You are on page 1of 13

Computers and Geotechnics 115 (2019) 103169

Contents lists available at ScienceDirect

Computers and Geotechnics


journal homepage: www.elsevier.com/locate/compgeo

Research Paper

Behaviours of wall and soil during pre-excavation dewatering under T


different foundation pit widths

Chao-Feng Zenga,c, , Gang Zhengb, Xiao-Feng Zhoua, Xiu-Li Xuea, Hai-Zuo Zhoub
a
Hunan Provincial Key Laboratory of Geotechnical Engineering for Stability Control and Health Monitoring, School of Civil Engineering, Hunan University of Science and
Technology, Xiangtan, Hunan 411201, China
b
School of Civil Engineering, Tianjin University, Tianjin 300072, China
c
College of Civil Engineering and Architecture, Guangxi University, Nanning, Guangxi 530004, China

A R T I C LE I N FO A B S T R A C T

Keywords: Dewatering before excavation can induce obvious wall deflection; however, engineers rarely monitor it before
Deep excavation excavation. This traditional monitoring data will undervalue the environmental effect induced by foundation pit
Dewatering construction. In this study, a dewatering test conducted in a large-scale foundation pit is reported. Then, 35
Wall defection numerical models considering different pit widths are developed to simulate the dewatering process based on the
Ground deformation
test results. The pit deformation behaviours during dewatering with different pit widths (Wp) are analysed. The
Groundwater seepage
Numerical analysis
results indicate that time effect and size effect are two features of dewatering-induced deformation: (1) the pit
deformations grow rapidly during the first few days of dewatering, but the growth rate decreases continuously;
(2) the wider pit exhibits greater deformations, but there exists a critical pit width (approximately 40 m in this
study), within which the pit deformations grow rapidly (average approximately 0.03% of Wp increase); however,
with Wp being greater than the critical width, the pit behaviours demonstrate a slight difference.

1. Introduction The other construction group represents the activities carried out
during soil excavation, covering the staged excavation and dewatering,
In recent years, a mass of underground structures have been con- the construction of slabs or struts, the removal of struts and backfill,
structed in large cities due to the rapid urbanization [1–5]. The deep and the groundwater level recovery [34].
excavation technique is extensively used to help realize underground Among the above stages, we can easily understand that the stages
space exploitation and ensure safety during construction [6–13]. When during soil excavation can cause retaining wall and soil deformations
the foundation pit is excavated in the vicinity of existing buildings or since the existing relevant studies have fully proven these effects
facilities, a large challenge to engineers is deformation control. These [35–40]. In contrast, researchers are not sure whether PED can lead to
engineers must strictly restrict the environmental deformation caused retaining wall deflection because less attention and very limited in-
by foundation pit construction [14–16]. vestigations have been devoted to it. Although some scholars
In fact, the construction process of a foundation pit comprises many [11,17,27,32,41–44] have carried out PED tests and relevant numerical
stages, which can be generally classified into two groups [9], as shown simulations, their concerns relate to the dewatering-induced drawdown
in Fig. 1. One group represents the work conducted before soil ex- curve and soil settlement induced by drawdown. These investigators
cavation, mainly including the construction of a retaining wall and pre- did not investigate the behaviour of the retaining wall and its re-
excavation dewatering (PED). Additionally, PED is also called test lationship with soil settlement during PED. In fact, most engineers
pumping and is used to check whether the discharge rate of pumping consider that there is no wall deflection before soil excavation and
wells and the groundwater drawdown in wells can meet the design believe that wall deflections start from the first step of soil excavation.
requirement [17–22]. Moreover, PED has also been employed as a For this reason, in most projects, engineers rarely monitor the wall
pumping test before soil excavation to obtain the hydraulic parameters deflections during PED until soil excavation begins. Since retaining
of aquifers [23,24], evaluate the hydraulic barrier effect of retaining walls have already existed before PED, the retaining wall may show a
walls [12,25–28], or optimize the dewatering system [11,17,29–33]. deformation response during PED. That is, the wall deflection may


Corresponding author at: Hunan Provincial Key Laboratory of Geotechnical Engineering for Stability Control and Health Monitoring, School of Civil Engineering,
Hunan University of Science and Technology, Xiangtan, Hunan 411201, China.
E-mail address: cfzeng@hnust.edu.cn (C.-F. Zeng).

https://doi.org/10.1016/j.compgeo.2019.103169
Received 27 February 2019; Received in revised form 21 May 2019; Accepted 12 July 2019
0266-352X/ © 2019 Elsevier Ltd. All rights reserved.
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 1. Entire construction process of a foundation pit.

occur much earlier. The large-scale pit was surrounded by city roads on the north, west
Based on field observations in a metro foundation pit, Zheng et al. and east sides, and an existing tunnel called the Tianjin Underground
[21] found that retaining walls can develop an apparent deflection Diameter Line (TUDL) on the south side. TUDL, with an overall length
during the PED stage, and the maximum deflection can reach 10 mm. of 5000 m and a diameter of 11.6 m, is the first urban railway shield
Based on numerical simulations, Zeng et al. [9] noted that the total tunnel used for high-speed trains in China. The minimum distance be-
pressure in the soil-wall interface inside the pit decreases progressively tween the TUDL and the pit was approximately 16.5 m. The buried
during PED, which disequilibrates the original total pressure on both depth of the tunnel was approximately 13 m.
sides of the retaining wall. Under the action of a pressure difference, the Considering the existence of the TUDL, diaphragm walls were em-
retaining wall develops an inward deflection, which further induces the ployed as retaining structures on the south side of the large-scale pit
surrounding ground deformation due to the ground loss behind the with depths and thicknesses of approximately 33.1 m and 1.2 m, re-
wall. The above analysis indicates that the PED stage has already in- spectively. However, single-row bored piles were applied to retain soils
duced considerable retaining wall deflection and surrounding ground in the remaining locations of the large-scale pit with φ1000@1200 in
deformation. The monitoring data that does not include the deforma- the north side and φ900@1100 in the others. All the outer retaining
tion caused before soil excavation will undervalue the environmental piles were buried at approximately 28.8 m below the ground surface
effect of foundation pit construction. Hence, engineers and researchers (BGS). The design values of elastic modulus, axial compressive strength,
should consider this part of the deformation when they create a design, and the axial tensile strength of concrete for both the diaphragm wall
conduct monitoring or embark on a relevant study. and bored pile were 30 GPa, 14.3 MPa and 1.43 MPa, respectively [45];
However, until now, minimal attention has been attracted to this the design values of these three parameters for the two level of concrete
problem. Although Zheng et al. [21] and Zeng et al. [9] have conducted struts were 31.5 GPa, 16.7 MPa and 1.57 MPa, respectively [45]. A row
some PED tests and numerical simulations focusing on this issue, their of φ850@600 soil–cement mixed piles was installed behind the outer
research was only based on a single foundation pit with a pit width of retaining structures as sealing curtains. The depth of the sealing cur-
approximately 20 m. The obtained results cannot reflect the wall and tains was slightly larger than that of the corresponding retaining
soil behaviours in foundation pits with different widths. In addition, the structures and was long enough to block groundwater seepage from
measured data regarding PED-induced pit deformation are extremely beyond the foundation pit. A row of φ800@1000 bored piles, with the
few, and thus far, we have never found a case study reporting the re- same properties as the retaining structure, was set up to isolate the
sponse of a retaining wall to PED in a large-scale foundation pit. TUDL to reduce the tunnel deformation caused by the pit construction.
In this paper, an in situ PED test conducted in a large-scale foun- The specific location of the TUDL can be seen in Fig. 2(b). In addition,
dation pit is reported. The observed retaining wall deflection is ana- according to the national construction standard in China [46], the
lysed. Then, 35 finite element (FE) models are developed to simulate alarm value of wall deflection for this project was 0.2% of the final
the PED test. The models are verified by field measurements and used to excavation depth (i.e., approximately 30.6 mm).
investigate the deformation behaviours of retaining wall and sur- Fig. 3 presents the typical soil profile and soil properties at the
rounding soil during PED under different foundation pit widths. foundation pit site. The deposit at the site is the typical soft deposit in
Moreover, the mechanism by which foundation pits with different Tianjin [23,47] and mainly consists of saturated silts, silty clays and
widths will exhibit different responses during PED is clarified. On this silty sands in the upper 50 m BGS. There is one phreatic aquifer (la-
basis, some schemes are developed to help engineers better design the belled Aq0) and three confined aquifers (labelled AqI, AqII and AqIII)
PED process and analyse PED-induced wall and soil deformation. within 50 m BGS. The aquifers are separated by aquitards. In situ
pumping tests conducted previously showed that the hydraulic con-
nections among Aq0, AqI, AqII and AqIII were not apparent. The long-
2. Case study: PED in a large-scale foundation pit term phreatic water level was observed at depths of approximately
1.8 m BGS. Hydrostatic equilibrium for the three confined aquifers was
2.1. Project description and soil conditions reached at approximately 7, 9 and 10.5 m BGS from the upper to the
lower layers.
Fig. 2 shows a large-scale foundation pit for commercial buildings in
Tianjin, China. The pit was 190–270 m long, 180–190 m wide, and
15.3–17.25 m deep with an area of approximately 43,890 m2. In the pit, 2.2. Arrangement of the dewatering wells and observation instruments
there were four 17.25-m-deep rectangular shafts that were used for the
construction of high-rise buildings (i.e., B1-B4). The remaining places The dewatering technique was adopted inside the foundation pit to
were 15.3 m deep and were applied to construct some annex structures. lower the water level to below the final excavation depth. Fig. 2(a)
Because the general contractor required that building B4 should be shows the plane layout of the dewatering wells. There were 227 wells
constructed in advance, a row of φ900@1100 bored piles were adopted inside the pit. The well spacing was 12–20 m, and the drainage area for
north of B4, dividing the large-scale pit into two parts (note: φ900@ a well was approximately 200–250 m2, which is consistent with the
1100 means 900 mm in diameter and 1100 mm in pile spacing). A local experience [48,49]. The well length was 24 m, which indicates
braced excavation technique was employed in the southern part of the that the well bottom was located in AqI. This design decision was made
pit, and soil berms were used in the northern part of the pit for tem- because the final excavation depth was close to the top of AqI, and the
porary support. water level in AqI should be lowered to avoid confined water entering

