You are on page 1of 1

Davis Langdon &Seah Consulting India Pvt Ltd

PROPOSED STRUCTURE FOR "THE V" - HYDERABAD INDIA

APPENDIX A TO RECOMMENDATION FOR EXTERNAL DEVELOPMENT WORKS (HARDSCAPE)


COST TRACKER FOR CONSTRUCTION Value in INR
BASE AREA 642,000 sqft

APPROVED BUDGET As PREVIOUSLY AWARDED WORKS CURRENT AWARD TOTAL AWARD TO DATE REMARKS
S.No PACKAGE per change of Contract
structure
M/sAswini fabricators and M/s S&P is
1 Excavation and Main Civil Works 348,997,478.48 346,387,883.00 346,387,883.00
awarded, Stagging charges for Painting
M/s Vijay Kumar Chourasia, M/s Signum and
2 Architectural with Contingency provisions 58,995,475.09 53,054,000.00 53,054,000.00
M/s Rangoli Marketing awarded
M/sDSGupta &M/s Gananadha industrial
3 PHE works plumbing & sanitary) 13,545,796.61 10,849,868.00 10,849,868.00
Corporation
4 Airconditioning and Mechanical ventilation works 80,043,343.60 68,000,000.00 68,000,000.00 M/s Blue Star Awarded

5 Electrical works 80,546,655.34 84,466,820.00 84,466,820.00 M/s Micron Electricals ( amended value)

6 Diesel generators 39,146,468.61 46,721,803.00 46,721,803.00 M/s Vibropower (amended value)

7 Structural glazing works 32,838,294.81 55,290,728.00 55,290,728.00 M/s Almech Enterprises

8 Building Management systems 3,283,829.48 4,113,254.00 4,113,254.00 M/s Race Technologies

9 Fire protection works 17,951,452.03 19,500,000.00 19,500,000.00 M/s Firepro awarded


M/s ETA Melco Engg & M/s Callidai Motor
10 Elevators 21,749,777.96 20,143,750.00 20,143,750.00
Works awarded
11 Landscaping 2,052,393.43 -

12 External Development 12,823,264.65 12,923,950.00 12,923,950.00 M/s Rao & Rao awarded

13 Kitchen Equipments 8,947,764.25 -

14 Café/Resturtant Furnitures 3,780,430.40 -

15 Health Club Equipments 3,914,646.86 -

16 Access control system 1,118,470.53 5,256,120.00 5,256,120.00 M/s Zicom Security


Tensile Structure in Terrace for Health Club &
17 3,914,646.86 - -
Restaurant
18 Add contingency ( provisioned in interior package) 15,682,510.00 - -

19 Substation extension works award 550,000.00 550,000.00

TOTAL AMOUNT IN INR ROUND OFF 749,332,699.00 714,334,226.00 12,923,950.00 727,258,176.00

COST PLAN FOR AWARDED PACKAGES 714,954,953.64 727,258,176.00


12,303,222.36
Notes
The cost tracker excludes all consultancy, other indirect costs

i1034/The "V"/External Development Page No : 1 of 1