Professional Documents
Culture Documents
Team Members:
Date: 2021/12/07
ENJ333: Power Systems 1 2-7
Abstract
This paper needs to design a transmission line to connect a 180MW wind farm with 230kV
original system.
First of all, through consulting data, combined with Matlab calculation of transmission line
parameters, combined with Power System simulation, cost calculation, four design schemes are
selected. Furthermore, through SWOT analysis, the most appropriate scheme is selected among the
four schemes. The solution is to connect Bus5 by tower B with a radius of 21.0mm.
Secondly, the fault current at the end and in the middle of the circuit is calculated by the
standard unit method to analyze the safety of the circuit. The project decided on series reactors to
offset the reactive power of the wind farm and new transmission lines to solve the overload problem.
The scheme has been improved.
Then, the rationality of the final scheme is evaluated, and power loss analysis, power flow
analysis, described the situation of reducing power generation.
The final design is a transmission line with high security and high cost performance. In the end,
it analyzes the challenges encountered in the design process and how to overcome them. Finally, the
contribution of team members is stated.
Key words: Transmission Line Design; Power World; Fault current; Safety Analysis
ENJ333: Power Systems 1 2-7
Content
1. Introduction...................................................................................................... 1
1.1 Design Method.......................................................................................................... 1
1.2 Overview of Wind Power..........................................................................................2
2. Design of Transmission Line........................................................................... 3
2.1 Conductor Selection of Transmission Line...............................................................3
2.1.1 Calculation of Current.................................................................................3
2.1.2 Selection of Conductor.......................................................................................... 3
2.2 Selection of Tower.................................................................................................... 4
2.3 scheme listing and Parameter Calculation................................................................ 5
2.3.1 List of Schemes........................................................................................... 5
2.3.2 Calculation of Parameters........................................................................... 5
2.3.3 Cost Calculation.....................................................................................................8
2.4 Simulation................................................................................................................. 8
2.5 Final Project Selection and Evaluation.....................................................................9
3. Fault current analysis.....................................................................................11
3.1 Introduction to Fault Current.................................................................................. 11
3.2 Calculation of Fault Current................................................................................... 11
4. Power system security analysis..................................................................... 14
4.1 Cause Analysis of Line Overload........................................................................... 14
4.2 Solutions to Safety Problems.................................................................................. 15
4.3 Cost Calculation of New Power System.................................................................16
5.Analysis and Evaluation of Design Scheme.................................................. 17
5.1 Rationality of The Design Scheme......................................................................... 17
5.2 Power Flow Analysis.............................................................................................. 17
5.3 Power Loss Analysis............................................................................................... 17
5.4 Reactive Power Analysis of Wind Farm.................................................................18
5.5 Analysis of Power Generation Reduction...............................................................18
5.6 Analyze the Urgent Problems To Be Solved In Wind Power Generation.............. 19
6. Summary.........................................................................................................19
7. Reflection........................................................................................................ 19
7.1 Challenges Encountered In The Design Process.................................................... 19
7.2 Difficult Solutions And Our Harvest...................................................................... 20
7.3 Contribution of Team Members..............................................................................20
Ⅰ
ENJ333: Power Systems 1 2-7
Acknowledgment................................................................................................ 21
Reference.............................................................................................................21
Appendix............................................................................................................. 22
Ⅱ
ENJ333: Power Systems 1 2-7
1. Introduction
Figure 1.1 mainly describes the work of this project. The steps and specific ideas of this design
are as follows:
(1) Analysis preparation. Learn about wind farms by consulting materials, field visits, and analyzing
specific plans.
(2) Transmission line design. First, the current on the transmission line is calculated and the
combination of conductor and tower that meets the requirements is selected. Then the parameters
of the line are calculated and simulated with Power System software. Finally, based on the cost
factor, choose the most appropriate combination.
(3) Analyze the scheme. Analyze the influence of power grid connection on power grid. The power
flow analysis was carried out. The reduction of power generation is analyzed.
(4) Calculate the fault current. This design uses the standard unit value method to calculate the
wind farm end and middle fault current.
