Professional Documents
Culture Documents
J Mechanical Engineering
Industrial Engineering
"
© Gateforum Educational Services Private Limited
301, Ashoka Bhoopal Chambers, S.P. Road, Secunderabad - 500 003
Ph: 040 44664243. Email: support@gateforum.com
www.gateforum.com
I ME I Correspondence Course
Syllabus
4. Operating Research:- PERT & CPM- PERT Network, Error in Drawing Networks,
Dummy Activity, Time Estimates, Earliest Expected Time, Latest Occurrence
Time, Float and Slack, CPM, CPM Network, Cost Analysis; Linear Programming-
Linear Equation and Inequalities, Optimization Problem, Graphical Solution,
Simplex Technique, Degeneracy, Duality; Transportation- Voge l's Approximation
Method, Assignment; Queuing Theory- Queuing System, Characteristics of
Queuing Systems, Queue Discipline, Queue Model with Poisson Input-Exponential
Service, Decision Variable.
... Correspondence Course'" TarGAl'E ... ICP- Intensive Classroom Program'" eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 1
I:
...u
o
--
~
a. Topics Covered
en
- I:
• Limits, Fits and Tolerances
• Comparators
• Form and Finish Measurement
When ' a system has been worked out, so that any component will assemble correctly
with any mating component, both being chosen at random, the system is called an
interchangeable system.
Concept of Interchangeability:-
It is very difficult to manufacture any component or part with exact dimensions due to
human in accuracy or machine or process incapability . Thus for the components to meet
functional aspect as well as to bring down the cost of production, principle of
interchangeability concept is introduced. Interchangeable production means production
of parts to such a degree of accuracy that will ensure an assembly which will meet the
functional requirements.
Tolerances:-
Tolerance can be defined as the magnitude of permissible variation of a dimension or
other measured or control .criterion from the specified value. The primary purpose of
tolerances is to permit variation in dimensions without degradation of the performance
beyond the lim its established by the specification of the design .
Limits of Size:-
There are three considerations in deciding the limits necessary for a particular
dimension. These are
IMEI Corre
2.
referred to as a matter of convenience.
Basic size:- This is the size of a part in relation to which an -limits of variation are
. (
determined. Often, basic size and nominal size of a part oftJimension are used with
the same sense. 1 ',C
(k1'
3. Zero Line:- This is a line which represents the basic size so that the deviation
from the basic size is zero.
3:
Ow
....IN
w_
eill./)
f-U
z-
:::ll./)
0<1:
eil
L
<1: ZERO LINE
BASIC SIZE
3:
Ow
....IN
w_
eill./)
f-U
z-
=>1./)
0<1:
eil
L
<1:
HOLE HOLE HOLE
ABOVE OF BELOW
BASIC BASIC BASIC
SIZE SIZE SIZE
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. .6 ·
I ME I Correspondence Co.urse
i. Clearance fit :- in thi s t ype of fit, the largest permitted shaft diameter is
,L' smaller than the diameter of the smallest hole, so that the shaft can rotate or
slide though wi t h different degrees of freedom according to the purpose of the
mating members
II J' f
... Correspondence Course'" tarGATE'" ICP- Intensive Classroom Program ... eTutor '" Online Test Series
© All rig hts reserved by Gateforum Educational Services Pvt. Ltd. No part of thi s booklet may be reproduced or utilized in any form
without the written permission. 7
~
I ME I Correspondence "®,bcurse
MINIMUM CLEARANCE
< . OR POSITIV ALLOWANCE
71'>
MAXIMUM !::." '{'..
CLEARANCE
,"elj'!
00 :, .0J 1 i r~i
~ !. .,
17. Allowance:- The difference between the maximum shaft size and minimum hole
is known as allowance. In a clearance fit, this is the minimum clearance and is
positive allowance. In an interference fit, it is the maximum interference and is
negative allowance.
MINIMUM
INTERFERANCE
MAXIMUM
INTERFERANCE
OR NEGATIVE
ALLOWANCE
18. Basic shaft is a shaft whose upper deviation is zero. It is designated as shaft 'h'.
Basic hole is one whose lower deviation is Lero. It is denoted as hole 'H'
For shafts 'a' to 'g', the deviatio~ ;s below the zero line and for shafts 'j' to 'zc', it
is above the zero line.
For holes 'A' to 'G', lower deviation is above the zero lien and for 'J' to 'zc', it is
below the zero line.
Upper deviation for shaft is denoted by cs and lower deviation by ei: For holes,
the corresponding devicftions are denoted by ES and EI respectively. The other
derivations may be derived directly using the absolute value of the tolerance IT
by means of the algebraic relationship. .
ei = es- IT
es = ei+ IT
In hole basis system, different clearances and interferences are obtained by
associating various shafts with a single hole whose lower deviation is zero (H
>
-+ Correspondence Course -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 8 '
I ME I Correspondence Course
hole). This is standard practice and it is very convenient to make correct holes of
fixed sizes.
Whereas in shaft basis system upper deviation of shaft is zero, and different fits
are obtained by varying the limits on the holes.
In 1.S. specification, 18 grades of tolerances are designated:
IT01, ITO, IT1 to IT 16. These are known as standard tolerances and their
numerical values have been determined in terms of the standard tolerance unit i,
where i in microns is expressed as
i(microns) = 0.454'0 + 0.0010
o is the geometric mean of the lower and upper diameters of a particular
diameter step in which the diameter lies, D is in mm.
This formula has been empirically calculated. The relative magnitude of each
grade is given below:
Gardes ITS IT6 IT7 ITS IT9 ITlO ITll ITl2 IT13 ITl4 ITlS IT16
Values 7i lOi l6i 2Si 40i 64i lOOi l60i 2S0i 400i 640i lOOOi
0= ""18 x 40 = 23.2mm
The value of fundamental tolerance unit
i = 0.45.vD + 0.0010 = 1.3microns.
For hole quantity 8, from table, the fundamental tolerance
= 25i = 33microns.
For the 'H' hole, the fundamental deviation=O
Hence the hole limits are 25.000mm and 25+0.033mm=25.033mm
Hole tolerance = 25.033-25.000=0.033mm
For the quality '9' shaft, the fundamental tolerance
= 40i = 40 x 1.302 = 52microns
For 'd' shaft the fundamental deviation is given as (from standard result)
= _160°.44 = -65microns.
'I,: ~ymbols for tolerance a'nd'.deviations, and symbols for fits:- oii
The tolerance, the value of which is a funceiSr:r;i1f fhe b8sl t size is designat~d~by a
j
. number symbol, called the grade. The posit-ion of tolerand~ zone with res p~ct to
the zero line, which is a function of the bask size is indi'cat€f€l by a letter symbol,
a capital letter for hol~~) ~,d a small ,letter shafts. Th~iot'9lerance size . is ... thu'S '
defined by its basic value followed by 5\ .. sym~9IJ~ .~qm'P§li$~d of a letter and a
numeral, e6 g{OS~g7' 01 bl" G Jln,; , 2"'1":-
A fit is indicated by the basic size cJ<':~J}l rnPtf:l, to both cqrpponents, followed by a
symbols corresponding tp_ ~~ch compone,Q t\s ~ t~,~h0.leJ~ei~ .g first, e.g. 50 H 8g7.
nt! 6f, ," .. ' c::. . .
TOLERANCE UPPER
DEVIATION
•
1 1 1
3. Deviation:- The algebraic difference between a size and the corresponding basic
size.
4. Zero Line:- In a graphica '( representation of limits and fits, a straight line to
which the deviations are referred. The zero line is the line of zero deviation and
represents the basic size.
5. Tolerance:- Tolerance is equal to the algebraic difference between the upper
and lower deviations and has an absolute value without sign. For limits and fits,
the difference between ~he maximum limit of size and minimum limit of size is
called the tolerance.
6. Tolerance zone:- In a graphical representation of tolerance, the zone bounded
by the two limits of size of the part is called the tolerance zone. It is defined by i!s
magnitude and by its position in relation to the zero line.
7. Shaft:- A term used by convention to deSignate all external features of a part,
including those which are not cylindrical.
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Serie~
.;:; p.-
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 10
: GATEFORUM
mfI : . Engineering Succeas
. "" • • f • • • • • • • • • .....iLl) I ME I Correspondence Collf~~._
ffj~
12. 'Not Go' Limit:- It refers to the lower limit of a shaft and upper limit of a hole.
Thus it corresponds to the minimum material condition.
13 . Maximum and minimum metal conditions:- Maximum metal condition (MMC)
corresponds to condition when a part has maximum amount of metal, Le.,
corresponding to high tolerance of shaft and low tolerance of the hole. Similarly
minimum metal conditions corresponds to minimum size of shaft and maximum
size of hole.
Classification of Fits:-
Depending on the basis of negative, positive or zero value of the clearance, fits are
classifieds as
L Selective Fit:- Selective fit is required where the object is to make a shaft and
hole with a finite fit and not a permi ssible range on fit. This fit is known as the
ideal or selective fit.
iL Push Fit:- Push fit also known as 'snug fit' represents the closest fit that permits
assembling parts by hand. It requires a greater force that can be exerted by hand
in assembling the parts. With a push fit, there should be no perceptible play
between the mating parts.
iii. Driving Shaft:- When a plug or shaft is made slightly larger than the hole into
which is to be inserted and the allowance is such that the parts can be assembled
by driving, this is known as a driving fit. Such fits are employed when the parts are
to remain in a fixed position relative to each other.
iv. Forced or pressed Fit:- forced or pressed fit is the term used when a pin, shaft
or other cylindrical part is forced into a hole of slightly smaller diameter,
ordinarily by the use of hydraulic press or some other types of press capable of
exerting a considerable pressure. A force fit has a larger allowance than a driving
fit, and therefore, requires greater pressure for assembling.
v. Shrinkage fit:- A shrinkage fit is obtained by making the internal member
slightly larger than the hole in the external diameter. In shrinkage fit, the
pressure is not required for assembly but instead the external member is heated
.- and expanded sufficiently to permit inserting the internal member easily. Then as
the external part cools or is cooled by applying water or dry ice, it shrinks tightly
around the internal part.
Limits Gauges:-
~
The simplex form of limit gauges are those used for inspecting holes of shaft. Gauges
are inspection tools of rigid design, without a scale, which serve to check the dimensions
of manufactured parts. Gauges do not indicate the actual value of the inspected
dimension on the work. They can only be used for determining as to whether the
inspected parts are made within the specified limits.
Plain gauges are used for checking plain (unthreaded) holes and shafts. Gauges are
classified as
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum· Educational Services Pvt. Ltd. No part of this booklet may be reproduced or u.tilized in any form
without the written permission. i 1
'~A'
- I ME I Correspondence';e ourse
,';
1. According to their type:-
a. Standard and limit gauges
b. Limit Gauges
2. According to their purposes:-
a. Workshop
b. Inspection
c. Reference or master gauges
3. According to the form of the tested surface:-
a. Plug gauges for checking holes
b. Snap and Ring gauges for checking shafts
4. According to their design:-
a. Single limit and double limit gauges
b. Single ended and doubled ended gauges
c. Fixed and adjustable gauges
Gauge Design:-
To a greater or lesser extent, every gauge is a copy of the part which mates with the
part for which the gauge is designed. If a gauge is designed as an exact copy of the
opposed part in so far as the dimension to be checked is concerned, is called a 'standard
gauge.
Taylor's Principle:- According to Taylor, 'Go' and 'No Go' gauges should be designed to
check maximum and minimum material limit which are checked as below.
'Go' Limit:- This designation is applied to that limit of the two limits of size which
corresponds to the maximum material limit considerations, i.e, upper limit of a shaft and
lower limit of a hole. The form of the 'Go' gauge should be such that it can check one
feature of the component is one pass .
'No Go' Limit:- This designation is applied to that limit of the two limits of size which
corresponds to the minimum material condition, i.e. the lower limit of a shaft and the
upper limit of a hole. •
Geometric Dimensioning and Tolerancing:-
Geometric dimensioning and tolerancing are means of spe~ifying engineering design and
drawing requirements with respect to actual function and relationship for part features;
which can be most economically produced. Geometric tolerances are concerned with the
accuracy of the relationship of one feature to another; and these are specified
separately. These represent the maximum permissible overall variation of form, or
position of form, or position d~ a feature.
Geometric characteristics and Symbo ls:-
The use of symbols on drawing in place of notes has the advantages of uniform-
meaning, no misunderstanding, compact and quickly and easily drawn, international
language requiring no interpretation etc.
,
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 12
, GATEFORUM
mil
~ Engineering Success
• • ~• • I . f • • • • • • • • • I ME I Correspondence C6fifse
-'---' - -
The various geometric characteristics and symbols used are given below
Geometric characteristic Symbol
Flatness
0
Straightness
.m 'lOlL
Roundness (circularity)
0
,-"
Cyl i nd ricity
q
Profile of a line f\
Profile of a surface
~
Perpendicularity
(squareness or normality) ~
Angularity
L
Parallelism
II
Circular runout
Total runout
I
'" -
Total
Position
-$-
Concentricity
.. 0-
Symmetry
Maximum material
condition MMC -----, G
Regardless of feature size RFS
(0
Projected tolerance zone ,
0
~
Datum target
Diameter (cylindrical)
tolerance zero
... Correspondence Course'" 1'arGATE ... ICP~Intensive
0
Classroom Program'" eTutor ... Online Test Series
© All rights-reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 13
.~~~,
I ME I Correspondencer;Course
} I
Cl 1
Symbol Toler-
Feature control symbol of dia ance At ma¥. materia l
characteristic
Comparators:-
The comparator is an instrument used for comparing the dimensions of a component
with a standard length. They work on relative measurements.
Characteristics of comparators:-
Various fundamental requirements which every comparator must fulfill are as follows:
i. The instrument must be of robust design and construction so as to withstand the
effect of ordinary usage without impairing its measuring accuracy.
ii. The indicating devices must be such that the readings are obtained in least
possible time and for this, magnification system used should be such that the
readings are dead beat. The system should be free from backlash and wear
effects and the inertia should be minimum possible.
iii. Provision must be made for maximum compensation for temperature effects.
iv. The scale must be linear and must have straight line characteristic.
v. rhe indicator should be constant in its return to zero.
vi. Measuring pressure should be low and constant
Uses of Comparators:-
The various ways in which the comparators can be used are as follows:
i. In mass production, where components are to be checked at a very fast rate
ii. For inspecting newly purchased gauges
iii. As laboratory standards, where components are to be checked at a very fast rate.
iv. In selective assembly· of parts, where parts are graded in three groups depending
upon their tolerance
v. As working gauges, to prevent work spoilage and to maintain required tolerance
at all important stages of manufacture.
Types of comparators:-
1. Mechanical comparators
2. Mechanical optical comparators
3. Electrical and Electronic'comparators
4. Pneumatic comparators
5. Fluid displacement comparators
6. Projection comparators
7. Multi check comparators
8. Automatic gauging machines
+ Correspondence Cou~se + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission.
~.
~ !~!~rfn~!~!!
~
•• • • , • • • • • • WI • • I ME I Correspondence Course
Mechanical comparators:-
In these comparators, magnification is obtained by mechanical linkage and other
mechanical devices.
i. System of Displacement Amplification used in Mechanical comparators:-
a. Rack .and Pinion
b. Cam and gear train
c. Lever with toothed sector
d. Compound levers
e. Twisted Taust Strip
c. Lever combined with band wound around drum
ii. Dial Indicator:- This is generally used for inspection of small precIsion machined
pC!rts, with a V-block attachment, it can be used for checking out of roundness of
a cylindrical component.
iii. The Johanson 'Mikro Kator'
iv. Read Type Mechanical comparator
v. Sigma Comparator
Electrical Comparator:-
These comparators have little or no moving parts and hence can retain their accuracy
over periods and also the sensitivity can be adjusted at will. A higher magnification can
be achieved , as compared to mechanical comparator. Linear variable differential
transformer (LVDT) is the most popular electro-mechanical device used to convert
mechanical displacement into electrical signals.
"\
Pneumatic Comparators:-
Air gauging has recently increased due to its very high amplifications as no physical
contact is made either with the setting gauge or the part being measured. Based on the
physical phenomenon on which the operation of pneumatic gauges is based, these may
be classified as
i. Flow or velocity type:- It operate by sensing the manometry rate of air
flow
ii. Back pressure type:- It operates by senSing the velocity differential
pressure across a venture chamber.
Optical comparators:- In optical comparators, magnification is obtained with the help
of light beans which have advantage of being straight and weightless. Optical
comparators have their own built in illuminating device which tends to heat the
instrument and thus accuracy is liable to suffer. In mechanical optical comparators, a
small displacement of the measuring plunger is amplified first by a mechanical system
consisting of pJvoted leavers and further a simple optical system involving the projection
of an image is amplified.
Electronic Comparator:- It is based on the principle of application of frequency
modulation or radio oscillation~ It provides a reliable means of measuring external and
internal measurements with a remarkable accuracy and ease.
Measurement of Geometry of form or Shape:-
The conditions of external and internal roundness demand the most attention of any
form or shape measurement, since this type of geometry comprises the great majority
of mecnanica\ form conoitions \nffianU~ac.tur\ng o?e.rat\cms.
,I
+ Correspondence Cours~ + TarGATE + ICP"':'Int0nsive Classroom Program .. eTptor + Online 'Fest Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any Torm
without the written permission. 15
; GATEFORUM
mil i . Engineering SUcce&s
• •- iI'.• • • • • • • • • II • • I ME I Correspondence·, G~
. . ~."
