ONE CRYSTAL ROCK ANCHORING WORK

RATE Amount RATE


SR NO DISCRIPTIONS UNITS QTY
KRISHNA PILES Tech Infra Foundation
1 Mobilization Per Nos 1 Set 30000 30000 20000
2 Rock Anchors Per Mtr 120 3850 462000 4000.00
3 Providing and Fixing Structural steel Per Ton 4.5 125000 562500 105000
4 Fixing Anchor fasteners Per Nos 80 750 60000 0
5 Stressing Per Nos 10 0
1114500

NOTES:
Payment terms and condition
KRISHNA PILES : Tech Infra Foundation Total Foundation
1) The above rates quote are exclusive of all taxes
1) The above rates quote are exclusive of
all taxes 1) The above rates quote
2) 15% adavance shall be
2) 60% adavance shall be given & same shall be 2) Structural steel charge be will paid in deducted from our bill pr
deducted from our bill proportionately advance.

3) Billing: Billing shall be made every 5nos of rock 3) If MS Linears need to b


anchors payment of which shall be made within 3 days linears than same shall be
from the date of submission of R.A Bill. Rmt additional

4) Ilde Charge: In case ou


4) Ilde Charge: In case our machine is kept idle due to to whatsoever reason fro
whatsoever reason from your end or decision pending pending from your end m
from your end more than 2days we shall charge RS charge RS 25000/-per rig
10000/-per day shift as idle charge charge
5) Stressing with Multipu
10,000/- per nos excludin

6) Supplying of Structura
client
7) Muck scope .
removal will be i
5) Billing: Billing shall be m
10nos anchor payment o
within 7 days from the da
Bill.
ORING WORK
Amount RATE Amount RATE Amount
Tech Infra Foundation Total Foundation Zed Geosystems Pvt Ltd.
20000 35000 35000 35000 35000
480000.00 4200 504000 3250 390000
472500 30000 135000 110000 495000
0 150 1500 510 40800
0 0 0
972500 675500 960800

Total Foundation Zed Geosystems Pvt Ltd.

1) The above rates quote are exclusive of all taxes 1) The above rates quote are exclusive of all taxes
2) 15% adavance shall be given & same shall be
deducted from our bill proportionately 2) More than 50% adavance shall be given & same
shall be deducted from our bill proportionately

3) If MS Linears need to be inserted in place of PVC 3) If MS Linears need to be inserted in place of PVC
linears than same shall be charged at RS 1500/- per linears than same shall be charged at RS 1450/- per
Rmt additional Rmt additional
4) Billing: Billing shall be made after completion of
10nos anchor payment of which shall be made
4) Ilde Charge: In case our machine is kept idle due within 7 days from the date of submission of R.A
to whatsoever reason from your end or decision Bill.
pending from your end more than 3days we shall
charge RS 25000/-per rig for anchoring shift as idle
charge
5) Stressing with Multipull jack charge extra Rs. 5) Basic rates of structural steel is considered as RS
10,000/- per nos excluding pocklain charges 68,000/- per MT.

6) Supplying of Structural steel and bolts will be in


client
7) Muck scope .
removal will be in client scope.
5) Billing: Billing shall be made after completion of
10nos anchor payment of which shall be made
within 7 days from the date of submission of R.A
Bill.