Government Of Nepal

National Reconstruction Authority


Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
B CIVIL WORKS
1.0 Site clearance before and after completion of work
Site Clearance 1.0 13.50 9.500 128.250

Sub Total 128.250 sqm


Total Quantity of Site Clearance 128.250 Sqm
2.0 Excavation and Filling Works
2.1 Earthwork Excavation in Foundation
Column Foundation
Footing Type (F1)
B4 & C4 2.0 1.20 1.200 1.500 4.320

Footing Type (F2)


A1, A3, D1 & D3 4.0 1.30 1.300 1.500 10.140

Footing Type (F3)


A2, D2 B1, B3, C1 & C3 6.0 1.55 1.55 1.500 21.620

Footing Type (F4)


B2, C2 2.0 1.55 1.55 1.500 7.210

-
14.0
Toe Wall Foundation
Grid (A1-A3 & Grid D1-D3) 2.0 5.85 0.530 1.150 7.130 Deducted Column
Grid (B1-B4 & Grid C1-C4) 2.0 5.73 0.530 1.150 6.980 Deducted Column
Grid (D1-A1, D3-A3 ) 2.0 1.30 0.530 1.150 1.580 Deducted Column
Grid ( D2-A2 ) 1.0 1.05 0.530 1.150 0.640 Deducted Column
Grid C5-B5 1.0 1.80 0.530 1.150 1.100 Deducted Column

Entrance Steps 1.0 4.500 1.100 0.225 1.110


Side Entrance 1.0 2.30 1.150 0.225 0.600
Ramp 1.0 1.90 1.600 0.225 0.680
Staircase midddle 1.0 1.10 0.700 0.725 0.560
Staircase start 1.0 3.20 1.100 0.725 2.550
Aprons (Petti ) 1.0 44.000 1.000 0.225 9.900
Manhole 4 1.060 1.060 0.525 2.360
1 1.210 1.210 0.525 0.770
For Sainatry Pipe Laying 1 40.000 0.600 0.900 21.600

Sub Total 100.850 cu.m.


Total Quantity of Excavation in Foundation 100.850 cu.m.
2.2 Filling Works
Earthwork Backfilling @30% OF Excavation 30.255 cu.m.
For Sainatry Pipe Laying 1 40.000 0.600 0.900 21.600
Total Quantity of Backfilling 51.855 cu.m.

2.3 Foundation Leveling


Flat Brick Soling
Column Foundation
Footing Type (F1)
B4 & C4 2.0 1.050 1.050 2.210

Footing Type (F2)


A1, A3, D1 & D3 4.0 1.150 1.150 5.290

Footing Type (F3)


A2, D2 B1, B3, C1 & C3 6.0 1.400 1.400 11.760

Footing Type (F4)


B2, C2 2.0 1.400 1.400 3.920

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.

Toe Wall Foundation


Grid (A1-A3 & Grid D1-D3) 2.0 8.10 0.380 6.160
Grid (B1-B4 & Grid C1-C4) 2.0 9.30 0.380 7.070
Grid (D1-A1, D3-A3 ) 3.0 4.80 0.380 5.470
Grid C5-B5 1.0 2.70 0.380 1.030

Entrance Steps 1.0 4.5 1.1 4.950


Aprons (Petti ) 1.0 44.0 1.000 44.000
Manhole 4.0 1.06 1.060 4.490
1.0 1.21 1.210 1.460

Sub Total 97.810 Cum.


Total Quantity of Stone Soling 97.810 Cum.
2.4 Sand Filling

In Side all Area 1.0 8.540 5.540 0.275 13.010 Cum


Entrance 1.0 2.840 1.270 0.275 0.990 Cum

Sub Total 14.000 cu.m.


Total Quantity of Gravel Sand mixture 14.000 cu.m.
3.0 P.C.C. (1:2:4)
3.1 Column Foundation
Footing Type (F1)
B4 & C4 2.0 1.05 1.05 0.075 0.170

Footing Type (F2)


A1, A3, D1 & D3 4.0 1.15 1.15 0.075 0.400

Footing Type (F3)


A2, D2 B1, B3, C1 & C3 6.0 1.40 1.40 0.075 0.880

Footing Type (F4)


B2, C2 2.0 1.40 1.40 0.075 0.290

Toe Wall Foundation


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.380 0.075 0.460
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.380 0.075 0.530
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.380 0.075 0.410
Grid C5-B5 1.0 2.7 0.380 0.075 0.080

Entrance Steps 1.00 4.50 1.10 0.075 0.370


Aprons (Petti ) 1.0 44.0 0.500 0.075 1.650
Manhole 4.0 1.06 1.060 0.075 0.340
1.0 1.2 1.2 0.075 1.5

Sub Total 7.040 cu.m.


Total Quantity of 75mm P.C.C. (1:2:4) 7.040 cu.m.
4.0 Reinforced Cement Concrete Works
P.C.C. for R.C.C. Works
4.1 Footings
Footing Type (F1)
B4 & C4 2.0 0.9 0.9 0.250 0.410 Thickness 250mm
2.0 0.5850 0.100 0.120 Trapezoid Part
Footing Type (F2)
A1, A3, D1 & D3 4.0 1.0 1.0 0.250 1.000
4.0 0.07 0.100 0.030

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Footing Type (F3)
A2, D2 B1, B3, C1 & C3 6.0 1.3 1.3 0.250 2.340
6.0 0.10 0.100 0.060
Footing Type (F4)
B2, C2 2.0 1.3 1.3 0.250 0.780
2.0 0.10 0.100 0.020

-
-
Manhole Cover 4.0 0.91 0.910 0.100 0.330
1.0 1.06 1.060 0.100 0.110
4.2 Foundation Tie Beam
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.230 0.300 1.120
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.230 0.300 1.280
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.230 0.300 0.990
Grid C5-B5 1.0 2.7 0.230 0.300 0.190