;·rse
Straightness:-
A tioe is said to be straight over a given length, if the variation of the distance:-, of its
pol:nt~ from two perpendicular to each other are parallel to the g~neral direction 'of the
line and it remains with in the specified tolerance limits. 'f C~i'
+ Correspondence Course +' TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be r13-pr!ldiJced or utilized in any form
without the written permission. . 16
(
I ME I Correspondence Course
r
Some Important Terminology:-
1. Surface Texture:- Repetitive or random deviations from the nominal surface
which form the pattern of the surface. Surface texture includes roughness,
waviness, lay and flaws.
2. Surface Roughness:- It concerns all those irregularities which form surface
relief and which' 'are conventionally defined with the area where deviations of
form and waviness ,are eliminated.
3. Primary Texture (Roughness):- It is caused due to the iar:egularities in the
surface roughness which result from the inherent action of the production
process.
4. Secondary Texture (Waviness):- It results from the factors such as machine
or work deflections, vibrations, chatter, heat treatment or warping strains.
Waviness is the component of surface roughness upon which roughness is
superimposed.
5. Flaws:- Flaws are irregularities which occur at one place or at relatively infrequent
or widely varying intervals in a surface (like scratches, cracks, random, blemishes
etc).
6. Lay:- It is the direction of the predominant surface pattern ordinarily determined
by the method of production used.
LAY
DIRECTION OF
DOMINANT PAlTERN
ROUGHNESS SPACING
ERROR OF FORM
Methods of Measuring surface Finish:-
There are two methods used for measuring the finish of machined part:
1. Surface Inspection by compa rison method
2. Direct instrument measurements .
1. Surface Inspection by comparison methods:-
The various methods available under this method are as follow:
i. Touch Inspection
ii. Visual Inspection
iii. Scratch Inspection
~
iv. Microscopic Inspection
v. Surface Photographs
vi. Micro Interferometer
vii. Wallace surface Dynamometer
viii. Reflected light intensity
ix. Comparison with standard specimens
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gat'eforum EducatPona.'1Services Pvt. Ltd " No part of this booklet may be reproduce"d or utilized in any form
without the written permission. 17
""~
-'-~.:-
+ Correspondence Cours&+ TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
©AII rights reserved by Gateforum Educational Services Pvt: Ltd, No part of this booklet may be~rWo<'iuCed 6fUiinzed iria'iiy form '
without the written permission, 18
-I
- -------------------------------------------------------~
. ~:::rrA
.-~.~n1lin 3
I ME I Correspondence Goti'
Level - 1
'-l
3. The diameter of a bore was measured by a pin gauge. The length of which was
measured by vernier caliper as 250.01mm. The swing of the free end of the
gauge was measured as 34.0mm, then the diameter of the bore is
(A) 262.3mm (B) 158.2mm (C) 356.1mm (D) 250.6mm
(B) Interchangeability ~
Number
of hole
gradings
1
(C) Matched fits
,
I~
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series .
"r ; 1 I" ,)A"," r. ..... 'n('l'1 •
© All rights reserved oy Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 19
~rAf)'
I ME I Correspondenc'e~~(!tjurse
(B) 3500
pointer
•
(C) 3800
(D) 4200
10. Basic shaft & basic hole are those whose upper deviations & lower deviations are
(A) +ve, -ve (B) - ve, +ve
(C) minimum, maximum (D)zero, zero
11. Which of the following method is not used for measuring (testing) straightness?
(A) spirit level method (B) auto collimator
(C) interference method (D) beam comparator
12. Which of the following method is not the correct way of specifying numerical
value of surface roughness?
(A) centre line average (CLA) value (B) mean line & envelop line system
(C) r.m.s. value (D) peak to valley height
-+ Correspondence Couise -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt Ltd, No part of this booklet may be re~r:;d~ced or utilj~ed i~ ~ny form
without the written permission, 20
GATEFORUM -¥-
Engineering Success
.'iI.II.' I. "' ••• a 'Ii • •
I ME I Correspondence Course
16. According to well accepted practice, slip gauges which have been handled for a
few minutes should be left for sometime. The reason for this could be
~ (A) The moisture transferred from hand would evaporate
(B) The structu ~ pf gauges, if d istu rbed would stabilize
(C) Gauges attain the room temperature again
(D) With continuoUs use, gauges may wear quickly
u
17. Which of the figure below gives the correct disposition of manufacturing tolerance
for screw thread limit gauges for both Go & No Go gauges in cas'e of ring caliper
gauges?
(A) A
(\)
u
(B) B C
tU
l...
(C) C (\)
0
~
(D) D
(E) E
B D
18. IS: 919 on limits & fits specifies following numbers of grades of fundamental
tolerances and fundamental deviations respectively
(A) 25, 18 (B) 25, 16 (C) 18, 22 (D) 18, 25
19. The comparator utilizing the principle of a button spinning on a loop of string is
(A) Aramson comparator (B) Sigma comparator
(C) optical comparator (D) Eden-Rolt comparator
20. In figure, the combination of hole and shaft represents hole basis system
~tolerance on hole
IIIi!I IIiIItolerance on shaft
Zero
li ne
B
22. An assembly between two parts should be such that the clearance between them
should be maximum. Now the maximum clearance is given by
(A) Maximum shaft- minimum hole (B) Maximum hole -minimum shaft
(C) Minimum shaft- maximum hole (D) Minimum hole- maximum shaft
+ Correspondence Course'+ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum EducatirYl'taJServices PvL Ltd. No part of this bookleit'may be reproduced or u.Wized in any form
without the written permission. 21
~;$JA~~ ( ..
~ •• y••
, GATEFORUM
, En ineerlng Succe&&
t ••••••••• I ME I CorrespondenC~~~;Q\.tTSe
23. The linear measurement device used for setting apart the work pieces atJ{Jesired
distances in milling, grinding and shaper vice is 'lQ
(A) Engineers square (B) Engineers taper '\j
(C) Engineers parallel (D) Feeler gauge
:J9 21J .
24. Squareness of any two'"IIJl~chan ical surfaces can be e,a,~;~y checked with tge help
of a ..
jnuc ' ~- '0." " "
(A) Auto collimator (B) Dial indicator
(C) Engineers parallel (D) Clinometers
1,
25. The appropriate device for measuring the relief angles on large cutting tools is
(A) Angle gauge (B) Sine bar
(C) Clinometer (D) Auto collimator
26. Which of the following fits requires heating of the external member?
(A) Forced fit (B) Driving fit
(C) Shrinkage fit (D) Interference fit
27. Certain terms connected with limits and fits are as below given. Of these, the
hole and shaft are involved with the terms
Terms:
1. Basic size 2. Tolerance 3. Allowance 4. Fit
(A) 1 and 2 (B) 2 and 3 (C) 3 and 4 (D) 1 and 4
28. The clearance between the piston and cylinder can best be measured by a
(A) Universal surface gauge (B) Feeler gauge
(C) Radius gauge (D) Screw gauge
29. The interference between a shaft and hole is given by the size difference of
(A) Maximum shaft and minimum hole
(6) Minimum shaft ctnd maximum hole
(C) Minimum shaft and minimum hole
(D) Maximum shaft and maximum hole
31. A casting jig is used i" the production engineering mainly due to the reason that
(A) It absorbs and dampens out vibrations
(B) In case of dropping, it brakes instead of bending and prevents production of
a defective part.
(C) A number of castings of same characteristics can be made frorti-'6ne pattern.
(D) Complicated shapes can only be cast.
'----------------~----------------------------------------------------
+ Correspondence Cour~e + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt, Ltd,' ,No part of this booklet may be reprodwced or utili·zed jl).,anY .fp~m.,
without the written permission,
:..' ,~~ ,/
~'~~
_ _ I ME I Correspondence COUT~S~
32" c9tldentify the manufacturing process through which a milling fixture is preferably
prepared.
(A) Forming (8) Casting (C) Milling (D) Welding
36. The pins used for locating a work piece whose dimensions are subject to variation
are
(A) cylindrical locating pins (8) support pins
(C) conical pins (D) jack pins
38. A body in free space has 12 (twelve) degrees of freedom. The number of pins
needed for arresting all the degrees of freedom will be
(A) 9 (8) 6 (C) 12 (D) 4
... Correspondence,Course -+ TarGATE ... ICP-Intensive Classroom Program ... eTutor ... Online Test Series
© All rights reserved by' Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission, 23
,~ fj.t~\
~!~!!rfn9s~~
~ .............. .
,
I ME I- Gerrespondehce--C-ourse
~;IP, , ?
1nt: '';,'
41. A shaft with
• 40-- 00.0494
.
025
specification and a hole with 35°·100
0.009 specification will have
(A) clearance bit
, r
(En interference bit (C) transition bit (D) None of these
-+- Correspondence Course -+- TarGATE -+- ICP-Intensive Classroom Program -+- eTut@r ·. Onlin~~Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 24
I ME I Correspondence Collr~e
46. In NC part programming spindle speed of 739 rpm will be coded by the magic - 3
rule as
(A) N730 (B) 5730 (C) N037 (0)5037
I
(2) Machining finish (B)
b-,
I
(3) Chipping finish (C)
/ 1L
(4) Concave contour (D)
/' ZS
(A) 1 - 0 2 - B 3 - C 4 - A (B) 1 - C 2 - 0 3 - B 4 - A
(C) 1 - C 2 - B 3 A 4 - 0 (D) 1 - 0 2 - C 3 - B 4 - A
+ Correspondence Course +- TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserveod by Gateforum Educational Services Pvt. ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 25
'·'·.• 'fA~l:~
I ME I Corresp_oh
_
d ~Jac e;:Ji~@Mrse
J .~ ~,
51. In tape preparation for an NC machine tool, the code 5624 would represent
. spindle speeds of
(A) 624 rpm, 240 rpm, 264 rpm (B) 624 rpm, and 240 rpm
(C) . 624 rpm and 246 rpm (D) 240 rpm and 246 rpm
52. One of the pins in a dual pin locator of jig or fixture is shaped as a "diamond pin
iocator" because
(A) Diamond pin does not wear fast.
(B) It is easy to clamp.
(C) Any variation between the centers of holes is taken care of.
(D) It will be easy to machine afterwards when the locator is worn out.
54. H7 - g6 provides
(A) Slacking running fit (B) Sliding and location fit
(C) Heavy fit (D) Press fit
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program ... eTutor ... OI!lin,e Test Series
I • ,~ :aa . _"" '_..J
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 26
, ..
'. , : '.~>i ~'i.
____ __ I ME I Con:espondence_C4lH'Se I'
"I\, f} ~ '~
I .......
Level - 2
1. The following resu lts were . obtained usi ng an NPL-type absolute length
interferometer with a slip gauge of nominal length 3rrm at 20°C. Ignoring
environmental corrections such as barometric pressure
~'1U2b observed ; ' calculated
Colour A(11m} "':;n9ir i
fra ction' j c fraction
Red 0.6438 0.91 0.66
Green 0.5086 0.66 0.09
Blue 0.4800 0.66 0.00
Violet 0.4678 0.70 0.99
Then the length of the gauge is -
(A) 0.003mm (6) 0.0004mm (C) 0.0072mm (D) O.ci017mm
2. The diameter of the bore in plain ring gauges was reassured by lying (t in a flat
surface & placing three 20mm diameter balls equally spaced inside it, with a
30mm diameter ball resting on them, the distance from the surface to the top of
the 30mm ball was measured as 42.60mm, then the diameter of the bore is
.. Co~w.p.9!!denc~ Course" TarGATE .. ICP-Intensive Classroom Program -+ eTutor .. Online Test Series ....
© All rights reserVed by GateforurTl Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form '
without the written permission. 27
, GATEFORUM
mil
! Engineering Success
. . . . . 1 .. . . . . . . . . .
S. The figure shows a train of gear wheels driven by a driving band which applies
pull to a drum 20mm in diameter, ca rried by wheel A. The whole arrangement
forms a displacement measurement system. The numbers of teeth on the wheels
A,B,C,O & E are lS0, 7S, lS0, 100 & SO
driving
band
6. For a sine bar, that the error of angular setting I S I arising from errors of the
dimensions I & h is given by
(A) ~S = secS ~h+ tanS M (B) ~S= tanS ~h_secs M
e e e e
(C). ~S = tanS ~h + secS M
e e
S. The limit of size for inspection gauges conforming to Taylor's principle to check
the rectangular hole is shown in figure. The limits of size for a SOmm HS hole are
low limit SO.OOmm, high limit SO.039mm. The limit size for a 7Smm HS hole is
low limit 7S.00mm & 7S.046mm. Fundamental deviation for H hole = 0,
i(micron) = 0.04501 / 3 + O.OOlD, ITS = 25i
SOmm is in diameter step 30 - SO
75mm is in diameter step SO - SO
Assume gauge tolerance to be 10% of work tolerance, Go gauge: -
(A) 75.011mm, 7S.00~m
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Onlin~ Test Series
-
3 0mm
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 28
: ~}~~ ,"
I ME I Correspondence C~'i"·se·-l;
..
~ ., "''- """'v'
10. Calculate the radius of curvature (R) of the dial of a spirit level of 200mm base
length with one scale division indicating a change of level of 2.51Jm in 100mm.
The length between scale divisions along the curvature is 3mm
11. A hol e & shaftin g system has the following dimen sions
50 HYcS
the standard tolerance is i = 0.45D1/ 3 + O.OOlD
D = diameter of geometric means of steps
The multiplier for grade S is 2~ .
Fundamental deviation for shaft C, for D>40mm is given by -(95+0.SD) microns
The diameter range is between 50 to SOmm
Then the minimum size of shaft is
(A) 49.S0mm (B) 49.S544mm (C) 49.7316mm (D)none
+ CorrespGndence Course + Tar GATE + ICP-Intensive Classroom Program" eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 29
GATEFORUM ,
.......•..•.
EngineerIng Succeas I ME I Correspondence Course
-,
12. A hole & shafting system has the dimension' 60 H - 7 . The standard tolerance is
m-6
i = 0.45(D/ + O;POO1O, D = diameter of ~eometric mean step of 50 to 80mm,
13
iee re
i = standard tolerance, micron, the multipliers are
',.~ grade: 6" ,r
mu Itiplier : 10 r'~£6 E' .
rt ,"
The fundam~ntal deviati·oill;':,;;for 'fit ~'i: Kilff i~:given 'by ,F,D. = + (IT 7 IT 6) for the
relevant rrftnge of diamet~rnhen the tYifp i~Ofifit is
(A) interference. fir (8) transition fit ."~~ (C) clearance fir (D) none
i = 0.45(D)1/3 + O.OO1O(microns)
D is geometric mean of diameter steps between 30 & 50mm
Grade of tolerance IT7=16i (microns)
Fundamental deviation f = -5.5D°.41 (microns)
The dimension of hole length Q is
0.100 0.131 0.100 0.120
(A) 36°. 009 mm (8) 36o . 100 mm (C) 350 ,oo9 mm (D) 3S0.0 10mm
%=1.10-b~ foro.6>%>0.8
.. Correspondence Course "~ TarGATE .. ICP-futensive Classroom Program" eTutor .. Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. 'No part of this booklet may be reproduced or utilized in any form
without the written permission. 30
I ME I Correspondence Course
15. The CLA(Ra) value of a surface for which the sampling length was 0.8mm
The graph was drawn to a vertical magnification of 10,000 & a . horizontal
magnification of 100 & the areas above & below the datum line were
above 150 80 170 40mm2
below 80 60 150 . 120mm2
(A) 2.611m (D) 2.811111m
17. The figure shown below indicates ,~ ste,el C-40 plug diameter is to be concentric
and the concentricity error should not exceed 0.02Smm. The square ness of the
faces with the axis of rotation is to be within a permissible error limit of 0.02mm
grade of tolerance ITS ~ 7i i = 0.4501 /3 + 0.0010
where 0 is the geometric mean of 18mm and 30mm
R350
I - ~
Ra O. 04
\I
Grou nd
_8
0.0
+0.040
<1>38 ADO 0.000
--- -- -1---------------
3 - <p 25.000hs
E ~ E 40 .280±0.050 ~~
E C =7.
78.380±O-lOO
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 31
'.,1:~ ·~ .' "'-I)
.' ' I ME I Corresponderice Cou:r:$e
B II A10 .OS
J.-
... -
<E(-~G~---+)~(-----O-.OO------+)
100- 0 . 10
The dimension of 27g8 is
(A) 27=g :g~7 mm (8) 28=g:g~8mm ( C) 2]+° ·007 mm
+0.04 (D) none
-+ Correspondence Cou~se -+ TarGATE + ICP- Intensive Classroom Program -+eTutor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 32
I ME I Correspondence Co:urse
21. The "Go" plug gauge and "Go" snap gauge inspects respectively the
(A) Maximum limit oJ hole and maximum limit of shaft
(B) Minimum limit of shaft and minimum limit of hole
(C) Maximum limit of hole and minimum limit of shaft
(D) Minimum limit of hole and maximum limit of shaft
22. Taylor's principle of design of gauges stipulates that 'No Go' and 'Go' gauges
should be designed to check respectively the
(A) Minimum material limit and minimum material limit
(B) Maximum material limit and max imum material limit
(C) Maximum material limit and min imum material limit
(D) Minimum material limit and maximum material limit
25. The difference in size between the 'Go' and 'No Go' limits of snap and plug
gauges represents the quantity
(A) Allowance (B) Lower deviation
(C) Upper deviation (D) Tolerance
27. 60 mm H7 - f8 designates a
(A) hole (B) shaft (C)fit (D) limit
-+- Correspondence Course +TarGATE -+- ICP-Intensive Classroom Program -+- eTutor -+- Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 33
GATEFORUM
~~;r!~.~~ ',-~ ,',
28 . A 80mm shaft rotates in a bearing. The tolerance for both shaft an'(ij .bearing ·i§ }::
0;08mm and the required allowance is 0.1 mm with the basic hole !?tand~rd, the
sizes of maximum shaft and minimum hole are (in mm) ' - , -
(A) 80.08 anvd 80 (B) 79.9 and 80 (C) 79.92 and 80 (D) SO and 79.92
30. The closest fit ·that permits assembling parts by hand among the following i~
(A) push fit (8) driving fit (C) selective fit (D) press fit
~I,.: .
