You are on page 1of 45

Measures of Material Handling

Systems

TVSM / PED / MSE / MHSE Slide 1


Performance Measure

Performance Measure
• A performance measure may be defined as a metric for quantifying efficiency
and effectiveness.

• As applied to material handling systems, the effectiveness of a material


handling system describes to what extent the system performs the required
handling tasks.

• Whereas, efficiency describes how economically the required tasks are


performed.

• It is possible for an effective system to be inefficient, and for an efficient


system to be ineffective.

• Performance measures may characterized based on


– Quality, time, cost, resource utilization, operating efficiency and flexible
measures

TVSM / PED / MSE / MHSE Slide 2


Measures

Measures

• Reliability

• Friction and noise

• Serviceability

• Maintainability

• TPM for MHF

TVSM / PED / MSE / MHSE Slide 3


Reliability

Reliability
• Reliability is the mathematical measure of the dependability of equipment.

• It may be measured in percent downtime or its converse, percent uptime.

• Either way measures the availability of the equipment to do the job it was
purchased to do.

TVSM / PED / MSE / MHSE Slide 4


Reliability

• Reliability is also a function of the user’s maintenance and operations


policies. Poor maintenance and continual overloading will decrease
reliability.

• Reliability data are usually an average derived from a sample of a number of


items. An individual item within the sample may deviate substantially from
the mean of the group.

TVSM / PED / MSE / MHSE Slide 5


Reliability

• Examples of commonly used reliability measures are :

1. Availability

2. Failure rate

3. Mean time between failure (MTBF)

4. Mean time to repair (MTTR)

TVSM / PED / MSE / MHSE Slide 6


Availability and Failure Rates

• Useful life should be High for any MHF

• It is the most common inquiry about a MHFS / MHES lifespan, and is


important in decision making process.

TVSM / PED / MSE / MHSE Slide 7


MTBF (Mean Time Between Failures)

MTBF

• When MHFS / MHES must be installed into critical application in Industry,


MTBF becomes very important.

• Failure rate of the each component of the system must be considered in


MTBF of the system.

TVSM / PED / MSE / MHSE Slide 8


MTTR (Mean Time To Repair)

MTTR
• It is the time needed to repair a MHFS / MHES.

• In an operational system, repair generally means replacing a failed part. Thus


MTTR can be viewed as mean time to replace a failed part in a system.

• Taking too long to repair a facility or equipment drives up the cost of


installation in the long run, due to down time until the new part arrives and
the possible window of time required to schedule the installation.

TVSM / PED / MSE / MHSE Slide 9


• Availability

• MTBF

• MTTR

TVSM / PED / MSE / MHSE Slide 10


Noise control

Noise control
• Since noise is an occupational hazard, noise control technology should aim at
reducing noise to acceptable levels by action on the material handling systems
and the work environment.

• Prior to the selection and design of control measures, noise sources must be
identified and the noise produced must be carefully evaluated.

• Sources of noise in Material handling systems:

– Mechanical shock between parts.

– Unbalanced rotating equipment like wheels of trolley.

– Friction between metal parts.

– Vibration of the parts in material handling system.

TVSM / PED / MSE / MHSE Slide 11


Noise control

• Methods to control noise :

– Maintenance
• Replacement or adjustment of worn or loose parts like joints, wheels, bearings.

• Balancing of unbalanced equipment.

• Lubrication of moving parts.

– Substitution of materials
• Plastic materials instead of metal parts.

– Specification of quiet material handling systems.

– Substitution of parts in equipment


• Usage of belt conveyors instead of roller conveyors.

TVSM / PED / MSE / MHSE Slide 12


Serviceability

Serviceability
• The availability, quality and accessibility of service facilities are important.

• The owner of equipment should be able to secure spare parts and good
maintenance service quickly and cheaply from the manufacturer or his
representative.