4.3 Column Up to plinth Level


Column Type C1
B4 & C4 2.0 0.3 0.300 0.925 0.170

Column Type C1
A1, A3, D1 & D3 4.0 0.3 0.300 0.925 0.330

Column Type C1
A2, D2 B1, B3, C1 & C3 6.0 0.3 0.300 0.925 0.500

Column Type C1
B2, C2 2.0 0.3 0.300 0.925 0.170

4.4 Plinth Tie Beam


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.230 0.300 1.120
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.230 0.300 1.280
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.230 0.300 0.990
Grid C5-B5 1.0 2.7 0.230 0.300 0.190

4.5 Column Up to Ground Floor


Column Type C1
B4 & C4 2.0 0.3 0.300 3.600 0.650

Column Type C1
A1, A3, D1 & D3 4.0 0.3 0.300 3.600 1.300

Column Type C1
A2, D2 B1, B3, C1 & C3 6.0 0.3 0.300 3.600 1.940

Column Type C1
B2, C2 2.0 0.3 0.300 3.600 0.650

4.6 Ground Floor Beam


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.230 0.230 0.860
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.230 0.230 0.980
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.230 0.230 0.760
Grid C5-B5 1.0 2.7 0.230 0.230 0.140

4.7 Column Up to First Floor

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Column Type C1
B1 & B2 2.0 0.3 0.300 2.195 0.400
For perapet Wall 4.0 0.3 0.300 1.000 0.360

Column Type C1
C1 & C2 2.0 0.3 0.300 2.195 0.400
For perapet Wall 4.0 0.3 0.300 1.000 0.360
4.10 First Floor Beam
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 0.230 0.355 0.660
Grid (C1-B1 & C2-B2 2.0 2.7 0.230 0.355 0.440

4.11 Slab
Ground Floor
Grid D1-A4 1.0 9.30 6.300 0.125 7.320
Exit Door 1.0 2.10 1.050 0.125 0.280
Door Drop 1.0 4.20 0.600 0.125 0.320
Deduction
Statue Area (1.0) 4.05 2.700 0.125 (1.370)

Entrance
Flat 1.0 4.80 2.250 0.125 1.350
Slope 1.0 9.30 0.600 0.125 0.700
9.97
Roof Slab
Side 1 18.300 0.600 0.125 1.370

4.12 Staircase
Staircase 1
Waist Slab 1.0 8.50 1.050 0.150 1.340
Steps 20.0 0.023 1.050 0.470 1.81
Beam for Support 3.00 1.00 0.355 0.230 1.070
Z-Beam 1 8.500 0.230 0.230 0.450
4.13 Lintel Beam
Ground Floor
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.230 0.150 0.560
Grid (D1-A1 & D3-A3) 2.0 4.8 0.230 0.150 0.330

First Floor
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 0.230 0.150 0.280
Grid (C1-B1 & C2-B2 2.0 2.7 0.230 0.150 0.190

4.14 Sill Tie


Ground Floor
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.230 0.100 0.370
Grid (D1-A1 & D3-A3) 2.0 4.8 0.230 0.100 0.220

First Floor
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 0.230 0.100 0.190
Grid (C1-B1 & C2-B2 2.0 2.7 0.230 0.100 0.120

Total Quantity 38.990 cu.m.


Total Quantity of P.C.C. for R.C.C. Works 38.990 cu.m.
5.0 Steel reinforcement bar
From Reinforcement Detail 6,021.823
Total 6,021.823 Kg
Total Quantity of Rebar 6,021.823 Kg
6.0 Formwork
6.1 Foundation
Footing Type (F1)
B4 & C4 2.0 3.6 0.250 1.800

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.

Footing Type (F2)


A1, A3, D1 & D3 4.0 4.0 0.250 4.000

Footing Type (F3)


A2, D2 B1, B3, C1 & C3 6.0 5.0 0.250 7.500

Footing Type (F4)


B2, C2 2.0 5.0 0.250 2.500

Total Quantity 15.800 Sq.m.


Total Quantity of Formwork 15.800 Sq.m.

6.2 Foundation Tie Beam


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.6 9.720
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.6 11.160
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.6 8.640
Grid C5-B5 1.0 2.7 0.6 1.620

6.3 Column Up to Plinth Level


Column Type C1
B4 & C4 2.0 1.2 0.925 2.220

Column Type C1
A1, A3, D1 & D3 4.0 1.2 0.925 4.440

Column Type C1
A2, D2 B1, B3, C1 & C3 6.0 1.2 0.925 6.660

Column Type C1
B2, C2 2.0 1.2 0.925 2.220

6.4 DPC Tie Beam


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.6 9.720
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.6 11.160
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.6 8.640
Grid C5-B5 1.0 2.7 0.6 1.620

6.5 Column Up to Ground Floor


Column Type C1
B4 & C4 2.0 1.2 3.600 8.640

Column Type C1
A1, A3, D1 & D3 4.0 1.2 3.600 17.280

Column Type C1
A2, D2 B1, B3, C1 & C3 6.0 1.2 3.600 25.920

Column Type C1
B2, C2 2.0 1.2 3.600 8.640

6.6 Ground Floor Beam


Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.690 11.180
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.690 12.830

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.690 9.940
Grid C5-B5 1.0 2.7 0.690 1.860

6.7 Column Up to First Floor


Column Type C1
C1 & C2 2.0 1.2 2.195 5.270
For Perapet 4.0 1.2 1.000 4.800
Column Type C1
C1 & C2 2.0 1.2 2.195 5.270
For Perapet 4.0 1.2 1.000 4.800
6.80 First Floor Beam
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 0.940 7.610
Grid (C1-B1 & C2-B2 2.0 2.7 0.940 5.080

6.90 Slab
Ground Floor
Grid D1-A4 1.0 8.61 5.380 46.320
Exit Door 1.0 2.10 1.05 2.210
Slope 2.0 4.20 0.60 5.040

Deduction
Statue Area (1.0) 4.05 2.700 (10.940)

Entrance
Flat 1.0 4.80 2.250 10.800
Slope 2.0 9.30 0.600 11.160

Roof Slab
Side 1 18.300 0.725 13.270

7.00 Staircase
Staircase 1
Waist Slab 1.0 8.50 1.050 8.930
Steps 20.0 0.18 1.050 3.780
Beam for Support 3.0 1.00 0.94 2.820
Z-Beam 1.00 8.50 0.69 5.870