Wear .allowance is normally taken as ,
.. .
(A) ' 0.5% of work tolerance (8) 5% of work tole'rance
(C) 0.1% of work tolerance (D) 10% of wor~ ~HJ erslnce
) . ,
~:) ,
37. A shaft has the limits of 45~~:~~ mm. When , 45 mm--is : its. di.a,meter/ the gauge
maker's tolerance to be taken for thts ,shaft ~ill.pe ... '.(:,' ' f , roE) /,
(A) 0.002 mm (8) 0.003 mm _',. (C)~.O;()OLmrn (D)0.005 / rhm
"" ::: ;..,.'1 .:;."1 ; -1. \ ,.,),l-- ~ (~.
38 . The dimensions of a hole are 50.05 nim on high limit and 49.94 mill on l'Ow limit.
For this gauge maker's tolerance and wear allowance are respectively
(.A) 0.001 mm and O..QO.?, .rnm, . . . c, ~., ,_ (8) 0.011 mm and 0.0055 mm
(C) 0.01 mm and 0.0055 mm (D) 0.011 mm and 0.005 mm
39. Choose the true statement about 'Go' and 'No Go' gauges
(A) No Go gauge's maSt cfiways be" pO(l nto conditions of maximum passability
(B) No Go and Go gauges must always be put into conditions of maximum
impassability .
(C) Go gauges must always be put into conditions of maximum passability
(D) No Go gauges must always be put into conditions of maximum impassability
40. The correct statement about work shop and inspection gauges is
(A) These two types of gauges tolerances are arranged to fall outside the work
tolerance .
(8) These two types of gauges tolerances fall inside the work tolerance
(C) Workshop gauges tolerances are arranged to fall outside the work tolerance
while inspection gauges are arranged to fall inside the work tolerance
(D) Workshop gauges tolerances are arranged to fall inside the work tolerance
while inspection gauge tolerances are arranged to fall outside the work
tolerance •
41. A 100 mm sine bar is used to find the included angle of a plug gauge as shown in
figure. Height of slips below the lower cylinder is
25 mm. If angle is 30° what is the height of slips
below the upper cylinder.
(A) 50 mm ,
(8) 75 mm 'T'"
h
(C) 125 mm
(D) 150 mm
1
-+ Correspondence Course -+ TarGATE -+ ICP-futensive Classroom Program -+ eTutor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 35
;., , "'lj'!I
I ME I Correspondence Course
42 . Figure shows some of the commonly used symbols for geometric characteristic
and tolerance son detail drawings as per ISO standards.
List I List II
(1)
(2)
$ (A) Symmetry , •
/:j
(4) (D) Position
(5)
L I (E) Diameter
+ Correspondence Course'+ TarGATE + ICP-futensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission, 36
I ME I Corresponde~ce6'Xr~e
A shaft and hole are specified a$ :25 H7 / f8 fit being given with usual notations.
. + Correspondence Course +\ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
~ithout the written permission . 37
--- -- -- - - - - - - - - - - - - - - - - - - - - - - - - ---.,i.
p t.lI!!!iii!!!!!liii!l!i!
~
' GATEFORUM .'~ .. . ". j
Engineering Success
• • • • 11 • • • • • • • • • I ME I Correspond:eh~e Course~
Answer Keys
Level-1
1 C 2 C 3 D 4 D 5 D 6 C , ,7 D
8 D 9 A 10 D 11 C 12 B 13 C 14 A
"
c.
15 B 16 C 17 B 18 D 19 A " 20 A 21 A
22 B 23 C 24 A 25 C 26 C 27 C 28 B
29 A 30 A 31 B 32 B 33 A 34 A 35 C
36 D 37 A 38 A 39 B 40 C 41 B 42 D
43 C 44 D 45 A 46 B 47 C 48 B 49 D
50 A 51 D 52 C 53 B 54 , A
-'
Level-2
• ~fl t:!!S Arl <:;:::1-::1
1 B 2 A 3 D 4 B C 6 D 7 A
8 C 9 C 10 D 11 " ~c;- 12 !r ,I;), 'r 13 C 14 A
15 B 16 C 17 B 18 C 19 A 20 B 21 D
22 D 23 A 24 C 25 A 26 B 27 C 28 B
•
29 C 30 A 31 B 32 A 33 A 34 A 35 A
36 B 37 D 38 B 39 A 40 D 41 B 42 A
43 A 44 A 45 B 46 C 47 C 48 B
Explanations:-
Level - 1
(250 .04)2
3. = 250.62mm
~(2 50.04)2 - (17.00)2
Level - 2
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rig hts reserved by Gate10rum Educational Services Pvt. Ltd. No part 01 this booklet may be reproduced or utilized in any 10rm
without the written permission. 38
I ME I Correspondence C~ur se-
3. Displacement is given by, d=W(i-t) =W{1-t) =10 XO.0003 Xl0( 1- /5) = O.Olmm
4. PP = -0.5 M M 0.5M
C + 1.1,0.55 = -0.5 C + 1.1,-C- = 0.55
. .
5. Gain of gear train = -150 x -150 100
-x - =6
75 100 50
In one revolution Of strum, the distpnce covered = ..:n: (~0) = 2n: x 10mm
The number of degre~s q:o'y'er:-~d by wheel E in one revolution of drum = 6 x 360 0
-+ Correspondence Course -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
© All rights reserved by Gateforum Ed ucational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 39
-- m GATEFORUM
Engineering Succe&S
.r~'-I(' ••••••• , .
I ME I
i~ ~( 0
. . 1/3
11. D = .j50 x 80 = 63.2mm, i = 0'.45 (D) + O.OOlD = 0.00185mm
the value of fundamental deviation for shaft C
= -(95+0.8D) microns = -0.14556mm, Max. size = 50-0.14556=49.8544mm
rcDLa
14. -p = 0 .6, 0.6 = 1.10 - 0.5x - - =? La = 0.25mm
p ~d2
4
. h-25
41. sm30 = => h =; -75mm
L
,i. ~lJ
Size of hole
Upper limit
= 25°. 021
0.00
= 0.0325 + 0.02 = 0.0525
0.020{
O} 0.0325
Size of shaft = 02
25-- 00 ..052 5
+ Correspondence Course + tarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 41
GATEFORUM
~~~E~nguin~e~~
. (~~SUUC~~SU~_'~'~
' ~
I ~:~________~__~____________~__~____~~____~~~~
I ME I Corresp'~~·denc:·.: t:i" ''7'
-..e
I:
o
U
-a
c
".-
III
I:
Topi,s Covered.
• Forecasting Models
C
-a-.
I:
&I
• Aggregate Production Planning
• Scheduling and Materials Planning
..1: '
.-o
U
:I
-a
e
a.
.
..".:.'-'-
, ,
- -~
<,0;' ;t ,~I:JITespondence Cour~e + TarGATE + ICP~futensive Classroom PrPgIatiJ. + eTutQr + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
2 wi~thout the written permission. ' 43
PRODUCTION, PLANNING AND CONTROL
Production is defined as the manufacturing of goods and serVices and planning is defined
as the service of related and coordinated activities - materials control, process planning,
scheduling
Production planning, therefore, is the pre-determination of manufacturing requirements
such as men, materials, machines, manufacturing process for the production of goods of
the right quality, in the right quantities and at the right time.
Control is to r~view the work progress; make corrections whenever required thereby
ensure that programmed production takes place . Production planning and control thus is
the process of planning production in advance, setting rate of each item, fixing starting
and finishing dates for each item, authorizing shop activity by release of production
orders, follow up the progress of products and expediting wherever required.
(2) Pre-production planning: It covers capacity planning and order intake control
(3) Ordering: It includes make or buy decisions and ordering of own made and
pu rchased items
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 45
I ME I Correspondence Course
Work order: A work order is an internal document of the PPC department and is raised
to authorize its different wings to initiate action on the item(s) indicated therein.
Order preparation: Order preparation is the process of converting sales orders into
work orders, converting work orders into shop orders, preparing auxiliary orders and
releasing subsequently to those concerned to authorize manufacturing activities.
Materials planning: Materials planning are the scientific way of determining the
requirements of raw materials, bought out parts and others and ensuring their
availability in the right quantities, at the right time within capital lock up.
A Direct material
(a) High value (i) Bill of materials
(ii) Material requirement planning
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 46
I ME I Correspondence Course
Bill of materials:
Bill of materials (BOM) also called part lists or building lists, is the document generated
at the design stage. It details the structure of the product by dividing the final assembly
into major assemblies, major assemblies into sub-assemblies and sub-assemblies into
parts. Bill of material provides details such as part name, part number, description,
quantity required, material etc.
Scheduling:
Scheduling is the process of fitting a shop order into the uncommitted time available for
a machine or a group of machines required for the manufacture of the item and within
the total time which is not greater than the promised delivery period.
The scheduling must:
(i) Ensure maximum utilization of the plant at minimum cost
(ii) Ensure that requirements of manpower is optimum and is evenly distributed, there
being no peaks and valleys
(iii) Keep itself abreast of hiring, dismissals, retrenchment etc : of the 'l'{ork force
(iv) Possess up-to-date information regarding availability of materials, expected
del ivery dates, materials rejection shortage, purchase orders cancelleq etc.,,,,
(v) Possess up-to-date data on each machine regarding its break down, availC!bility of
spares, average frequency of breakdowns, replacement schedules
~.-"
etc. "
·t ~ l'('-~lr.,
Input of scheduling:
The following are the major inputs of the scheduling function
(A) Performance standard
(8) Unit of measurement
(C) Unit of loading and scheduling
(D) Effective capacity per work
.-/
centre -
Loading: It is defined as the assignment of work of a facility. The facility may be man,
machine, a department, a grotlp of men, group of machine of a plant. In loading the
sequence of operations of the jobs, and the actual time of starting a job are not
mentioned.
For effective loading anq scheduling, these should be followed as rules:
(1) Loading should be done at the higher level of organization
(2) Whenever possible, in formal loading, scheduling should be done
... Correspondence Course'+ TarGATE ... ICP-Intensive Classroom Program ... eTutor ... Online Test Series
© All rig hts reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 48
~!~!~IPs~~
~ •• ".II ••••••••• I ME I Correspondence Course
Master scheduling:
The technique is very simple. It does not provide the detailed information regarding a
job, rather it gives an overall picture of the jobs.
Perpetual Loading:
This system makes use of load analysis sheet, Gantt chart and a file known as open
order file. The open order file collects a copy of every work order. The work order is a
document which in a way and authorization letter passed on to the lower level in a shop
for carrying out the work.
Order scheduling:
It is the most detailed technique of planning the activities. In this technique the
following information are necessary for each operation:
(i) Set up time
. (ii) Starting time
(iii) Completion' time
(iv) Material movement time
I
'-------'
Loading by scheduled period:
In this system; Gantt chart is used to show the scheduled periods. For each job, the
following information are collected
(i) Set up time
(ii) Operation time
(iii) Total number of operations.
(iv) Technological sequence of each job
(v) The machine on which operation will be performed
Gantt charts:
Gantt chart is very useful in loading and scheduling, dispatching and progressing
The chart consists of a simple grid formed by a series of horizontal and vertical lines.
The vertical lines divide horizo~tal lines into small squares representing units of
measurement which may be days, weeks or months. The horizontal lines divide vertical
lines into sections which are used to represent either operations Uob schedule) or to
represent work centers (load chart)
The chart may be drawn to show at a glance the scheduling of various operations
involved in a job or it may be drawn to show work ahead of each machine or work
centre with respect to time i.e. in days or weeks.
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 49
'*
m!jGATEFORUM , "'''''w' """\"~
.-. ,
·C··d·
Engineerin~
Success
Ir • • • • • • • • •
I ME I Correspon'ii,eri~ce Cour~e
The former is known as thejob schedule while ,the lat er is called load charts.
A typical Gantt chart is shown below.
r-~--~
. J
~T.
__~
,.~---------------------------------------------.
Routing: Routing is the path followed by products for being processed at various
machine tools and departments . The sequence of operations required for least back
tracking is maintained.
-+ Correspondence Course -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
" '@'AlirightS'reserved by Gateforum Educational Services PvL Ltd, No part of this booklet may be reproduced or utilized in any form
witQout the written permission. ' 50
~ ------·--- - - - - - - - - -- - - - - - - -."""'M
-c--;
-
' GATEFORUM.
mil i
•En• fI ineering Sliccess
• • •-...... .. . .
FORECASTING
Sales forecasting is the estimate of level of demand to be expected for a product for
some period of time in the future.
Types of forecasting c;w
(3) To make proper arrangement for training the personnel in its own industry or
sending them in other industries in the country or aboard to meet the future need
of skill and expertise~ " , 'tL,',,:::
Forecasting Techniques
(1) Historical estimate ., ", .{
'~
(3) Statistical analysis • f I
Table 1 ;,(-:i i
Sd = ~( di - del / (n - f)
where
n = number of observations
f = degree of freedom
,
To minimize Sd, we should minimize the factor A, 'f) Y', ,
)
(d) Forecaster - The curve which is assumed to represent the demand and from which
the forecasting will be done for the future periods, is known as a forecaster.
Types of forecaster:
(i) Constant forecaster
(ii) Linear forecaster
(iii) Quadratic forecaster
•
(iv) Cyclic forecaster
+ Correspondence Coursd + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 52
I ME I Correspondence Course
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. ' 53
. 3~.- ':~
~Ij·~
~~~!~rfn~s~!~
, , , ' • • •0
, . ,~ :,.' "..:.;
.,'
Level - 1
1. The most commonly used criteria for measuring fore cast error is
:::fJb
(A) mean, absolute deviation (B) mean
I
standard error
(C) mean absolute percentage error (D) mean square error
(A) ABC analysis (B) Gantt chart (C) EOQ mudel (D)CPMjPERT
6. Given
T = underlying trend
C
S
= cyclic variations
= seasonal
,
within the trend
variation within the trend
R = residual, remaining or random variation as per time series analysis of sales '
forecasting, the demand will be a function of
(A) T & C (B) R & S (C) T, C & S (D)T, C, S & R
+ Correspondence CourSe + TarGATE + ICP-Intensive Classroom Program + eTIltnr + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . .' ' . 54
. ' '. ,~""~''flI<~.:'':!t
I ME I Correspondence CQtft;~e5
(C) Despatch of finished product to the user(Oy dispatch of work ordersi 'through
shop floor
13. Men, material and machine are the important resources of production . The
combination of these that can't have a flow process chart for them is
(A) Material and machine (B) Men and machine
(C) Material, men (D) None of these
+ Correspondence Course +TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by G;;.tefonJ~' Educational Services Pvt. Ltd. No part of this booklet may be reproduced o(utilized in any form
without the writter permission ss
1r.:19n~!~rfnPs~Jl!
~ . .
••• ' I I •• ' . " ."
14. The production unit requiring all the functions of the production, planning and
control is "
(A) job shop unit (8) mass production unit
(C) flow production unit (D) batch production unit
15. The departmentco'nc€rned with Jigs and fixtures ne@tve8 and cutting and process
parameters i.n a production concern are/is ~f!
(A) production, planning and control ' " (8) ind'ustrial engineering
(C) maintenance :.'. , " (D) production
18. In material resource planning, the question of "What and When to produce" is
addressed by the
(A) Master production schedule (8) Planned order release
(C) Inventory status file (D) Bill of materials J
Scheduling is
(A) time phase of loading (B) cost phase of loading
(C) Both (A) and (B) (D) None of thes~
+ Correspondence Cours~ + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 57
----- - -------------- .....
~·';iJ ~l'-~n' . '. Level-2
~. f~, 1r; ,' j ,~. ,. _,i', . I ; I
A M J J A S··(P. 0 N 0
3 ..
560 640 510 710 800 820 ,, 909 860 950
I~~,U-1 Eb r ~W~) demand" in the month of Jan 1994 is 857 nos. then the forecast for
the month of Feb 1994 is
(A) 865 (8) 873 (C) 890 (0)910
,> . '/
2. Last 10 months sales of a product of A8C Company are
Month J F M A M J J A S 0
Sales 350 640 420 480 510 450 638 720 805 750
',' ,,' ,
3. Historical data on the sale of tractors of company for the year 1987 t.0 1993 is
given below i
year sales
1987 3286
r <
)
1988 4751
1989 5867
1990 4580
1991 5020'
1992 8444
., '
1993 11072"
"i,1
Extrapolate the trend for the year 1994 ignoring the effect of seasonal and
random fluctuation
(A) 10417 • (8) 11142 (C) 9316 (0)10818
- "., Corie~pondence CQu~e + :TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Series
@Ajj'rigfiisieseiVedb:Y GateiprumEduc~iionar:Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
withol,lt the written permission . 58
,1
a) 1 Set up time
~
b) 2 Date of updating ~f the chart
~ .' , "
,,, , ,, ,
c)
~ ~
3 Time when work started
5
10. A job shop incurs at a cost of Rs. 60/ - per day for each day a job is in the shop.
At the beginning of a month there are five jobs in the shop with the following
data
Job 1 2 3 4 5
Processing time 5 3 8 2 6
(day)
due date
(days)
10 12 20 9 8
(
then the minimum total cost is
(A) 2830 (8) 3420 (C) 3890 (0)4360
11. A Gantt plan with an 80% guarantee is used on a job that is 30% process
controlled. The plan uses a standard hourly rate of Rs. 20 and a bonus rate of Rs.
