Professional Documents
Culture Documents
Related terms:
The elimination or reduction of groundwater around and below open deep excava-
tions has a number of positive attributes in addition to providing a dry workspace.
The pressures exerted by water in the ground add significant load to the lateral earth
pressures along the sides of the excavation. In addition, the water pressure at the
base of an excavation can provide an upward force that may be enough to surpass the
weight (and/or strength) of the soil in the bottom, resulting in heave, or worst case, a
failure mode called “blowout,” which would potentially result in a catastrophic failure
and flooding of the excavation. Contractors should consider these loads and possible
failure mechanisms, and design accordingly. Some structures with components
below the normal water table will require dewatering during construction as well
as long-term control after the project is completed and put into operation. For
cases where analyses show that there would be a continual large inflow of water
that needs to be evacuated, a cutoff wall may be appropriate and economical. There
are many varieties of cutoff walls for both temporary and permanent applications
that utilize different structural and nonstructural components, including slurries,
grouts, soil admixtures, sheet piles, and steel beams. Cutoff walls are essentially
hydraulic barriers (discussed below), but also may be designed to perform one or
more structural functions, like serving as foundations or walls.
Figure 7.1. Multistage well system for excavation dewatering: (a) first stage and (b)
second stage.
The process of jet grouting involves the cutting of soil by a mixture of water and
air under high pressure and the placement of grout, also under high pressure.
Hence, the process of jet grouting may tend to displace the adjacent soil away from
the grouted zone. Thus, the process of jet grouting may have some effects on the
retaining structures, adjacent soils, and nearby structures.
The performance of a field jet grout trial and the production grouting carried out
during the basement construction for the Singapore Post Centre is presented and
evaluated herein. Emphasis is given to the effects of jet grouting on movements
of diaphragm walls, adjacent soils, and structures and on changes in lateral earth
pressure and water and piezometric levels in adjacent soils.
Dewatering in Construction
Ruwan Rajapakse, in Construction Engineering Design Calculations and Rules of
Thumb, 2017
Add more pumps as necessary to keep the excavation dry. A combination of sub-
mersible pumps and vacuum pumps can be used. Large scale dewatering for base-
ments or deep excavations:
Alternative 1: Well points or trenches are constructed. The main artery pipe is
connected to each pump as shown. A strong, high-capacity pump will suck the water
out of all the wells as shown (Fig. 17.5).
(3.8)
where , critical unsupported height of vertical sides (m); , bulk unit weight of soils,
kN/m5; , soil cohesion, kN/m2; , soil inner friction angel.
In the case of urban areas, where buildings are congested, diaphragm walling is used
in most cases. Thus, the calculation of soil displacement around deep excavation
supported by a propped diaphragm wall in soft clay formation will be introduced.
The coefficients and factors that need to be strictly considered and controlled are
as follows:
Based on experience in Shanghai, it is known that strut delay time will have a
major influence on wall movement (ΔHmax). We use influence factor ati to reflect
this influence. Table 3.3 shows the value of this influence factor (ati). The additional
movement due to the delay of strut support time is
5. Influence factors of strut prestress ( p)Mana and Clough also studied the relation
between strut prestress () and design stress using the FEM as shown in
Fig. 3.21. In practice, strut prestress should be 80%, because stress loss will
always happen to some degree. This conclusion is based on experience in
Shanghai practice.Figure 3.21. Effect on strut prestress on maximum lateral
wall movement/design stress.
6. Modified maximum lateral movement of diaphragm wall (ΔH*max)ΔH*max can be
calculated using the following formula:(3.11)
7. Maximum ground surface settlement (ΔV*max)The relationship between ΔV*max
and ΔH*max is shown in Fig. 3.22. As Fig. 3.22 shows, the following formula
is reasonable:(3.12)Figure 3.22. Case history data of the relationship between
maximum ground settlements and maximum lateral wall movement.Modified
from Mana and Clough (1981). Prediction of movements for braced cuts in
clay. Journal of Geotechnical Engineering, American Society of Civil Engineers, 107,
759–777.
8. Ground surface settlement curve of cross section of diaphragm wallThe ground
surface settlement scope, X0, can be calculated as follows:(3.13)where H, depth
of excavation, m; D, penetration of diaphragm wall, m; , soil inner friction
angle, degrees.Based on Peck’s assumption of the exponential function curve,
the ground surface settlement curve of cross section of diaphragm wall is
as follows:(3.14)where X0 can be found using Formula (3.13); Z, X, axes (Fig.
3.23); a, factor, based on Shanghai experience, as follows:(3.15)Figure 3.23.
Diaphragm wall diagram.
9. Longitudinal ground surface settlement curve along diaphragm wall
Liou Jianhang studied the following formula, which can be used to calculate the
scope (L) of longitudinal ground surface settlement based on Shanghai MRT station
construction experience:
(3.16)
The shape of the longitudinal ground surface settlement curve is shown in Fig. 3.24.
“a” is the length of circular arc with radius of “R,” and “b” is the length of tangent
line between two circular arc. “R” can be calculated based on the following formula:
(3.17)
Formula (3.17) can be used to predict the differential settlement of adjacent utilities,
which are parallel to the diaphragm wall.
To better understand how the coefficients affect design a case study on a Shanghai
stadium metro station, which was built by the cut-and-cover method, is described
later.
