Construction Program Package 2
Construction Program Package 2
435 290
RCC Structure 725 Sqm
35% 65%
Masonary & Plastering 100%
25% 45% 30%
FireFighting / Electrical / HVAC works 100%
35% 65%
Flooring / Interoirs 100%
100%
Final Painting 100%
100%
Handing Over 100%
Important Note
1 Date of start of work shall be considered as 15 days from the handing over of emcrumbrance free site.
2 The program is tentative and will be modified based on actual site conditions and approved master plans and designs etc.