25 per hour. The standard time for the job is 0.1 hr/piece. Then the earnings for
a worker per day (8 hours) of work, if 85 pieces were produced on a given day is
guaranteed
wages
~~--------------~
>-
co
U
'-
(])
0-
i'" ( )!
(])
0.5
12. In a time series forecasting model, the demand for five time periods was
10,13,15,18 & 22. A linear regression fit resulted in an equation F = 6.9 + 2.9t
where F is the forecast for period t. The sum of absolute deviations for the five
data is {\
(A) 2.2 (8) 2 (C) -1.2 (D) 24.3
13. Scheduling is
(A) Cost phase of loading (8) Time phase of loading
(C) Cost and Time phase of loading (D) None of these
... Correspondence Course'" TarGATE ... ICP- futensive Classroom Program'" eTutor'" Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. ' 60
'" .- .~.'~ -', '9: ~e."~.~,~~" '; "'i;~
I ME I Corre~poriden:c~~'~'t~~e
,:. "
(A) A I (B) A I
B C :J B L :J
c I----
C r-- c C =:J (
-
D - D b
I---- I---
E I---- P E t---- b
0 4 8 12 16 20 24 28 32 o 4 8 12 16 20 24 28 32
(C) A (D) A
';J \! 1-, 2 B .1'011 t B cb
I J ...... .. " l
C L: . c c :J
D D L
E E - b
-
0 4 8 12 16 20 24 28 32 o 4 8 12 16 20 24 28 32
+ Correspondence Course + tarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series ,
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 61
I ME I Correspondence Course
17. A firm finds that a relationship exists between the rupees sales of one of its
product group and a given economic indicator specially a comparison between
past sales and the corresponding values of the indicator reveals the following
period sales economic index
-- (Rs,lO,OOO)
1 2.1 104
2 1.9 101
3 2.3 106
4 1.5 99
5 1.2 95
6 2.7 109
7 3.6 120
8 1.4 98
9 0.9 90
;,
10 2.0 103
If the value of the index for a further period is expected to be 111. Then the
sales can be expected during that period is
(A) 1.06 (B) 2.87 (C) 3.2 (D) 3.9
18. The product structure of product P is shown in figure. The assembly of 2 units of
Band 3 units of C t~ produce 1 unit of A takes 1 week. The ordering lead t imes
for B, C & Dare 2, 1 & 2 weeks
The master schedule for product P is as follows
weeks: 6 7 8
demand: 20 10 50
-+ Correspondence C6urse -+TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 62
I ME I Correspondence Course
The net requirements of item C if the initial inveiltory of A, B, C & D is 10, 20, 15
& 50 is
(A) 265
(B) 195 1
A
~3
(C) 216
4
~ ~
D
CD) 183
19. There are two machines Ml & M2 which process jobs A, B, C, D, E & F. The
processing sequence of these jobs is Ml followed by M2 • Consider the following
data in this regard .
Process time required in minutes
Jobs A B C D E F
Ml 4 7 3 12 11 9
M2 11 7 10 8 10 13
The processing sequence of jobs that would minimize the make span is
CA) C - A - F - E - D - B (B) C - A - B - D - E - F
(C) C-A-D-B-F-E CD) E-F-D-B-A-C
20. Consider the ·following sets of tasks to complete the assembly of an engineering
component
task time precedence
(in seconds)
A 10 -
B 20 -
C 15 A
D 5 B
E 30 C
F 15 E
G 5 . D
The expected production rate is 3000 units per shift of 8 hour duration. The
minimum number of work stations that are needed to achieve, this production
level is
(A) 4 (B) 8 (C) 10 (D)ll
23. In exponential smoothing method of forecasting, the weightage : given for most
recent data and the older periods are respectively .",
.. . I .
(A) More, dec~ease exponentially (8) Lesser; decrease exponentially
" . . ' !f I ,.
(C) More, increase exponentially (D) Less~er;' increase exponentially
27. The demand for a branded tooth paste in Hyderabad in the .month of Ju/y,'05 is
200 units. The forecast for the same in the month is 120 units. If the smoothing
constant is 0.25 then the forecasted number of tooth pastes for August, 2005 is
(A) 20 (8) 140 (C) 240 (D) 80
28. The demand for particular product of a company for the months August,
September, October, November and December 2005 are on hand. In applying
exponential smoothing method for arriving at the demand in the first month of
the New Year 2004, he weightage will be maximum for the month of
(A) August 2005 (8) September 2005
(C) November 2005 . (D) December 2005
29. In a study to estimate the idle time of a machine, out of 100 random
observations, the machine was found idle on 40 observations. The total random
observations required for 95% confidence level and ± 5% accuracy are.
(A) 384 (8) 600 (C) 2400 (D) 9600
+ Correspondence Course + TarGATE -+ ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
64
without the written perrniSl!ion.
GATEFORUM
Engineering Success
• •••• J •••••• • •• I ME I Corr-espondence Course
31. Match List I with List II and select the correct answer:
list I (Topic) list II (Method of solving)
.... ..:.'
(f\) forecasting (1) North-West corner method
<
32. There are two machines M1 and M2 which process jobs AI BI C I DI E and F. The
processing sequenre -·f..o::-r these jobs is M1 fo llowed by M2 . Consider the following
data in this regard
Process time required in minutes
Jobs A B C D E F
M1 4 7 3 12 11 9
M2 11 7 10 8 10 13
The processing sequence of jobs that would minimize the make 'span is:
(A) C-A-F-E-D-B (B) C-A-B-D-E-F (C) C-A-D-B-F-E (D)E-F-D-B-A-C
+ Correspondence CourSe -+- TarGATE -+- ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 65
~~~!~!9~~!!e~'
~ •••• 'I.' •• ' • • " l ~ ,
,- i.c c..
~ .- ~"
Answer Keys . i. "', , ,-
- '.
Level-1 , ~~,
,
'{
, .
1 D 2 B 3 C 4 B 5 ~ ~13 :" , 6 \" C 7 D
8 D 9 C 10 D 11 B 12 ~\B 13 A\ 14 A
,\..t
'."
15 B 16 A 17 B 18 A 19 'A 20 6 21 B
u ,',.
22 A 23 D
Level-2
1 C 2 B 3 A 4 B 5 .i B 6 C ,7 A
8 C 9 C 10 B 11 B 12 --~ - 13 B 14 C
15 B 16 D 17 B 18 B 19 C 20 D 21 C
22 D 23 A 24 C 25 D 26 C 27 B 28 A
29 A 30 D 31 C 32 B
Explanations:-
Level - 1
3. New forecast = old forecast + a (actual - old forecast) = 78 + 0.2{73 -' 78) = 77
Level - 2
Forecast for the month of February 1994 = average of three immediate months
preceding the month of February
= 2719+857-906 =890
3
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Qnline, Test S~rj.M,.._~_
© All rights reserved by Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form ' " ';iJ,1 J "
without the written permission, 6'6
Weighted
2. Month Sa les Weight sales
Oct 750 0.500 375
_ Sep 805 0.25Q__2DL_. ___ ,_..
Aug 720 0.125 C.9 0
i ______ --' J
-',-' - _.... 1 ._ _ . _ •
. at L '.'
. '- ..- '- --'--1 _ .. ...
,t.".
{.~.-,- Apr 480 0.008 .4
Mar 420 0.004 3
Feb 640 0.002. d 1 L. 2 L d .,<
3. J i o I 2f
deviation of
year (sales) year from 1990 X2 xy
(y) (x)
1987 3286 -3 9 -9858
88 4751 -2 4 -9502
89 5867 -1 1 - 5869
90 4580 0 0 0
91 5020 +1 1 +5020
92 8494 +2 4 +16888
93 11070 +3 9 +33216
n = 1 LY = 43,020 LX = 0 LX2 = 28 LXY = 29,893
a = LY = 6145.7
n
b = LXY = 1067.8
LX2
:. equation of line of best fit is y=6145.7+1067.8x
By putting x=-3,-2,-l,O,l,2,3
trend
year X
values
1987 - 3 2942
88 - 2 4010
89 -1 5078
90 0
91 1
6146
7214
,
92 2 8281 '..
93 3 9349
from above equation the projection of forecast for the year 1994 will be 10417
X = 4 )
tractors (
,Y = 6145.7 + 1067.8 x 4
• Correspondence Course' . TarGATE • ICP-Intensive Classroom Program. eTutor • Online Test Series
©Ali rights reserved by Gateforum Educational; Services Pvt.Ud. No part of this booklet may be reproduced or utilized in any form
without the written permission. 67
. ,1
miJ2~!~rfn~s~~!
~ ,~ ~
\- ~'A ~
... . . . . . . . . . . . 1: • • I ME I Correspqndence C,o..: .~e
4. population demand X2
XV
(x) (y)
15 65 225 975
'~~t.."'''.. 1
22 80 484 1760 .~ ~.. f i :... I;
25 96 625 2400
36 130 1296 46~O
42 185 1764 7770
LX = 140 LY = 556 LX2 = 4394 LXV = 17585 .
\.tj, r'"'~
9. year x y X2 xy
1970 10 11 100 110
71 11 13 121 143
72 14
• 15 196 210
73 15 16 225 240
74 20 18 400 360
n = 5 LX = 70 LY = 73 Lx2 = 1042 LXY = 1063
LY = n.a + bLx
LXY == aLx + bLx2
by solving above a = 5.36
.. b = 0.66
trend equation y = 5.36+0.66x (1)
1
The x & y in equation (1) are 10 of actual (x,y)
:. Y = 53.6 + 0.66x
... Correspondence Course '" TarGATE ... ICP- Intensive Classroom Program ... eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 68
~!~!~rfn~s~~!!
''''Jj'
10. Jobs are to be arranged in the ascending order of their processing time.
(4) ~ (2) ~ (1) ~ (5) ~ (3)
Job Processing ready for due completed
no. time despatch date or not
4 2 2 9 Y
2 3 -5'~ 12 Y
1 5 10 10 Y
5 6 16 8 N
3 8 24 20 N
f' ~
57
'>'-' C'=vJ12!=;r i "
Minimum cost: average cost/day per job
Total number of days spent = 57
= 60/- l
Minimum cost = 57 x 60 = 3420/-
12. t f deviation •
1 9.8 0.2
2 12.7 0.3
3 15.6 0.6
4 18.5 0.5
5 21.4 0.6
2.3
-+ Correspondence Course -+ TarGATE -+ ICP- mtensive Classroom Program -+ eTutor -+ Online Test Series
© All rigjlts reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 69
mGATEFORUM
t::ngineerlng Success
. • 11: " II ,I • •• • • 1: " 'I. a ..
Economic
17. Period Sales (S) SI 12
10,000 index (I)
1 2.1 104 218.4 10816
2 1.9 101 191.9 10201
3 2.3 105 243.8 11236
4 1.5 94 148.5 9801
5 1.2 95 114.0 9025
6 2.7 109 294.3 11881
7 3.6 120 432.0 14400
8 1.4 98 137 .2 9604
9 0 .9 90 081.0 8100
10 2.0 103 206.0 10609
19.6 1025 2067. 1 105673
Linear forecast of the firm S = a + b1
IS=na+bLI • '1,
ISI=aLI+bLI2
Solve the above b=0 .0951 a = -7.78
S = -7.78+0.09511
Economic index is 112
S = 2.87
29. Accuracy =a p
= ~,p = %
fli- idle, q = 100- p
+ Correspondence Course -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Online Test Series
© All rig hts .reserved by Gateforum Educational Services Pvt. Ltd. No pa rt of this booklet may be reproduced or utilized in any form
without the written permission . 70
I ME I Correspondence Course'
, ':
J _
..c
CD
E
CD
en
as Topics Covered
I:
ca • Deterministic and Probabilistic Models
:IE
.....
~
0
• Safety Stock Inventory Control Systems
c
=
-
c
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 71
._. __ .._.. ,
_-- ------------------
~!~!~rfnPs~!!!
IIU.!:J •••••
I
.• • • • • • 1; • • I ME I Correspondence Course
INVENTORY CONTROL
+ Correspondence Course +' TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. • 73
Mi~h "
I ME I Corresp.a h.rumce Coil
Ye = Total yearly cos t = Material cos t + Inventory carrying cos t + procurement/ ordering cos t
= Cx D+ i ,C e + ~ .D '\
Q= ~2DCo
Cc
... Correspondence Course'" TarGATE'" ICP-Intensive Classroom Program ... eTutor -+ Online Test Sene,s ".
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be repr'oduced or utilized in any form
without the written permission. 74
Model-II:- When supply is instanteous, consumption is continuous and there is reserv.;e-
stock.
For this model, the pattern of inventory is shown
''31 f .
I
Quantity
R - reserve stock
Material cos t = CD
C
set up cos t = ~. x D
Model-III:- Economic lot size when there is shortage and zero lead time.
For this model, the pattern of invefltory is shown.
Ir-_ _ _ _ _....;.;.
I.r;..;. "1. 0
. f ..i,;;;;....
= (:;. ~ _______ _
Quantity
I
q Q
Time---+
Let Cs = Fine or penality on per unit short or shortage cost per unit time .
. - . ' Correspondence Course + TiirGATE + ICP-futensive Classroom Program + eTutor + Online Test Series
,·.... T , '~ -.;; ~, . •'._ .... , _¥ .' ' • , _r '" _, '. . .' ,,' , '. • • , , , • . • .
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
wit~8 ut the written permission". 75
lilil;~~~r~~~~~ I ME I Correspondence Course
Q = Maximum Inventory
N = number of orders placed annually
D
Q
cycle time = tl + t2
Total yearly cost, yc = Material + set up cost + Inventory
cost
carrying cost + shortage cost
_ Co q Q- q
-D,C+(f.D + Ce 2"t1 .n + -2-Cst2n
to get optimum Q, ~~ = 0
. Ce Cs
Model - IV:- Economic batch size, when supply is continuous (not instantaneous)
consumption is continuous, no shortage and no buffer stock. The inventory pattern is
shown below.
t
Quantity
Time~
Let r = rate of sup ply
P = rateof consumption and r > P
Total yearly cost'Ye = Material cost+ setup cost+ Inventory carrying cost
Ye = D.C + ~ D + ~ ( i-/{) Ce
dYe = 0 '
dQ
Q= 2DCo
Ce (1- j{)
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 76
I ME I Correspondence Co 1"Se
Inventory Models with Probabilistic Demand:- the models discussed above are on ly
artificial since in practical situations, demand is hardly known precisely. In most of the
situations, demand is probabilistics since only probability distribution of future dema nd,
rather than the exact value of demand it self, is known. The probability distribution of
future demand is usually determined from the data collected from past experience. In
such situations, such po licies are chosen which minimize the expected cost rather than
total cost. .
A.B.C. Analysis:-
As a manufacturing concern increases its activities, it is required to purchase more and
more items and the responsibility of taking care of each items also increases. It also
becomes difficult to pay equal attention to all the items thus purchased. In case all the
items are purchased at a time and that too in bulk quantities which can not be put to
immediate use, their controlling will involve lot of money and manual operation. ABC
analysis is a fundamental management principle used for inventory management. In this
analYSiS, the inventories are categorized according to their annual usage in terms of
rupees.
As the name suggests, the inventories are categorized into three groups A, Band C.
A. High valued items, contribute about, 70% or so of tota l inventory cost. These
items need careful and close inventory control. They should be though of an
advance and purchased will in item. Proper handling and storage should be given
to them
B. Medium valued items, contribute about 20% or so of total inventory cost.
These items need moderate control. They need less care when compared to A-
item. But some of the B-Items are :v..er,y" cr;itical.
C. Low valued items, amounting about 10% of the total inventory cost. Items do not
need any control. They are least important and low valued .
•
Figure below shows a graph between the percentage of total annual usage cost for the
respective category
100
SO
70 ,
0/0 of inventory
cost
A B c
+ Correspondence Course ~ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series .
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. ' 77
, ,
[ilGATEFORUM
Engineering Success
• • • 111 . . . . . . . .. . . I ME I Correspondence Course
Sales
(
incom
~reak
/'
Cost and
t Total
cost
varia~ dS'st
/',
/'
income
/' /' Fixed cost
Ql Q2
Units--+-
The total cost are given by the sum of fixed and variable cost and the point of
intersection of this line with that of sales income is break even point corresponding to a
sales volume Ql' Activity below Ql results in loss whereas activity above Ql gives profit.
At the pOint of intersection,
F
Q1 = B-A
where F = Fixed cos t
A = Constant total cos t per unit
B = Income per unit
If a plant is operating at a point Q21 it is working with a margin of safety (~) which is
defined as
~ = Q2 - Q 1 = Q2 _ 1 t -
Q1 Q1
Q2 = Qd 1 + ~) = Q1 ( 1 + ~ J
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTlltor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 78
~2~!~fn~s~~~
~." •• 1 •• '." -1I" I ME I Correspond ence Course
Level - 1
2. For a given level of safety stock and EOQ ordering, the re-order point
(A) Is dependent on rate of consumption
(B) Is independent of rate of consumption
(C) Only depends on lead time
(D) Depends on lead time and rate of consumption
-+ Correspondence Course -+ TarGATE -+ ICP-Intensive Classroom Program -+ eTlltor -+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvl. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. · 79
t. Jll~ ~"
+ Correspondence Course +'TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd , No part. of this booklet may be reproduced or utilized in any form
without the written permission , ' 80
·.41f~
I ME I Correspondence Cours.e . 1.
