Bill Of Quantity

PT. Bima Nusantara Muda

PENGGANTIAN ATAP FUMIRA & DINDING NUSA BOARD (9 MM) P12

UNIT PRICE TOTAL PRICE


NO WORK ITEMS VOLUME SATUAN
IDR IDR
A PENGGANTIAN ATAP FUMIRA
1 Mob. & Demob. 1.00 ls Rp 5,000,000.00 Rp 5,000,000.00
2 HSE, ADM. & APD 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
3 Pembongkaran atap ( 14 x 18 ) 252.00 m² Rp 75,000.00 Rp 18,900,000.00
4 Pemasangan atap fumira ( 14 x 18 ) 252.00 m² Rp 350,000.00 Rp 88,200,000.00
5 Pemasangan nok 20.00 ml Rp 150,000.00 Rp 3,000,000.00
6 Fabrikasi posisi cerobong 1.00 ls Rp 5,000,000.00 Rp 5,000,000.00
7 Lis plank 12.00 ml Rp 75,000.00 Rp 900,000.00
8 Scaffolding 1.00 ls Rp 5,000,000.00 Rp 5,000,000.00
9 Painting lis plank 50.00 ml Rp 50,000.00 Rp 2,500,000.00
Sub Total A Rp 131,000,000.00
B PENGGANTIAN DINDING & PAINTING
1 Pembongkaran dinding ( 50 x 2,4 ) 120.00 m² Rp 50,000.00 Rp 6,000,000.00
2 Pemasangan dinding nusa board ( 9 mm ) 120.00 m² Rp 150,000.00 Rp 18,000,000.00
3 Painting dinding ( Nippon paint ) 150.00 m² Rp 115,000.00 Rp 17,250,000.00
4 Kayu 5/7 0.50 m³ Rp 6,000,000.00 Rp 3,000,000.00
5 Penggantian engsel & close door 2.00 ea Rp 1,000,000.00 Rp 2,000,000.00
6 Penggantian kunci pintu 2.00 ea Rp 350,000.00 Rp 700,000.00
7 Penambalan dinding 2.00 ea Rp 750,000.00 Rp 1,500,000.00
8 Penambahan pintu rak di ruan AAS 18.00 ea Rp 500,000.00 Rp 9,000,000.00
9 Rehab dinding rak ruang AAS 1.00 ls Rp 1,000,000.00 Rp 1,000,000.00
10 Penggantian engsel pintu rak laboratorium 30.00 ea Rp 750,000.00 Rp 22,500,000.00
11 Pemasangan pintu rak 4.00 ea Rp 500,000.00 Rp 2,000,000.00
Sub Total B Rp 82,950,000.00
C RUANG MAKAN
1 Pembongkaran atap ruang makan 45.00 m² Rp 75,000.00 Rp 3,375,000.00
2 Pemasangan atap (seng kecil) 45.00 m² Rp 125,000.00 Rp 5,625,000.00
3 Penggantian dinding bagian bawah 40.00 m² Rp 150,000.00 Rp 6,000,000.00
4 Painting ruangan makan (all) 90.00 m² Rp 150,000.00 Rp 13,500,000.00
Sub Total C Rp 28,500,000.00
D RUANG INSPEKSI

1 Perbaikan/penggantian dinding pada ruangan 3.00 ea Rp 500,000.00 Rp 1,500,000.00


inspeksi dan painting
Sub Total D Rp 1,500,000.00
E PENAMBAHAN CANOPY/TERAS
1 Penambahan canopy teras 9.00 m² Rp 750,000.00 Rp 6,750,000.00
Sub Total E Rp 6,750,000.00
Grand Total (A+B+C+D+E) Rp 250,700,000.00
Bill Of Quantity
PT. Bima Nusantara Muda

ADDITIONAL FABRIKASI SHOP

UNIT PRICE
NO WORK ITEMS VOLUME SATUAN
IDR
1 Mob. & Demob. 1.00 ls Rp 700,000.00
2 Tambahan Atap ( 2m x 12 m) 1.00 ls Rp 2,500,000.00
3 Las Plavon 40.00 m' Rp 50,000.00
4 Tambahan Cloddy Spandek()5 + 16) 80.00 m² Rp 175,000.00
5 Pengelasan di Fabrikasi 120.00 Inchi Rp 19,000.00
Sub Total
tity

TOTAL PRICE
IDR
Rp 700,000.00
Rp 2,500,000.00
Rp 2,000,000.00
Rp 14,000,000.00
Rp 2,280,000.00
Rp 21,480,000.00
Bill Of Quantity
PT. Bima Nusantara Muda

RENOVASI BANGUNAN P14

UNIT PRICE TOTAL PRICE


NO WORK ITEMS VOLUME SATUAN
IDR IDR
A MOB. & DEMOB.
1 Mob. & Demob. 1.00 ls Rp 5,000,000.00 Rp 5,000,000.00
2 APD, HSE & ADM. 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Sub Total A Rp 7,500,000.00
B TERAS/CANOPY
Pembongkaran seng gelombang kecil (30 m x 2,5
1 m) 75.00 m² Rp 75,000.00 Rp 5,625,000.00

2 Pemasangan seng gelombang kecil 75.00 m² Rp 125,000.00 Rp 9,375,000.00


3 Scaffolding 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
4 Dinding lorong (penggantian & pengecatan) 3.00 ea Rp 500,000.00 Rp 1,500,000.00
Sub Total B Rp 34,000,000.00
C PENGGANTIAN ATAP FURNECE ROOM
1 Pembongkaran atap (fumira) 4x6 24.00 m² Rp 75,000.00 Rp 1,800,000.00
2 Pemasangan atap (fumira) 4x6 24.00 m² Rp 350,000.00 Rp 8,400,000.00
3 Repair atap ruang asam 1.00 ls Rp 3,500,000.00 Rp 3,500,000.00
4 Scaffolding 1.00 ls Rp 2,500,000.00 Rp 2,500,000.00
Sub Total C Rp 16,200,000.00
D PERBAIKAN PINTU ALMARI
1 Pintu almari ruangan bomb 2.00 ea Rp 500,000.00 Rp 1,000,000.00
2 Penggantian engsel pintu 18.00 ea Rp 75,000.00 Rp 1,350,000.00
3 Pintu almari ruangan TS 2.00 ea Rp 500,000.00 Rp 1,000,000.00
4 Penggantian engsel 16.00 ea Rp 75,000.00 Rp 1,200,000.00
5 Penggantian talang air ruangan tabung gas 14.00 ml Rp 250,000.00 Rp 3,500,000.00
6 Penggantian dinding ruangan adm preparation 2.00 ea Rp 500,000.00 Rp 1,000,000.00
7 Repair cerobong bocor pada ruangan lab 1.00 ls Rp 3,500,000.00 Rp 3,500,000.00
Sub Total D Rp 12,550,000.00
Grand Total ( A+B+C+D ) Rp 70,250,000.00