• Considering of all standard parts / materials (with standard dimensions) readily


available in market can eliminate the Non availability of system components,
thus MTTR can be reduced.
TVSM / PED / MSE / MHSE Slide 13
Maintainability

Maintainability

• Maintainability is the measure of the ease and efficiency with which a materials
handling system can be maintained.

• The increased efficiency and lower unit cost of mass producing original
equipment have led to lower first costs in relation to maintenance costs.
TVSM / PED / MSE / MHSE Slide 14
Maintainability

TPM for MHFS :

• An important operational aspect of a material handling system is good


maintenance of the equipment.

• “Maintenance is defined as to keep in an existing state (as of efficiency, repair


and validity) to preserve from failure or decline.”

The major features of maintainability are designed into the system from the
start. They include location of controls, lube points and panels for each
access, avoiding components subject to frequent failure, and redundancy of
vital components.

TVSM / PED / MSE / MHSE Slide 15


Maintainability

• Activities covered under Maintenance are :

– Repairing components and assemblies.

– Replacing defective parts.

– Adjusting the system for maximum operating efficiency.

– Routine preventive actions like lubricating, checking and inspection of


MHE.

– Keeping maintenance record for effective work.

TVSM / PED / MSE / MHSE Slide 16


Maintainability

• Maintenance objectives:

To keep the system operating at highest possible efficiency.

 To minimize production loss and downtime. Minimize system failures


and breakdowns.

 To perform the maintenance function as efficiently and economically as


possible.

TVSM / PED / MSE / MHSE Slide 17


Reactive maintenance

Reactive maintenance
– No matter how good the maintenance, emergency calling for immediate
maintenance action will arise. Some are due to poor preventive
maintenance, some to accidents, and some to failures that could not be
forecast or predicted.

TVSM / PED / MSE / MHSE Slide 18


Preventive Maintenance

Preventive Maintenance
– Preventive maintenance is designed to prevent future serious
maintenance problems and emergencies.

– Small amounts of time and money are spent continuously in order to


avoid large expenditures and losses later.

– Preventive maintenance includes regular lubrication, minor checking,


quick tests, and routine inspections. Some of these will prevent future
troubles.

– Emergency repairs are costly by themselves, but this expense is minor


compared to production interruptions.
TVSM / PED / MSE / MHSE Slide 19
Maintenance

TVSM / PED / MSE / MHSE Slide 20


Design / Selection Measures

Design / Selection Measures :

• Feasibility Analysis.

• Functional Analysis.

• Flexibility in Material handling systems.

• Traceability in Material handling systems.

TVSM / PED / MSE / MHSE Slide 21


Feasibility Analysis

• Feasibility analysis is an investigation into the extent to which a proposed


design can be carried out and to which it will be economically viable.

• Feasibility analysis is essential for effectiveness of Material handling


systems.

TVSM / PED / MSE / MHSE Slide 22


Feasibility Analysis

Contents of Feasibility Analysis:

1. Description of the material handling system.

2. Technical feasibility.

3. Operational feasibility.

4. Economic feasibility.

5. Other factors.

6. Alternatives.

TVSM / PED / MSE / MHSE Slide 23


Feasibility Analysis

1. Description of material handling system:

• Introduction of the report should be a narrative description of the project.

• It should identify the project, discuss its background and the reasons for the
project, and present the major features.

• Along with the narrative, the project should present the important conditions
surrounding the project.

• The goals and objectives of the proposed system and the criteria and
constraints should be listed.
TVSM / PED / MSE / MHSE Slide 24
Feasibility Analysis

2. Technical feasibility:

• Technical feasibility includes the ability of the material handling system to


move the product, maintainability, reliability, and ability to withstand loads
and forces.

TVSM / PED / MSE / MHSE Slide 25


Feasibility Analysis

3. Operational feasibility:
• This is defined as the ability of the material handling system to meet operational
requirements such as units of product moved per hour.

Technical feasibility is the ability of the system and its components to meet the
required strength and similar specifications. whereas Operational feasibility is
its ability to meet the movement requirements of the production system of
which the material handling system is a part.