7.01 Lintel Beam


Ground Floor
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 2.000 0.150 4.860 Both Side taken
Grid (D1-A1 & D3-A3) 2.0 4.8 2.000 0.150 2.880 Both Side taken
Door/Window Top 1.0 9.0 0.230 2.070

First Floor
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 2.000 0.150 2.430 Both Side taken
Grid (C1-B1 & C2-B2 2.0 2.7 2.000 0.150 1.620 Both Side taken
Door/Window Top 1.0 6.0 0.230 1.380

7.02 Sill Tie


Ground Floor
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 2.000 0.100 3.240 Both Side taken
Grid (D1-A1 & D3-A3) 2.0 4.8 2.000 0.100 1.920 Both Side taken

First Floor
Grid (B1-B2 & Grid C1-C2) 2.0 4.1 2.000 0.100 1.620 Both Side taken
Grid (C1-B1 & C2-B2 2.0 2.7 2.000 0.100 1.080 Both Side taken
Total Quantity 329.300 Sq.m.
Total Quantity of Formwork 329.300 Sq.m.
7.0 Stone Masonry Work 1:6 C/S Mortar
7.1 Sub structure Stone Masonry Work 1:6 C/S Mortar

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
a Foundation
Grid (A1-A3 & Grid D1-D3) 2.0 8.1 0.300 0.925 4.500
Grid (B1-B4 & Grid C1-C4) 2.0 9.3 0.300 0.925 5.160
Grid (D1-A1, D3-A3 ) 3.0 4.8 0.300 0.925 4.000
Grid C5-B5 1.0 2.7 0.300 0.925 0.750

Total Quantity 14.410 cu.m.


Total Quantity of Stone Masonry Work (1:6) 14.410 Cu.m.

8.0 Brick Work 1:4 C/S Mortar


8.1 Sub/Superstructure Brick Work 1:4 C/S Mortar

a Ground Floor Level


Grid (A1-A3 & Grid D1-D3) 2.0 8.10 0.230 3.245 12.090
Grid (D1-A1 & D4-A4) 2.0 4.80 0.230 3.245 7.160
Entrance Steps 1.00 6.300 0.53 0.150 0.500
1 6.300 0.23 0.150 0.220
Side Entrance 1.00 4.20 0.230 0.500 0.480
Ramp 1 3.450 0.23 0.175 0.140
1 1.800 0.23 0.225 0.090
Staircase 1
Middle Wall 1 1.050 0.230 1.900 0.460
Front of Side Exit
Plate form 1 3.280 1.100 0.500 1.800
Exit 1 4.000 0.230 0.500 0.460 Averege Height
Aprons (Petti ) 1.00 44.00 0.23 0.250 2.530
Manhole 4.0 0.680 0.23 0.500 0.310
1.0 0.830 0.23 0.500 0.100

Deduction
Door
MD (1.0) 1.80 0.230 2.400 (0.990)
D1 (1.0) 0.90 0.230 2.100 (0.430)
Windows
W1 (3.0) 1.50 0.230 1.500 (1.550)
W2 (2.0) 1.50 0.230 1.500 (1.040)

Total Quantity 22.330 cu.m.


Total Quantity of Brickwork in Superstructure 22.330 Cu.m.

First Floor Level


Grid (B1-B2 & Grid C1-C2) - 4.05 0.230 2.645 -
Grid (C1-B1 & C2-B2 - 2.70 0.230 2.645 -
Parapet Wall 1.0 26.70 0.230 1.000 6.140
d Entrance top 2.0 5.00 0.500 1.000 5.000
Side Entrance Top 1.0 4.20 0.500 1.000 2.100
Grid (B1-B2 & Grid C1-C2) 2.0 4.05 0.230 2.640 4.920
Grid (C1-B1 & C2-B2 2.0 2.70 0.230 2.640 3.280

Deduction
Windows
W1 (4.0) 1.50 0.230 1.500 (2.070)

Total Quantity 19.370 cu.m.


Total Quantity of Brickwork in Superstructure 19.370 Cu.m.
9.0 Plaster Works
9.1 Plaster in Brick Work Wall
a Ground Floor Level
Grid (A1-A3 & Grid D1-D3) 2.0 8.54 3.475 59.350
Grid (D1-A1 & D4-A4) 2.0 5.54 3.475 38.500

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Scorting 1 28.160 0.150 4.220
Column 4.0 4.00 3.475 55.600
Side of Internal beams 6.0 9.30 0.230 12.834 Two Sides
Side of Internal beams 6.0 4.80 0.230 6.624 Two sides
Entrance 2.0 5.100 0.230 2.346 Two sides

Deduction
Door
MD (1.0) 1.80 0.500 2.400 (2.160)
D1 (1.0) 0.90 0.500 2.400 (1.080)
Windows
W1 (3.0) 1.50 0.500 1.500 (3.375)
W2 (2.0) 1.50 0.500 1.500 (2.250)

c First Floor Level


Grid (B1-B2 & Grid C1-C2) 2.0 4.05 2.875 23.290
Grid (C1-B1 & C2-B2 2.0 2.70 2.875 15.530

Deduction
Windows
W1 (4.0) 1.50 0.500 1.500 (4.500) one side deduction only

Sub Total 204.929 Sq.m.