2
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 2. Diagrams of the investigated foundation pit: (a) plan view; and (b) cross-section at A-A.

the base of the pit [25,26,50–52]. In addition, from the perspective of can be allocated at different depths in the dewatering well by engineers
construction technology, the wells were drilled with a diameter of to accomplish dewatering at varying depths.
800 mm and were fitted with a non-sand concrete well liner with a Fig. 2(a) also shows the plan arrangement of observation instru-
diameter of 500 mm. Because there were no fine sands in the concrete, ments. There were 20 inclinometer tubes (i.e., C1-C20) mounted on the
the well structure was full of gaps, and the groundwater around the well retaining structures to monitor their deflections. The inclinometer ac-
could easily flow into the well under the action of a seepage gradient. curacy can reach ± 0.02 mm/0.5 m, which meets the requirement
The borehole annuli were filled with gravel along the well depth. In specified by the national construction standard in China [53]. The
addition, each well was equipped with a submersible pump. The pump length of the inclinometer tube was approximately 29 m. The

3
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 3. Typical soil profile and soil properties at the foundation pit site in this study and in Ref. [9]. Note: γ = unit weight; ω = water content; e0 = initial void ratio;
mv = coefficient of volume compressibility; N = SPT blow counts; Kh = horizontal hydraulic conductivity; Kv = vertical hydraulic conductivity.

observation wells G1-G8 and YG1-YG2 were used to monitor the water connection between the wall behaviour and the dewatering progress
level change in Aq0 and AqI, respectively, outside the pit during con- inside the pit, Table 1 shows the PED construction details near each
struction. In addition, the soil and tunnel deformation markers were inclinometer tube. In addition, the PED test site reported in this study
also mounted around the pit, but because the environmental deforma- was approximately 2 km from a metro foundation pit site, in which a
tions were not observed during the PED construction, their markers are PED test was also conducted [9]. The soil conditions within 50 m BGS in
not shown in Fig. 2(a). the two sites are extremely similar (see Fig. 3). Hence, Fig. 4 also
presents the comparisons of the PED-induced wall deflection observed
in these two project sites.
2.3. PED test and field observation results
The following points can be obtained according to Fig. 4. First,
cantilever-type wall deflections were observed at all of the available
After the retaining structures and dewatering wells were set up on
inclinometer tubes, and the wall deflections became more apparent as
site, a PED test was conducted inside the foundation pit to check
the dewatering time elapsed (i.e., time-dependent effect). In practical
whether the discharge rate of the dewatering wells and drawdown in
engineering, engineers should notice this time effect and avoid long-
the dewatering wells can meet the design requirement. The PED test
term dewatering before soil excavation. Otherwise, the engineers
lasted 21 days (i.e., from May 24th to June 13th in 2013). During the
should take countermeasures to restrict the PED-induced deformation
test, the dewatering wells were opened to pump water the moment they
(e.g., installing the first level of the struts on the wall top in advance
were buried and formed. The pumps in the wells were always allocated
and then conducting the PED and subsequent soil excavation).
at 17.75 m BGS (i.e., approximately 2.5 m below the final excavation
Second, the maximum wall deflection of approximately 15 mm ap-
depth). In the first few days, it was found that a mass of wells did not
peared at C8 and reached approximately 50% of the alarm value of the
yield groundwater or yielded only a small amount of groundwater. The
wall deflection for this project. Because the designers did not consider
discharge rate of these wells was only 1–4 m3/d, which is significantly
this part of the wall deflection when designing the retaining wall, they
smaller than the designed discharge rate (i.e., 40 m3/d). The reasons
did not select a stronger retaining wall to restrain a larger deformation.
were the collapse of hole during the drilling of wells, and the untimely
Under such conditions, the appearance of a wall deflection before soil
development of dewatering wells after the well completion had been
excavation will make the deformation control in the follow-up series of
done. For this reason, the engineers reconstructed 78 wells near these
constructions (e.g., soil excavation) quite passive. Apparently, it is
poor-quality wells from May 31st to June 9th. The discharge rate of the
difficult to let the final accumulative wall deflection be smaller than the
newly reconstructed wells was stable and ranged from 20 m3/d to
alarm value or the allowable value if additional measures are not
40 m3/d. Meanwhile, the water level in the wells declined continuously
adopted to restrain the deformation. In this project, the final wall de-
and was located at the pump depth at the end of the PED test, which
flection at C8 was approximately 60 mm, which reached approximately
meant that the designed dewatering depth was reached. At that mo-
197% of the alarm value and led to the fracture of the city road behind
ment, it was concluded that the well quality was reliable and met the
C8. The above analysis indicates that the designers should consider the
design requirement.
PED-induced wall deflection when comparing schemes and thus select a
During the PED test, the water level change outside the foundation
stronger retaining wall to restrain the deformation induced by the en-
pit was observed. The water levels at G6 and G7 fell approximately
tire construction processes of the foundation pit, including the PED-
1.1 m and 0.2 m, respectively. However, the water levels at other lo-
induced deformation.
cations were basically unchanged. This behaviour indicates that the
Third, the development of the PED-induced wall deflection is closely
sealing curtain may have some defects near G6 and G7, causing a de-
related to the dewatering progress in the vicinity of the wall. Taking the
gree of hydraulic connection between the inside and outside of the
wall deflection change at C8 as an example (see Fig. 4(c)), before the
foundation pit near G6 and G7.
new wells were reinstalled near C8 (i.e., before June 6th), the wall
During the PED test, retaining wall deflections were also observed.
deflection induced by 7-day PED (i.e., from May 30th to June 6th) was
Unfortunately, it was inconvenient to conduct monitoring at many lo-
rather small. This effect may be because the water level decline inside
cations, such as C1-C4 and C11-C20, during the test due to conflicts in
the pit around C8 was not apparent before June 6th since the discharge
the construction. In this paper, only measurements at C5, C7, C8 and
rate of dewatering wells near C8 was extremely small. Under such
C10 were introduced. Fig. 4 shows the measured wall deflections at
conditions, the wall deflection will not be greatly developed due to the
these locations. To facilitate the following description and develop a

4
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 4. Measured wall deflections at (a) C5, (b) C7, (c) C8 and (d) C10 and their comparison with those reported by Zeng et al. [9].