17 . Analysis depends upon the value of inventory passed by the firm, rather than
what has been consumed is
(A) XYZ classification (8) VEO classification
(C) HML classification (D) FSM classification / '
19. The system in which the second bin contains the number of units equal to re-
order pOint is
(A) two bin system (8) Q system (C) P-S system (D) S-A system
20. In the S-S optional replacement system, the decision not to place the order is
taken when the stock level during the review time is
(A) above the level of S (8) below t he level of S
(C) at the level of S (D) none of these
22. As for the inventory control, the cost of items useful in availing the price
discounts is
(A) production cost (8) capital cost
(C) shortage cost (D) replenishment cost
23. What will be the economic or der quantity for a product if yearly requirement is
4000 units, ordering cost is Rs.225 carrying cost is Rs.2 per unit per year and
25% of ordered quantity is always maintained as reserve 'stock?
(A) 711.51 (8) 774.6 (C) 1018.25 (D) 1341.6
24. The annual demand, ordering cost and holding cost for a component are 2000
units, Rs.10 per order and Rs.2.4 per unit per year respectively. How much
quantity should be ordered al\d at what point in order to minimize total cost.
Assume lead time as 5 days.
(A) An order of 31 when inventory position drops to 2
(8) An order of 31 when inventory position drops to 27
(C) An order of 129 when inventory position drops to 2
(D) An order of 129 when inventory position drops to 27
+ Correspondence Course + TarG'ATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 81
GATEFORUM
.•.........•..J"
Engineering Succe&S.
._-----..J.:-
":}~1 .U<'f
_--. --.
'1.' ..'-,
- . ,-~--
.~ .'
.-._'."
'l' Fi j.) Ii
25. Following table shows the forecast value and actual demand for a component
over 2 months. . .t,'':;},,'
What will be the forecast value for t!J~hI;)1RnJh of August if smoothing constant is
0.047 ' '
·... :·,1· · ,
(A) 992.16 (B) 993.96 (C) 1192.125 (0)994
26 . For a manufacturing industry the average inventory and annual consumption are
500 and 25000 respectively. The inventory turri-over ratio wiil be "~',' ,
• - : \ ~ A "
27. A company uses 2400 units of a raw material which costs Rs.12.50 per unit.
Placing each order costs Rs .22.50 an d the carrying cost is 5.4%, pe.,.r year of the.\.
average inventory . Find the economic order quantity.
(A) 1265 (B) 223 (C) 126.5 (D) 822.3 ·
'. ,
i , j
".... Correspondence.Course .- +TarGATE -+ ICP-Intensive Classroom Program -+ eTutor -+ Onlin.e Test Series
@"AjJright!He!il~ri.edby Gateforuni..Educati6nal Services PVt. ,Ltd. No part of this booklet may be reproduced or 'utilized 'irnrny'forin'" "'.
without the written permission. . . . . . $2
I''';''
Level - 2
'om
Common Data Questions: 1, 2 ,&. 3
, -.~-
From the following infdrmation
.";.' G' ;:15)', ' . " ', 3d I~iw :tori\'!
Maximum consumption = 200 unit/day
,;$\0 ,\
Minimum consumption = 120 unit/day
" ,, ;:.? (A.
Normal consumption = 160 unit/day
Re-order period = 10 - 15 days
Re-order quantity = 1,600 units .. , . ~ .'
. ,
(A) 3000 units (8) 3200 units (C) 2400 units (D) 2000 units
• Correspondence Course. TarGATE • ICP-Intensive Classroom Program . ' eTu't6t' 'tt)n1irte"r~$t~¢fi¢~" ''' ' ': ' '
@AII rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any'form'" " , ~. ,' ,.K,"',
withoufthe written permission. 83
rijGATEFORUM
Engineering SL.JCCe&S
•• • ••• • • .1 • • • 5 • • I ME I Correspond¢oce Cou~.ii: :
Factory requires 1500 units of an item per month, each costing Rs. 27, cost per
order is Rs . 150 and the inventory carrying charges work out to be 20% of unit
cost per year.
15. An enterprise consumes 48000 units per year of material costing Rs. 1.20 per
unit. Procurement cost for each order is Rs. 45 and the carrying cost is 15% per
year of unit cost. Determine the EOQ
(A) 4899 (6) 5000 (C) 5100 (0)5129
,
16. The monthly demand is Rs . 2000 of sales. Annual carrying cost is Rs. 2400. The
ordering cost per order is Rs. 600. EOQ is
(A) one month of sales (B) two month of sales
(C) three month of sales (D) four month of sales
+ Correspondence Course + TirrGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 84
I ME I Correspondence Course
17. If annual carrying cost is Rs. 2 per annum per unit and annual procuring cost is
Rs. 500, what would I?e the EOQ?
(A) 400 units ,fl!J S) 500 units (C) 600 units ., (D) none
18. If the lead time consumption is .30.0 un its, EOQ is 500 . units and safety stock is
450 units, calculate the re-order level
(A) 800 units (B) 950 un its (C) 1250 units (0)750 units
24. The penalty cost is four times that of carrying cost for an item, and the demand
rate is constant, if shortage is permitted, the service level that could be
maintained at EOQ ordering is
(A) 0.75 (B) 0.80 (C) 1.25 (D) 1.33
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational SeNices Pvt. ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 85
~--'- -------------------""'-!!!!!II
i~k_~
1 'i~"
J'i1
'- "'''- .;
~ • _13 ~ ,.~
I ME I Correspondence C0ui<se'
25. An industry has a capacity of manufacturing 60000 units a year. The demand in
the market is of 3000 units only. It is independent on the supply of input
materials and on supply from sister units. The supply of input materials is
restricted to 300 units per day. The average producbbn rate is 200 units per day.
If the cost of unit material is Rs. 50, inventory carrying rate is 20% of unit cost
and the preparation or-set up cost is 5000, calculate economic lot size.
(A) 6000 units (B)- 7-864 u-nits (C) 8864 units (D)9487 units
,
, l - ~
; '-\_H?:'I lP
/
28. Maximum inventory level will be
(A) 219 units (B) 127 units (C) 100 units (D) 173 units
31. The demand and production rate of a particular product is 20/day and SO/day
respectively for a working year of 300 days. The inventory carrying lost is Rs.20/-
If the setup cost is Rs.7500/- the economic manufacturing quantity of the
product is
(A) 3600 units (B) 3000 units (C) 4200 units (D) 4000 units
+ Correspondence Course\+ TarGATE + ICP-Intensive Classroom Program + eTutor .. Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission, . .' 86
"
I ME I Correspondence Course
,, C1 C2 __,Jf..':
"
A 9 4 ,
, ,
B 3 5
C 8 12
0 2 7
E 10 6
In the best possible sequence, the job that will be processed in the middle is
(A) D ' (B) C (C) B (D)A
33. Thet
number of items on hand at the end of first week of manufacturing concern'
is 60. The ' receipts during the second week are 120. If the number of items on
hand at the second week is 150, the projected requirements are
(A)' 210 ' !. (B) 30 (C) 90 (D) 60
34. The sales of a consumer good company are like this. January,'03 - 300,
Fei?,r,\.I9,ry','03 - 3 5,0,. March,'03 - 375. The forecasted demand for January is 320
units. The forecasted demand for April,'03, if the exponential smoothening
constant is 0.32 is
(A) 314 (B) 325 (C) 352 (0)341
36. Econometric forecasting establishes a cause and effect relationship between two
variables for forecasting. It utilizes
(A) Both regression analysis and correlation analysis
(B) Only regression analysis technique
(C) Only correlation analysis technique
(D) Neither of these regr~ssion nor correlation analysis
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved 0)' Oateloru•.1 Ed ucational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
. without the writle:-. I: ermir.sion. 87
\: fr~ ;c\ ;.,":. ~
I ME I Correspondence Co!itr e
- -
39. Th-e demands of the market for leaf sprirrgs of a particular company are 9, 00,000
per annum. Another' client ; company purchases these and sells them. Cost of
making purchase order is Rs.1500/-. The cost of storage of leaf springs is
Rs.150/- per spring/annum. The economic order quantity is
(A) 4343 (B) 4242 (C) 4545 (D) 4646
40. The B-class items in ABC analysis constitute X of total items and Y of money
spent on them. The X and Yare
(A) 10 - 15% and 15 - 25% (B) 5 -10% and 70 - 7'5%
(C) 10 - 15% and 10 - 15% (D) 70 - 80% and 5 - 10%
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Education'aI 'ServicespVt. t..id_ No part of this booklet may be reproduced or utilized in any form
without the written permission. 88
<;~ ~ff
I ME I Correspondence Counse
Level - 3
(A) (B)
Quantity Quantity
Time~
(C) (D)
. Quantity Quantity
c \ .
Time~
1.....,- ,.,
2. Which of following represent the inventory trend when there is shortage and lead
time is zero? '
(A) (B)
Quantity Quantity
Time ~
(C) (D)
Quantity Quantity
Time~
3.
•
Inventory trend for EOQ when supply is continuous (not instantaneous)
consumption is continuous, no shortage and no buffer stock is
(A) (B)
Quantity Quantity
(C)
~antityktV1VK (D)
Quantity
1ime -4
+ Correspondence Course' + TarGATE + ICP-mtensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 89
Common Data Questions: 4, 5 & 6
.~ .
, __ .. ",,' A's job shqp- buy, two parts (X and Y) for use in its--production system from' two
,.,t di.fferent suppller$. The parts are needed throughoutl:the entire 52' week year. :Xs
~r:e U$~.9 ar a tel~tiv~ry' constant rate and are ord 1r~d whenever the remainjng
.q·daqtit~ __dr.ops·to. the' reorder level. Ys are ordered from a supplier who stops by .
5v..-e 1 _~~e~ _w:~:eks... ~~!a fQ~t~oth ;~roducts are as follows.
Item .: ; ',::',: ";X oS;;
..l , Y
'''Annual Demand 10,000 5,000
Helding cost (% of item cost) 20% 20%
.Set up or order cost Rs. 150 Rs.25 \
Leadtime.. 4 weeks 1 week \
Safety stock " 55 units 5 units
mam cost ': .,.. ,. Rs. 10.00 Rs.2.00 ~',~
.>" ..
What is re-order quantity for X?
• f:' A i 'tE t-
(A) 824 .. ~. (8) 1225 (C) 2049 (D) none of these
.'-_:::"......J__...!~ L__ ~
r
5. Re-order point for X is
(A), 824 (8) 1225 (C) 2049
7. A firm produces and consumes 3200 tools made of stainless steel annually. The
cost of setting up for production is Rs.750 and the monthly production rate of
tool is 550 units. The production cost is Rs.15 per item. The annual storage and
carrying is 20% of unit cost. The time taken for optimum production run is:
(A) 98 days (8) 298 days (C) 198 days (D) 322 days
.... Corr~spondence Course. TarGATE • ICP-Intensive Classroom Program .. eTutor .. Online Test Series
OoAJIr.i9Atsreserved'by:-Gateforum EducationatServices Pvt, Ltd, No part of this booklet may be reproduced or utilized in anY form
without the written permiSSion, ' . . 90
_ATEF.O"R.llM."y, ,,','j \ ::>." '
.:
...... , ........ .
Engmeermg ~~~': . _ ,_ . . .
,\ .
Answer Keys
Level- l _. d f"f r i' )' ~
;
1 " , ,
B: ,,' 2,-- C
,
'8 B ', -Ij~~f
. B
15 A 16 D c
22 A 23 B 24 D 25 BX 26 A 27
Level - 2 ' , , c,,_'
- " ','
1 A 2 C 3 B 4 C 5 C 6 , ' D -- ,
',1,' B
8 A 9 A 10 D 11, C 12 D 13 B ,14 B
15 A 16 C 17 B .. ' " 18 , D 19 C 20 ': '-8 , 21 C
22 D 23 C 24 'B 25 D 26 A 21 A '2 8 " D
29 C 30 B 31 B 32 B 33 B 34 D 35 D
"
36 A 37 A 38 A 39 B 40 C 41 C 42 0
43 A 44 C 45 B
Level - 3
ci 4 B 51 A 6 B' !7
Explanations:-
Level - 1
1. Carrying cost depends on the lot size., lower the lot size lower the
, . ," "
ca~rYi' ngtost.
Lot size Q = ' demand
order placed
, :. Incr;ease in order placed, will re.d,ucethe lot :size .and hence the carrying cost.
2. Re-order point
, .
= safety 'stock +: lead'tiil1e x rate of consumption
,
". . " , . I f d i d No. f d' . demand
3. O r d enng cost IS proportlona to ,no. 0 or er pace, 0 or er= , ' " " .
, oroer quanttty Q
Increase in ordered qualltity will decrease the no. of ordered placed in unit time
and thus reduce the ordering cost.
. . ~2X2000X10
24. Economic order quantity = = 129.09
2.4
. 2000
Re-order pOint =- -x 5 = 27.39
365
-+"Correspondence Course '+ TarGATE -+ ICP-Intensive Classroom Prograuv. • ...eTritol' .• Online Test JSerie8 ''':'~'
© All rights reserved by Gateforum Educational Services Pvt, Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 91
. ;
I ME I Correspondence Co-u.rse
25. For August = 998 + 0.04(900 - 998) + 0.04(1 - 0.04) (950 - 1000) = 992.16.
26. Inventory turn-over ratio = Annual consumption = 25000 = 50
Average inventory 500
Level - 2
1. Re-ordering level = maximum consumption x maximum ordering time
= 200x15=3000units
2. Maximum
, stock level
= Re-ordering level + re-ordering quantity - minimum consumption x minimum
re-order period = 3000 + 1600 - 120 x 10 = 2400 units
3. Minimum stock level
= Re-order level - normal consumption x normal re-order period
= 3000 -160 x 10 = 1400 units
4. EOQ = ~2~~, Here demand D = 20 units per year,procureme~t ~~s~ = 40/- per day
Holding cost He = 0.16x 100 = Rs. 16 per unit per year :. EOQ = 2 x 20 x 40 = 10 units
\ . 16
5. Holding cost He
= interest cost + deterioration cost + storage cost
6. Procurement cost
= Ordering cost + handling cost + inspection cost = 3 + 12 = 15/- per order
7. EOQ = ~2PD
He'
D = 50000
,
2 x 50000 x 15 =
/----------- 4226 unl'ts
0.084
. Demand per year 50000
8. No. of order In a year = - - = 11.83 C::' 12 orders per year
no. of units per order(EOQ) 4226
. 491400
14 . Average cost per unit ~ 18000 = Rs. 27.30
... Correspondence Com'se ... TarGATE ... ICP-Intensive Classroom Program ... eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. ' 92
. ," .. - ~ ,,~'l. ·f~~ ..~t~~:
I ME I Corresponden"ce. ¢~'6:,t~e
, -
EOQ = '~2PD =
~
C = Rs. 40, H = 40% of C, C1 = 10, EOQ = /2 x 800 x 800 ~16 + 10 = 456 units
V 16 10
20.
C1 10
Qm = Q CH + C = 456 16 + 10 = 175.4 = 175
1
21. Maximum 'no. of back order units;; Q - Qm = 456 -175 = 281 units
25. EOQ =
CH 1-
rD)'
%
P = Rs. 5000, D = 30000 units
•
CH = 0.2 x 50 = Rs. 10 per unit per year,p=200 units per day
. 2x5000x30000
5=300 units per daY,EOQ= 0 ( _ 200/ ) =9487 units
1 1 / 300
26. EOQ = ~2PD ~CH+C1 P = 160 CH = 20 C = 10 D = 1000 units, EOQ = 219 units
CH C1 ' \ ' '1'
+ Correspondence Course'+ TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Series ,
© All rights reserved by Gateforum Educational Services Pvt. Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission. 93
.., 0_.
' GAT~-'lRUM
", mil EngineerIng Succe-.ss
i ,
I ME I Correspondence Course
.,11'.,1' . . . . . . . . . . ..
= 1 1.4 101.50/-
. 10 0
i:tli:· ':'" J -.
43. Number of random ob's ervatlons:
N = K2 9 (1 - P) = 6400
(Sp)2
Level - 3
EOQ = ~2CoR ~ K
Cc K-R
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission . 94
.,
GATEFORUM
Engineering Succss& I ME I Correspondence Course
.I:
e
II
CD
en
Topics Covered
.I • Linear Programming
• Queuing Method
-+- Correspondence Course +TarGATE -+- ICP-Intensive Classroom Program -+- eTutor -+- Online Test Series
© All rights reserved by Gateforum Educational Services Pv1. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 9S
...
I ME I Correspondence Course'
OPERATION RESEARCH
Projects are large non-repetitive tasks. They vary hugely both in their subject and in
their size.
Main characteristics of a project'are:
(i) A project is non-routine, non-repetitive undertaking often plagued with
uncertainties
(ii) A project has a particular objective to achieve
(iii) A project has clearly identifiable start and finish
(iv) A project is composed of a large number of inter-related activities. The activities
of the project are physical independent actions which require time for completion
and consume one or more resources.
(v) A project uses a variety of resources and skills
Project that are not properly scheduled generally tend to extend beyond the
contract data and thus cause heavy losses to the contracting firms.
Delays in completion of projects:
(a) Tend to increase investment in work in progress
(b) Delay in invoicing and thereby reduce working capital
(c) Penalize the contracting firm when the completion lags behind the agreed
data since most of the contracts of the projects contain penalty clauses
Cd) Result in unwelcome additions to the fixed manufacturing expense as men
and machines are employed beyond the economic time span
Critical Path Analysis:
Critical path analysis, an impotent aid to planning, scheduling and coordinating the
activities of large scale projects, is a synthesis of two independent techniques.
(1) Programme evaluation and review technique (PERT)
(2) Critical Path Method (CPM)
Though the two techniques were developed independently, they are only superficially
different. The methods have many features in common and are now combined into a
technique, called critical path analysis (CPA) or network analysis .
