensions and weights

Units Per Pallet

Pallet Length

13.5m Trailer

40' Container

20' Container
Pallet Weight
Pallet Height

Pallet Width

Pallets per

Pallets per

Pallets per
Unit

Mil 1 7 2.03m 1.14m 1.40m 1060kg 18 16 8


(80") (45") (55") (2332lb)
EPW 1 1 0.84m 2.1m 2.3m 890kg 20 15 6
(33") (83") (90") (1962lb)
Mil 1.9 6 0.80m 2.18m 2.74m 1220kg 12 8 4
Load (32") (85") (107") (2688lb)
HESCO Construction Guide for Engineers

Bearing
Mil 2 120 0.84m 1.90m 2.0m 1220kg 18 12 6
(33") (75") (78") (2684lb)
Mil 3 8 1.78m 1.17m 1.17m 860kg 22 20 10
(70") (46") (46") (1892lb)
Mil 4 8 1.70m 1.04m 2.67m 1313kg 10 8 4
(67") (41") (105") (2889lb)
Mil 5 50 0.84m 1.9m 2.00m 1160kg 18 12 6
(33") (75") (78") (2552lb)
Mil 6 27 0.76m 1.9m 2m 1255kg 18 12 6
(30") (75") (78") (2761lb)
Mil 7 1 0.6m 2.20m 2.30m 980kg 20 15 6
(24") (86") (90") (2156lb)
Mil 8 4 1.5m 1.06m 1.27m 640kg 18 18 8
(59") (42") (50") (1408lb)
Mil 9 7 1.7m 1.1m 1.1m 714kg 20 20 10
(67") (43") (43") (1571lb)
Mil 10 1 0.79m 1.62m 2.35m 1079kg 20 14 6
(31") (64") (92") (2374lb)

Note: Pallet weight includes the units, the pallet and the packaging.
5mm

Notes
Packing and shipping
10.04

HESCO Construction Guide for Engineers


11
Conversion
tables
Conversion tables 11.01

The following pages provide


tables of conversions for
common measurement systems,
in both directions.

Caution:
Every care has been taken
to ensure that the conversion
factors are accurate.
However, the conversion
factors contained within this
document are included as a
courtesy and should not be
HESCO Construction Guide for Engineers

relied upon for use in complex


engineering problems.
Conversion tables 11.02

Dimension To Convert Into Multiply by

Length Inches mm 25.4


feet m 0.3048
yards m 0.9144
miles km 1.609
Area square inches cm2 6.452
square feet m2 0.093
square yards m2 0.8361
acres hectares 0.405
square miles km 2
2.590

HESCO Construction Guide for Engineers


Volume cubic feet m3 0.0283
cubic yard m3 0.765
imperial gallons litres 4.5461
US gallons litres 3.7851
Mass ounces g 28.35
pounds (lb) kg 0.4536
hundred weight kg 50.8
ton kg 1.016

Note: Hundred weight are UK long. Ton is UK long.


Conversion tables 11.03

Dimension To Convert Into Multiply by

Length mm Inches 0.039


m feet 3.28
m yards 1.09
km miles 0.621
Area mm2 square inches 0.0016
m2 square feet 10.764
m2 square yards 1.196
m2 hectares 0.0001
hectares acres 2.47
HESCO Construction Guide for Engineers

km2 square miles 0.386


Volume cm3 cubic inches 0.061
m3 cubic feet 35.31
m3 cubic yard 1.307
cm 3
fluid ounces 0.035
litres m3 0.001
litres imperial gallons 0.2198
litres US gallons 0.264
Mass g ounces 0.035
kg pounds (lb) 2.204
kg hundred weight 0.020
Tonnes ton 0.984

Note: Hundred weight are UK long. Ton is UK long.


Conversion tables 11.04

Dimension To Convert Into Multiply by

Density ton/yard t/m3 1.329


Speed Miles/hour m/s 0.4470
Miles/hour km/hour 1.61
knots m/s 0.5148
Force lb.force (lb.f) N 4.444
Poundal (pdl) N 0.1383
ton force kN 9.964
Pressure lb/ft2 N/m2 47.88
Psi (lb/in )2
kN/m2 6.895

HESCO Construction Guide for Engineers


Ton/ft2 kN/m2 107.2
Ton/in2 N/mm2 15.44
Bar N/mm 2
0.1
atmosphere bar 1.013
PSI (lb/in2) kPa 6.895

Note: Ton is UK long. Standard atmosphere used.