Table 1 metro pit reported by Zheng et al. [21] increased by 10 mm during the
. Date for starting dewatering and reconstructing new wells near each in- 10-day PED (note: the dewatering depth in the metro pit was 16 m,
clinometer tube. which is close to 17.75 m in this study). A similar rule can also be found
Inclinometer tubes Date for starting Date for reconstructing new at C5, C8 and C10. In practical engineering, PED in a large-scale
dewatering wells foundation pit with a greater width should be conducted more care-
fully, and on this occasion, the engineers should increase the mon-
C5 June 2nd /
itoring frequency of the retaining wall deflection during PED con-
C7 June 2nd June 7th
C8 May 30th June 6th struction.
C10 June 6th / The above analyses reveal that the foundation pit width may have a
great effect on the PED-induced deformation. To further obtain the
deformation behaviours of the retaining wall and surrounding ground
unapparent transformation of the pore-water pressure to the effective during PED under different foundation pit widths and to seek the me-
stress [9]. However, after the new wells were reinstalled near C8 (i.e., chanism of why the foundation pit with different widths will exhibit
after June 6th), the PED-induced wall deflection obviously increased different responses during PED, a series of numerical simulations were
since the water level inside the pit declined continuously. The max- conducted.
imum wall deflection increased by 14 mm during the 7-day PED (i.e.,
from June 6th to June 13th). This wall deflection increment is ap-
proximately 12 times larger than that caused by the former 7-day PED 3. Numerical model
(i.e., from May 30th to June 6th). In practical PED construction, the
engineers may need to dynamically adjust the PED scheme (e.g., adjust 3.1. Simulation method and calculation range
the dewatering depth) according to the monitoring wall deflection.
Once a large deflection increment appears, they should reduce the de- In this Section, 35 numerical models considering different founda-
watering depth or even stop PED. tion pit widths were established to simulate the PED process. For sim-
Moreover, the PED-induced wall deflection will be more apparent in plicity, the plane shape of the foundation pit was set as a rectangle in all
a wider foundation pit than in a narrow pit under roughly the same PED of the models, the pit length (Lp) was kept unchanged at Lp = 200 m,
condition (i.e., roughly the same soil condition, dewatering time and and the pit width (Wp) was varied from 20 m to 200 m (i.e., Wp = 20,
dewatering depth). For example, as for C7 (see Fig. 4(b)), the maximum 30, 40, 80, 120, 160 and 200 m). In addition, the dewatering depth (Hd)
deflection increased by 11.7 mm during the 10-day PED (i.e., from June was also selected as a changing parameter (i.e., Hd = 5.5, 11, 16, 19
2nd to June 12th). However, the maximum wall deflection in a narrow and 21.5 m) in the simulations to help better reveal the Wp effect on the
PED-induced wall and soil deformations under different Hd values. All

5
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 5. Mesh of the model and layout of the foundation pit.

of the models were developed in the package ABAQUS, which considers The linear elastic model was used to simulate the behaviour of the re-
soil-fluid coupling based on the Biot consolidation theory [54]. taining wall. The elastic modulus of the retaining wall was 30 GPa [45].
Zeng et al. [9] developed a numerical model to simulate a PED test The unit weight and Poisson's ratio of the retaining wall were set to
in a metro foundation pit, which was approximately 2 km away from 25 kN/m3 and 0.2, respectively [21]. The wall was considered to be
the large-scale foundation pit described in Section 2.1. The soil condi- impermeable, and its thickness was set to 1 m for all the models. The
tions in the two pit sites were extremely similar, and only the thickness soil-structure interface in ABAQUS was a zero-thickness interface
of the soil layers was slightly different (see Fig. 3). In Zeng’s model, the formed by duplicated nodes of soil and structure elements in contact. It
Wp and Hd were set as 20 m and 16 m, respectively. Apparently, the can simulate slip along the soil-structure interface. The friction beha-
calculation case in Zeng’s model is one of the conditions considered in viour complies with the Coulomb frictional law. A detailed description
this study, and thus, the computed results in Zeng’s study can be em- of the interface property can be seen in Zheng et al. [57].
ployed as a comparison with those in this study. To facilitate this
comparison, some model information such as the soil conditions and 3.4. Dewatering well simulation
properties adopted in this study (see Section 3.3) are set to be the same
as those in Zeng’s model. The dewatering wells in the model were arranged according to their
Taking the case of Wp = Lp = 200 m as an example, Fig. 5 shows the usual distribution in engineering practice. For the 20-m-wide founda-
mesh of the FE model. Only a quarter of the foundation pit was simu- tion pit, the wells were set up in two rows [9,21,58]. For the pits with
lated in the model due to the symmetry. The model calculation range widths greater than 30 m, the wells were distributed evenly with the
was set to 200 m by 200 m in-plane, and thus the distance of the outer drainage area for a well of approximately 200–250 m2, which is con-
soil boundaries (the asymmetric sides) to the retaining wall was 100 m, sistent with that in the project described in Section 2.2. Fig. 5 shows the
which exceeds the range of the influence radius of the dewatering well plane layout of the dewatering wells in the case of Wp = Lp = 200 m.
estimated by Sichardt’s formula [55]. The vertical depth of the model There were a total of 49 wells in this 1/4 model. The well spacing was
was 50 m, along which the model soils were divided into 9 layers. 14.6 m, and the distance between well and retaining wall was 5 m. In
other calculation cases, the dewatering well distribution is similar to
3.2. Initial-boundary conditions that in the case of Wp = Lp = 200 m, but the well spacing has a slight
difference. In all of the models, the wells were always kept at one length
The initial water level was assumed to be located at the ground (i.e., 24 m); this well length is consistent with that in the case study. In
surface, and the soils are considered to be under the normally con- practical engineering, there are two types of material often used for
solidated state before dewatering [9]. The soil boundary will influence producing the structure of dewatering wells. One is steel, and the other
the computed results if the boundary conditions are not reasonably is non-sand concrete. In the case study reported in Section 2, the latter
defined [41]. Since the outer soil boundaries (the asymmetric sides) material was used for the dewatering well; therefore, this type of de-
were specified beyond the range of the influence radius of the well, i.e., watering well was simulated in all of the numerical models in this
there were no pumping-induced soil deformations there, the soil study. The linear elastic model was employed for the dewatering well.
movements at the two asymmetric sides and the bottom boundary were According to compression test, the elastic modulus of the non-sand
restricted in all directions. The grid points over two symmetric sides concrete used for dewatering well was approximately 10.6 GPa. The
were restrained from movement in the horizontal direction perpendi- unit weight and Poisson's ratio of the well were set to 23 kN/m3 and
cular to the symmetric sides but were free to move in other directions. 0.2, respectively [21].
In addition, a constant-head hydraulic boundary was applied on the two The function of the dewatering well was simulated by applying a
asymmetric sides with the water head at the ground surface. The two seepage boundary on a zone where the screen of the dewatering well
symmetric sides and the bottom of the soil were considered to be im- was located. In this paper, the drainage-only flow (DOF) seepage
permeable. boundary [9,21] was set on the screen zone because this seepage
boundary can well simulated the practical dewatering process in the
3.3. Soil, retaining wall and soil-structure interaction simulations case study. The DOF boundary assumes that the pore fluid velocity (vn)
at the specified zone was equal to kspw (i.e., vn = kspw) when pw is
The behaviour of the soils was assumed to obey the constitutive positive, where ks is termed the seepage coefficient and pw is the pore-
theory of modified cam-clay (MCC) [56] during dewatering. Table 2 water pressure on the element surface. Apparently, for a specific ks, vn
summarizes the main parameters for each soil layer. K0 was obtained will decrease due to pw decrease with the elapsed dewatering time; in
based on pressuremeter testing. The parameters λ, κ and M were cal- PED process in the case study, the discharge rate of dewatering well
culated from the triaxial test results. KH and KV were acquired by an would also decrease with the dewatering time elapsed due to the weak
inversion calculation based on pumping tests reported by Zeng et al. hydraulic connection between inside and outside of the foundation pit.
[9]. In addition, the Poisson’s ratio for the silty clays and clays and for Therefore, in the numerical model, the moment that the DOF boundary
the silts and silty fine sands was set to 0.33 and 0.30, respectively [21]. is activated, the dewatering process in the case study can be well