1
ENJ333: Power Systems 1 2-7
(5) Analysis of security problems. If one line is disconnected during operation, it can overload the
rest of the grid. Therefore, this project provides three solutions.
(6) Final evaluation of the design. Combined with various factors, the rationality of the project
design is evaluated.
(7) Reflection and summary. Finally, we analyze the challenges encountered in this design, and the
challenges are analyzed and summarized. It also illustrates the contribution of each person on the
team to the project.
Figure 1.2 Wind turbine Figure 1.3 Wind farm control room
Our team visited a power plant in Shandong. Their control room is shown in Figure 1.3, where
you can see the value of the power generated by the wind turbine and its operating status. According
to local staff, the power plant will make certain regulations and adjustments to the amount of
electricity discharged according to users' electricity consumption to avoid power loss. This is the
problem of absorbing space. In addition, the automatic control and energy storage of the fan are also
being studied.
2
ENJ333: Power Systems 1 2-7
The current of the transmission line is 450A. Therefore, the rated current of the transmission
line selected for the project shall be greater than 450A.
3
ENJ333: Power Systems 1 2-7
Combined with the calculated current of the transmission line, the conductor has the following
options, as shown in Table 2.2. That is, when the conductor does not split, select the conductor with a
diameter of 31.5mm is suitable.
In addition, split wires have the following benefits. Splitting the wire can make the transmission
line less reactance, better cooling, less corona effect and so on. According to experience, two bundle
conductors are generally used for transmission lines above 220kV.
Three types of corner towers are listed in this project. The main difference lies in the different
phase spacing, which affects the transmission line parameters, as shown in Table 2.3.
4
ENJ333: Power Systems 1 2-7
Before calculating the values of inductance and capacitance, it is necessary to calculate the
mean geometric radius (GMD) of the three-phase conductor and the mean geometric radius (rb) of
the split wire, as shown in FIGURE. 2.1. For the diallel traverse of tower B, the average geometric
radius is:
Since the conductance is very small, it is assumed to be zero in this design. When calculating
GMD parameters, the distances between wires are shown in the Figure below.
Calculate the reactance X and susceptance B of the circuit according to the formula:
� = �� = 2��� = 2� × 50 × 1.0647 = 0.3345 �/��
� = �� = 2��� = 2� × 50 × 0.01096 = 3.4417 × 10−6 �/��
6
ENJ333: Power Systems 1 2-7
In this design, the long line model as shown in Figure 2.2 is used to calculate the parameters Z
and Y of the line:
Figure 2.2
7
ENJ333: Power Systems 1 2-7
2.4 Simulation
This part mainly describes the simulation standards developed in this design to evaluate these
48 schemes in the same way. All the above 48 schemes are simulated. Except for the overload
condition of the scheme connected to BUS8, all the other requirements are met. The simulation
results of 48 schemes are in Appendix D.
The criteria of this design guideline are as follows: Assume that the wind farm generates
180MW of electricity at this time. The resistance, reactance, susceptance and other parameters of the
line are found in Appendix C. The scheme that meets the requirements should be the voltage with a
PU value between 0.95 and 1.05 and without overload.
The simulation diagram of a certain scheme (2 split wire, wire diameter 21.0mm, tower B) as an
example is shown in Figure 2.3. Combining the above criteria, it can be found that this situation is in
line with the requirements.