Propped diaphragm walling was used as an excavation support system. The exca-
vation has length (L) 232 m, depth (H) 14 m, and standard width (B) 22 m. The
penetration depth of diaphragm wall (D) is 12 m.
The wall is supported by four strut layers. The elastic module of the wall (Ew) is
2.6×107 kPa. The thickness of the wall is 0.8 m. The stiffness of the wall (Ew·Iw)
is 1.109×106 kN-m2/m. The outside diameter of the steel strut is 580 mm. The
thickness of the cylindrical steel strut is 10 mm.
The horizontal spacing between two struts (d) is 3 m. The vertical spacing between
two struts (h) is 3.5 m. The elastic module of the strut (Eg) is 2.1×108 kPa. The
net cross-area is Ag=1.791×10−2 m2. The stiffness of the strut (Sk) is Eg·Ag/(d·h-
)=3.582×105 kN/m2. The prestress value of the strut is 70% of the designed stress.
The ground is gray muddy clay. The main parameters of the soil are =17.7 kN/m3,
C=8.28 kPa, =14.76 degrees, E=4343 kPa, and Cu= ·H tg +C=73.6 KPa.
The pumphouse may also house auxiliary pumps for duties such as compressor
cooling, hydrant systems and auxiliary cooling water. Figures 2.71 and 2.72 show
one of the two similar pumphouses at Drax power station.
Figure 12.13. Deep shaft with jet grouted cut-off plug for sewer pump station in
Portland, OR.
Field evidence in sewer reconstruction projects confirms that these methods were
used. Voids or loosely packed material are encountered above the stone flag (Fig. 3.9-
). Even so, it is still uncertain exactly in detail how the sewers were constructed. No
recorded accounts of construction have survived (if indeed they were ever made) and
therefore it is possible only to speculate from the evidence of excavations.
It is just conceivable that the larger sections were constructed in tunnel, i.e. the face
being advanced and the brickwork lining following closely behind. This procedure
requires that all the materials and spoil be carried through the completed section of
tunnel. Considering the size and weight of the flagstones used for a 900 mm × 600-
mm size of sewer – 800 mm minimum width × 100 mm thick × 500 mm running
length (average) with a weight of 90–100 kg – the difficulties presented by this
method of construction are immense.
The alternative method, that of heading, i.e. excavation of an oversized void to the
furthest point from the working shaft and then construction of the sewer structure
in the reverse direction, is more plausible. Indeed, because of size restrictions alone,
some form of heading method must have been used for the smaller section sewers.
However, for heading methods to be used, the distance between working shafts
would necessarily be limited and ground conditions would need to be moderate
or good. Blind eye shafts (referred to in detail later) which may have been used as
working shafts occur at intervals of around 30 m on U-shaped sewers. Evidence of
temporary (timber) support used for headings is only very rarely seen and although
ground conditions throughout much of the older parts of the city could generally
be described as good to fair for heading purposes, presumably only minimum
temporary support was provided during construction and this was subsequently
removed as the heading void was backfilled.
Hybrid methods for tunnel/heading construction might also have been feasible. For
example, the brickwork part of the sewer could perhaps be built during the initial
excavation behind the face, with the roof being temporarily propped and then the
flag stones could have been inserted from the far end working backwards towards
the working shaft.
Further investigations of documents and field evidence are obviously needed be-
fore conclusive answers can be given to the questions raised. Probably a variety
of techniques were used dependent on ground conditions, or the experience of
different contractors. However, whatever the method adopted, it is apparent that
very considerable problems must have been experienced in handling materials in
very confined spaces, particularly in manoeuvring the stone flags into position.
These problems may account, in part, for the relative crudeness of the construction.
Brickwork coursing and jointing are irregular, variations in section size and shape
occur. Open joints exist between the stone flags, and the space above has often
been imperfectly backfilled. The sewers exhibit wandering alignment and sometimes
abrupt changes in level as illustrated previously.
The location of the pumphouse, screen chamber and intake varies with the topog-
raphy, bathymetry and the geotechnical problems associated with construction and
operation of the system. The structures may be combined with a jetty, the intake may
also be separated from the fine screens and pumps by tunnel or tube. Each site has
a series of variations on possible types of structure and the final system is developed
from total lifetime cost comparisons.
Construction needs can also affect the design; for example, dewatering is easier
from the pumphouse than the intake, and tunnels, are more readily driven uphill
than level or down. Soft ground tunnelling carries non-technical risks and may be
impossible to drive with adequate safety. Submerged tubes offer an alternative but
must not be buoyant if dewatered, and must not represent a permanent hazard by
being insufficiently buried in the river or sea bed.
The option of putting the pumps close to individual condensers to save costs on
pressure culverts leads to complications with layout and foundations, which often
lead to its rejection in favour of a combined screen and pump chamber.
Abstract
Jet grouting is an increasingly used technique for in situ soil improvement in many
types of soils, especially in soft clays such as the Singapore marine clay. Among
many of its applications, one of the common uses is to improve the ground for deep
excavations. In this chapter, quality assurance and quality control for jet grouting
works, properties of jet grouted piles, and design and construction issues associated
with the use of jet grouted slabs at the base of excavations are presented. These
topics are discussed with reference to jet grouting applications in the construction
of the cut and cover tunnels at Race Course Road and in the station construction by
cut-and-cover method at Clarke Quay station during the construction of the North
East Mass Rapid Transit Line in Singapore.