6
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Table 2
Main parameters for each soil layer.
Soil classification Hydrogeology Depth (m, BGS) γ (kN/m3) ω (%) e0 N (blows/0.3 m) Parameters for MCC model

K0 KH (m/d) KV (m/d) ecs λ κ M

Silty clays Phreatic aquifer 0–5.5 19.35 29.9 0.811 4.4 0.49 0.1 0.1 0.961 0.0553 0.0065 0.979
Clayey silts Phreatic aquifer 5.5–11 19.30 26.5 0.792 11.2 0.43 0.5 0.5 0.906 0.0312 0.0036 1.192
Silty clays Aquitard 11–19 20.10 26.4 0.696 7.5 0.5 5e−4 1e−4 0.890 0.0445 0.0052 0.979
Sandy silts Confined aquifer 19–24 20.15 21.9 0.640 22.4 0.42 1 1 0.777 0.0293 0.0034 1.202
Clays Aquitard 24–27 19.75 30.4 0.764 16.1 0.55 5e−5 1e−5 0.962 0.0397 0.0046 0.800
Sandy silts Confined aquifer 27–33 20.65 20.2 0.583 26.7 0.35 1 0.7 0.727 0.0283 0.0033 1.202
Silty clays Aquitard 33–37 20.50 22.4 0.611 16 0.39 5e−4 3e−4 0.786 0.0320 0.0037 0.900
Silty fine sands Confined aquifer 37–42 20.05 18.2 0.585 49.3 0.3 2.5 1.5 0.686 0.0191 0.0022 1.382
Silty clays Aquitard 42–50 19.30 23.8 0.676 – 0.39 5e−4 2e−4 0.851 0.0305 0.0035 0.900

Note: γ = unit weight; ω = water content; e0 = initial void ratio; N = SPT blow counts; K0 = coefficient of the earth pressure at rest; KH = horizontal hydraulic
conductivity; Kv = vertical hydraulic conductivity; ecs = critical state void ratio at reference pressure (1 kPa); λ = slope of the normal consolidation line; κ = slope of
the elastic swelling line; M = frictional constant.

Fig. 6. Computed η contour at Section 1-1 for the case of: (a) Wp = 200 m, Hd = 16 m; and (b) Wp = 200 m, Hd = 19 m.

simulated. The initial value of ks can be calculated using Eq. (1), where dewatering depth in all of the models was the same and was at 24 m. In
D is the well diameter; L is the length of the screen range; and q is the simulating the cases with different dewatering depth (Hd), the DOF
discharge rate. The derivation process of Eq. (1) can be referred to in boundary was applied on a specified zone in the well-soil interface; for
Zheng et al. [21]. The parameter q observed in the PED tests in this example, as to the cases of Hd = 5.5, 11, 16, 19 and 21.5 m, the de-
study and reported by Zeng et al. [9] can be adopted to calculate ks. watering simulation can be achieved with only applying the DOF
q boundary on a depth range of 5.5, 11, 16, 19 and 21.5 m in the well-soil
ks = interface.
πDLpw (1)

In addition, it should be noted that although the well length was


specified as 24 m in all of the models, it did not mean that the

7
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

3.5. Simulation procedure

After the soil initial state was established and the wall and dewa-
tering wells were installed in the model, the DOF seepage boundary was
activated, i.e., the PED process was simulated. For simplicity, let all of
the wells pump water simultaneously. The dewatering simulation time
was set to 21 days. Considering that the mass of the foundation pits
were not equipped with the first level of struts before PED, all of the
simulations in this study were conducted based on this situation.

4. Results and analyses

4.1. Model verification

4.1.1. Groundwater seepage


In the finite element analysis, the real drawdown of the water table
during dewatering was not considered, while the model can reflect the
effect of reductions in pore-water pressure in the soil for the case where
Fig. 7. Variation of δhm with t for the cases with similar Wp and Hd.
the water table remains unchanged. Similar treatment of water table
during dewatering simulation can also be seen in some literatures (e.g.,
Booker and Carter [59], Booker and Carter [60], Zheng et al. [21], and dewatering depth (Hd) will lead to a larger wall deflection. Hence, the
Zeng et al. [9]). In the model, the change in the pore-water pressure observed δhm should lie between the two computed curves. Apparently,
(pw) can demonstrate the groundwater seepage. During the PED simu- when t < 4 days, the monitoring data are below the simulating curves,
lation, the pw of the soils around the wells decreased, which means that indicating that the calculated results overestimate the PED-induced
the water volume is reduced. For clearly describing the groundwater δhm. However, after t > 4 days, the observed and computed results
seepage inside and outside the foundation pit during PED, a normalized correspond with the aforementioned conclusion obtained by Zeng et al.
index called drainage degree (η) is defined by the pw reduction (Δpw) [9]. In the following, the computed data used in texts and figures are
during dewatering divided by the initial pw value (pw, ini) (i.e., η = Δpw/ the values after dewatering for 21 days, which is much longer than
pw, ini). η is close to 1 during the PED simulation. 4 days. Therefore, the use of the computed results to investigate the
Taking the two cases of (Wp = 200 m, Hd = 16 m) and PED-induced deformation is reasonable and reliable.
(Wp = 200 m, Hd = 19 m) as examples, Fig. 6 shows the computed η
contour at Section 1-1 (see Fig. 5) at the end of dewatering. A denser 4.2. Effect of the foundation pit width
contour is observed around the wells, meaning that a greater hydraulic
gradient (i) formed there. With the action of i, drainage occurs. The 4.2.1. Wall deflection and surface settlement profiles
parameter η is larger for the soil elements with a closer distance to the
wells due to the depression cone formed around the wells (1) General trend: the size effect
[10,41,42,61]. For both of the cases, η is greater than (or equal to) 0.8
for the soils very close to the wells within Hd, indicating that the water Taking the cases with Hd = 19 m as examples, Fig. 8 presents the
level decline in or near the wells can be roughly equal to the dewatering wall deflection and surface settlement profiles with different foundation
depth. This result is consistent with the field measurements (see Section pit widths (Wp). Apparently, all of the wall deflection curves show a
2.3). cantilever-type profile. At shallow locations, the wall deflections are
In addition, by comparing Fig. 6(a) and (b), it can be seen that with more apparent with an increase in Wp. However, at deep locations, the
an increase in Hd, the soil zone with pw reduction is deeper. However, in variation law of wall deflection with Wp is exactly the opposite, i.e., a
spite of this, the η values outside the foundation pit are always equal to wider foundation pit exhibits smaller wall deflection. This behaviour
0 for both cases, i.e., the water level outside the pit is almost un- indicates that the foundation pit size greatly affects the wall behaviours
changed. This result indicates that the retaining wall can effectively during PED. In the following, this phenomenon is referred to as the size
block the hydraulic connection between the inside and outside of the effect.
foundation pit, providing that there is no defect in the wall. This result The surface settlement curves show a spandrel-type profile. Unlike
is also in accord with the field measurements (see Section 2.3). the complex change in the wall deflection, the variation in surface
settlement with Wp is monotonic. That is, a wider foundation pit always
4.1.2. Retaining wall deflection shows a larger surface settlement. This variation law is consistent with
Fig. 7 shows the change in the maximum wall deflection (δhm) over that of wall deflections at shallow locations. Hence, it can be considered
the dewatering time (t) for three cases with a similar foundation pit that the surface settlement is primarily influenced by wall deflections at
width (Wp) and dewatering depth (Hd). One is the case (i.e., shallow locations. Moreover, an empirical curve for estimating surface
Wp = 180–190 m and Hd = 17.75 m) reported in Section 2.1, and the settlement is adopted as a comparison with the computed surface set-
others are two calculation cases with the same Wp (i.e., 200 m) but tlement for the cases of Wp = 20 and 200 m. It should be noted that the
different Hd values (i.e., 16 and 19 m). Apparently, the difference of the empirical curves shown in Fig. 8 were created based on the Hsieh-Ou
foundation pit geometry between in the numerical model and in the curve [62] after replacing the excavation depth used in their paper with
case study influences the matching degree between the computed and the PED depth; the reason the Hsieh-Ou curve can be referred to esti-
observed results. However, the computed curves and the trendline of mating the PED-induced surface settlement is that the surface settle-
the observed data have similar shapes. Both the observed and computed ment mechanism due to PED is similar to that due to soil excavation
results indicate that δhm increases nonlinearly with t, and the growth [9]. For a narrow foundation pit (e.g., Wp = 20 m), the empirical curve
rate decreases continuously. Because the wall deflection grows rapidly is well matched by the computed curve. However, for a wider foun-
in the first few days, the engineers should increase the monitoring dation pit, relatively great mismatches can be seen in the range of d/
frequency of the wall deflection during that time. Hd < 2. In addition, within a small distance from the wall (i.e., d/
Moreover, Zeng et al. [9] concluded that the PED with greater Hd < 1), severe differential settlement will appear in a wide pit, which