8
ENJ333: Power Systems 1 2-7
Plan Bundled conductor Conductor type Tower Conductor material System stability Security Cost Total
Plan No bundling/Bus
8 8.5 9 10 9 8.5 9.5 8.929
A 5/Tower C
2 Bundling
Plan
conductor/Bus 9 9 9 10 8.5 9 9 9.071
B
5/Tower B
2 Bundling
Plan
conductors/Bus 5 8.5 9 9 10 8.5 9 8.5 8.929
C
Tower C
Plan 3 Bundling 8.5 8.5 9 10 8 9 7.5 8.643
9
ENJ333: Power Systems 1 2-7
D conductors/Bus
5/Tower B
Table 2.9 SWOT analysis of scheme
SWOT Positive Negative
Plan A The cost is low One wire for each phase, high resistance
To sum up, the final scheme of the project is shown in the Table 2.10 below
Table 2.10 Detailed parameters of the final scheme
Figure
After a comprehensive
Tower evaluation, the score for
this part was 9.5
Phase Layout Vertical phasing
Phase Spacing 2.2m
Average
Cost $74,000 per km score: 9.17
Bus Name Bus5 After comprehensive (10 points
Bus Length 25km
evaluation, this part is scale)
rated 9.0
Code Name SATURN
X=0.263Ω/km
Parameter B=4.308 s/km After comprehensive
Conductor R= 0.055Ω/km evaluation, this part is
Bundled conductor Bundling spacer-2 rated 9.0
Overall diameter 21.0mm
Cost $9000*2/km
The total cost $2950000(Labor and later operation and maintenance costs are not included)
10
ENJ333: Power Systems 1 2-7
11
ENJ333: Power Systems 1 2-7
following formula (4-1 and 4-2), the reference current is 251.02a and the reference reactance is 529
Ω.
�� 100��
�� = = = 251.02A
3�� 3 × 230��
�� 230��
�� = = = 529�
3�� 3 × 251.02�
Calculate the unit value of motor reactance and transmission line reactance according to the
formula (4-3 to 4-5) :
�� 100
���(�) = = = 0.56
� 180
�0 ��� 0.2626 × 25 × 100
���(����) = = = 0.0124
�2� 2300
Where, Xpu(G) is the reactance per unit value of the wind turbine, Xpu(line)is the reactance per unit
value of the transmission line, and Xpuis the total per unit value.
Assumed that a fault occurs at K1, the unit value of the total reactance at the end of the line is:
��� = 0.56 + 0.0124 = 0.56
Therefore, the short-circuit current and short-circuit capacity are obtained:
Short circuit current:
�� 251.02
�= = = 438.539�
��� 0.5724
Short circuit capacity:
��� = 3��� = 3 × 230�� × 438.539� = 174.7���
Assumed that the system fails at K0, the unit value of the total reactance of the line is:
��� = 0.56
Therefore, the short-circuit current and short-circuit capacity are obtained:
�� 251.02
�= = = 438.539�
��� 0.5724
��� = 3��� = 3 × 230�� × 440.386� = 175.44���
Think about the whole system:
�� 251.02
��� = 0.17 �= = = 1476.588�
��� 0.17
��� = 3�� � = 3 × 230�� × 1476.588� = 588.23���
Table 3.1 Fault circuit calculation results
12
ENJ333: Power Systems 1 2-7
13
ENJ333: Power Systems 1 2-7
14
ENJ333: Power Systems 1 2-7
When one part of the line is disconnected, current can only flow from somewhere else,
overloading the rest of the grid.
15
ENJ333: Power Systems 1 2-7
rating than the previous one. The simulation shows that, as shown in Figure 4.4, the scheme can
effectively solve the overload problem.
Bundled
B(s/km) Tower2 Conductor Cost per km Length Total Cost
conductor2
16
ENJ333: Power Systems 1 2-7
18
ENJ333: Power Systems 1 2-7
6. Summary
Through calculation of transmission line parameters, fault current calculation and safety
analysis, the project finally designed a transmission line connecting the wind power plant to the
original line. The end result of the design was to split the wire with a radius of 21.0mm and connect
the wire to Bus5 using tower B. The rationality evaluation, power flow analysis and power loss
analysis of the transmission line (series reactor, parallel new transmission line) are carried out.
Finally, the original design scheme is improved to design a transmission line with high security and
high cost performance. At the end of this paper, the design of a summary, described the challenges
encountered in the design, and explained the way to overcome the challenges, stated the team
members to the design of the contribution.
7. Reflection
This part mainly describes the various challenges encountered in the design process of the
project, analyzes the causes of these challenges, and expounds how to deal with these challenges
and what to learn from them. At the same time, the ideas of how to improve the design and the
contributions of team members are described.
Acknowledgment
We would like to thank all those who helped us during the writing of this report.
First of all, We would like to thank Dr. Sarah Lyden for his help to us. Thank Dr. Sarah Lyden
for her patient live broadcast and video guidance, and for providing us with necessary materials and
valuable suggestions. It is Dr. Sarah Lyden's suggestions that let us notice some deficiencies and
promote our progress.
We would also like to thank Mr. Yao Fuqiang for his offline help and solving problems for us
face to face.
Finally, We would like to thank our team members for their unity and cooperation in this work,
helping each other to complete this report.
Reference
[1] Huang Zhongwen, Tang Mingzhe, Huang Zhao, Zhang Bowen, Wang Fafa. Modeling and
simulation analysis of micro wind turbine blades[J]. Mechanical Engineering and Automation,
2021, (06): 74-76.
[2] Hu Lanye, Jiang Wenbo, Li Yanting. Wind turbine fault diagnosis based on LightGBM[J]. Acta
Solar Energy, 2021, 42(11): 255-259.
[3] Huang Jundong, Xia Hongjian, Li Deyuan, Guo Kunxiang. Analysis of the influence of the swept
structure mode and flutter characteristics of wind turbine blades[J]. Acta Solar Energy, 2021,
42(11): 273-279.
[4] The pitch system of wind turbines[J]. New Energy Technology, 2021, (11): 41.
[5] Yang Xingxiong, Sun Shiyun, Huang Kehao. Wind farm output transformer fault identification
based on BP neural network model[J]. Electric Power Science and Engineering, 2021, 37(11):
23-31.
21
ENJ333: Power Systems 1 2-7
Appendix
Appendix A:
This section contains four charts: WBS, network diagram, Gantt chart and milestones. This
shows our work plan, process arrangement and decomposition of project tasks.
22
ENJ333: Power Systems 1 2-7
Appendix B:
Matlab code:
function [A,B,C,D, zc, y, Z, Y] = parameter(RX,B,l)
%This code is used to calculate the various parameters of the
%transmission line.
zc = sqrt((RX)/(B*10^-6));
y = sqrt((RX)*B*10^-6);
Z = zc*sinh(y*l);
Y = 1/zc*tanh(y*l/2)*2;
A = 1+Z*Y/2;
B = Z;
C = Y*(1+Z*Y/4);
D = 1+Z*Y/2;
end
23
ENJ333: Power Systems 1 2-7
Appendix C:
The calculation results of 48 combination parameters.
24
ENJ333: Power Systems 1 2-7
Appendix D:
48 combinations of simulation results.
Bus4:
Type
Type A
A
Bundling
No Type
spacer – 2 Type B
bundling B
conductors
Type
Type C
C
Type
Type A
A
Bundling Bundling
Type
spacer – 3 spacer – 4 Type B
B
conductors conductors
Type
Type C
C
25
ENJ333: Power Systems 1 2-7
Bus 5:
Type
Type A
A
Bundling
No Type
spacer – 2 Type B
bundling B
conductors
Type
Type C
C
Type
Type A
A
Bundling Bundling
Type
spacer – 3 spacer – 4 Type B
B
conductors conductors
Type
Type C
C
26
ENJ333: Power Systems 1 2-7
Bus 6:
Type A Type A
Bundling
No
Type B spacer – 2 Type B
bundling
conductors
Type C Type C
Type A Type A
Bundling Bundling
spacer – 3 Type B spacer – 4 Type B
conductors conductors
Type C Type C
27
ENJ333: Power Systems 1 2-7
Bus 8:
Bundlin
Bundling Tower Towe
Simulation results g Simulation results
pattern type r type
pattern
Type A Type A
Bundling
No
Type B spacer – 2 Type B
bundling
conductors
Type C Type C
Type A Type A
Bundling Bundling
spacer – 3 Type B spacer – 4 Type B
conductors conductors
Type C Type C
28
ENJ333: Power Systems 1 2-7
Appendix E:
Our PPT (Double-click the icon below to open our PPT, which is a PDF file)
Appendix F:
Our Power World document (Double-click the icon below to open our PPT, which is a PDF file)
29