REVISION NO: 06
1.0. PURPOSE : To ensure that all products purchased as according to specified requirements.
2.0. SCOPE : This procedure describes activities related to purchasing of all materials.
5.0. PROCEDURE :
All purchases should be properly pre-planned and stores assistant has to take the Re– Order
Report (i.e. Price Request & Approval Form – QP 11 – A) from the system for all
purchasing items by the 20th of each month.
Then send Price Request & Approval Form (QP 11 – A) to purchasing department to obtain the
quotation prices for these Re- order items.
Purchasing Executive should give his recommendation for this quoted prices and send (QP 11 –
A) to Assistant Stores Manager for his authorization.
After the authorization, QP 11 – A should be sent to approval of Management Accountant and
Factory Manager.
Finally, completed QP 11 – A form should be sent back to Stores Assistant (i.e. by 24 th of each
month) to raise PRNs for that particular month. All PRNs should be in sequentially
numbered order and indicate the required date. Separate PRN should be raised for each
supplier.
If any items are to be purchased outside initially submitted PRNs, DGM’s approval has to be
obtained.
Before raising PRN, call quotations through Purchasing Department for the items, which are
not purchased regularly and at least 3 quotations should be attached to PRN.
All PRNs should be checked by the Assistant Stores Manager and sent to Factory Manager and
he should pay attention to purchase price, quantity, correct supply & supplier.
Thereafter Factory Manager should give his recommendation to make the purchase and all the
PRNs should be sent to Management Accountant for her/his approval.
Following officials are authorized to recommend & approve the PRNs up to following limits.
After the approval, PRNs will be handed over to purchasing dept. they will send the
stores copy (pink) to Stores & keep the other two copies in their custody.
On receipt of PRN’s Purchasing Executive should prepare a schedule for purchasing &
inform the stores days within which purchases are to be made and communicate the
difficulties in purchasing the items in the following Memo Format:
PRN #ITEMREASON
Whatever the case, if not purchased within one month PRN will get automatically
cancelled.
Following officials are authorized to recommend & approve the PRNs up to following limits.
Rupee Value of PRNRecommended byApproved byUp to Rs. 5000.00Head of the Dept.Financial
AccountantOver Rs. 5000.00 and up to Rs. 20,000.00Head of the Dept.Financial Accountant &
Deputy General ManagerOver Rs. 20,000.00Head of the Dept.Financial Accountant,
Deputy General Manager &
Managing Director
Quotations should be called for items, which are not purchased regularly.
GRN (Factory)
On receipt of items, should be accepted by the Assistant Stores Manager or his nominated
representative with the presence of security personnel.
Stores should compare the items received with Order Copy & any documents sent by the
Supplier (Ex. Invoice. ADN) & inform any discrepancies to the supplier’s
representative or to the Purchasing Executive immediately.
Stores should raise GRNs on receipt of goods & the original copy should be sent to the
Purchasing Department with the approval of the Assistant Stores Manager & the
Factory Manager along with Purchase Order (Pink Copy) and Original Invoice.
Purchasing Executive should update his register & submit the original copy of the GRN along
with payment copy (Pink) of the Purchase Order & the original of the Supplier’s
Invoice & Original PRN within 3 days of receipt of the documents.
Purchasing Executive will raise GRN on receipt of goods & security should check
& place the seal on relevant documents.
All purchased items should be handed over to the respective departments within
the same day. Acknowledgement should be obtained from the department.
Either the respective Head of Dept, or an Executive should approve GRN.
After the Head of the Department’s approval, Purchasing Executive should update
his register & submit the original copy of the GRN along with the payment copy
(Pink) of the Purchase Order & Original of the Supplier’s Invoice & Original PRN.
General Points
Purchasing Department has to maintain a register for Registered Suppliers & also
obtain Price List from Suppliers. Management approval should be obtained for the
prices. Fresh quotation should be called every three months & list should be
updated. Copy of the list should be submitted to the Finance Department for
reference.
The same procedure should be followed for the purchase of Fixed Assets after
obtaining Managing Director’s approval.
Payments will be made on receipt of all relevant documents.
Purchasing will be done only twice a week. Special approval has to be obtained
from General Manager for additional visits by the Purchasing Staff.
Purchasing Staff have to arrive to office on or before 4.30 p.m.
Batch
NoBank &
TermsConfirm
DateLast LME
Nominating DateETATo the FacGap of the
ShipmentsQTY
(Mtns)SupplierStatus
Copies of the RM plan to be forwarded to the Director, DGM, Accountant, FM and AM
stores.