8
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 8. (a) Wall defection and surface settlement profiles under Hd = 19 m for the foundation pit with different width; (b) surface settlement in the range of d/
Hd < 2.

may cause the buildings or public facilities within this distance to be increasing Wp. In particular, δhs, hz at the ground surface increases from
damaged. 0.47Hd to 1.73Hd with Wp changing from 20 m to 200 m. This finding
indicates that the shallow soil movement inside the pit will be more
(2) Mechanism of the size effect apparent in a wider foundation pit. Hence, at shallow locations, a larger
retaining wall deflection will appear in a wider pit since the wall will
Zheng et al. [21] noted that the soil inside the foundation pit will move with the soil. However, δhs, vx=0 decreases as Wp increases, which
move towards the middle axis of the pit during PED. Because the re- means that at deep locations, δhs, hz will decrease with increasing Wp
taining wall is embedded in the soil, the soil movement will affect the (note: this trend is especially obvious when Wp changes from 20 m to
retaining wall response. In fact, the reason for the aforementioned size 40 m). Hence, at deep locations, the soil movement inside the pit will be
effect is that soil movement inside the foundation pit differs in different smaller in a wider pit, which eventually leads to the appearance of
cases. Taking the cases with Hd = 19 m as examples, Fig. 9 presents the smaller wall deflections in a wider pit.
zone of soil horizontal deformation (δhs) inside the foundation pit at Notably, in the cases of Wp = 20, 30 and 40 m, δhs, hz at shallow
different Wp values. In Fig. 9, t = the retaining wall thickness, locations basically reaches Wp′/2. Because the soils on both sides of the
Wp′ = the net width of the foundation pit, and Wp = Wp′ + 2t. To fa- middle axis of the foundation pit will move towards the middle axis
cilitate the description, δhs, hz is adopted to represent the horizontal [21], and meanwhile, there exists symmetry in the numerical model,
length of the δhs zone at different buried depths, and δhs, vx=0 is em- Wp′/2 is the maximum value that δhs, hz can obtain. This result indicates
ployed to represent the vertical length of the δhs zone at the soil-wall that in the cases of Wp = 20, 30 and 40 m, shallow soil movement on
interface (i.e., the location of x = 0). one side of the middle axis may suffer the deformation restraint effect
Apparently, at shallow locations, δhs, hz will be greater with from the soil movement on the other side. Apparently, in a narrower

9
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Fig. 9. δhs zone inside the foundation pit under Hd = 19 m for the cases with different Wp: (a) Wp = 20 m, (b) Wp = 30 m, (c) Wp = 40 m, (d) Wp = 80 m, (e)
Wp = 120 m, (f) Wp = 160 m, (g) Wp = 200 m.

foundation pit, this deformation restraint effect will be more apparent,


and thus, the shallow soil movement and the corresponding wall de-
flection will be smaller. Most likely, because the soil movement at
shallow location is restricted in the narrow pit, the soils at deep location
can move more apparently due to the deformation compatibility arising
in the soils and at the soil-wall interface [21].
Moreover, in the cases with Wp larger than 40 m, the soil movement
inside the pit will not be affected by the aforementioned deformation
restraint effect since δhs, hz is always smaller than Wp′/2. In this con-
dition, it can be seen that the δhs zones in these cases have little dif-
ference, and their δhs, hz values at the ground surface averages ap-
proximately 1.7 Hd with smaller differences. This result indicates that
δhs, hz is primarily related to Hd rather than Wp, providing that the soil
movement inside the pit is not restricted.

4.2.2. Maximum wall deflection (δhm) and maximum surface settlement


(δvm)
Fig. 10. Variations of δhm and δvm with Wp under different Hd.
(1) General trend: the existence of the critical foundation pit
width
cases with greater Ηd (e.g., Ηd > 16 m), it appears to have a critical
foundation pit width, which is approximately 40 m. Within this critical
Fig. 10 shows the changes in δhm and δvm with Wp at different de-
width, the variations in δhm and δvm are sensitive to a change in Wp, and
watering depths (Ηd). Generally, δhm and δvm become greater with in-
a fast growth in δhm and δvm can be seen. However, with Wp being
creasing Wp, and their variation laws are basically identical. For the

10
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

recognition about this type of deformations.