Conversion tables 11.05

Dimension To Convert Into Multiply by

Density t/m3 ton/yard 0.752


Speed m/s Miles/hour 2.237
km/hour Miles/hour 0.621
m/s knots 1.945
Force N lb.force (lb.f) 0.225
N Poundal (pdl) 7.233
kN ton force 0.1
Pressure N/m2 lb/f2 0.021
kN/m2 Psi (lb/in2) 0.145
HESCO Construction Guide for Engineers

kN/m 2
Ton/ft2 0.009
N/mm2 Ton/in2 0.065
N/mm2 Bar 10
bar atmosphere 0.987
kPa PSI (lb/in )2
0.145

Note: Ton is UK long. Standard atmosphere used.


5mm

Notes
Conversion tables
11.06

HESCO Construction Guide for Engineers


12
Contacts
Contacts 12.01

Contact information

Company address
HESCO Bastion Limited
Knowsthorpe Way
Cross Green Industrial Estate
Leeds LS9 0SW
United Kingdom

www.hesco.com

Sales enquiries
For product sales and shipping
HESCO Construction Guide for Engineers

enquiries, please contact:


Email: sales@hesco.com
Tel: +44 113 248 6633
Fax: +44 113 248 3501

Technical enquiries
For specific technical enquiries,
or enquiries about product
training, please contact:
Email: technical@hesco.com
Tel: +44 207 350 5454
Fax: +44 207 350 5455

Marketing enquiries
For marketing materials or to
order more copies of this
document, please contact:
Email: marketing@hesco.com
Tel: +44 207 350 5454
Fax: +44 207 350 5455

Contacts photograph courtesy of US DoD


5mm

Notes
Contacts
12.02

HESCO Construction Guide for Engineers


HESCO Bastion Ltd
41 Knowsthorpe Way
Cross Green Industrial Estate
Leeds LS9 0SW
United Kingdom

Tel: +44 113 248 6633


Fax: +44 113 248 3501
Email: info@hesco.com
Web: www.hesco.com

Disclaimer Patents
The information contained in this publication RAID is covered by patent nos. 2445356 (UK)
is provided by HESCO Bastion Ltd ('HESCO') and 7905685, 7896583, 7789592, 7708501,
or is derived from sources that HESCO 7883297, 7891913 (US); and is subject to
reasonably believes to be reliable and application no. 0808420.4 (UK). EPW is
accurate or are otherwise expressions of covered by patent nos. 1951963, 2432611 (UK);
independent third party opinion. Whilst and is subject to application no. 12/090,648
HESCO has made reasonable efforts to (US). HLBR is subject to application nos.
ensure the accuracy, completeness and 0820411.7 (UK) and 12/937,888 (US).
relevance of such information, any reliance on HAB 1 is covered by patent nos. 2145064,
it, in whole or in part, is entirely at the risk of 1992768 (UK) and 7856761 (US); and is
the party using it and it will not rely on such subject to application nos. 0803661.8 (UK)
information in substitution for making all and 12/595,436 (US) and other international
proper and necessary enquiries from HESCO equivalents.
or other relevant third parties. The selection,
configuration and installation of any of Trade Marks
HESCO’s products on site is not HESCO’s HESCO, Concertainer, Mil, RAID and HAB
responsibility and, HESCO, its directors, are registered® trade marks of HESCO
employees, agents, distributors, suppliers or Bastion Ltd.
contractors shall not be liable for any failure
of any of HESCO’s products caused by Quality Standards
improper installation. HESCO Bastion Ltd manufactures to quality
standards ISO 9001 (1987), BS 5750 Part 1
At the sole and absolute discretion of (1987) and EN 29001 (1987) certificate no.
HESCO, the contents of this publication are 910654.
subject to change at any time without notice.

HESCO further reserves the right to amend


specifications without notice.

Copyright Notice
Certain material featured in this document is
subject to copyright protection. Any lawful
reproduction of such material is subject to
obtaining prior written permission from
HESCO Bastion Ltd. Any requests for such
permission should be made in writing.

Copyright © HESCO Bastion Ltd 12.07.11

You might also like