Reapportionment
3/6 x 10,980 2/6 x 10,980 1/6 x 10,980
Maintenance Maintenance hours (3:2:1) 5,490 3,660 (10,980) 1,830 0
360/480 x 33,100 120/480 x 33,100
Store No. of materials req. (360:120) 24,825 8,275 (33,100) 0
TOTAL PRODUCTION OVERHEADS 130,065 106,355 0 0 236,420
= RM5.73/MH = RM3.80/DLH
iii. 𝑇𝑜𝑡𝑎𝑙 𝑏𝑢𝑑𝑔𝑒𝑡𝑒𝑑 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑎𝑙𝑙 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑑𝑒𝑝𝑎𝑟𝑡𝑚𝑒𝑛𝑡𝑠 130,065 + 106,355 236,420
𝐵𝑙𝑎𝑛𝑘𝑒𝑡 𝑂𝐴𝑅 = = = = 𝑅𝑀7.12 𝑝𝑒𝑟 𝑀𝐻
𝑇𝑜𝑡𝑎𝑙 𝑏𝑢𝑑𝑔𝑒𝑡𝑒𝑑 𝑚𝑎𝑐ℎ𝑖𝑛𝑒 ℎ𝑜𝑢𝑟𝑠 22,700 + 10,500 33,200
b. Cleaning Packaging
5.73 x 30,500 3.80 x 30,000
Overhead absorbed (OAR x Actual basis)
174,765 114,000
3,965 (2,000)
Over/(under) absorption of overheads
OVER UNDER