Professional Documents
Culture Documents
1.0earthwork Operation
1.0earthwork Operation
.
.
.
.
.
.
.
.
.
.
Terrain
Chapter-2
classification
. Chapter-3
Earthwork Operation
3/6/2019 G/egziabher G/hiwot 36
3/6/2019 G/egziabher G/hiwot 37
E arthworks
The most common form of earthworks consists of the preparation of a level
base on which the road body is constructed.
The existing terrain where the road passes is seldom flat.
The ground on which the road is built therefore needs to be reshaped to form
level base on which the road pavement can be constructed.
Consist of :
Excavations works
Building up earth fills or embankment
Loading
Unloading
Transport of soils,
Spreading and compaction
It is the largest operation when building road, often accounting for more
than half of the construction cost.
• If the slot is more than 0.5 m high at any point, the sides of
the slot excavation should be back-sloped instead of vertical.
• Ensure with a straight edge and spirit level that the slot is
exactly horizontal.
3/6/2019 G/egziabher G/hiwot 49
.
.
.
0+000 0+020 0+025
Check the quality of ETL on a regular basis and take corrective measures if
required.
Who: Contractor’s supervisor as well as the consultant Supervisor.
Why: To ensure that ETL is carried out correctly.
When: Before the start of ditch excavation.
Supervisor should carry out following checks:
1. Uniform levels over cross-section
What: 2. Smooth gradients in longitudinal direction
3. Width of platform is conform specifications
4. Platform is properly compacted
Tools: Boning rods, line level and a 25m tape measure.
65
Formation of the road in flat terrain
94
Borrow Pits
The use of borrow pits is necessary when large fills are
required.
In rolling and mountainous terrain, any demand for fill
materials should be sourced from within the road reserve by
utilizing soils from the side cuts.
Widening the side drains or reducing the gradient on back
slopes is also a feasible way to obtain additional fill
material.
In flat terrain, where the road needs to be lifted to a level
above the surrounding terrain, it is often necessary to open a
borrow pit.
3/6/2019 G/egziabher G/hiwot 95
To access appropriate soil materials, any vegetation and
.
topsoil need to be cleared away.
Topsoil should be stored at a safe distance from the work
site and returned once the borrow pit is no longer in use.
Excavation works in borrow pits need to be planned in a
manner so it causes the least damage or interference to the
normal use of the land.
Deep borrow pits should be avoided as they may become a
hazard to people and animals.
Equally, deep pits will fill with stagnant water and
thereby cause health problems.
3/6/2019 96
When using labour- based work methods, it is possible to operate
. friendly manner by
borrow pits in a more environmentally
increasing the area of excavation and thereby limiting the depth of
excavation.
By limiting the excavation depth, it is easier to reinstate the land
and allow the continuation of previous farming activities.
Equally, the opening of a borrow pit should not commence before
farmers have been allowed to harvest their crops.
Although it is preferable to be as close as possible to the road site,
the borrow pit should be located at a safe distance from the
embankment or fill thus avoiding that the borrow pit causes any
damages to the road.
The exact location of the borrow works is set out by the supervisors.
3/6/2019 G/egziabher G/hiwot 97
3/6/2019 G/egziabher G/hiwot 98
Super-elevation of Curves
Super-elevation is applied to sharp curves to counteract the centrifugal
force exerted on vehicles travelling through the curve.
Super-elevation is created by inverting the camber slope on the outer
half of the roadway, thereby preventing vehicles from slipping of the
road while negotiating the curve.
For rural roads, the super-elevation can be built up over a 20m section
before entering into the curve.
Equally, the super-elevation is gradually run off over a 20m section
starting at the end of the curve.
Throughout the curve, the super-elevation is constant.
On gravel roads a cross slope of 8% across the road carriage width is
recommended (10% before compaction).
.
.
.
Compaction
• Compaction decreases the volume of a layer of soil. By
forcing soil particles close together, the soil becomes stronger.
• By applying compaction to the materials used for road
construction, the road body will be strengthened, and better
withstand the envisaged traffic loads and natural erosion.
• There are four methods of compaction:
Manually or mechanically operated tampers or rammers,
Deadweight rollers,
Vibrating compaction
Natural compaction
3/6/2019 G/egziabher G/hiwot 102
3/6/2019 G/egziabher G/hiwot 103
Watering
Example-1
𝑬𝒙𝒄𝒂𝒗𝒂𝒕𝒆𝒅 𝒘𝒊𝒅𝒕𝒉, (𝒘) = 𝟔𝒎
𝑬𝒙𝒄𝒂𝒗𝒂𝒕𝒆𝒅 𝒕𝒉𝒊𝒄𝒌𝒏𝒆𝒔𝒔 = 𝟑𝟎𝒄𝒎
𝑳𝒐𝒏𝒈𝒊𝒕𝒖𝒅𝒊𝒏𝒂𝒍 𝒅𝒊𝒔𝒕𝒂𝒏𝒄𝒆 𝒕𝒐 𝒃𝒆 𝒆𝒙𝒄𝒂𝒗𝒂𝒕𝒆𝒅 = 𝟏𝟎𝟎𝒎
𝑩𝒖𝒍𝒌𝒊𝒏𝒈 𝒇𝒂𝒄𝒕𝒐𝒓 = 𝟏. 𝟓
119
.
The box length can be calculated with the
formula as given below:
121
.
123
• The best practice for a Labour Based site is shown on
Picture below, where gravel, once dumped, is spread
.
124
.
𝐴 = 𝑠 𝑠−𝑎 𝑠 − 𝑏 (𝑠 − 𝑐)
1
𝐴 = 𝑎𝑏 sin 𝑐
2
1
𝑠 = (𝑎 + 𝑏 + 𝑐)
2
𝑎, 𝑏, 𝑐 = 𝑠𝑖𝑑𝑒𝑠 𝑜𝑓 𝑎 𝑡𝑟𝑖𝑎𝑛𝑔𝑙𝑒
ℎ = 𝑎𝑙𝑡𝑖𝑡𝑢𝑑𝑒 𝑤ℎ𝑒𝑛 𝑏 𝑖𝑠 𝑡ℎ𝑒 𝑏𝑎𝑠𝑒
𝑐 = 𝑡ℎ𝑒 𝑎𝑏𝑔𝑙𝑒 𝐴𝐵
130
Average-Ordinate
131
𝑂1 + 𝑂2 + 𝑂3 + 𝑂4 + 𝑂5
𝑂𝑚 = .5
In general
.
𝑂1 + 𝑂2 + − − − − +𝑂𝑛 +1
𝑂𝑚 =
𝑛+1
Therefore,
𝑛 +1
𝐴= 𝑂𝑖
𝑖 =1
If L=2d
𝒅
𝒗 = 𝒔𝒖𝒎 𝒐𝒇 𝒕𝒉𝒆 𝒂𝒓𝒆𝒂𝒔 𝒐𝒇 𝒆𝒏𝒅 𝒔𝒆𝒄𝒕𝒊𝒐𝒏 + 𝟒 𝒔𝒖𝒎 𝒐𝒇 𝒕𝒉𝒆 𝒓𝒆𝒎𝒂𝒊𝒏𝒊𝒏𝒈 𝒆𝒗𝒆𝒏 𝒔𝒆𝒄𝒕𝒊𝒐𝒏
𝟑
+ 𝟐 𝒔𝒖𝒎 𝒐𝒇 𝒓𝒆𝒎𝒂𝒊𝒏𝒊𝒏𝒈 𝒐𝒅𝒅 𝒔𝒆𝒄𝒕𝒊𝒐𝒏𝒔
143
144
.
.
.
Side-hill two level section
.
.
.
Example
A 100-m length of earthwork volume for a
proposed road has a constant cross-section of cut
and fill, in which the cut area equals the fill area.
The level formation is 30 m wide, transverse
ground slope is 20◦.
The side slopes in cut-and-fill are 1 horizontal to 2
vertical and 1 horizontal to 1 vertical, respectively.
Calculate the volume of excavation in the 100-m
length.