You are on page 1of 26

JOLA VENTURES LIMITED

SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

A110 A359
Performance Bond Setting out of works

3,800
3,800.0

GH¢ 4,000 3,800m

A120 - A150
Insurance of works, A 311.1
equipment,third party Setting up Contractors
and against accident office and compound
to workmen

GH¢ 6,000
GH¢ 8000

A250
A311.2
Provide for material site Maintaining Contractor
investigation office and compound
8
1 8.00
GH¢ 800 8 mth

A311.3
Removing contractor's
A290 office and compound
Provide Progress
Photographs
GH¢ 1000
12
12.00 12 Set

Page 1
JOLA VENTURES LIMITED
SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

A420.1 A420.4
Provide safe drinking Provide First Aid Kit and
water for site employees train First Aider.
including storage facilities
( Polytank )

GH¢ 482

GH¢ 1,500

A420.5
Provide assistance to
and facilitate site
A 420.2 visit by MOH Personnel
Provide and maintain to educate workers and
protective clothing,safety communities in STDs,
equipement for use by site HIV/AIDS awareness and
employees consultation meeting

GH¢ 3,950 GH¢ 500

A420.3
Provide and maintain
temporary latrines, relocate
as necessary and remove
and remove and backfill on
completion.

GH¢ 800

Page 2
JOLA VENTURES LIMITED
SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

D100.1 B/F 767.40


General site clearance of
thick bush including 203.00 From 2+227-2+430
undergrowth of tree of 6.00 length = 203m
all sizes and other 0.59 718.62
obstructions, grub up all 2
root and clear away
From 0+600-3+800 0.5 203.00
Length = 3,200m 0.89
2 0.59 106.60 ( Side Slope )
3200.00 Width = 12.6m
Less Existing Width= 4m 60.00 From 2+720-2+780
4.30 27,520 m² Width = 8.6m 6.00 length = 60m
10,000 = 2.75Ha 0.45 162
2
2.75Ha 1,971m³
0.5 60.00
0.68
0.45 18.36 ( Side Slope )
E 424&625
General excavation in 65.00 From 3+265-3+330
barrow pit to any depth 6.00 length = 65m
and haul up to 1km 0.46 179.4
& 2
Filling with material from
barrow pit . 0.5 60.00
From 0+000-0+350 0.69
length = 350m 0.46 19.04 ( Side Slope )
1,971.4
E551
350.00 Excavate for culvert inlet
6.00 6 and outlet channels
0.29 609 including clearing of
2 vegetation and silt in
60.00 From 1+920-1+980 20.00 approaches and disposal
6.00 length = 60m 1.50
0.4 144 0.50 180 180m³

Page 3
2 60.00
0.6
0.5 0.4 14.40
C/F 767.4

JOLA VENTURES LIMITED


SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

K 463.1
E592.3 Excavate drainage ditch
Blading road surface 500.00 500.00 as turnout.
to crossfalls
3,412 From 0+000-3+800
length = 3,800m 500m
6.00 20,472 Less total Culvert Filling
approach = 388
Length =3,800 - 388
Total = 3,412
K 463.1
Excavate of existing
20,472m² unlined vee-shaped
ditched to section area
( 0.5 - 1.0sq.m)
From 0+300-3+800
2 length = 3,500m
E900.1 3050 6,100.0 Less total Culvert Filling
Haulage of excess of 1 km approach = 450
for all items ( 1-20) Length =3,500 - 450
Distance = 5 km Total = 3,112
Less 1 km
4 Total Distance = 4 km
1,971.4 7,886 6,100 m

7,886m³.km

E 420.1
90.00 Excavate material
2.00 in cutting
1.31 235.80 From 0+100-0+190

Page 4
236m³

JOLA VENTURES LIMITED


SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

K 493.4 CULVERT POSITION


CH 1+950 ( 700 X900 )
CH 2+311 ( 700 X900 )
0.12 0.45 0.12
CH 2+340 ( 700 X900 )
CH 2+397 ( 700 X900 )
0.50 CH 2+750 ( 700 X900 )
CH 3+300 ( 700 X900 )
0.12
0.69 Construct 700x900mm
diameter 'U' culvert,
Construct lined 'U' section relief type with catch
drain - sectional area pit inlet structure
(0.25-0-50m²) size 450x500 including excavation
internal x 120mm thick concreting,formwork
including excavation, reinforcement,ect
backfill and formwork K 673.1
complete. 6 Barrel of 'U' culvert
7.40 44.40
302 302.00 ( Right Hand side )
44m
296 296.00 ( Lift Hand side )