(2) Mechanism of the existence of the critical width

According to the description in Section 4.2.1, three facts can be


obtained: (1) during PED, the zone of soil horizontal deformation (δhs)
inside the foundation pit will enlarge continuously; (2) if the δhs zone
reaches the middle axis of the foundation pit, then the deformation
restraint effect (DR effect) between the soils on both sides of the middle
axis begins to appear; and (3) if the foundation pit is wide enough, then
there will be no DR effect occurring inside the pit.
Based on Facts (2) and (3), it can be concluded that there exists a
critical width, which determines whether the DR effect could appear
inside the pit. If the foundation pit width is smaller than this critical
width, then the DR effect will occur, which will restrict soil movement
inside the pit and further limit the development of the wall deflection.
Under this condition, the narrower pit will exhibit a more apparent DR
effect, which eventually leads to a smaller wall deflection. Hence,
Fig. 11. Relationship between δhm and δvm.
Fig. 10 shows a fast decrease in δhm and δvm within the critical width.
However, if the foundation pit width is greater than the critical width,
greater than the critical width, δhm and δvm become insensitive to the then the DR effect will not appear inside the pit. Under this condition,
Wp change, showing little difference among the cases. Moreover, for the the δhs zone and soil movement inside the pit will have little difference
cases with smaller Ηd (e.g., Ηd < 16 m), the Wp effect on the wall and under the same dewatering depth (see Fig. 9(d)–(g)). Therefore, Fig. 10
ground movement will be weak, and all the cases basically show the shows that δhm and δvm become insensitive to the Wp change as Wp is
same δhm and δvm under equal Ηd. greater than the critical width.
In addition, from Fig. 10, for the same Wp and Ηd, PED-induced δvm
is always smaller than PED-induced δhm. To better understand the re-
lationship between δhm and δvm, Fig. 11 summarizes δhm and δvm from 4.2.3. δhm increment and δvm increment
all the calculation cases in this study. The δvm values lie between In practical engineering, many foundation pits of different sizes can
δvm = 0.45δhm and δvm = 0.76δhm. With an increase in Ηd, the corre- be observed under similar geological conditions in the same city.
sponding δvm values are closer to the upper bound. This finding in- Typically, if the designers want to evaluate the PED-induced wall de-
dicates that PED will lead to more apparent surrounding surface set- flection and surface settlement, then they should develop a complicated
tlement (compared to wall deflection) in a deeper foundation pit due to soil-fluid numerical model to compute them, as described in Section 3.
the required larger dewatering depth. Moreover, plenty of researchers This calculation is a time-consuming process, and sometimes the results
(e.g., Mana et al. [63], Moormann et al. [64], and Tan et al. [65]) have may be not reliable since they are not verified by field measurements.
obtained the relationship between δhm and δvm during soil excavation; However, if we can develop a mathematical relationship between the
to reveal the difference of this relationship between in this study and in deformation increment and the pit size increment based on the mass of
previous studies, a comparison is made and is shown in Fig. 11. It can the computed and observed results, then one can easily calculate the
be seen that the PED-induced δvm/δhm had a smaller range than the PED-induced deformations of a planned foundation pit according to the
reported δvm = 0.5δhm to δvm = 1.0δhm by Mana et al. [63], measured deformations of an already built pit with a similar size and
δvm = 0.5δhm to δvm = 2.0δhm by Moormann et al. [64], and soil condition. This relationship should be useful in a preliminary
δvm = 0.3δhm to δvm = 2.0δhm by Tan et al. [65]. It should be noted that analysis. For this purpose, the computed and observed δhm increment
the data obtained in references [63–65] were from excavation projects (i.e., Δδhm) and δvm increment (i.e., Δδvm) are analysed in this section.
in soft clays in many cities (e.g., San Francisco, Chicago, and Shanghai); After analysing and processing a large amount of data, we find that
all of these data only covered the deformations induced during soil the variation in Δδhm/ΔWp (or Δδvm/ΔWp) with the logarithm of Wp/Hd
excavation, and did not include the deformations induced before soil (i.e., ln(Wp/Hd)) follows a unified relationship, which can be seen in
excavation (e.g., the PED-induced deformations). More data about the Fig. 12. Δδhm/ΔWp and Δδvm/ΔWp signify the δhm increment and the
PED-induced deformations needs to be gathered to form a much better δvm increment under the corresponding Wp increment, respectively.

Fig. 12. Relationship between (a) Δδhm/ΔWp and ln(Wp/Hd); and (b) Δδvm/ΔWp and ln(Wp/Hd).

11
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Apparently, with an increase in ln(Wp/Hd), Δδhm/ΔWp and Δδvm/ΔWp the pit and the deformation compatibility arising in the soils and at the
decrease nonlinearly. We can use two simple equations to fit the data, soil-wall interface can account for the computed wall behaviour at deep
and thus, it is convenient to calculate the PED-induced δhm and δvm locations. Hence, the computed results are to some degree reasonable,
based on the already known δhm and δvm from another foundation pit but the obtained wall behaviour at deep locations still requires further
with similar width and dewatering depth. This may be beneficial for the verification. In addition, in the future, more refined simulation such as
preliminary design of PED in a foundation pit. using discrete-element method or discontinuous deformation analysis
In addition, when ln(Wp/Hd) is smaller than 1 (i.e., Wp is < 2.72 [66] can be conducted to investigate the problem of PED-induced de-
Hd), the values of Δδhm/ΔWp and Δδvm/ΔWp are relatively great, which formation.
means that a smaller ΔWp could lead to a larger Δδhm and Δδvm, re-
spectively. Hence, in a foundation pit with variable Wp (for example, in 6. Concluding remarks
a metro pit, the Wp of standard segment is usually smaller than that of
end shafts), if Wp of this pit is smaller than 2.72Hd, then the PED-in- This paper reports a PED test in a large-scale foundation pit. The
duced δhm and δvm in different pit segments may differ even under the observed retaining wall deflection during PED was analysed. Then, 35
same PED depth; the pit segment with a larger Wp will generally exhibit numerical models considering different foundation pit widths were
greater δhm and δvm values (note: in the location close to the corner of developed to simulate the PED test. The models were verified by field
the pit, the corner effect on the deformation behaviour of foundation pit measurements and were used to investigate the effect of foundation pit
should be also considered). On this occasion, the designers should re- width on the behaviours of the retaining wall and surrounding soil
duce the PED depth in the pit segment with a larger Wp for fear of the during PED. The following conclusions can be obtained:
occurrence of overlarge δhm and δvm values in that segment.
(1) In the PED test, cantilever-type wall deflections were observed, and
5. Discussion the maximum deflection reached 15 mm (approximately 50% of the
alarm value for the project). The deflection development is closely
The above analyses prove that the time-dependent effect and the related to the PED progress inside the pit. A fast increase in wall
size effect are two features of PED-induced deformation. Meanwhile, deflection can be observed if an apparent water level decline ap-
mathematical equations are proposed to evaluate the PED-induced pears near the wall. In practical PED construction, the engineers
maximum wall deflection and maximum surface settlement. It is hoped need to dynamically adjust the PED depth according to the mon-
that these results can help engineers better design the PED process and itoring wall deflection. Once a large deflection increment appears,
analyse the PED-induced wall and soil deformation. Notably, all the they should reduce the dewatering depth or even stop PED.
calculated and measured results in this paper are based on the strata (2) The PED-induced deformation is dependent on the PED time (i.e.,
condition with soft-to-stiff silty clays and silts alternately appearing the time effect). As PED starts, the wall and soil deformations grow
within 50 m BGS. Hence, the obtained results (e.g., the critical foun- fast during the first few days, but the growth rate decreases con-
dation pit width, the relationship between the maximum wall deflection tinuously. The engineers should increase the monitoring frequency
and the maximum surface settlement, and the mathematical relation- of the wall and surrounding soil deformations during the first few
ship between the deformation increment and the pit size increment) can days of PED.
be applied to analyse the PED-induced deformations under similar (3) The PED-induced deformation is dependent on the foundation pit
strata conditions. However, the applicability of the obtained results in size (i.e., size effect). In a wider foundation pit, the maximum wall
this study in analysing the PED process in sandy gravel strata needs to deflection (δhm) and the maximum surface settlement (δvm) are
be further studied or verified. more apparent compared to those in a narrow pit under the same
In addition, the computed results in this study are overall consistent PED condition. The δvm values average approximately 0.70δhm. In
with the field measurements (see Section 4.1). However, on the surface, addition, there exists a critical pit width (approximately 40 m in
there still appears to be some differences in the observed and numerical this study), which determines the deformation behaviours of the
results. In the case study, it is found that the PED-induced wall de- wall and soil during PED. Within this critical width, the variations
flections, both at shallow and deep locations, are greater in a wider in δhm and δvm are sensitive to a change in the pit width (Wp).
foundation pit than those in a narrow pit under roughly the same PED However, with Wp being greater than the critical width, the Wp
condition (see Fig. 4). Nevertheless, the numerical results indicate that effects on δhm and δvm are weak. The engineers should especially
at shallow locations, the wall deflections will be larger with increasing notice that in a pit with variable Wp, when Wp is exactly smaller
foundation pit width (Wp), but at deep locations, the wall deflections than 2.72Hd (a value obtained in this study), the PED-induced δhm
decrease as Wp increases (see Fig. 8). There seems to be a conflict in the and δvm may differ apparently in different pit segments, even if the
wall behaviour at deep locations for the computed and observed results, PED depth in each segment is the same.
but they are all reasonable. The reason may be as follows. In Fig. 4, the (4) The reason for the size effect is that the soil movement inside the pit
wall deflections monitored in this study are the retaining pile deflec- differs in different cases. In a narrow pit (less than approximately
tions, while the wall deflections quoted from Zheng et al. [21] are the 40 m in this study), the soil movement on one side of the middle
diaphragm wall deflections. Apparently, the diaphragm wall possesses a axis will restrict the soil and wall movements on the other side. This
greater stiffness and a better integrity and thus has a stronger ability to deformation restraint (DR) effect will be more apparent in a nar-
match the deformation between the wall top and the wall sections rower pit, and thus, a smaller wall deflection can be observed in
below the wall top [9,21]. In contrast, the retaining pile movements are narrower pits. However, if the pit is sufficiently wide, there will be
under fewer restrictions below the wall top, and thus, the piles can no DR effect inside the pit. Under this condition, the wall and soil
develop a relatively larger deflection at deep locations. This effect can movements will exhibit little difference under the same PED con-
be apparently seen from Fig. 4 because the deflection difference be- dition.
tween the diaphragm wall and retaining pile becomes greater with in-
creasing depth. From this point of view, the observed results are rea- Acknowledgements
sonable. As for the numerical results, since the diaphragm wall is
adopted in all of the models, the effect of structure stiffness on the This work was supported by the National Natural Science
results can be eliminated. In fact, the computed results can better reflect Foundation of China [grant number 51708206]; the China Postdoctoral
the Wp effect on the wall behaviours during PED. As described in Science Foundation [grant numbers 2018M633297 and 2019T120797];
Section 4.2.1, the deformation restraint effect of soil movement inside and the China Scholarship Council [grant number 201808430270].