TVSM / PED / MSE / MHSE Slide 26


Feasibility Analysis

4. Economic feasibility:
• It is the ability of the material handling system to earn back the investment plus a
return acceptable to management.

• Unless a system is economically worthwhile, technical and operational feasibility


is immaterial.

• Methods of assessing economic feasibility:

1. Payback period

2. Present worth

3. Equivalent uniform annual amount

4. Rate of return

5. Unit cost

TVSM / PED / MSE / MHSE Slide 27


Feasibility Analysis

Problems related to economic feasibility :


# 1.

A materials handling system report carries the following estimates:


Installed cost = $ 14,500
Annual savings = $ 18,000
Annual operating costs = $ 3,200

What is payback period?


Hint : Payback period = (Installed cost / Net annual savings).
Activity : Plot the graph for solution. (hint : Dollars v/s Years).

TVSM / PED / MSE / MHSE Slide 28


Feasibility Analysis
# 2.
A company is investing buying a warehouse. Two locations are under
consideration. The required rate of return is 35 % per year before taxes.
Location.
A B
Land cost $ 600,000 $ 900,000
Building cost $ 3,500,000 $ 2,000,000
Service life 20 years 20 years
Salvage value after 20 yrs. $ 1,000,000 $3,000,000
Operating costs / year
Material handling $ 900,000 $ 600,000
Others $ 300,000 $ 500,000
Which location do you recommend on a present – worth basis?
Hint :
Present worth of a uniform annual amount: ((1 + i)n – 1) / (i (1+ i)n )
Present worth of a future sum : 1 / ( 1 + i)n
i= Rate of return,
n = Service life in years.
Activity : Prepare a chart for solution. (hint : bar diagram)
TVSM / PED / MSE / MHSE Slide 29
Feasibility Analysis

5. Other factors :

• Characteristics and data like downtime, delivery time, personnel requirements,


training, and information on similar systems if available.

6. Alternatives:

• In this section are listed the alternatives considered but not recommended.

• Each should have a brief description and a statement of reasons why the
selected option was recommended over a rejected one.

TVSM / PED / MSE / MHSE Slide 30


Feasibility Analysis

Multicriteria evaluation:

• Feasibility analysis for non – economic and qualitative factors.

1. For and against:


a. List down the advantages and disadvantages of each alternative for
each criteria.

b. No attempt is made to weight, rank, scale or otherwise


quantitatively evaluate the factors.

Example :

TVSM / PED / MSE / MHSE Slide 31


Feasibility Analysis

2. Scaling :
a. One way to combine several criteria into one figure of merit for
evaluation in scaling.

b. The estimated worth of each criterion is expressed as a numerical scale


value usually on the basis of 1 to 100.

c. The scale values can be combined since they are independent of the
units of measurement.

d. Major difficulties with this method are establishing the scale and
assigning values to the individual alternatives.

Example :

TVSM / PED / MSE / MHSE Slide 32


Feasibility Analysis

3. Ranking :
a. In this method, each alternative is ranked against the others for each
of the chosen criteria.

b. The rankings are added. The lowest alternative is ranked 1.

c. Others are ranked in order up to the highest, which is given a rank


equal to the number of alternatives.

d. The alternative with the highest rank total is recommended.

Example :

TVSM / PED / MSE / MHSE Slide 33


Feasibility Analysis

4. Weighting :
a. Not every criterion in a multi-criteria evaluation is equally important.
Normally economic factors will predominate.

b. One way to handle this problem is to weight each factor in


accordance with its relative importance.

c. Weighting usually goes with ranking or other similar methods.


5. Factor analysis :
a. Factor analysis is a combination of ranking or scaling with weighting.

b. A weight is assigned to each factor according to its importance.


This weight is then multiplied by the rank assigned to the alternative for
that factor.

c. The weighted ranks are added. Note that in this method, the ranks
are from 3 for the best to 1 for the worst.

TVSM / PED / MSE / MHSE Slide 34


Feasibility Analysis

Example :

TVSM / PED / MSE / MHSE Slide 35


Functional Analysis

Functional Analysis

• Vehicle travel

• Vehicle travel proportions

• Vehicle travel : Response time

• Handling time per job

• Vehicle utilization

• Mean load waiting times

• Mean queue lengths

TVSM / PED / MSE / MHSE Slide 36


Functional Analysis

Vehicle travel

• Vehicle travel is generally measured as actual path distances travelled by


the Material handling equipment.

• The total vehicle travel distance consists of loaded and empty vehicle travel.

• Vehicle travel distance is easily calculated when the flow volumes and the
distances between the stations are known.

TVSM / PED / MSE / MHSE Slide 37


Functional Analysis

Vehicle Travel Proportions

• A Material handling equipment / facility may be in one of the three states at a


given time:
Travelling loaded
Travelling empty
Idle

• Travel time percentages may be calculated as a fraction of time that a device is


travelling loaded, travelling empty and waiting in an empty state.
• That is, T = TL + TE + TI

TI = total idle time,


T = total time,
TL = as above (total loaded travel time),
TE = as above (total empty travel time).

TVSM / PED / MSE / MHSE Slide 38


Functional Analysis

Handling Time Per Job

• The handling time per job is comprised of the time directly


associated with material handling.

• This time includes:


– The time the job spends in queues waiting for the material handling
vehicle.
– The total travel time.
– The total loading and unloading times.
– The total vehicle blocking times.

• The total handling time per job includes the time from when a job
enters the system until it leaves the system.

TVSM / PED / MSE / MHSE Slide 39


Functional Analysis

Mean load waiting times :

• The mean load waiting time is defined as the mean time loads wait in queues for
material handling transportation.

• These queues are located either at processing stations or at separate load


transfer stations.

Mean queue lengths :

• The mean queue length is the mean number of loads waiting for a material
handling vehicle over a specific length of time.

TVSM / PED / MSE / MHSE Slide 40


Traceability of MHFS

• Tracking keeps track of the location and status of every work piece in the
system.

TVSM / PED / MSE / MHSE Slide 41


Traceability of MHFS

• Tracking can serve several purposes like,

• Making adjustments to the production schedule to compensate for


breakdowns and to meet changed priorities.

• Aiding scheduling of future production.

• Material handling control, i.e timely movement of material to and from the
workplace is essential to be efficient.

• Recording maintenance activities of MHFS.

• Status tracking and reporting.

• Provide communication between operator and management.

TVSM / PED / MSE / MHSE Slide 42


Traceability of MHFS

VEHICLE MONITORING SYSTEM (VMS) :

• INTELLIGENT SYSTEM to monitor Battery of the TOW TRUCK.

• Record starting & ending time of moving, idling and charging of the truck.

• Communicate with Server via GPRS.

• Indicates Tow Truck’s movement details on a 2 x 16 LCD as well as set of


LEDs.

TVSM / PED / MSE / MHSE Slide 43


Traceability of MHFS

OVERALL ARCHITECTURE
Cell-
Phone
Service
provider

TVSM / PED / MSE / MHSE Slide 44


Traceability of MHFS

Components that make VMS

The TOW TRUCK is fitted with VMS unit. The VMS unit (using
GPS) time stamps and records the position and activities. The
DATA is sent through GPRS to the data server in the factory
TOW TRUCK VMS in near real-time.
Module

The factory Server has a Static IP. Each TOW Truck has a
GPRS Module and sends data over Cell Phone service
provider’s network to Factory Server’s Static IP. The factory
FACTORY
SERVER server is connected to LAN and all PCs in LAN.

The Vehicle Monitoring System (VMS) is an intelligent µC


based unit with an unique ID and monitors truck’s battery
2x16 LCD current and voltage. VMS records its current position and
speed using a GPS module. VMS has an inbuilt memory to
Vehicle Monitoring log the data even in case of a communication fault.
System with GPS &
GPRS Modules

TVSM / PED / MSE / MHSE Slide 45

You might also like