598.00
598m K 979.2
Wingwall and apron
outlet structure
2
6.00 12.00
H 510
Pruvide and place precast
concrete slab, size 1.5 x 12Nr
0.45 x 0.12 thick.
40
1.00 40.00

Page 5
40 Nr

JOLA VENTURES LIMITED


SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

HAULAGE B/F 2.89 Apron


0.12 0.45 0.12
1300
2
0.50

1150
6
0.12 1.91 2512
2 0.69 1.15
598 0.05 1.32 AV. = 1300+2512
0.50 2 2
0.12 71.76 ( Vertical Walls) = 1.91
598 6
0.69 2.51
0.12 49.51 ( Bottom Slab) 0.2
2 0.05 0.30 ( Toe )

0.21 598.00 4.51


0.25
0.25 15.70 ( Bell mouth )

136.97
F 253& F632
6
Volume of concrete 7.40
for 700x900 'U 'culvert 1.30
Main Trench 0.20 11.544 ( top slab)
7.40
1300

2512

F 234 & F511 F 253& F522


Provide of concrete Provide of concrete
C15/40mm aggregate in 6 ditto
blinding . 7.40
1.30

Page 6
6 0.20 11.544 ( Main Channel )

7.40 C/F 23.09


1.30
0.05 2.89
C/F 2.89

JOLA VENTURES LIMITED


SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)
B/F 23.09
2 B/F 51.20
6
6 1.91
1.15 2
0.20 5.27 ( apron)
0.21
2 7.40
0.35
6 2.51 0.35 2.28 ( Bell mouth)
0.20
0.40 2.41 ( Toe ) 53.48

HAULAGE
Wing walls Grade 1:2:4

' U ' Culvert = 53.48


20 ' U ' Drain = 136.97
0

Total = 187.46
900

200

Chips = 190.45x0.88
167.6
1.21

AV = 900+200 Sand = 187.46 x0.44


By 2 = 83.78
4 = 550mm
Grade 1:3:6
6 1.21 Total = 4.51
0.20
0.55 3.19 ( Wing walls) Chips
2 4.51x0.92 = 4.15

Page 7
6 1.30 Sand
0.20 4.51 X 0.56= 2.53
0.40 1.25 ( Head walls)
6
2 7.40
0.90
0.20 15.984 ( Abutment walls)

C/F 51.20

JOLA VENTURES LIMITED


SPOT IMPROVEMENT OF ANUM APAPAM- KOFIPARA FEEDER ROAD ( 3.80 KM)

TOTAL
R 114
SAND CHIPS Spread gravel wearing
83.78 167.6 course material from
2.53 4.15 barrow ,shape and
84.18 168.36 compact to 150mm thick
layer.
E 900.1 Sectional Gravelling
Haulage of aggregate From 1+800- 1+900=100
in excess of 1 km
( 0-20 km) From 2+200- 2+800=600
42
86.31 3,625.02 ( sand ) 700.00 Total length = 700
E 900.2 6.00 4,200
Ditto ,ditto, haulage
136.7 ( 100-250)
171.75 23,478 4200m²

SAND

R 900.1
3,625m³.km Haulage of gravel sub-
base material in
excess of 1 km ( 0-20km)

CHIPPINGS Distance 5 km
Less 1 km
Total 4 km

Page 8
23,478m³.km 4
700
6.00 2,520m³.km
0.15 2,520.0

Page 9
Page 10
0.15 0.45 0.15

0.45

0.15
0.75

Page 11
0.75

0.15 0.90 0.15

0.70

0.15
1.2

Page 12
1.2

Page 13
4.00
1300

2512

1300
1150

2512

Page 14
20
0
900

200

1.21

Page 15
12.00
1300

2512

1300
1150

2512

Page 16
20
0
900

200

1.21

Page 17
4.00

1300

2512

1600
1559

3158

Page 18
20
0

1100

300
200
1.56

Page 19
Page 20
1200
1300

2512

1600
1559

3158

Page 21
20
0
1100

300
200

1.56

Page 22
Page 23
Page 24
Page 25
Page 26

You might also like