12
C.-F. Zeng, et al. Computers and Geotechnics 115 (2019) 103169

Finally, we deeply appreciate for the warm and efficient work by edi- [32] Zhang YQ, Wang JH, Chen JJ, Li MG. Numerical study on the responses of
tors and reviewers. groundwater and strata to pumping and recharge in a deep confined aquifer. J
Hydrol 2017;548:342–52.
[33] Wang JX, Liu XT, Liu SL, Zhu YF, Pan WQ, Zhou J. Physical model test of trans-
References parent soil on coupling effect of cut-off wall and pumping wells during foundation
pit dewatering. Acta Geotech 2018.
[34] Wu Y-X, Lyu H-M, Han J, Shen S-L. Dewatering-induced building settlement around
[1] Zeng CF, Zheng G, Xue XL, Mei GX. Combined recharge: A method to prevent
a deep excavation in soft deposit in Tianjin, China. J Geotech Geoenviron Eng
ground settlement induced by redevelopment of recharge wells. J Hydrol
2019;145(5):05019003.
2019;568:1–11.
[35] Orazalin ZY, Whittle AJ, Olsen MB. Three-dimensional analyses of excavation
[2] Pujades E, Vázquez-Suñé E, Culí L, Carrera J, Ledesma A, Jurado A. Hydrogeological
support system for the Stata Center basement on the MIT campus. J Geotech
impact assessment by tunnelling at sites of high sensitivity. Eng Geol
Geoenviron Eng 2015;141(7):05015001.
2015;193:421–34.
[36] Finno RJ, Roboski JF. Three-dimensional responses of a tied-back excavation
[3] Goh ATC, Zhang RH, Wang W, Wang L, Liu HL, Zhang WG. Numerical study of the
through clay. J Geotech Geoenviron Eng 2005;131(3):273–82.
effects of groundwater drawdown on ground settlement for excavation in residual
[37] Clough GW, O'Rourke TD. Construction induced movements of insitu walls. Geotech
soils. Acta Geotech 2019. https://doi.org/10.1007/s11440-019-00843-5.
Spec Publ 1990;25:439–70.
[4] Xu YS, Shen SL, Lai Y, Zhou AN. Design of sponge city: Lessons learnt from an
[38] Hsieh PG, Ou CY. Mechanism of buttress walls in restraining the wall deflection
ancient drainage system in Ganzhou, China. J Hydrol 2018;563:900–8.
caused by deep excavation. Tunn Undergr Space Technol 2018;82:542–53.
[5] Lyu H-M, Shen S-L, Zhou A, Yang J. Perspectives for flood risk assessment and
[39] Whittle AJ, Corral G, Jen LC, Rawnsley RP. Prediction and performance of deep
management for mega-city metro system. Tunn Undergr Space Technol
excavations for courthouse station, Boston. J Geotech Geoenviron Eng
2019;84:31–44.
2015;141(4):04014123.
[6] Tan Y, Lu Y. Forensic diagnosis of a leaking accident during excavation. J Perform
[40] Hashash YMA, Whittle AJ. Ground movement prediction for deep excavations in
Constr Facil 2017;31(5):04017061.
soft clay. J Geotech Eng 1996;122(6):474–86.
[7] Goh ATC, Zhang F, Zhang W, Zhang Y, Liu H. A simple estimation model for 3D
[41] Liu KW, Su Q, Yue F, Liu B, Zhao WH, Yue F. Effects of suffusion-induced contact
braced excavation wall deflection. Comput Geotech 2017;83:106–13.
variation on dynamic responses of saturated roadbed considering hydro-mechanical
[8] Serrano-Juan A, Pujades E, Vázquez-Suñè E, Crosetto M, Cuevas-González M.
coupling under high-speed train loading. Comput Geotech 2019;113. https://doi.
Leveling vs. InSAR in urban underground construction monitoring: Pros and cons.
org/10.1016/j.compgeo.2019.103095. Article ID 103095.
Case of la sagrera railway station (Barcelona, Spain). Eng Geol 2017;218:1–11.
[42] Shen SL, Wu YX, Misra A. Calculation of head difference at two sides of a cut-off
[9] Zeng CF, Xue XL, Zheng G, Xue TY, Mei GX. Responses of retaining wall and sur-
barrier during excavation dewatering. Comput Geotech 2017;91:192–202.
rounding ground to pre-excavation dewatering in an alternated multi-aquifer-
[43] Zhang YQ, Li MG, Wang JH, Chen JJ, Zhu YF. Field tests of pumping-recharge
aquitard system. J Hydrol 2018;559:609–26.
technology for deep confined aquifers and its application to a deep excavation. Eng
[10] Wang JX, Deng YS, Ma RQ, Liu XT, Guo QF, Liu SL, et al. Model test on partial
Geol 2017;228:249–59.
expansion in stratified subsidence during foundation pit dewatering. J Hydrol
[44] Zhang YQ, Wang JH, Li MG. Effect of dewatering in a confined aquifer on ground
2018;557:489–508.
settlement in deep excavations. Int J Geomech 2018;18(10):04018120.
[11] Wu YX, Shen SL, Yuan DJ. Characteristics of dewatering induced drawdown curve
[45] Code for concrete structure design. GB 50010–2010. Beijing: China Architecture
under blocking effect of retaining wall in aquifer. J Hydrol 2016;539:554–66.
and Building Press, China Academy of Building Research; 2010.
[12] Pujades E, Jurado A, Carrera J, Vázquez-Suñé E, Dassargues A. Hydrogeological
[46] Technical Code for Monitoring of Building Foundation Pit Engineering. Beijing:
assessment of non-linear underground enclosures. Eng Geol 2016;207:91–102.
China Planning Press, Shandong Construction Department; 2009.
[13] Lim A, Ou CY, Hsieh PG. Investigation of the integrated retaining system to limit
[47] Wu YX, Lyu HM, Shen JS, Arulrajah A. Geological and hydrogeological environ-
deformations induced by deep excavation. Acta Geotech 2018;13(4):973–95.
ment in Tianjin with potential geohazards and groundwater control during ex-
[14] Liang R, Wu W, Yu F, Jiang G, Liu J. Simplified method for evaluating shield tunnel
cavation. Environ Earth Sci 2018;77(10):392.
deformation due to adjacent excavation. Tunn Undergr Space Technol
[48] Liu GB, Wang WD. Excavation engineering handbook (in Chinese). 2nd ed. Beijing:
2018;71(Supplement C):94–105.
Chinese Construction Industry; 2009.
[15] Li MG, Chen JJ, Wang JH, Zhu YF. Comparative study of construction methods for
[49] Yao TQ, Shi ZH, Cao HB. Foundation pit dewatering Handbook (in Chinese). 1st ed.
deep excavations above shield tunnels. Tunn Undergr Space Technol