Total Quantity of Inside Plaster 204.929 Sq.m.
Outside The Building
Outside The Building
Ground Floor 1.0 30.00 4.050 121.500
Entrance Steps 1.00 6.30 0.300 1.890
1.00 6.30 0.150 0.950
Ramp 1 3.450 0.175 0.600
1 1.800 0.225 0.410
Staircase 1
Middle Wall 1 2.100 1.800 3.780
Front of Side Exit -
Plate form 1 3.280 0.650 2.130
Exit 1 4.000 0.400 1.600 Averege Height
Waist Slab Bottom 1 8.500 1.050 8.930
Steps 20 0.450 1.050 9.450
Trangular Part 20 0.023 0.450
Side of waist slab 1 9.500 0.125 1.190
Manhole 4.00 1.800 0.450 3.240
1.00 2.400 0.450 1.080
Column 2 1.200 3.600 8.640
Deduction
Door
MD (1) 1.800 0.500 2.400 (2.160)
D1 (1) 0.900 0.500 2.100 (0.950)
Windows
W1 (3) 1.500 0.500 1.500 (3.380)
W2 (2) 1.500 0.500 1.500 (2.250)

First Floor Level


First Floor Wall 1.0 15.90 2.600 41.340
Parapet Wall 2.0 26.70 1.000 53.400 Both Side
Top 1 25.800 0.230 5.930
Entrance top 4.000 5.00 1.500 30.000
Side Entrance top 1.000 4.20 1.500 6.300

Total Quantity 294.070 Sq.m.


Total Quantity of Out Side Plaster 294.070 Sq.m.
7.2 Cement Plaster on Celling

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Ground Floor
Hall 1.0 8.54 5.540 47.310 Sq.m.
Entrance ceiling 1.0 4.60 2.250 10.350 Sq.m.
Side Entrance 1.0 2.10 1.050 2.210 Sq.m.
Deduction (1.0) 4.05 2.700 (10.940) Sq.m.
Roof Slab
Side 1 18.300 0.725 13.270

Total Quantity 62.200 Sq.m.


Total Quantity 62.200 Sq.m.
10.0 Flooring Work
Ground Floor
10.1 Flat Brick Solling
In Side all Area 1.0 7.80 5.100 39.780 Cum
Entrance 1.0 2.70 1.200 3.240 Cum
Sub Total 43.020 Cum
Total Quantity 43.020 Cum
Total Quantity 43.020 Cum
10.2 75mm Thick PCC 1:2:4
In Side all Area 1.0 7.80 5.100 39.780 Sq.m.
Entrance 1.0 2.70 1.200 3.240
Step 2 6.300 0.600 7.560
RAMP 1.0 1.80 1.200 2.160 Sq.m.
Sub Total 52.740 Sq.m.
Total Quantity 52.740 Sq.m.
Total Quantity 52.740 Sq.m.

Supplying and laying of one layer of 500 gauge


10.3
Polythene sheet on prepared surface
All Floor Area 1.0 7.80 5.100 39.780

Sub Total 39.780 Sq.m.


Total Quantity 39.780 Sq.m.
Total Quantity 39.780 Sq.m.
10.4 50 mm Thick PCC 1:2:4
All Floor Area 1.0 7.80 5.100 39.780
Entrance 1.0 2.70 1.200 3.240
RAMP 1 1.800 1.200 2.16 Sq.m.
Side Entrance 1.0 2.10 1.050 2.210
Stair case 1 8.500 1.000 8.50

Deduction
Statue Area (1) 4.05 2.70 (10.94)

First Floor Level


Terrace 1 9.000 6.000 54.00
Deduction (1) 2.700 2.700 (7.29) Sq.m.

Sub Total 91.660 Sq.m.


Total Quantity 91.660 Sq.m.
Total Quantity 91.660 Sq.m.
Ground Floor Level
10.5 3 mm thick cement sand punning on floor
Scorting 1.0 7.80 5.100 0.150 25.800 Perimeter
Same as 50 mm PCC 1.0 91.660
Entrance 1.0 2.70 1.200 3.240
Skiirting 1.0 25.80 0.150 3.870
Side Entrance 1.0 2.10 1.050 2.210
Steps 1.00 9.30 1.100 10.230
Waist Slab Bottom 1 12.500 1.050 13.130 Include Side
Steps 20 0.150 1.050 3.150
Trangular Part 20 0.023 0.450

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Manhole 4 1.80 0.450 3.24 Wall
1 2.40 0.450 1.08 Floor
Entrance top Side 2 3.750 0.960 7.20
2 1.425 0.960 2.74
Top 1 0.600 2.700 1.62
Side Entrance 1 2.100 1.210 0.500 1.27
2 1.050 1.210 0.500 1.27

First Floor
Parapet Wall TOP 1 25.800 0.230 5.930

Sub Total 132.260 Sq.m.


Total Quantity 132.260 Sq.m.
Total Quantity 132.260 Sq.m.

First Floor Level


10.6 Ceramic Tile on Floor
All Floor Area 1.0 7.80 5.100 39.780
Skirting 1.0 25.80 0.150 3.870
Deduction
(1.0) 4.05 2.700 (10.935)

Total Quantity 32.715 Sq.m.


Total Quantity 32.715 Sq.m. Ceramic Tile on Floor

11.0 Door and Window Works


11.1 Wood Works for Door
Sal Wood Works
Door Chaukhat
MD 1 6.60 0.100 0.075 0.680
D1 1 5.10 0.100 0.075 0.530 WOODEN SOLID CORE DOUBLE SW

Sub Total 1.210 Cum.


Total Quantity of Sal wood 1.210 Cum.
Total Quantity 1.210 Cum.
11.2 38mm thick Dilla Khapa Door
MD 1.0 1.80 2.40 4.320
D1 1.0 0.90 2.10 1.890

Sub Total 6.210 Sq.m.


Total Quantity 6.210 Sq.m.
Total Quantity 6.210 Sq.m.

Supply and fixing of Aluminums casement windows


11.3
of section (54 x38 x1.1)
W1 7.0 1.50 1.500 15.750
W2 2.0 0.90 1.500 2.700

Sub Total 18.450 Sq.m.


Total Quantity 18.450 Sq.m.
Total Quantity 18.450 Sq.m.
12.0 Painting Works
12.1 Inside the Building
In Walls 204.929 Sq.m.
In Walls 62.200 Sq.m.
Total Quantity 267.129 Sq.m.
Total Painting inside 267.129 Sq.m.

12.2 Outside the Building 294.070 Sq.m.

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
Total Painting outside 294.070 Sq.m.

12.3 Enamel Paint for Door


MD 1.0 6.60 0.250 1.650
D1 1.0 5.10 0.250 1.275
12.4 38mm thick Dilla Khapa Door
MD 2.5 1.80 2.400 10.800
D1 2.5 0.90 2.100 4.730
18.455 Sq.m.
Total Quantity 18.455 Sq.m.

13.0 Railing on Staircase

Staircase 1 1.0 10.00 1.000 10.000


Ramp 2.0 2.00 1.000 4.000

Total Railing Quantity 14.000 Sq.m.


Total Quantity Railing Quantity 14.000 Sq.m.

14.0 Roofing Works


Fabrication and fixing of I.S. or B.S. Standard iron
14.1
section with one coat primer painting all complete
150 * 150 * 6 mm MS Base Plate 4.00 4.240 1.06 Kg/m
50 mm MS Black Pipe Truss
Top 4.00 2.600 47.216 4.54 Kg/m
2.00 0.660 5.993
Bottom 2.00 4.000 36.320
For Corner 4.00 3.250 59.020
32mm MS Black Pipe Truss (Chord) 2.00 4.410 24.343 2.76 Kg/m
32mm MS Black Pipe Purlin
4.800 1.00 19.200 52.992
3.750 1.00 15.000 41.400
2.200 1.00 8.800 24.288 Top Bottom
1.250 1.00 5.000 13.800
1.000 3.00 3.000 24.840
Sub Total 334.452 Kg
Total Quantity 334.452 Kg
Total Quantity IS BS 334.452 Kg

14.3 CGI Sheet for Roofing


First Floor 4.500 4.500
2 2.750 2.288 12.58
2 2.550 2.288 11.67
1 1.000 0.600 0.60

Sub Total 24.853 Sq.m.


Total Quantity 24.853 Sq.m.
Total Quantity CGI Sheet for Roofing 24.853 Sq.m.
14.4 GI Gutter
1.0 18.00 18.000
Sub Total 18.000 R.m.
Total Quantity 18.000 R.m.
Total Quantity CGI Sheet for Roofing 18.000 R.m.
14.5 GI Ridge
4.0 2.29 0.500 4.580
1.0 1.50 1.000 1.500
Sub Total 6.080 Sq.m.
Total Quantity 6.080 Sq.m.
Total Quantity CGI Sheet for Roofing 6.080 Sq.m.

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
C ELECTRICAL WORKS

Supply, installation, testing and commissioning of


factory
fabricated and factory assembled, sheet steel clad
1.0 powder coated, wall/recess mounting dust and
vermin proof double door vertical type
Distribution Boards fabricated from 16 guage
sheet .
Ground Floor 1.0 1.000

3.1 Power Point Wiring


Ground Floor 6.0 6.000
for Fan 4.0 4.000

Sub Total 10.000 Point


Total Quantity of Power Point 10.000 Point
3.2 Lighing Point Wiring
Ground Floor 13.0 13.000

Sub Total 13.000 Point


Total Quantity of Lighting Point 13.000 Point

3.3 AC/Fan Point Wiring


Ground Floor 4.0 4.000

Sub Total 4.000 Point


Total Quantity of Point 4.000 Point

4.0 Light Fixtures/Luminaires & Accessories


4.1 Dome Light 6" Brace Base
Ground Floor 8.0 8.000

Sub Total 8.000 Nos


Total Quantity of Power Point 8.000 Nos

Wall Bracket/Spot Light/Mirror Light best quality


4.2
Homedec,Decon or ISI eqv.
Ground Floor 5.0 5.000
First Floor 8.0 8.000

Sub Total 13.000 Nos


Total Quantity 13.000 Nos
4.3 Supply and Install 42" Ceiling Fan
Ground Floor 4.0 4.000

Sub Total 4.000 Nos


Total Quantity 4.000 Nos

5.0 Earthing system


Copper electrode. 1.0 1.000
Sub Total 1.000 Nos
Total Quantity of Power Point 1.000 Nos
D SANITARY WORKS

1.0 Supply and Install 110 mm UPVC Pipe


UPVC Pipe With necessaries assories 4.0 7.50 30.000

Sub Total 30.000 Rm


Total Quantity of Lighting Point 30.000 Rm
2.0 Supply and Install 150 mm HDP Pipe

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Quantities Estimate of Civil Works


Fiscal Year :- 075/76
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item
Description Nos. Length Breadth Height Quantity Unit Remarks
No.
HDP Pipe With necessaries assories 2.0 10.50 21.000
1.0 9.00 9.000
Outlet 1.0 10.00 10.000

Sub Total 40.000 Rm


Total Quantity of Lighting Point 40.000 Rm

E Others Component
Providing and Fixing Chatras Diameter= 1'-6"
1.0 4.00 4.000 No
Height= 2'-8"
2.0 Providing and Fixing Gajur (main) 1.0 1.000 No
Diameter=0'-6" Height= 2'-6"
3.0 Providing and Fixing Gajur (secondary) 1.0 1.000 No
Diameter=0'-6" Height= 1'-6"
Providing and Fixing Dharmachakra and 2 deers
Diameter= 1'-6" Height= 3'-6"
4.0 Length= 2'-6" Height= 2'-0" breath= 1'-0" 1.0 1.000 No

5.0 Providing and fixing Dragons 4.00 4.00 No


Length= 1'-6" breath= 1'-0"
F Miscelleneous Works
Providing and Fixing 9 Kg BC/ABC type Dry
1.0 Pouder Fire Extinguisher Attack fire Brand or
equivalent
Model: BC/ABC 9 KG
IS Specification:15683
Type of Fire:BC/AB&C
Extinguishing Type:Stored Pressure
Extinguishing Media
Dry Powder:(Mono Ammonium Phospate/Sodium-bi-
carbonate) IS: 4308 / IS: 14609 Pressured with N2 Gas
Ground Floor 2.00 2.000 No
Sub Total 2.000 No
Total Quantity of Fire Extinguisher 2.000 No

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Reinforcement Calculation of main Building

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item Nos.
Description Nos. (Bar) Length T. Length Unit Wt. Quantity Unit Total Weight
No. (Items)
1.0 Reinforcement Bars
1.1 TMT Reinforcement Bars

i Column Foundation
Footing Type (F1)
B4 & C4 2 18 1.100 39.600 0.888 35.16 12mmØ @150c/c Both Ways

Footing Type (F2)


A1, A3, D1 & D3 4 18 1.200 86.400 0.888 76.72

Footing Type (F3)


A2, D2 B1, B3, C1 & C3 6 22 1.450 191.400 0.888 169.96

Footing Type (F4)


B2, C2 2 22 1.450 63.800 0.888 56.65

-
- - - - - 0.888 -

14.0 Sub Total 338.490 k.g.


Total Quantity 338.490 k.g.
Total Quantity of Steel 338.49 k.g. 338.49

ii Columns
Foundation - Up to Ground Floor
C1
Main Bars- 16 mm dia 14 4 7.100 397.600 1.580 628.21
Main Bars- 12 mm dia 14 4 7.050 394.800 0.888 350.58
Stirrups- 8 mm dia
Outer 14 56 1.030 807.520 0.390 314.93
Inner 14 56 0.790 619.360 0.390 241.55

Ground Floor - First Floor


C1
Main Bars- 16 mm dia 4 4 2.500 40.000 1.580 63.20
Main Bars- 12 mm dia 4 4 2.500 40.000 0.888 35.52
Stirrups- 8 mm dia
Outer 4 25 1.030 103.000 0.390 40.17
Inner 4 25 0.790 79.000 0.390 30.81

Total Quantity 1,704.970 k.g.


Total Quantity of Steel 1,704.97 k.g. 1,704.97

iii Beams

Foundation Tie Beam


Grid (A1-A3 & Grid D1-D3) 2 9.300 12.300 24.600
Grid (B1-B4 & Grid C1-C4) 2 10.800 13.800 27.600
Grid (D1-A1, D3-A3 ) 3 6.000 8.000 24.000
Grid C5-B5 1 3.300 5.300 5.300
81.500
Main Bars- 12 mm dia 1 3 81.500 244.500 0.888 217.12
Main Bars- 12 mm dia 1 3 81.500 244.500 0.888 217.12
Stirrups- 8 mm dia
Outer 1 652 1.150 749.800 0.390 292.42

Plinth Tie Beam


Grid (A1-A3 & Grid D1-D3) 2 12.300 24.600
Grid (B1-B4 & Grid C1-C4) 2 13.800 27.600

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Reinforcement Calculation of main Building

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item Nos.
Description Nos. (Bar) Length T. Length Unit Wt. Quantity Unit Total Weight
No. (Items)
Grid (D1-A1, D3-A3 ) 3 8.000 24.000
Grid C5-B5 1 5.300 5.300
81.500
Main Bars- 12 mm dia 1 3 81.500 244.500 0.888 217.12
Main Bars- 12 mm dia 1 3 81.500 244.500 0.888 217.12
Stirrups- 8 mm dia
Outer 1 652 1.150 749.800 0.390 292.42

Ground Floor Beam


Grid (A1-A3 & Grid D1-D3) 2 12.300 24.600
Grid (B1-B4 & Grid C1-C4) 2 13.800 27.600
Grid (D1-A1, D3-A3 ) 3 8.000 24.000
Grid C5-B5 1 5.300 5.300
81.500
Main Bars- 16 mm dia 1 4 81.500 326.000 1.580 515.08
Main Bars- 12 mm dia 1 2 81.500 163.000 0.888 144.74
Stirrups- 8 mm dia
Outer 1 652 1.120 730.240 0.390 284.79

First Floor Beam


Grid (B1-B2 & Grid C1-C2) 2 4.650 6.650 13.300
Grid (C1-B1 & C2-B2 2 3.300 5.300 10.600
23.900
Main Bars- 12 mm dia 1 4 23.900 95.600 0.888 84.89
Main Bars- 12 mm dia 1 2 23.900 47.800 0.888 42.45
Stirrups- 8 mm dia
Outer 1 192 1.120 215.040 0.390 83.87

iv Sill Tie
For All Floor
Main Bars - 10mm dia 1 2 41 81.20 0.620 50.34
Stirrups - 7mm dia 1 271 0.300 81.30 0.300 24.39

v Lintel Beam
For All Floor
Main Bars - 12 mm dia 1 4 41 162.40 0.888 144.21
Stirrups- 8 mm dia 1 271 0.710 192.41 0.390 75.04

Total Quantity 2,903.120 k.g.


Total Quantity of Steel 2,903.12 k.g. 2,903.12

vi Slab
Reinforcement @ 1% of
a 1.00 9.97 782.65
Concrete Volume of Slab

Total Quantity 782.645 k.g.


Total Quantity of Steel 782.65 k.g. 782.65

vii Staircase
Reinforcement @ 1.5% of
1 1.81 213.13
Concrete Volume of Stair Slab
Beam for Suport 3.0 1.0 3.000
1.0 8.5 8.500
Z-Beam 11.500
Main Bars - 12 mm dia 1.0 6.0 11.960 71.76 0.890 63.87
Stirrups - 8mm dia 1.0 80.0 0.500 40.00 0.390 15.60

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Reinforcement Calculation of main Building

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Item Nos.
Description Nos. (Bar) Length T. Length Unit Wt. Quantity Unit Total Weight
No. (Items)
Total Quantity 292.598 k.g.
Total Quantity of Steel 292.60 k.g. 292.60

Total Steel Quantity 6,021.82 k.g. 6,021.82

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity

A GENERAL WORKS
Provide insurance for the loss of damage to works, plant, material, equipment, property
1 1.00 PS 85,234.91 85,234.91
and personnel injury or death as per specification and instruction.
Provision of laboratory tests as required and order outside the project Laboratory as per
2 1.00 PS 18,849.00 18,849.00
the specification and instructions of the Site engineers.
Provide , erect and maintain project site notice boards as per instruction of Site engineer
3 1.00 PS 17,553.60 17,553.60
and specification all complete.
As Built Drawing of project (civil, electrical, sanitation in 1:100 scale 5 sets hard copy
4 1.00 PS 40,033.40 40,033.40
including digital copy as per the instruction of the Site Engineer
Total Works of A 161,670.91

B CIVIL WORKS

1 Site clearance
Site clearance before and after completion of work including disposing the remaining
1.1 construction materials & plants & making the site in working condition all complete as 128.25 Sqm 18.51 2,373.91
per instruction of site Engineer.
2 Earthworks
Earthwork in excavation in hard/boulder mix soils in foundation including 10m hauling
2.1 distance and 1.5 m. lift all complete as per design, drawing, specification and instruction 100.85 Cum 663.32 66,895.82
of site Engineer.
Earthwork backfilling in 150 mm layers by ramming & watering at required places as per
2.2 instruction & disposing all surplus excavated materials within the site as per design, 51.86 Cum 799.25 41,445.11
drawing, specification and instruction of site Engineer all complete.

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Flat dry brick soling on flat in foundation and floor including sand filling in joints, leveling,
2.3 ramming etc. with sand as per design, drawing, specification and instruction of site 97.81 sq.m. 1,019.63 99,730.01
engineer
Earth filling in 150 mm thick layer, watering, ramming including supply of filling materials
2.4 14.00 Cum 1,093.99 15,315.86
all complete.
3 PCC Works
Plain cement Concrete (PCC) in 1:2:4 ratio for foundations, flooring and walls with
3.1 supplying of approved quality of cement and sand and crushed stone aggregate 7.04 Cum 14,865.92 104,656.08
including mixing, laying, curing etc. all complete in approval of site engineer.
4 PCC for RCC Works
Plain cement Concrete (PCC) for RCC works (1:1.5:3) for slab/lintels with supplying of
4.1 approved quality of cement and sand and crushed stone aggregate including mixing, 38.99 Cum 18,487.68 720,834.64
laying, curing etc. all complete in approval of site engineer.
5 Reinforcement Works
Supplying of Tor steel reinforcement bar of fe 415/500 grade including straightening,
5.3 cleaning, cutting, binding & fixing in position with annealed tying binding wire as per 6021.82 Kg 134.56 810,324.14
drawing, design & instruction all complete.
6 Form Works
Formwork, shuttering, centering with approved materials for Foundation works
6.1 necessary propping, scaffolding, staging, supporting inclusive of wedging and cutting 15.80 Sqm 694.62 10,975.00
holes for utilization till the support if fully unyielding nett.
Formwork, shuttering, centering with approved materials for column and beam
6.2 necessary propping, scaffolding, staging, supporting inclusive of wedging and cutting 329.30 Sqm 1,509.73 497,154.09
holes for utilization till the support if fully unyielding nett.
7 Stone Masonry Works

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Providing and laying Rubble masonry in 1:6 C/S mortar in perfect line level finish
7.1 14.41 Cum 11,927.50 171,875.28
including, racking the joints and curing the work for at least 7 days all complete.
8 Brick Works
Brickwork in cement sand mortar (1:4) in Superstructure (Ground Floor) with supplying
of approved quality first class chimney burnt bricks, in perfect line and level including
8.1 soaking bricks in water, provision for recesses, openings, toothings, packing the joints 22.33 Cum 15,646.11 349,377.64
and curing the work in all types and thickness of wall as per specification, drawing and
instruction of Site Engineer, all complete.
Brickwork in cement sand mortar (1:4) above Ground Floor level with supplying of
approved quality first class chimney burnt bricks, in perfect line and level including
8.2 soaking bricks in water, provision for recesses, openings, toothings, packing the joints 19.37 Cum 16,060.69 311,095.57
and curing the work in all types and thickness of wall as per specification, drawing and
instruction of Site Engineer, all complete.
9 Plaster Works
12.5mm thick cement sand plaster in (1:4) ratio on wall with good finish including
supplying of approved quality of cement & sand, racking the joint, Chipping the concrete
9.1 surface, wetting of surfaces & curing the work all complete including necessary single or 499.00 Sq. m 402.69 200,941.91
multiple stage scaffolding at all heights. as per the design, drawing, specification and
instruction of site engineer.
12.5mm thick cement sand plaster in (1:3) ratio on ceiling with good finish including
supplying of approved quality of cement & sand, chipping the concrete surface, wetting
9.2 the surfaces & curing the work all complete including necessary single or multiple stage 62.20 Sq. m 480.24 29,870.93
scaffolding at all heights. as per the design, drawing, specification and instruction of
site engineer.
10 Flooring Works

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Flat brick soling on flat in foundation and floor including sand filling in joints, leveling,
10.1 ramming etc. with sand as per design, drawing, specification and instruction of site 43.02 sq.m. 1,019.63 43,864.48
engineer
75mm thick P.C.C. (1:2:4) for flooring with supplying of approved quality of cement &

10.2 sand and crushed stone aggregate including mixing, laying and compacting and curing 52.74 Sqm 1,212.41 63,942.50

etc. all complete as per design, drawing, specification and instruction of site Engineer
Supplying and laying of one layer of 500 gauge Polythene sheet on prepared surface
10.3 39.78 Sqm 153.75 6,116.18

50 mm thick (1:2:4) concrete screeding work with water proof compound including
10.4 mixing laying and rubbing with steel trowel to a hard, smooth and shining surface and 91.66 Sqm 891.31 81,697.47
curing all complete.
Floor Finishing Works
Providing and Laying 3 mm thick cement sand punning on floor, skriting, dado etc.,
including mixing laying and rubbing with steel trowel to a hard, smooth and shining
10.5 132.26 sq.m. 293.80 38,857.99
surface and curing all complete.as per specification, drawing and instruction of Site
Engineer.
Providing and laying 8 mm thick glazed/nonglazed ceramic tiles (Spartek, Kajaria, or
approved equivalent) of approved shade, size and pattern on Skirting, perapet wall top
and floor in perfect line and level on 12.5 mm thick base cement sand mortar (1:4) and
10.6 32.72 Sq.m 3,113.43 101,855.86
jointed with cement slurry mixed with pigment to match the shade of the tile including
adhesive chemical all complete as per specification, drawing and instruction of Site
Engineer.
11 Door / Windows