•
The difference between a PERT network and CPM network are as follow:
PERT CPM
3
4
Complex and difficult to implement
Very good for simulating
, Easy to use and update
Very good for scheduling highly sequential
alternative plan, resource work with parallel and independent chains
allocations
5 Most costly system to maintain Easy to maintain
+ Correspondence Course "" TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvl. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. . 97
\'~~~ <: r
fM'il!~!!r fnPs~~
ILL!:.I ..• .. .•.. •.. •.• I ME I Corresporiq ence
1,;;P'~
COlI,~'
Network Logic: A network is a graphical representation of the project and is composed '
as series of connected arrows and circles to describe the inter- relationship of the
activities involved.,
The network is constructed from the following elements: I
(a) Activity:, -An activity represents ,a task ,which" has a definite beginning and
definite end. An activity is represented 'by' an "arrow" (~). The description of the
activity is written above the arrow and the time consumed is written below the
arrow.
Design
)
For example : 10 days
Activities proceed from left to right. The tail of the arrow represents the s,t a"rt of ,
an activity and head of the arrow represents the completion of the activity.
(b) Events: Events represent start or finish points of activities. They are not time
constrained. They are usually represented by circles and they are numbered.
Since each activity has a definite beginning and definite end, each arrow
representing the activity is bounded by two events.
For example:
Starting Completion
Event Event
A , C
>0
B
Merge
ex D
Burst
D
Combination of merge
Event Event and burst event
Network Interpretation
Activity B can not start until Activity 'A' is completed. 'A'
is therefore, a preceding activity and 'B' is a succeeding
~ activity
.. Correspondence Course" TarGATE .. ICP-Intensive Classroom Program" eTutor .. Online Test 'Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 98 "
~ . "<j ,'.-r' ;~'''~-.~
I ME I Corres;.~npence c<?i£t~
Activity " D' as well' as activity' 'E' can' not start ' uhtil
activity ' C is completed . Hbwever, both activitiesD and E
can be started simultaneously. Acti,ti'ties Dand E,
thereforer are though ' c::oncurrent between themselves
but are succeeding to activity 'C'
A<:;ti'V.ity , PI.,-can ..f1,o.t .;stal;t ur:Jtil activities v F.f ifainGlI 'G' are
"oompletl=!d > ,4. (.c ' C7·'~':' .c, • J ~, 'C~ ":'11I'i 4 .7 •
··.'1.,1
Two activities can not have common start and finish points. They can have either
common start or finish pOints, but not both.
Network construction:
A network is a graphical repres·entation of activities comprising the project. The network
is formed by a series of connected arrows and circles which give technological
relationships to the activities involved.
():!:o B
o::Jo
[Correct]
[Incorrect]
+ Cerrespondence Course'" TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. tid . No part of this booklet may be repr oduced or utilized1 n any form
wittl0ut the written permission . 99
',,", ....,
~' GATEFORUM ' ~ .. r
. Engineering Success
• • • • WI • • • • • • 1I • • I ME I Correspondence Cour'se
[Incorrect Network]
(C) All activities must be tied into the network. Dangling must be avoided.
(D) A network should have one starting event and one completion event
(Incorrect)
(Correct)
(E) A network should employ only those dummy activities which are absolutely
necessary
Node Labeling:
Once the network is drawn, it is good practice to label the events systematically. As a
general rule, the numbering system must ensure that
(i) The event numbers as far as possible reflect logical relationships of the activities.
(ii) For a given activity, the number of its tail event is lower than that of its head
event.
Fulkerson's rule is normally used for node labeling.
I ME I Correspondence Course
Project classification:
Depending upon the nature of the activity times, the projects may be classified into
following two categories.
(1) Projects in which activity times can be estimated with sufficient certainty
(2) Projects in which there is high degree of uncertainty about the activity t imes.
Time estimation of the activiti.es pf the project in the first category is done by
using critical path method while time estimation of the activities in the second
category is done using Programme Evafuation and Review Technique (PERT)
The concept of multiple times (three time estimates) is evolved in PERT to reduce
the incidence of uncertainty in project planning. The three time estimates are
(i) Optimistic time (a): This indicates the minimum time that an activity can take
if everything goes smoothly without any interruptions.
(ii) Pessimistic time (b): This indicates the maximum time an activity can take
under adverse conditions.
(iii) Most likely time (m): This indicates the time an activity can take most often if
it is repeated again and again under the same conditions.
Three time estimates are not directly entered into the network. They are
transformed into an expected time using the relation given below. te = a + 4m + b
6
Critical path: A network consists of chains of activities called paths of network.
Addition of durations of activities on any path gives the duration of that path. It is
this path, with the longest duration, which sets the overall duration of the
project, is called critical path. And the activities on the critical path are known as
critical activities.
Figure below represents the network of a project. The expected time of each
activity has been entered into the network itself.
+ Correspondence Course + TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Selies
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 101
··Yl .
I ME I Correspon21~nce COUr;~ ,~
As the number of activities increases, it becomes very difficult and time consuming to
find the critical path by complete enumeration or inspection. Therefore, for larger
networks, a more systematic procedure is needed to determine the critical path. The
most commonly used method employs two sets of calculations .
(i) Forward pass computation
(ii) Backward pass computation
The forward pass computation begins from start event and moves towards the end event
of the project network. It determines the earliest expected time for each event, called
earliest time (TE). The backward pass computation begins from the end event and
moves backward to the start event of the project network. It determines the latest
allowable time for each event, called latest event time (TL)' The convention used in
recording of the events time is given below
Event Number
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© Allrights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized inanyform
without the written permission. 102
I ME I Correspondence Course
(iii) The earliest event time Te of a merge event equals largest of th e sum of IE of t he
preceding event plus' duration of the activity emanating from the preceding
event. 'J .1 '
Figure shown below -shows the earliest event times of sample network w ith
explanation.
where
TLi = the latest allowable time of event i
TL j = the latest allowable time of event j towards which activity (i/j) is headed
... Correspondence Co~rse ... TarGATE ... ICP-Intensive Classroom Program '" eT;tor ... Online Test Series
© Allrights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 103
I ME I Corresponaence Course
(iii) The latest event time of a burst event equals the smallest of the difference
between the latest event time of the head event less duration of the activity
converging on the head event
i.e. TLi = min(TLij - t ij )
Figure below shows the latest event times of sample network with explanation':
Following the above rules let us calculate latest event time (TL) for the network
(i) Latest event time of = Earliest event time since it is
the event 8 (TLa) the end event (TEa)
(i i) TL7=TL8-t78 = 30 - 2 = 28
(i i i) TL6=TL7-t67 28 - 7 = 21
(iv) TL5=TL7-t57 28 - 7 = 21
(v) TL4=TL6-t46 21-4=17
(vi) TL3 = Min Min(17-2,28-5,21-7)
[TL4 - t34, TL7 - t37, TL5 - t35] Min(15,23,14) = 14
(vii) TL2 = TL3 - t23 14-7 = 7
(viii) TLl = TL2 -t12 7-7=0
(ii) Earliest Finishing Time: This equals the earliest starting time plus duration of
the activity emanating from the tail event
(iii) Latest Finishing Time: This is the latest event time of the head event
i.e. L~j = TL j
(iv) Latest Starting Time: This is the latest finishing time minus activity duration
i.e. L5ij = L~j - t ij
+ Correspondence Course + TarGATE + ICP-:-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 104
I ME I Correspondence Course
Float Analysis:
Float of an activity represents the excess of available time over its duration. Float,
therefore is the leeway available to the project planner for this scheduling activity. It
allows planners to
(i) Decide priorities in allocation of resources
(ii) Transfer resources from less pressing areas to more pressing areas.
(iii) Minimize requirements of a resources
(iv) Prevent peaks and valleys in the requirements of a resource.
Types of floats:
(i) Total float
(ii) Free float
(iii) Independent float
All activities lying on the non-critical paths have total float and some of them may also
have free float
Total float: Total float signifies the maximum delay that can be permitted in the
completion of the activity without affecting the project completion. Total float can be
interpreted in two ways
(i) The maximum time available to delay the commencement of an activity
(ii) The maximum expansion of the duration of the aCtivity
If total float is used up on activity, that activity and subsequent activities in the chain
become critical.
Total float of an activity can be obtained as
Total float = latest occurrence time of the succeeding event - earliest occurrence time of
the preceding event - duration of the activity
= TL j - TEi - t ij
Free float: Free float is the amount of time an activity can be delayed without affecting
the commencement of a succeeding activity as its earliest start time but may affect the
ffoat of previous activity. Free float results when all preceding activities occur at the
earliest event times and all s·ucceeding activities also occur at the earliest event times.
Free float = Earliest occurrence time of the succeeding event - Earliest occurrence time
of the preceding event - duration of the activity
Free float = TEj - TEi - t ij
Independent float: Indepe'ndent float is the amount of time an activity can be delayed
when all proceeding activitie~ are completed as late as possible and all activities are
completed as early as possible. Independent float neither affects the float of preceding
activities not that of the succeeding activities.
Independent float = Earliest occurrence time of the succeeding event - Latest
occurrence time of the preceding event - duration of the activity
= TE j - TLi - t ij
. "+ Correspondence Cou~e + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 105
.
:,~)I ~J'j ~""'. ,-.-~.';
milGATEFORUM
!
! . EngineerIng Success
• • 4' • • I • • • • • • • • •
.1 t
I ME I Correspondence Course·:
Points to remember: ' ' ' ' i ) . ' ' ; ' : 'I
between 'm' and mid range (a; b) away from most likely time.
(iv) Standard deviation (cr) a'nd variance (V) of an activity respectively equal
(v) The expected time (te) of each activity independently a~though has 13-distribution
but their total along the critical path (project duration) has a normal distribution
with mean Tcp and variance Vcp ('
Imagine a project consisting of n independent critical tasks with expected times
of tel' te 2 ,te 3 ".te n. Each of these tasks though is expected to follow 13-distribution
but their total time (project duration), Tcp, if n is large, is expected to follow ,
normal distribution with mean Tcp and variance of critical path Vcp
Tcp == tel + te2" .ten
Vcp == Vl + V2 ".Vn
The conclusion is based on the concept of central limit theorem
Using the above mentioned principles, the probability of completion of the project
can be established as under:
Let tel, te2 ... te n == the expected times of the activity on the critical path
And Vl , V2 " ,Vn = Varianceoftheaboveactivities
Tcp == Expected time of completion of the project
, = tel+te2+te3+".ten
T == Scheduled time of th~ project
·1 .
cr = ~Vl + V2 + ",Vn
Once Tcp and cr have been calculated, then from table of normal curve, the
probability corresponding to standard normal deviate
LINEAR PROGRAMMING
Programming techniques are usually concern with allocation problem in which a variety
of resources must be allocated to a number of users in an optimal manner. In many
programming problems, all the variables and restrictions on the solution which may be
specified can be expressed as equations of first degree. E.g. if the total amount of time
(T) consumed in machine-operation (B hrs), material (say Phrs) and a w.orking hr (S
hrs) must not be greater than 8 hrs, then
8<B+P+S =T
B+P+S+A=8
where A isan additional variable. This types of problem in which all equations are of first
degree is called linear programming.
Linear programming refers to techniques of solving general class of optimization
problems dealing with the interactions of many variables subject to restraining
c~r;Jditions. It is used to maximize and minimize a given objective function which is linear
and is governed by linear constraints. Problems that deal with the minimization or the
maximization of objective functions are called optimization problems .
-
Method for solving linear programming problems:-
(i) Graphical Method
(ii) Simplex Method
. + -Correspondence Course + TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd . No part of this booklet may be reproduced or utilized in any form
w\:\l13~t the written permission . 107
I ME I Correspondence Course
TRANSPORTATION MODELS
The problem is to determine the number of items to be transported from each source to
the various destinations (viz. Xij s) such that:
a. The demand at each destination is fully satisfied
b. The total cost of transportation, r. r. cij Xij is minimum.
The mathematical model would be in the format
Minimise z = ITC;jXij
n
such that: L X;j = Si (i = 1,2, ..... , n)
j=1
n
L Xij = Dj (j = 1,2, ..... ,n)
i=l
Xij ~ 0
The general procedure of Transportation Model consists of the following steps.
Step-l: Determination of the initial feasible solution of allocation
Step-2: Testing it for optimality
Step-2: Development of the next iterative, improved allocation
Step-3: Repeating the iterations until optimality is reached.
Let us consider the methods l!Jsed for the above steps by means of an example .
Example-l
The number of units available at the supply centers A, Band Care 6, 1 and 10. The
demand at the distribution centers E, F, G and Hare 7, 5, 3 and 2units.The
transportation costs per unit from the supply to the demand centers are given in the
follow ing matrix. Determine how many units are to be transported from each supply to
the demand centers, so that thf\ total transportation cost is minimum.
E F G H
A 2 3 11 7
B 2 1 6 1
C 5 8 15 9
+ Correspondence Course'+ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights rese rved by Gatelorum Educational Services Pvt. Ltd. No part 01 this booklet may be reproduced or utilized in any form
without the written permission. 108
I ME I Correspondence Courst! '
r
COST MATRIX
. . +'Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 109
I ME I Correspondence Course
'-------'--1
- 1 : ~--'------':
~: 1,-----,-:1:~~-,------,:
1 : 1 : 1 - 1
Cost Matrix
~ 6 ®
7 5 3 2
1 CD
10 CD 0 G) @
Allocation Matrix
•
The tota I cos t = (2 x 6) + (1 xl) + (5 xl) + (8 x 4) + (15 x 3) + (9 x 2) = 113
+ Correspondence Course"+ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 110
I ME I Correspondence Course
• Determine the new penalty values, based on the un-scored matrix, and
proceed as before, until all the Rim conditions are fully satisfied.
D 7 5 3 2 Penalty
Values
5
"' W 2J
6 2 3 11 7 1
5
-.1J
1 2 1 6 1 o
~ ~ -.1J
10 5 8 15 9 3 4
Penalty o 2 5 6
Values
3 5 4 2
5 15 9
VAM Method:
Tota I cos t = (2 xl) + (3 x 5) + (1 xl) + (5 x 6) + (15 x 3) + (9 xl) = 102
The Xij and Cij values for each cell are shown in the same cell jtself.
The manner, in which the allocations are shown, is casually called as 'stones'. In the
cells where there no allocations, the stones . are not present, such cells are called as
'water'. The cells containing the allocation (i.e. the stones) are the base cells' and the
'water' represents the 'non base cells'.]
Theoretically there is no assurance that anyone method (explained above) used for the
initial iterations would lead to the reduction of successive iterations for reaching
optimality. However, VAM be initial iteration, as it considers both the cost and penalty.
... Correspondence COl{Yse ... TarGATE ... ICP-Intensive Classroom Program'" eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 111
GATEFORUM \ J ~J ~" \~
.'.............. .
Engin,e erlng Success
I ME I Correspondence Course»~
suitable non-allocated cell (or cells), so that the total number of base cells (allocated) is
equal to (m+n-l)
Let us consider the allocations made by using VAM as the -initial iteration. The total
number of base cells =m+n-l=3+4-6. The total number of aflqcated base cells is also 6.
Hence there is non degeneracy.
Step-2:
Optimality Test:
It is minimization problem. The optimality is reached when all Llj values (index values)
are positive. It would have noticed, in the Simplex Tables, that the Llj values under base
variables are always zero and it is sufficient if Ll j values are determined for the non-base
variables (i.e., the non-base cells)
MODI Method:
It is called as Modified Distribution Method (shortened as MODI method). This is used to
determine the Llj values for the non-base cells
Llj indicates the amount of increase in the value of the object function, 'z' per unit of the
item of the non - base variable, if it enters into the base, in the next iteration.
The tota I cos t : z = LL<;jX jj ". (1)
The Ui and vi are arbitrary values given for each row and column, such that the value of
(<;j - U; - Vj) is zero 'in each and every Base Cell (stones). When xii is non-zero, the value
(<;j - uj - vJ is zero; and when xii is zero (i.e., non-base cells), the value (Cjj - U; - vJ can
be non-zero. Thus LL~j (Cjj - U; - vJ would always be zero.
Let us consider a non - base cell i,j, where its xii=O. Suppose we make an unit allocation
in this cell, the new value of the total cost,
z' = LL<;jXjj - LLCjj~j (Cjj - 11 - v j ) + ~ (Cj - 11 - Vj ) ". (3)
(z' - z) indicates, the increase in the total cost per unit increase in the allocation in the
non-base, which represents the in~ex value V jj . Therefore,
The total cost of transportation for the existing allocation can be determined in terms of
'uI 's and 'v's
J
as
.
'follows: •
. + Correspondence Course + TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Series
©AII' ri ghts r~se~ved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in a.ny form~,
without the written permission. 112
I ME I Correspondence Course
n n
~ = LXij and Dj = LX;j
H H
Total Transportation cos t :
m n
z= I~u, + IDj Vj ... (6)
H j~l
2. Consider the base cells (stones) for which allocations have been made and
their cost coefficients Cij' Assign the other values of Ui and Vij, such that
Cjj = uj + Vj for these base cells
[In the case of degeneracy, i.e., when the total number of base cells
«m+n-l), it will not be possible to assign, all Ui and Vj values. In such cases,
allocate E in one or more of the base cells, taking care that the total number of
base cells inclusive of the ones allocated with E should not exceed (m+n~l),
3. Determine the Index values for non - base cells, using Lljj = cj - (uj + Vj) [i.e., The
cost value minus the sum of Ui and Vj of the corresponding cell]
4. Check whether all the index values are non-negative (i.e., all 'Lljj 's are ~ 0) as it
is a minimization problem.
[The index values are calculated for the non-base cells only. Hence they are
called as 'Water values ' .]
The following format is used to indicate Xij, Cij and Ll;j in the same cell, in the
iteration ta ble:
Note: Wherever 'Xi/ s are indicate, there will be no' Ll jj 's and vice versa
Consider the first iteration, for the example, by VAM
+ Correspondence Course '+ TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written pe"rmission. 113
-3
-8
1
10 o
5 6 15 9
The solution is not optimal as all the ~ij 'S (water values) are positive (~
I 0).
