You are on page 1of 2

Allocation and Apportionment and Job and Batch Costing Solution

Question 2
(a). Overhead Analysis Sheet
Overheads Basis Total Machining Assembly Stores Canteen
90000 30000 12000 8000
(140000X8750) (140000X8750) (140000X8750) (140000X8750)
Depreciation Non-Current assets cost 8750 5625 1875 750 500
14100 2650
(16750X27000) (16750X27000)
Machinery maintenance Maintenance hours 27000 22728 4272
3750 2500 750 250
(7250X15370) (7250X15370) (7250X15370) (7250X15370)
Power Kilowatt hours 15370 7950 5300 1590 530
750 500 150 50
(1450X63510) (1450X63510) (1450X63510) (1450X63510)
Rent of premises Floor area 63510 32850 21900 6570 2190
Total Allocated and Apportioned
overheads 114630 69153 33347 8910 3220
First Re-Apportionment
20 30 3
(53X3220) (53X3220) (53X3220)
- Canteen Staff 1215 1823 182 (3220)
Second Re-Apportionment
150 75
(225X9092) (225X9092) (8 910 + 182)
- Stores Stores requisitions 6061 3031 (9092)
Total Budgeted Overheads 114630 76430 38200 - -

(b).Overhead absorption rate


OAR Machining = Budgeted overheads / Budgeted machine hours
= 76 430 / 14 100 = $5.42 per machine hours

OAR Assembly = Budgeted overheads / budgeted labour hours


= 38 200 / 13 900 = $2.75 per labour hours
(c). Total Cost
Product A Product B
Direct costs 5.75 8.25
Add Overheads
(1.5 X 5.42) (0.3 X 5.42)
- Machining 8.13 1.63
(0.5 X 2.75) (2 X 2.75)
- Assembly 1.38 9.51 5.5 7.13
Total cost per unit 15.26 15.38

(d). Over and under absorption


Machining Assembly
(5.42 X 16 210) (2.75 X 12 650)
Overhead absorbed (OAR X ACTUAL BASIS) 87 858 34 788
Less actual overheads (76 750) (45 675)
Over / (Under absorption) 11 108 (10 887)
Over absorption Under absorption

(e). Allocation is the process of charging whole costs directly to a cost unit or cost centre. There is no need to
share overheads between cost centres. The overheads for each cost centre is already known.

(f). An overhead cost is a cost that cannot be directly traced to a product manufactured.
It is an indirect cost that is not used to produce a product directly.
It helps in the production of goods.

(g). So that each unit of production contains a share of total production overheads costs only.
In a service cost centre, production does not take place. It is in the production cost centres that production
take place. So, for a product to contain all overheads incurred, the service cost centres must be re-
apportioned to the production cost centres.

(h). Reasons for changing:


- Simple and quick to operate
- No apportionment of overheads needed
- Fixed costs are treated as period costs and so remain unchanged at different activity levels
- There is no over/under absorption of overheads
- No further adjustment needed in the income statement for over/under absorption
- Closing inventory is realistically valued at variable production cost
- Allows easy calculation of profit when changes in activity occur
- Helps in decision making such as accept or reject orders, number of units to produce in situations of limiting
factor, make of buy decisions and accepting or rejecting orders.

Reasons for absorption costing:


- It shares fixed production costs to units of production, which is fair as these costs are incurred in order to
make the output
- It is easier to determine profitability of several products as they include a share of fixed overheads
- It values closing inventory fairly and is acceptable by IAS 2
- It is widely used for publication purposes

Though marginal costing is very useful internally for decision making for publication purpose only
absorption costing is acceptable. It is advisable to continue using absorption costing.

You might also like