Beijing: China Architecture and Building Press; 2006.
2018;71(Supplement C):329–39.
[50] Xu YS, Shen SL, Du YJ. Geological and hydrogeological environment in Shanghai
[16] Xu C, Chen Q, Wang Y, Hu W, Fang T. Dynamic deformation control of retaining
with geohazards to construction and maintenance of infrastructures. Eng Geol
structures of a deep excavation. J Perform Constr Facil 2016;30(4):04015071.
2009;109(3–4):241–54.
[17] Wang JX, Liu XT, Wu YB, Liu SL, Wu LG, Lou RX, et al. Field experiment and
[51] Shen SL, Ma L, Xu YS. Interpretation of increased deformation rate in aquifer iv due
numerical simulation of coupling non-Darcy flow caused by curtain and pumping
to groundwater pumping in shanghai. Can Geotech J 2013;50(11):1129–42.
well in foundation pit dewatering. J Hydrol 2017;549:277–93.
[52] Shen SL, Wu HN, Cui YJ. Long-term settlement behaviour of metro tunnels in the
[18] Cashman PM, Preene M. Groundwater lowering in construction: a practical guide to
soft deposits of Shanghai. Tunn Undergr Space Technol 2014;40:309–23.
dewatering. 2nd ed. Boca Raton: CRC Press; 2012.
[53] Technical code for monitoring of building foundation pit engineering. GB50497-
[19] Zeng CF, Yuan ZC, Xue XL, Zheng G, Mei GX. Countermeasures to retaining wall
2009. Beijing: China Planning Press, Shandong Construction Department; 2009.
deflection induced by pre-excavation dewatering. In: Qiu T, Tiwari B, Zhang Z,
[54] Biot MA. General theory of three-dimensional consolidation. J Appl Phys
editors. Proceedings of GeoShanghai 2018 International Conference: Advances in
1941;12(2):155–64.
Soil Dynamics and Foundation Engineering: Springer, Singapore; 2018. p. 455–63.
[55] Li M-G, Wang J-H, Chen J-J, Zhang Z-J. Responses of a newly built metro line
[20] Zeng CF, Zheng G, Xue XL. Wall deflection induced by pre-excavation dewatering in
connected to deep excavations in soft clay. J Perform Constr Facil
large-scale excavations. Chin J Geotech Eng 2017;39(6):1012–21.
2017;31(6):04017096.
[21] Zheng G, Zeng CF, Diao Y, Xue XL. Test and numerical research on wall deflections
[56] Roscoe KH, Burland JB. On the generalized stress-strain behavior of ‘wet’ clay. In:
induced by pre-excavation dewatering. Comput Geotech 2014;62:244–56.
Heyman J, Leckie FA, editors. Engineering Plasticity. Cambridge: Cambridge
[22] Zheng G, Zeng CF. Lateral displacement of diaphragm wall by dewatering of
University Press; 1968. p. 535–609.
phreatic water before excavation. Chin J Geotech Eng 2013;35(12):2153–63.
[57] Zheng G, Diao Y, Ng CWW. Parametric analysis of the effects of stress relief on the
[23] Shen SL, Wu YX, Xu YS, Hino T, Wu HN. Evaluation of hydraulic parameters from
performance and capacity of piles in nondilative soils. Can Geotech J
pumping tests in multi-aquifers with vertical leakage in Tianjin. Comput Geotech
2011;48(9):1354–63.
2015;68:196–207.
[58] Wang ZW, Ng CW, Liu GB. Characteristics of wall deflections and ground surface
[24] Wu YX, Shen JS, Cheng WC, Hino T. Semi-analytical solution to pumping test data
settlements in Shanghai. Can Geotech J 2005;42(5):1243–54.
with barrier, wellbore storage, and partial penetration effects. Eng Geol
[59] Booker J, Carter J. Long term subsidence due to fluid extraction from a saturated,
2017;226:44–51.
anisotropic, elastic soil mass. Quart J Mech Appl Math 1986;39(1):85–98.
[25] Pujades E, Vàzquez-Suñé E, Carrera J, Jurado A. Dewatering of a deep excavation
[60] Booker JR, Carter JP. Analysis of a point sink embedded in a porous elastic half
undertaken in a layered soil. Eng Geol 2014;178:15–27.
space. Int J Numer Anal Meth Geomech 1986;10(2):137–50.
[26] Pujades E, Vázquez-Suñé E, Carrera J, Vilarrasa V, De Simone S, Jurado A, et al.
[61] Feng Q, Zhan H. Constant-head test at a partially penetrating well in an aquifer-
Deep enclosures versus pumping to reduce settlements during shaft excavations.
aquitard system. J Hydrol 2019;569:495–505.
Eng Geol 2014;169:100–11.
[62] Hsieh PG, Ou CY. Shape of ground surface settlement profiles caused by excavation.
[27] Xu YS, Shen SL, Ma L, Sun WJ, Yin ZY. Evaluation of the blocking effect of retaining
Can Geotech J 1998;35(6):1004–17.
walls on groundwater seepage in aquifers with different insertion depths. Eng Geol
[63] Mana AI, Clough GW. Prediction of movements for braced cuts in clay. J Geotech
2014;183:254–64.
Eng Div 1981;107(6):759–77.
[28] Pujades E, López A, Carrera J, Vázquez-Suñé E, Jurado A. Barrier effect of under-
[64] Moormann C. Analysis of wall and ground movements due to deep excavations in
ground structures on aquifers. Eng Geol 2012;145–146:41–9.
soft soil based on a new worldwide database. Soils Found 2004;44(1):87–98.
[29] Wu YX, Shen SL, Xu YS. Characteristics of groundwater seepage with cut-off wall in
[65] Tan Y, Wang D. Characteristics of a large-scale deep foundation pit excavated by the
gravel aquifer. I: Field observations. Can Geotech J 2015;52(10):1526–38.
central-island technique in Shanghai soft clay. I: Bottom-up construction of the
[30] Wu YX, Shen SL, Yin ZY, Xu YS. Characteristics of groundwater seepage with cut-off
central cylindrical shaft. J Geotech Geoenviron Eng 2013;139(11):1875–93.
wall in gravel aquifer. II: Numerical analysis. Can Geotech J 2015;52(10):1539–49.
[66] Huang GH, Jiao YY, Wang L, Zhao Q. Three-dimensional spherical DDA method for
[31] Wang JX, Wu YB, Liu XT, Yang TL, Wang HM, Zhu YF. Areal subsidence under
modeling friction problems. Int J Geomech 2017;17(5):E4016016.
pumping well–curtain interaction in subway foundation pit dewatering: conceptual
model and numerical simulations. Environ Earth Sci 2016;75(3):1–13.

13

You might also like