Step-3
Develop the next iterative (i.e. improved) allocation
a. Find the non-base cell, which has the most negative index value (i.e., the cell for
which ~ij is minimum).
This is the entering base cell in the next iteration (similar to simplex criterion I
for the entering variable to the base). This is also called as the designated cell.
Put a' '+' ill this cell (at the both left hand corner of this cell) .
[Refer Example: The cell (2, 3) is the designated cell. The closed loop is formed
as:
(2,3) ~ (+);(3,3) ~ (-);(3,4) ~ (+); and (4) ~ (-)]
b. Find the allocated valCtes, Xii in the cells marked (-) negative. Choose the
minimum of these values. The cell having this value is the one to ( ) the base.
Allocate this value at the designated in the next iteration. Subtract this value
from allocations made in the cells marked (-), and this value to the allocations
made in the cells marked (+). There well be no change in the allocations made in
the other base cells.
In the example, the designated cell (2, 3). The minimum value of Xii in the cells
marked as is 1, which is the Xii value in the cells (2, 4) marked cell (2, 4) is the
one to leave the base in 'he iteration. The allocated values in the next iteration
are (2,3) ~ 1,(3,4) ~ (1+ 1 = 2),(3) ~ (3-1 = 2).
Note: for the cell (2, 4)it is 1-1=0, that is no allocation and it leaves the base in
the next iteration. Check whether the rim conditions are satisfied; otherwise it
indic;:ates that you had committed some error in the step,3(b)]
.' .. Correspondence Course" TarGATE .. ICP-Intensive Classroom Program" eTutor .. Online Test Series
@All rights reserved'byGateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized iri -anyform.
without the written permisSion. .~,;, ';!~;. '~;, 114
GATEFORUM
•.••.....•.. ...
Engineering SUcce&6
Step-4
Go to step 2 and iterate until optimum is reached,
6 -3
-8 .
1
10 o
5 6 15 9
Iteration 2
. \ ,".\,
. "
7 5 3 2 ·'u··'
1
.
• ·,'1
6 4
-9
1
10 o
7 15 9
Iteration 3
The optimum has been reached, as all the index values are positive (~O),
+ Correspondence Course"" TarGATE + ICP-Intensive Classroom Program .• eTutor + 'Online :rest-8eries:'''' ....
.\ . '
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized iF! any form .'. '.'
without the written permission. 115
; GATEFORUM
mil
l _ Engineering Succe.ss-
••••• 1 •••••••••
.;,
I ME I Correspondence Course
. .- "IBr
' .. 'OS"
:. Z = -(6x 4) -(lx9) + (lOx 0) + (7x 5) + (5x7) + (3x 15) + (2x9) = 133- 33 = Rs.100
'I
-+- Correspondence Course'-+- TarGATE -+- ICP-Intensive Classroom Program -+- eTutor -+- Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any fOIm .
without the written permission . ~, " 116
·',
I ME I Correspondence Course
ASSIGNMENT MODELS
n
Si = LXij and Dj = LXij , can be any
j=l i=l
Si = L Xij = 1. The total number of units n n
j=l positive integers. And LS, = 'LDj
required at the jth destination i=l j=1
3. The number of resources ,(machines) = The number of sources (m) need not
number of jobs = n. Hence the cost be equal to the number of destinations
and allocation matrices \lre always (n) i.e. 'm' need not be equal to 'n'.
square (nxn).
4. cij represents the cost of assignment of Cij represents the cost per unit of
a resource (machine) 'i' to an activity transport from the ith source to jth
. (job) 'j' . destination
5. Assignment problem always Degeneracy need not be present in all
degenerates in its solutions the problems ..
"
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Senes
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form
without the written permission. 117
; GATEFORUM .
" ...,j-~.;.!' . . • . .
.,i'l"" :- -'';'il i:y,
' . ...'.'-;.\.';I~
.
j
...............
Engineering SUcce&s I ME I
..'J
Degeneracy in Assignment Model:
Assignment models always degenerates in the feasible and optimal solutions. As only
one job could be allocated tone machine or vice-versa. The total number of allocation is
always 'n'i in the n x n matrix. The condition for ~on-existence of degeneracy is that, the
number of allocations should be equal to (m+n-1). Wh~n m=n, we have m+n-1=n+n-
1=2n-1. The total number of allocations in the ,assignm~ent problem is always equal to
'n', which is always less than (2n-1) :- HeAce assignment problems always degenerate.
- _._ _ . ___ 1.-. _____ --__ ..'_..•
i
t ~
Example - 39
There are four jobs A, B, C, D to be assigned to four machines W, X, Y, Z. Only one job
could be assigned to one machine. The cost involved in assigning ith job to jth machine
is given in the cost matrix. Determine the optimum assignment to minimize the total
cost.
~
Job
W X Y Z
A 1 4 6 3
B 9 7 1.0 9
C 4 5 11 7
D 8 7 8 5
Cost Matrix Cj
Step-1
• Consider the cost matrix
a. In each row, subtract the minimum value in the row from each element in that
row.
1 4 6 3 ( -1)
9 7 10 9 ( -7)
4 5 11 7 (-4 )
( -5)
8 7 8 5
Cost Matrix
0 3 5 2
2 0 3 2
-
0 1 7 3
3 2 3 0
+ Correspondence Course + TarGATE + lCP-In.tensive Classroom Program + eTllt0r + Online Test Series
@AII rights reserved by ~ateforum Educational Services Pvt. Ltd. ' No part of this booklet may be reproduced or JtiIiZ~.fJ:"i.rJ. ar~J6,\rn '
without the wntten permission. ':1' . ' 118
I ME I Correspondence Cour~~",
b.From the resulting matrix, in each column, subtrgct, the minimum value in the '
column, from each element in that column
i:'~'- .. I·-,;:-'nrrr;'
"uj
i
-" -r
son:;.. :;:. '0 3 5 2
-'n ,
P"1 !
"
2 0 ,.;; 3.~ ~. 2
_::'1 ~..
3 2 3 0
j ~
(0) (0) ( -3) (0)
/
0 3 2 2
2 0 0 2
0 1 4 3
3 2 0 0
First iteration
Step - 2
Check whether a feasible assignment could be obtained by assigning at the elements
containing zeros. If so, optimum feasible solution has been obtained, and stop. If not go
to step 3.
[QJ 0 0 0
2 X 0 2
)( 1 4 3
'3 2 )( []]
"
Final Iteration Optimality reached
I'
+ Correspondence Course'" TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© 'AII rignls rese'rved byGatel6rum Educatio nal Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form'
without the written permission. 119
IME I Corresp ~l1deric~ Coutse
w " X Y Z
A OJ 4 6 3
.,
B 9 7 [IQJ 9
C ..
'
,
4 [[J , .
11 7
D
:.\
8
-
7
"
8 []]
Assignment' indicated in the origina l m atrix Cij
Answer: ::
Th e optimum ass ignment is: A --7 W. B --7 Y. C --7 X. and D --7 Z.
Total cost z = 1 + 10 + 5 + 5 = 21.
-+- Correspondence Course' -+- TarGATE -+- ICP- fi1tensive Classroom Program -+- eTutor -+- Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd, No pa rt of this booklet may be reproduced or utilized in any form
without the written permission. 120
I ME I Correspondence Course
QUEUING THEORY
The queuing theory deals with all aspects of a situation are which customers requIring
some kind of services have to wait for those services. The work queue refers to waiting
in time.
Queuing system: Customers arrive at a constant or variable rate for services at service
facilities. If the service facility is free, they are served immediately. If the service facility
is busy providing services to other customers, the newly arrived customers have to wait.
Thus if they must for services, they either begin a queue or join an existing queue and
remain in the queue until they are served. The service rate may be constant or variable.
After a customer is serviced, he leaves the system
The queuing system = Service facility + Waiting line
Figure below shows a typical queuing system
Input output
(customers) (customers)
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 121
Queue discipline:
This is the manner (or rule) which determines the formation .o f queue and the behaviors
of waiting units (i.e. customers) ) ' "
-,
These are ' .,
(i) First come, First served(FCFS)
or
First in, First out (FIFO)
(ii) Last come, First served (LCFS)
,or
Last in, First out (UFO)
(iii) First come, Last Served (FCLS)
or
First in, Last out (FILO)
(iv) Random selection
(v) , Priority selection
:.. Cpn;espondence;CoJrse .. Tar,G ATE .. ICP-Intensive Classroom Program .. eTutor .. Online Test Series
'@':4ITr'ignfs"reserveO 'bY',GaiiilO'rumEdu'caiional services Pvt, Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission , 122
CATEFORUM
....... , ......... .
Engineerlng,5Qcce6S'
IMEI
(1) Expected number of customers in the system (L) ',. " ' t
Let
A = mean arrival rate
)l = mean service rate
L= _ A_
)l-A '""!/'
(2) Expected queue length (Lq) - This also stands for mean number of customers in
A2
the queue Lq = )l()l-A)
(5) The probability that the number Of customers in the queue being served ' is
. (l)K+l
greater than k IS PrS>K) = l~
A
Po = 1--
)l
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program :toe.Tutor ... Online Test Series . "
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
wi.thout the written permission. 123
GATEFORUM
,l Enginee.rlng Success
• • • • • 1 • • • • • • 111 • • I ME I Correspondence Course
Alternatively, if n ;::: S, th~n all servers will be busy and mean service rate = S.).1
Where 5.).1 must be greater than "- if the queue is not to become bounded
Case I: n<S
Where
n = no. of customers
S = no. of servers
1
Pn =-x - (,,-)n xPo .... O<n<S
n! ).L
P = 1 X -
(,,-)n xP
n S!.(st-S ).L 0
=
=
LP =
(tr xPo
--'-'---0-"-------,-
n=S n S{ 1- ).L~)
.. Correspondence Course -+' TarGATE" rCP-Intensive Classroom Program" eTutor .. Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 124
Level - 1
,
c~! fh.J, \ ' I
1. PERT is
(A) Project evaluation and review test
(B) Programme evaluation and review technique
(C) Project estimation and review technique
(D) Programme estimation and review technique
3. PERT is
(A) activity oriented (B) event oriented (C) cost oriented (D) time oriented
5. CPM is
(A) Critical Process Method (B) Critical Path Method
(C) Common Planning Method (D) Combined Process Method
6. CPM is
(A) Cost oriented technique (B) Activity oriented technique
(C) Event oriented technique (D) Target oriented technique
7. CPM has
•
(A) one time estimate , (B) two time estimate
(C) three time estimate (D) ,four time estimate
9. Which of the following tJechnique should be used for planning and scheduling of
an R&D project?
(A) XYZ analysis (B) HML analysis (C) CPM (D) PERT
+ Correspondence Course'+ TarGATE + ICP- Intensive Classroom Program + ~Tutor + Online Te~t Series , .'
© All rights reserved by Gateforum Educatio nal Services Pvt. Ltd . No part of this booklet may be reproduced or utilized in any form .
without the written p e r m i s s i o n . ' 125
~~~!~rfn~s~~
iII.l.!.I .•
If • • • • • • • • • -II • •
I ME I Correspondence Course
18. Critical path moves along ~he activities having total float of
(A) positive value (8) negative value (C) zero value (O)same value
+- Correspondence Course' +- TarGATE -+ ICP-Intensive Classroom Program +- eTutor +- Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 1 26
I ME I Correspondence Course
In a M/M/l queue, the mean rate of arrival is Il and the service rate is Illl
28. In the graphical method of linear programming problem, every corner of the
feasible polygon indic?ltes
(A) An optimum solution
(C) Both (A) and (B)
, (B) Basic feasible solution
(D) None of these
29. The initial feasible solution in transportation model can be determined by the
application of
(A) least cost method (B) North West corner method
(C) Vogel's approximation method (D) all of these
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educ;ational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 127
I ME I Correspondence Course
36. In the single server system of queuing discipline, inter a"rrival and service times
follow . <
38. At a private bank in heart ~f Hyderabad, the customers arrive at the rate of 2 per
. minute . The bank can serve 180 numbers of customers in an hour. The average
time a customer is seen in the premises of bank is
(A) 1 minute (B) 0.6 minutes (C) 0.3 minutes (D) 1.8 minutes
+ Correspondence Course + TarGATE + ICP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt : Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 128
I ME I Correspondence Course
39. Which of the following cannot be the three time estimates for an activity in PERT
network? to, tp and tm denote optimi$tic, pessimistic and most likely time
respectively?
(A) tp = 25, to = 12,tm = 16 (8) tm = 18, tp = 23, to = 9
(C) to = 6, tp = 8, tm = 15 (D) to = 15,tm = 18,tp = 28
40. Which of the following statements is true in 'c ontext of 'Free float'?
(A) Free float should not be' absorbed by activity since affects both previous and
subsequent activities.
--CB) Free float does not affect subsequent activities.
(C) Free float can be absorbed without any further planning since it affect on
subs~quent activities.
41. In a one person barbershop, the inter arrival time is 12 minutes. The arrival
pattern approximates Poisson distribution. If a customer spends on an average
10 minutes exclusively for service (excluding waiting time) than what is the
probability that a customer has to spend more than 45 minutes in the system?
(A) 40% (8) 60% (C) 47% (D) 75%
42. On a typical day in a bank, customers arrive at the rate of 3 per hour and the
s'ervice rate by the bank employe~ is on-e customer every 30 minutes. The bank
has 2 identical service channels. What is the average total time' that a customer
has to wait in the system if average waiting time in line is 20 minutes?
(A) 20 minutes (8) 32.48 minutes
(C) 25.67 minutes (D) 36 .66 minutes
44. Which of the following is not used for initial allocations in transportation method?
(A) Vogel's method (8) Leastcost method
\
(C) Northwest-corner method
, (D) Southeast-corner method
45. In a garage, the customers arrive at the rate of four per hour and jobs are
performed at an average rate of one every twelve minutes. The mechanics in the
garage operate as a team on one car at a time. What will be the average time a
customer has to wait before he gets his car repaired? .,
(A) 15 minutes (8) 30 minutes (C) 60 minutes (0)90 minutes
... Correspondence Course'" TarGATE'" ICP-Intensive Classroom Program'" eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services PvL Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission, 129
~~~!~rfn9s~!!~
~ • • • • • It • • • • • • 'IE • • I ME I \
Correspondence Course
46. In a PERT network the expected time to finish one activity is 21 and variance of
the activity is 9. What will be the ratio of pessimistic time to optimistic time, if
most likely time for finishing the activity is 22 days? .
(A) 15
1 4
(B) 15 (C) ~~ (D) None of these
47. In a queuing model, A is the mean arrival rate and B is the m~an Service time
and A < B: The probability that the, queue length .is greater than N is
48. Consider an activity having a duration time of Tij.E is the earliest occurance time
and L the latest occurrence time.
+ Correspondence Course + TarGATE + ICP-Inte'nsive Classroom Program + eTutor + Online Test Serie~
© All rights reserved by Gateforum Edu'cational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 130
Level - 2
(A)
4
I ~\
':11 ,,,,,,If O!
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program ... eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. ·No part of this booklet may be reproduced or utilized in any form
without the written permission. 131
-- ---.--.--. ~ ----------------------------------- ....~!I!!IIIII!IIIIII!!!!II
, 'J'.,y r
fITil!~!~rfnPs~Y!:!
oJ. !'
IIU.!!.I ..
II • • .: • • • • • • • • •
I ME I Correspondc1:tce Course
8. For any activity i-5 (EOT)i and (EOT)] is the earliest start time of event i and j.
(LOT)i; (LOT)j are latest occurrence time of event i and j, and t i-j will be is the
time required to complete the activity i-j. Total float of the activity i-j
(A) (EOT)) - (EOT)j - til /' / /(B) (LOT)j - (EOT)j - t j_j
..... "
9. Free float of the activity i-j
(A) (EOT)j - (EOT)i - tjj (B) (L0:r)j - (EOT)i
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 132
, GATEFORUM
~~.~~.g~~u~r~!~~.s~.~~
••u.~.__~____________________________~I~M~E~I~C~o~r~re~s~p~o~n~d~en=c~e~C~o~u~rs~e~,
22 . The earliest occurrence of the event of the tail node (i) and head node J of an
activity i-J, in the critical path are 10 days and 15 days, the free float of the
activity is
(A) 5 days (8) 10 days (C) 15 days (D) zero
23. The estimated duration of times for an activity in the PERT network under the
worst and best environ ~ ent is 10 days and 4 days respectively. The variance of
the activity is
(A) 6 days (8) 10 days (C) 4 days (D) 1 day
24. The difference between the time available to do the job and time requ ired to do
the job is
(A) event (8) float (C) constraint (D) duration
+ Correspondence Course + TarGATE + rCP- Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt, Ltd , No part of this booklet may be reproduced or utili zed in any form
without the written permission. 133
----.---.---- - - - - - -- - - - - - - - - - - - - - - - -- ....iJ!III.....,
~.
: GATEFORUM
mil
~
..........•....
Engineering Sqccess I ME I
i, •
CorrespondeI}ce Course
,.. 25. For an activity i-j if earliest occurrence at tail node i and head node j are 10 and
15 days. Latest occurrence at node i and j are 10 and 21 days respectively and
time required to do the job is 4 days. Total float of the activity is
(A) 0 (B) 5 days (C) 11 days (D) 7 days
-,
26. What would be free float in question 257
(A) 0 days (B) 1 day (C) 5 days (D)none
-Xl + x 2 ~ -1
2Xl - 2X2 ~-2
Xl ~ a
X2 ~ a
(A) -1, 1 (B) l,, - i
-~
.. Correspondence Course .. Till-GATE" ICP-Intensive Classroom Program .. eTutor .. Online Test Series
© All rights reserved by Gateforum Educational Serviees Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission . 134
~
~!~!~rfn~s~Y!