FM / Prod. Eng. / Prod. Executive should prepare PRNs for the imports according
to the RM plan & the signed PRNs by AM stores & FM to be forwarded to the
Management Accountant. Management Accountant should check & sign the same
& will have to be forwarded to the Financial Accountant, DGM, Directress & MD
for authorization.
Management Accountant should call quotations, & decision can be made on prices
of suppliers with the instructions of the Managing Director / Director.
Management Accountant should clearly indicate the Suppliers Name, Item, Price,
Qty & the ETA of the shipment in PO.
Once forward the SLT application to the bank the Financial Accountant should
follow up of clearing the documents, paying the duty & clearing the shipment with
Wharf Executive & the clearing agent.
MA should coordinate with Financial Accountant & the Wharf Executive to get the
information about the shipments clearing & to give necessary instruction to the
stores for arrangements of fork lift & unloading on the receipt of the raw material
to the factory.
To avoid the shortages arriving at shipment delays we have to keep a buffer stock
at least of 60 tons & to avoid the Factory been idle at any time we have to keep one
shipment in Work – In Progress.
According to our Sales Mix 74 % are Fast Moving Items, 12% is Moderate Moving Items & 14 % is Slow
Moving Items.
Due to that in Buffer Stock we have to keep 74% of the tonnage on Fast Moving Items 12% of the
tonnage on Moderate Moving & 14% of the tonnage on Slow Moving Items.
DescriptionMoving Rate1/1.13 Full CoilsFast Moving7/0.53 – 7/1.04 Single & FTFast Moving7/0.67
EWFast Moving16/0.20 TTF – 16/0.20 2 CoreFast Moving14/0.30 Auto WireFast Moving7/1.35 – 7/2.14
Single & FTModerateSpecial SizesModerate19 SizesSlow MovingAuto Wires other than 14/0.30Slow
MovingOther FlexibleSlow MovingBattery CablesSlow MovingEarth Wires other than 7/0.67 EWSlow
MovingAntenna WiresSlow MovingTelephone CablesSlow Moving
5.7.11. Following pattern will be followed to maintain the buffer stock (Assuming
a Sales Tonnage of 45 Tons) of raw materials,
ItemConfirm DateGap for ETD & ETAFor clearingCopper45 days before the budgeted ETA7 – 10 days
for Energya5 daysAluminium3 months before the budgeted ETA25 days for Universal5 daysPVC45 days
before the budgeted ETA15 – 20 days5 daysPE2 months before the budgeted ETA18 days5 daysXLPE2
months before the budgeted ETA14 days5 daysSteel65 days before the budgeted ETA30 days5 days
After building up the stock to maintain the buffer we can produce 45 tons per month by
giving 2 Copper shipments in a month according to the following schedule.
Confirm DateLME Nominating dateETDETATo the Factory12th of the Previous month1st -5th of the
month15th – 20th of the month27th of the month30th – 2nd of the month22nd of the previous month10th – 15th of
the month25th – 30th of the month7th of the month10th – 12th of the month
5.7.12 Management Accountant should prepare the Imports Schedule on every Thursday
& Copies should be forwarded to MD, Director, DGM, FM and Accountant.
5.7.13. All the documents related to any shipment will be lodged in a separate import file
numbered in sequence order from the beginning of the year which will be
maintained by the Finance Department under the custody of the Financial Accountant. All
file numbers are included in imports register with the details of the shipment for easy
reference.
Management Accountant should update all the shipments in supplier database, & hard copy has to
be filed for future reference and copies should be forwarded to DGM and FA on 6 th of every
month. For each supplier Management Accountant has to maintain separate files, which
includes the data of the order, confirmed prices quoted, etc.
Evaluation of Supplier
Once the Complaint (QP 11 – M) is received it should be entered in a (QP 11 – P) as per the
given instruction in (QP 11 – P).
Purchasing Executive should separately maintain the complains (QP 11 – M) file for reference &
a list of black listed suppliers (QP 11 – R).
Material complaint (QP 11 – M) has to be raised by the Departmental Heads & sent to
Purchasing Executive through Factory Manager.
Evaluation Criteria for local suppliers is clearly mentioned in supplier Evaluation Form (QP 11
– P)
MACHINERY PARTS
Depending on the machinery breakdowns and the engineering stock availability PRNs will
be raised through the stores similarly as above and the rest of the procedure will be same.
Depending on the value and the supplier terms, payment term will be changed as L/C,
bank draft or a TT.
Import & Local Purchases ( Raw Materials & Imported Spare Parts )
Management Accountant shall maintain the supplier register for Raw Materials &
Imported Spare parts ( QP 11 – K ) & Supplier Evaluation Form for Raw Materials &
Imported Spare Parts ( QP 11 – N ) separately for each supplier.
Raw Materials & Imported Spare Parts supplier evaluation has to be carried out for a
period of two years the process to be started again. If a particular supplier was black
listed (QP 11 – R & QP 11 – S) during the past two years period, he should not be
considered as a supplier thereafter.
Under the evaluation of supplier for items mentioned in 5.8.2. following two categories
are identified :
Raw Material complaints (QP 11 – M) are generated by the Quality Assurance Executive or relevant
Department Head, based on the data recorded in the following registers,
The above Registers are maintained according to the specification Manual QP 11 – E and Incoming
Inspection plan QP 11 – J.
Imported Spare parts defects / complaints (QP 11 – M) are generated by Maintenance Department.
QP 11 – M has to be sent to Management Accountant (Imports) or Purchasing Executive (Locals) through
the Factory Manager.
6.0. REFERENCE :
To : Date : …………………….
PRN No. : …………………….
DescriptionBrandQtyPricesRemarks12312345678910
Checked by Approved by Approved by
Asst. Stores Manager :…………….. Accountant :………………….………… Managing Director :………………….
Remarks:
………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………
No. :
SignatureRemarks
Lot No.BrandTypeTested bag No. & ColourReceived DateTested DateSpecific GravitySG value in Manufacture’s T/ReportUniformity of
Lot No.Received DateInspected DateInspected Drum No.Drum DimensionsWood preservative applicationQC SignatureRemarksFlange
Lot No.Label No.Received DateInspected DateLabel ColourLabel Dimensions LXWXTDescription on cableQC SignatureRemarksWire
Resistivity8 ± 0.38 mm
Max. 0.017241 Ω mm2 /mASTM B-49
Manufacture’s test reportQP 11 –F
QP 02 –BLabels01 NosOne sample per each lot and each typeArt work
DescriptionAccording to specification manualSpecification manual
(QP 11 –E)QP 11 –I
QP 02 –B
MATERIAL COMPLAIN NOTEFOR LOCAL PURCHASES & IMPORTSSerial No. : To : PURCHASING EXECUTIVE
- LOCAL PURCHASES / IMPORTSDATE ITEM PRN NO. NAME OF THE SUPPLIER SHIPMENT / BATCH
IDENTIFICATION NON CONFORMITY ………………………………...………..…………………………….
……………………………… Complain raised by (Name)Dept. Signature COMPLAIN AUTHORIZED BY : Factory Manager :
………………………………….Date :………………………………………... ACTION TAKEN
……………………………………………………………………………. Purchasing Executive / Management
Accountant Date
EVALUATION
CRITERIAMAX.150
MARKSMAX.200 MARKSMAX.150 MARKSPRICE EVALUATIONQUALITY
EVALUATIONDELIVERY EVALUATIONLowest – 150For each ComplaintOn time – 150 2nd Lowest – 10050
marks will be Delayed - 503rd Lowest – 80Reduced.4th Lowest – 60Others - 0
ORDER NOPO NOPRICE EVALUATION MARKSQUALITY EVALUATION MARKSDELIVERY
EVALUATION MARKS12345678910AVERAGESUM OF AVERAGE MARKS
If Sum of Average Marks < 350,
That Supplier has to be Black Listed & Black Listed Local Suppliers’ List ( QP 11 – R ) should be also
maintained by Purchasing Executive ( Local ) for reference.
Note :- Goods arrived in the required date mention in the purchase order (PO) has to be called as “ On
Time Deliveries” & gets 150 marks.
Goods which come after the required date mention in the purchase order (PO) has to be called as “Delayed
Shipments” & gets 50 marks.
Item : ………………………..
Batch
NoBank &
TermsConfirm
DateLast LME
Nominating DateETATo the FactoryGap of the
ShipmentsQTY
(Mtns)SupplierStatus
Plan for the month of .............................CopperQty (Kgs)PVCQty (Kgs)Opening Stock Opening Stock Finished GoodsFinished
GoodsWIPWIPTotal Opening StockTotal Opening StockAdd:Add:ETA-ETA- Payment-Payment- ETA- ETA- Payment-Payment- ETA- ETA-
Payment-Payment- ETA- ETA-Payment- Payment- ETA- ETA- Payment- Payment- Less: Less: Wastage Allowed (0.5%)Wastage Allowed
(0.5%)Closing Stock Closing Stock Finished GoodsFinished GoodsWIPWIPTotal Closing StockTotal Closing Stock Total Production- Total
Production- Total Available for Sales- Total Available for Sales- Total Planned for Sales- Total Planned for Sales- Buffer Stock (Planned 15
MT)Buffer Stock