Professional Documents
Culture Documents
Theory:
PERT was developed by the US Navy for the planning and control of the
Polaris missile program and the emphasis was on completing the program in
the shortest possible time. In addition PERT had the ability to cope with
uncertain activity completion times (e.g. for a particular activity the most likely
completion time is 4 weeks but it could be anywhere between 3 weeks and 8
weeks).
An Activity Network Diagram helps to find out the most efficient sequence of
events needed to complete any project. It enables you to create a realistic
project schedule by graphically showing
· the total amount of time needed to complete the project
· the sequence in which tasks must be carried out
· which tasks can be carried out at the same time
· which are the critical tasks that you need to keep an eye on.
The Activity Network diagram displays interdependencies between tasks through
the use of boxes and arrows. Arrows pointing into a task box come from its
predecessor tasks, which must be completed before the task can start. Arrows
pointing out of a task box go to its successor tasks, which cannot start until at least
this task is complete.
Procedure:
Tasks or Activities : Effective planning of projects requires careful thought and the
application of logic. To illustrate this planning tool, let's consider the manufacture
of a small item. Some typical processes might be:
Output:
Integration of
Modules
2 6
Testing
16
5 17
9 8 ` 7
Feedback
Deployment