You are on page 1of 4

TENTATIVE CONSTRUCTION PROGRAM - BHIWANI ACADEMIC BLOCK - PACKAGE 2

Construction Period in Months


S.no Activity Qty Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1 Design & Survey
Engagement of Design Consultant
Topograpic Survey
2 Approvals
Municipal Approval
Environmental Clearance
Forest Clearance
3 Submissions
Submission of Master Plans for NMC Approval
submission of Design basis report
Approval of Master Plan by B&R
Submission of Architectural Drawings
Submission of Structural Drawings
Submission of MEP Drawings
Submission of makes and vendors
Approval of Drawings incl Proof Checking
4 Site Handing Over
Vita Plant Area

5 UG Boys Hostel ( G+10 )


100%
Foudations 100%
RCC Structure
426 348
Ground Floor Slab 774 sqm
416 341
1st Floor Slab 757 sqm
413 338
2nd Floor Slab 750 sqm
413 338
3rd Floor Slab 750 sqm
416 341
4th Floor Slab 757 sqm
300 450
5th Floor Slab 750 Sqm
168 392
6th Floor Slab 560 Sqm
142 425
7th Floor Slab 567 Sqm
560
8th Floor Slab 560 Sqm
560
9th Floor Slab 560 Sqm
567
10th Floor Slab 567 Sqm
3% 7% 8% 10% 10% 15% 15% 12% 10% 10%
Masonary & Plastering 100%
3% 10% 12% 15% 15% 20% 10% 10% 5%
FireFighting / Elecrical works 100%
3% 8% 9% 10% 10% 10% 10% 10% 15% 15%
Flooring / Interoirs 100%
10% 20% 25% 25% 20%
Final Painting 100%
100%
Handing Over 100%
6 UG Girls Hostel ( G+10 )
100%
Foudations 100%
RCC Structure

Ground Floor Slab 774 sqm


757
1st Floor Slab 757 sqm
TENTATIVE CONSTRUCTION PROGRAM - BHIWANI ACADEMIC BLOCK - PACKAGE 2
Construction Period in Months
S.no Activity Qty Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
450 300
2nd Floor Slab 750 sqm
329 329
3rd Floor Slab 658 sqm
227 340
4th Floor Slab 567 sqm
224 336
5th Floor Slab 560 Sqm
168 392
6th Floor Slab 560 Sqm
113 454
7th Floor Slab 567 Sqm
560
8th Floor Slab 560 Sqm
560
9th Floor Slab 560 Sqm
567
10th Floor Slab 567 Sqm
3% 5% 8% 10% 12% 15% 15% 16% 11% 5%
Masonary & Plastering 100%
3% 6% 10% 13% 15% 17% 18% 13% 5%
FireFighting / Elecrical works 100%
3% 6% 10% 13% 15% 17% 18% 13% 5%
Flooring / Interoirs 100%
20% 25% 30% 15% 10%
Final Painting 100%
100%
Handing Over 100%
Handing Over
7 Directors Bunglow
100%
Foudations 100%
RCC Structure
95 95
Ground Floor Slab 190 sqm
66 80
1st Floor Slab 146 sqm
25% 55% 20%
Masonary & Plastering 100%
35% 65%
FireFighting / Elecrical works 100%
35% 65%
Flooring / Interoirs 100%
30% 40% 30%
Final Painting 100%
100%
Handing Over 100%
8 Medical College
100%
Foudations 100%
RCC Structure 2330 1906
Ground Floor Slab 4236 sqm
2012 1647
1st Floor Slab 3659 sqm
2177 1781
2nd Floor Slab 3958 sqm
2177 1781
3rd Floor Slab 3958 sqm
2177 1781
4th Floor Slab 3840 sqm
2038.85 1668.15
5th Floor Slab 3707 Sqm
1859 1521
TENTATIVE CONSTRUCTION PROGRAM - BHIWANI ACADEMIC BLOCK - PACKAGE 2
Construction Period in Months
S.no Activity Qty Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
6th Floor slab 3380 sqm
1091 892
7th Floor slab 1983 sqm
3% 8% 10% 10% 12% 13% 14% 15% 10% 5%
Masonary & Plastering 100%
3% 5% 7% 10% 11% 12% 12% 15% 11% 9% 5%
FireFighting / Elecrical works/ HVAC / ELV works 100%
5% 10% 15% 17% 18% 20% 10% 5%
Flooring / Interoirs 100%
10% 15% 20% 25% 20% 10%
Equipment / Plant & Final MEP
5% 10% 15% 18% 22% 20% 10%
Final Painting / Fixtures
100%
Handing Over 100%
9 Services
3% 5% 6% 7% 7% 10% 10% 11% 13% 13% 10% 5%
ESS 100%
5% 15% 15% 20% 15% 15% 10% 5%
HVAC Plant 100%
5% 10% 20% 20% 15% 15% 10% 5%
DG Yard 100%
3% 5% 7% 8% 12% 15% 30% 20%
STP 100%
3% 5% 7% 8% 12% 15% 30% 20%
UG tank 100%
10% 10% 10% 15% 20% 20% 10% 5%
Parking 100%
10% 10% 10% 15% 20% 20% 10% 5%
Land Scaping 100%
10 Type 6 & 8 Combines
100%
Foudations 100%
RCC Structure
544 544
Ground Floor Slab 1087 sqm
673 362
1st Floor Slab 1035 sqm
673 362
2nd Floor Slab 1035 sqm
518 518
3rd Floor Slab 1035 sqm
466 569
4th Floor Slab 1035 sqm
414 621
5th Floor Slab 1035 Sqm
414 621
6th Floor Slab 1035 sqm
673 362
7th Floor Slab 1035 sqm
673 362
8th Floor Slab 1035 sqm
3% 5% 10% 12% 15% 20% 20% 10% 5%
Masonary & Plastering 100%
3% 5% 8% 12% 15% 18% 20% 14% 5%
FireFighting / Elecrical works 100%
5% 8% 12% 18% 22% 25% 10%
Flooring / Interoirs 100%
25% 30% 35% 10%
Final Painting 100%
100%
Handing Over 100%
11 Dining Hall 100%
TENTATIVE CONSTRUCTION PROGRAM - BHIWANI ACADEMIC BLOCK - PACKAGE 2
Construction Period in Months
S.no Activity Qty Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Foudations 100%

435 290
RCC Structure 725 Sqm
35% 65%
Masonary & Plastering 100%
25% 45% 30%
FireFighting / Electrical / HVAC works 100%
35% 65%
Flooring / Interoirs 100%
100%
Final Painting 100%
100%
Handing Over 100%

Important Note
1 Date of start of work shall be considered as 15 days from the handing over of emcrumbrance free site.
2 The program is tentative and will be modified based on actual site conditions and approved master plans and designs etc.

You might also like