1iU.!:..I •••••
I •••••• c •• I ME I Correspondence Course
31. In a linear programming model, there are n variables and m constraints. The
condition of degeneracy is that during iteration, the total number of allocated
base cells should be
(A) equal to (m+n-l) (8) more than (m+n-1)
(C) less than (m+n-1) (D) none of these
t~:'. "
32 . In assignment model
(A) Degeneracy always pr~sent in the problems
(8) Number of resources is equal to number of jobs
(C) Only one unit from the ith source can be assigned to anyone of its
destination
~ 1...1 ' "fl' '.
35. What will be the probability of completing a job in less than half hour?
(A) 0.5 (8) .0.8 (C) 0.37 (D) 0.262
36. •
Calculate the probability of more than 5 jobs in the system
(A) 0.5 (8) 0.8 (C) 0.37 (D)0.262
In a maintenance shoil, jobs come at an average rate of 15 per day. The inter-
arrival time follows an exponential distribution and the service time distribution is
also exponential with an average of 48 rnjn. If the job arrival rate increases by
20%, what changes would occur in the following
37. Mean queue length
(A) 20% decrease (8) 20% increase (C) 50% decrease (D) 50% increase
+ Correspondence Cou;se + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No'part of this booklet may be reproduced or utilized in ariy form
I· • , "
41. For the following network with times sh ow n o~ the arrows, the critical path is
6
(A) 1-3-5-9
4
(B) 1-3-7-8-9
(C) 1-2-6-8-9
(D) 1-4-5-9
4
42. For an M/M/I queuing system, the arr ival rate x = 10 per hour and service rate IJ
= 15 per hour. The expect ed le ngth of busy period and the expected number of
customer served per busy l2eriod respectively are
43. Simplex method and graphical method of solving linear programming problems
are used when the variables involved in them are respectively
(A)' any number and two (B) two and any number
(C) three and any number \ (D) any number and three
44. For obtaining the optimal solution to an LPP, number of iterations is made on the
initial simplex table. Now the variable that enters the basis will have .
(A) Most positive value in Z equation
(B) Most negative value in Z equation (C) Zero value in Z equation
(D) Either Zero or Most negative value in Z equation
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program'" eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission. 136
,;
I ME I Correspondence Cours~
. ...,,' . I '1'
47. The Penalty in the allocations of transportation problems means the difference
between the '
(A) Smallest and the largest cost
(8) Smallest and the next smallest cost
(C) Largest and the next largest cost
(D) Largest and the second smallest cost
48. In M/M/I systems of queuing problems, the average time a customer waits is
obtained from the average time a customer spends in the system by
(A) multiplying with traffic intensity (e) (8) dividing by traffic intensity
••: , I :.-oJ
49. WithMu'SClal ndtations, the free and independent floats are given by (in network
analysis) i.e. Ff and ~ ,
51. The times in PERT analysis viz., optimistic, pessimistic and most likely times
follow the
(A) ~ - distribution (8) Poisson's distribution
(C) Normal distribution (D) Exponential distribution
+ Correspondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series '
© All rights reserved by Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission, 137
I ME I Correspondence Course
53. j In the PERT, the \\Fr~~ float" refers to the tiln\ ,! tllW t1te:h 1
54. Choose the true statement about the Dual Simplex method of solv.ing Linear
programming problem
(1) It is developed by C E Lemke
(2) It is developed by George Dantzing
(3) It starts with basic infeasible optimal solution ,
(4) It starts with basic feasible optimal solution '"
(A) 1 and 2 (6) 2 and 3 (C) 1 and 3 (D)2 and 4
55. A transportation problem has 3 sources and 4 destinations. The number of non
negative i.e., ~O allocations of a basic feasible solution to this problem would be
equal to
(A) > 6 and < 12 (6) ~ 7 (C) :s; 6 (D) >6 and < 10
56. On a machine shop floor, the arrival rate of the jobs for processing is 4 per
minute. The service rate of a machine is 5jobs/minute. The average waiting time
of the job in queue is
(A) 0.8 m inute (6) 1 minute (C) 1.2Sminutes (D) 20 minutes
•
57 . An LPP i.e. linear programming problem is like this:
Maximize Z = Xl + 2X2 + X3 subject to
(i) 3xl + x 2 + X3 = 9 and (ii) 2Xl + 3x2 + X3 = 15
The number of basic solutions for this problem is
(A) 5 (6) 3 (C) 2 (D) no solution
~
58. The probability factor associated with the completion of a project in PERT is
(A) always one i.e. unity (6) always negative
(C) always 0.5
(D) any value positive, negative or zero
,..f Correspondence Course:+ .tarO,A TE:+ ICP-Intensive Classroom Program:+ eTutor:+ Online Test Series
© All rights reserved by Gateforum Educational Services Pvt . Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 138
I ME I Correspondence Course
.. Correspondence Course" Tara''ATE .. ICP-Intensive Classroom Program" eTutor .. Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 139
.t. • ~'.~~ :.. ••
.. -
I ME I Correspondence Course
65. The mean arrival rate to a service centre is 3 per hour. The mean service time is
10 minutes. Assuming Poisson arrival rate and exponential servicing time i.e.
(M/M/l); (F(FS/a/(x'). Determine expected number!of units in the system.
I
1 I
(A) 2 customer (B) 2" customer (C) 3 customer
I
(D) 1 customer
The expected time and variance of the each activity are given in the table below.
16
E 5
9
1
8
9
2 o
68. The critical path of the Network shown is
(A) A - 8 _ ' [J ..:..,lp ,.l?@ Isml0Vl U'i (8) A- C- F - G
f(C) A - C - E - G > (DJ A - ' 8 - D - E - G
\.... ,..., .t -
69. What will be desired completion date for the project if probability of finishing the
project is 19%. [Assume from standard normal distribution Z(-0.87) == 0.19].
(A) 36 weeks (8) 35 weeks (C)' 38 weeks (D) 40 weeks
f b 911SJ 9 (':'",\': L
70. The earliest occurrence time for an event 1 is 8 ' weeks and the latest occurrence
time for event 'l'lr~S' : :26 -'Weeks.- The earliest occurrence time for event '2' is 32
weeks and the latest 9c<;:.urrenc~, time for event '2' is- 37 weeks. If the activity
time is 11 weeks, then fhetof'a ( float will be.
(A) 11 (8) 13 (C) 18 (D) 24
71. For a MIMll oo/FCFS queue, the mean arrival rate is equal to 10 per hour and
the mean service rate .is 15 Per hour .The expeGt,::!d of queue length is
(A) 1. 33 (8) 1.53 (C) 2.75 (D) 3.20
... Correspondence Course'" TarOATE ... ICP-Intensive Classroom Program'" eTutor'" Online Test Series
© All rights reserved by Gateforum Educational Services Pvt, Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission. 141
. ""
I ME I Correspondence Course
73 . Z will be maximum at
(A) Xl = 0, x 2 = 4 (8) Xl = 6, x 2 = 0
(C) Xl = 6, x 2 = 4 (D) N6'ne 'of these
75. For the PERT network shown in the given figure the probability of completing the
project in 27 days is (te in days) use table.
Z 0.04 0.06
0.1 0 .5557 0.5636
1 0.8508 0.8554
-"..
'.
'-.1.. •
t ..
t2=15, cr=4
tz=6, cr=2
\J"I I
.
}1 '" II rt
(8) 0.5636 (C) 0.8508 (D)0.0554
\
\
,
,
\D2
4'\~
(A) 1-2-3-4-8-9 (8) 1-2-3-5-6-7-8-9
(C) 1-2-3-4-7-8-9 (D) 1-2-5-6-7-8-9
77 . In a single server queue customers are served at rate of jJ. If VIIs and Wq represent
the mean waiting time in system and queue respectively, then ~ will be equa l to
1
(8) W
q
+!J.L (D) W - -
q J.L
+ Correspondence Course +'TarGATE + rCP-Intensive Classroom Program + eTutor + Online Test Series
.© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
wiihout the written permission. 142
I ME I Correspondence Course
Tra ins arrive at the Y:Cji,Q>every 15 minutes and the service time is 33 minutes .
The line capacity of the yard is limited to 4 trains.
, :
78. The probability that the yard is empty is
(A) 0.037 (B),-0 )54 " ' (C) -0.45 (D) 0.023 )
,
,
1
79 . The probability that the yard has 3 trains in th; 'system is'
q
(A) 0.093 (B) 0.25 (C) 0.157 (D) 0.023
A supermarket has two girls ringing up sales at the counters . The service t ime fo r
each customer is exponential with mean 4 minutes, and if peop le arrive in a
Poisson fash ion at the counter at the rate of 10 per hour.
80. Calculate the pro,b ability that an arrival will have to wait for service
81. Find the expected perc~D tage of'j'dte .t ime for each girl.
(A) 67% (B) 75% (C) 33% (D) 45%
+ COITe~pondence Course + TarGATE + ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd . No part of this booklet may be reproduce d or utili zed in any form
without the written permission , 143
I ME I Correspondence' Course '
Level - 3 ,,
American Vending Inc. supplies vended food 9ft(~ large university. Because
students kick the machines at every opportlJlfNtlyout of anger 'a nd frustration,
management has a constant repair problem t 2'fhe machines break down on an
average is on three per hour and the , breakdowns are 'distributed in a Poisson
manner. Downtime costs the company Rs.25/hour per machine and each
maintenance worker gets RsA per hour. , . '
1. What will be the total cost if one worker is servicing machines at an average rate
of five per hour, distributed exponentially?
(A) Rs.41.50 (B) Rs.26.75 (C) Rs.27.00 ' (D) none of these
2. What will be total cost if two workers, are \A{ofkinQ.toge~h'~r, who can service
seven per hour, distributed exponentially
(A) Rs.41.50 (B) Rs.26.75 (C) Rs.27.00 (D)none of these '
3. What will be total cost if a team of three workers are working and they can do
eight per hour
(A) Rs.41.50 (B) Rs.26.75 (C) R$.:.27.00 (D) none of these
.........) -- " ,"
The table below contai fiS a. list of activities sequencing requirements and duration
of each activity .
Pre- TilJle '_1 _', C .i
c b 2
d c 2
e a,d 2
f d 1
g a,d .'. 6
h e 5
g,h r(' 6
j 2
k g 4_
j,k 3
m I
8. Draw a network for the above activities.
. '\- ;) ~ ,
9. What will be the project duration?
••
+ Correspondence Course + TarGATE+ ICP-rntensive Classroom Program + eTutor + Online Test Series
© All rights reserv~d by Gateforum'Educational 'Services Pvt. Ltd, No part of this booklet may be reproduced or utilized in any form
without the written permission , 145
,,. '
(~
,',
4'{ ,
" Of
,,,
I ME I Correspondence Course
Answer Keys
Level 1
1 B 2 D 3 B 4 C S B 6 B 7 A
~'",
8 B 9 D 10 A 11 A 12 C 13 B 14 A
15 C 16 C 17 A 18 C 19 D 20 A 21 B
22 B 23 C 24 A 25 A 26 C 27 C 28 B
e
29 D 30 B 31 C 32 C 33 C 34 B 35 A
36 C 37 A 38 A 39 C 40 B 41 C 42 D
43 D 44 D 45 C 46 B 47 D I 48 A
Level - 2
1 C 2 C 3 C 4 D 5 B 6 C 7 B
.. ,
8 B 9 C 10 B 11 A 12 A 13 D 14 C
15 C 16 B 17 D 18 D 19 " "A - '20 A 21 A
22 D 23 D 24 B 25 D 26 , ~ 27 D 28 A
29 A 30 C 31 C 32 D 33 A 34 B 35 C
36 D 37 B 38 B 39 D 40 B 41 A 42 B
43 A 44 B 45 C 46 A 47 B 48 A 49 C
; : -
50 B S1 A 52 D ·53 D 54 't 55 C 56 A
57 B 58 D S9 A 60 C 61 A 62 B 63 A
64 B 65 D 66 A 67 C 68 B 69 B 70 C
-
71 A 72 A 73 C 74 A 75 A 76 B 77 B
-
78 B 79 D 80 A 81 A
Level - 3
I 1 I A 2 B 3 c 4 B S D 6 A 7 A
Explanations:-
Level - 1
9. Exact time of completion is unknown in R & D f so PERT is used.
. A
30.
.
Expected no. of customer in system =- -=
~-A
2
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program ... eTutor ... Online Test Series
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in any form
without the written permission. 146
I ME I Correspondence CourSe
3+1 -
35. P(k>3) = (~AJ = 0.198 '
1) 't .
(1-':: rt
. 5}45
41. P T >-
( ' 2
=e - .Ii
Ii , = e-6l 1--6 -
60
Level - 2
•
2.
Activity i node j node EST LST TF Remarks
P 1 2 0 4 4
Q 1 3 0 2 2
R 1 4 0 0 0 critical
S 2 5 ~ 6 4
T 3 6 3 5 2
U 4 7 4 4 0 critical
V 5 6 11 11 0 critical
© All rights reserved by Gateforum Educational SerVic~s Pvt. Ltd, No part of this booklet maYbe'repi&!uq8d or Ut.iliz~d in any forril J . i . $';,.. : ,
without the written permission. l~'f
''f" .~ ,,:~l' ' " ~I) ~'",
4. (TF)4 = 0
14.
Activity Path Time EST EFT LFT LST! TF Remarks
- "
L 1 ~ 2 3 0 3 03 0 0 \ t cHtical
M 1-3 4 0 4 12 8 8
N 2- 3 9 3 12 12 3 0 critical
0 2-4 3 3 6 12 9 6
P 4-6 3 6 9 18 12 6
Q 3-6 6 12 18 18 12 0 critical
f-
R 3-5 4 12 16 16 12 0 critical
"
20. Because L is critical activity, any delay in L will increase project time
•
25. (Total float)i_j = (LOT)j - (EOT)i - t i_j = 21-10 - 4 = 7 days
33. A. = S,Il = 10, Average elapsed time in the system, W= _l_ = 0.5 hr.
, \' ~A.
-. Correspondence Course + 'TarGATE. ICP-Intensive Classroom Program. eTutor • Online Test Series ,
"_ 1 , ' " _
© AII,f;i{jhts feseliVed by Gateforl:lm.E;;dI!JGationat.sel'VicesPvt,-Ltd , 'No'part'ofthis' booklet may' be reproduced 'or utilized in aiiy'forni ' " , "'"
without the written permission,, : ' 1, ~$
~.. ': .
\ .".
I ME I Correspo~derice Course
A.
34. p=-=0.8
~
35.
1
P (T > - ) = e
-J.l (1 --I!A)xt ="0:3'7
~.;J
I j /,
' ~-::
,
•1
2 '.) _J ~_.i.~
; I J
-1- - ' - .- -
8 I - I'll ,.. -.J
", ____
.. Ii! !
36. P(k>5) = (~J = 0.262 f) I
'~
1
37-39. A. = 9 6 jobs Jmin ~ = 4~ jobs / min A.1 = 810 jobs / min I Now calculate the asked
parameter with both values of A. and A.l and calculate the difference
64, From the graph, at point (2.5, 35), the objective function is 147.5.
L
S p.-..l 6-3
O-T.
69. Z = ~ . 2 E ,0 = 35 weeks
Ia c p
5,5
te=15, a=4
75.
te=4, a=2
4
79. Probability that yard has 3 trains in the system, P3 = PoP
p=
-1(spf (Spt ]-1 = 1
I--+
5.
o n!
.[ n=O s ! (1 - p) 2
+ Correspondence CourSe + TarGATE +.ICP-Intensive Classroom Program + eTutor + Online Test Series
© All rights res,!!rved by Gatefarum :Educational Services Pvt. Ltd. :No part of this booklet may be reproduced or utilized in any form
without the written permission. 150
I ME I Correspondence Course
81. The fraction of the time that the service rem:ain~~ busy (i.e :~ traffic' intensit? is
.
given by p = - A = -1) .
sfJ. 3 , '" - _. _. - .. -
Therefore, the fraction of the time the service remains idlE( is
,
= (l-j) = ~ = 67% (nearly)
Level - 3
1. A = 3, f..L =5
Average r:lumber of machines in system ns = _ A_ = 1.5 machines
f..L- A
Total cost, Down time = 1.5x25=37.50
Labour cost = 4.00
Rs.41.50
- A .
2. A = 3, f..L = 7, ns = - - = 0.75 machines
f..L- A .
Total cost, Down time = 0.75x25=18.75
Labour cost = 2x4= 4.00
Rs.26.75
3
3. A = 3, f..L = 8 ns = _A_ = 8 3 e: 0.60 machines
f..L- A -
Total cost, Down time = 0.60x25=15.00
Labour cost = 3x4= 12.00
Rs.27.00
5. Calculate activity time and find out the path along which the sum of time is
maximum
... Correspondence Course'" TarGATE ... ICP-Intensive Classroom Program ... .;:Tutor ... Online Test Serie~
© All rights reserved by Gateforum Educational Services Pvt. Ltd. No part of this booklet may be reproduced or utilized in~ny forr:n
without the written permission . 151
I ME I Corresporidence: Cd;r~e
8.
J--:=---.~
••1 ~e.
I
.'
\
4
.- .. Correspondence Course" TarGATE .. ICP-Intensive Classroom Program" eTutor" Online Test Series
@ AII'~ights reserved by Gateforum Educational Services PvL Ltd. No part of this booklet may be reproduced or utilized in any forin
without the written permission. : 152
\1'
QATEFORUM
ei'19in~er i llg ~U~~
·,"1ME ~Correspoiad€n-ce Cour~~
I.f:>8, O:: :
Reference Books
Industrial Engineering: