Professional Documents
Culture Documents
History •
•
CPM by DuPont for chemical plants
PERT by U.S. Navy for Polaris missile
4
When embarking on a project, one has to keep the
following objectives in mind
1. Determine the shortest possible time in which a
project can be completed
2. Find a suitable time-cost trade-off i.e strike a
balance between higher operating cost of rapid
completion methods and the longer time of normal
methods
3. Leveling of resources for example utilizing a constant
number of men on a project rather than reassigning
personnel or other necessary resources.
4. Find the best scheduling procedure when
insufficient resources and facilities limit the number
of jobs that can be done
• The CPM and PERT are used to find the
shortest possible time in which a project can
be completed.
• The CPM is a deterministic method, in that the
estimated completion times for individual
components are assumed to be definitely
known.
• The PERT method provides for the use and
combining of estimated completion times of
components parts wherein the time estimates
contain a probable amount of error or
variance.
ADVANTAGES OF CRITICAL PATH
PLANNING
• It is a logical method for setting down and organizing
a plan of action.
• It facilitates additional breakdown of activities into
smaller activities.
• It permits fuller utilization of individual capacities for
planning and organization.
• It points out those activities which are in the critical
path, those whose delay would result in delay of
completion of the entire project.
• Critical path planning can help to point out where
best efforts will be most rewarding.
Description
• In the CPM, the individual activities that make
up a total project are represented as a
network of arrows.
• There are some activities that can be done
concurrently , hence parallel paths appear in
the arrow diagram.
• For the entire projects, the series of
consecutive activities which requires the
longest time and therefore determines the
completion date is referred to as the CRITICAL
PATH
The Project Network
i
CALCULATION OF LATEST FINISH
VALUES
PERT
• Activity duration times cannot always be estimated
precisely. Sources of uncertainty include weather,
uncertain delivery of supplies, equipment failure,
lack of knowledge concerning procedures and
methods to be used, etc
• PERT method consist of making estimates from
which the expected duration times as well as their
variance can be obtained.
• Adding the expected duration times for individual
activities along a path gives the expected time for
completion of the path.
• Adding their variances give the TOTAL
VARIANCE
• The combined variance of a path corresponds
to a normal distribution.
• Use of the normal distribution offers a way to
calculate the probability of achieving various
completion dates.
• Three time estimates are used in the PERT
method. The time estimates are
• OPTIMISTIC (L): An estimate of the minimum
time required for completing an activity if
there is unusually good luck and all goes well
without any trouble.
• MOST LIKELY (M): An estimate of the normal
duration time, which would be repeated most
often if a large number of trials were made.
• PESSIMISTIC (H): An estimate of the maximum
time an activity will require for its completion
if an unusually bad luck is encountered.
EXAMPLE
• The PERT time estimates for a project is shown
below: using the data in the table,
a) Calculate the duration time (TE) for each activity
b) Calculate the variance for each activity
c) Draw an activity-on-arrow diagram of the project
showing the expected duration time (TE) on each
arrow
d) Calculate both the expected time for completion
and the total variance for the critical path
e) Calculate both the expected time for completion
and the total variance for the near critical path.
f) Calculate the probability of completing the project 1
week before the expected completion time and the
probability of completing the project prior to the
end of 1 week after the estimated completion date
for (i) the critical path (ii) the near critical path
• (b) To install a water injection plant in an oil company’s field, decision to
start will be made. This will take 0 day. Pumps to be used will be ordered
and the concrete foundations can be poured and given time to harden
while waiting for the pumps to arrive. The procurement of the pump will
take 15 days while the pouring and hardening of the foundation will take
20 days. Both of these activities can be done concurrently.
• On arrival of the machinery (pumps), they can then be installed. This will
take 10 days. When this is done, a building can be built over the pumps
and testing of the machinery can proceed concurrently, which would
complete the project. Testing of the machinery will take 5 days and the
erection of the building will take 10 days.
• (i) Show the above information (activities and duration times) in an
activity on arrow diagram with dummy arrows. (2 marks)
• (ii) Calculate the earlier start times of all the activities. (4.5 marks)
• (iii) Then, calculate the latest finish times of all the activities. (4.5
marks)