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Suppling and fixing Salwood chaukhat frame works for doors & windows as approved
11.1 by site engineer , the timber shall be matured, seasoned free from wraps. Knots holes 1.21 Cum 301,732.63 365,096.48
and other defects all complete.
Making and fitting, fixing sal wood Panelled door shutter with 38 mm thick sal wood
11.2 6.21 Sqm 15,511.76 96,328.03
frame including all necessary hardware fitting all complete.
Supply and fixing of Aluminium sliding windows of section (88 x38 x1.1) all complete.as
11.3 18.45 sq.m. 6,548.06 120,811.71
per specification, drawing and instruction of Site Engineer.
12 Painting Works
Providing and Coloring with two coat distemper paint with one coat primer to give
12.1 uniform coloring after rendering the surface all complete. As per instruction of site 267.13 Sqm 164.35 43,902.65
Engineer
Providing and applying two coats of weather proof exterior emulsion paint of approved
brand and color on the external facade with one coat of primer including preparation of
12.2 surface through cleaning as per specification and making good all small holes of nails, 294.07 Sq.m. 334.73 98,434.05
open joints and minor defects of every kind after application of primer coat as per
specification and instruction of Site Engineer.
2 coats of ready made enamel paint of approved colour over 1 coats of primer Painting
12.3 18.46 Sqm 343.48 6,338.92
over properly sanded wooden surface all complete for door
13 Railing Works
Making and fitting fixing of stainless steel pipe railing with 38mm.dia.stainless steel pipe
handrail 2 row 25mm.dia.stainless steel pipe in between handrail and floor and
13.1 14.00 Sq.m. 3,342.92 46,800.91
38mm.dia.stainless steel pipe for vertical post @ 2m. c/c including welding , cutt all
complete.as per specification, drawing and instruction of Site Engineer.
14 Roofing Works

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Fabrication and fixing of I.S. or B.S. Standard iron section with one coat primer painting
14.1 334.45 kg 173.06 57,880.26
all complete
Supplying of 0.50mm color CGI sheet roofing including fixing in proper shape & size with
14.2 all necessary rails, screws, bolts & nuts washers, J & L hocks etc. as per drawing & 24.85 Sq.m 11,507.40 285,991.11
instruction all complete.
Supplying of 0.50mm Color GI plain sheet for gutter on roofing including fixing in proper
14.3 shape & size with all necessary rails, screws, bolts & nuts washers, J & L hocks etc. as 18.00 R.m 1,753.29 31,559.22
per drawing & instruction all complete.
Supplying of 0.50mm color GI plain sheet for ridge cover on roofing including fixing in
14.4 proper shape & size with all necessary rails, screws, bolts & nuts washers, J & L hocks 6.08 Sq.m. 1,518.83 9,234.49
etc. as per drawing & instruction all complete.
Total Works of B 4,931,578.29

C ELECTRICAL WORKS
1 DISTRIBUTION BOARDS

1.1 DISTRIBUTION BOARDS (Breaker make Schneider , L& T or Equivalent) 1.00 Set 27,600.00 27,600.00

Supply, installation, testing and commissioning of factory


fabricated and factory assembled, sheet steel clad powder coated, wall/recess mounting
dust and vermin proof double door vertical type Distribution Boards fabricated from
16 guage sheet .
20 Ways SPN DB for Ground Floor
Incoming
1 No 32 A P MCB 10 kA
1 No. 25 A DP MCB
Outgoings
14 No 6/16 A SP MCB

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Invertor Back Up
2 Power Cables,End Termination, Raceways
Power Cables(Pioneer, Mahalaxmi, Trishakti make)

Supply unloading, storing, handling, laying, testing &


commissioning of the 1100 Volts PVC/XLPE insulated PVC sheathed/ XLPE cable in
indoor trenches/ Indoor & outdoor cables tray/ cable rack/ clamps iron supports including
0.00 rm 375 -
suitable size of PVC conduits with required accessories as per specifications, inclusive
of all clamps/ saddles/ screws/ cables identification tages (made of GSS sheets) etc. as
required, but exclusive of supply & fixing of cable trays.

2.1 3 core6 sq.mm PVC insulated copper unarmoured Cable for DB main.

Point Wiring( Switch socket make : Schneider or equivalent, Wire make: Pioneer,
3 10.00 points 2,500.00 25,000.00
Mahalaxmi, Trishakti make)
3.1 6/16 A twin Power point wiring
Supplying, wiring, testing and commissioning and putting into
operation for 6/16 A and 13 A power point using 2 x 4 sq mm
+ 1 x 2.5 Sq mm stranded copper conductor, 1100 volts grade, PVC insulated wires
drawn through HDP conduit, cable sleeve/support but including specified dia pipes
concealed in wall and floor/false ceiling including all fixing and connecting materials. The
rate for point wiring shall include the circuit wiring from deginated Distribution Board
(DB) up to the first power point then the looping between sockets. The cost shall be
including modular formation twin switch sockets and their flushing GI box , cutting and
filling chases for recessed pipes as deemed as per drawing and lay out plan all
complete.(Average Length=12 m)
3.2 Light point Wiring 13.00 points 2,250.00 29,250.00

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity

Supplying, wiring, testing and commissioning and putting into


operation for one way and two way light point wiring using 2 x 2.5 sq mm + 1 x1.5 Sq
mm stranded copper conductor, 1100 volts grade, PVC insulated wires drawn through
HDP conduit, cable sleeve/support but including specified dia pipes concealed in wall
and floor including all fixing and connecting materials. The rate for point wiring shall
include the circuit wiring from deginated Distribution Board (DB) up to the first power
point then the looping between sockets. The cost shall be including modular formation
switch , and their flushing GI box and GI fish wire, cutting and filling chases for
recessed pipes as deemed as per drawing and lay out plan all complete.(Average
Length 8 m)
3.3 1 Ton Single Split AC/Water heater Point Wiring 4.00 points 2,055.12 8,220.48

Supplying, wiring, testing and commissioning and putting into


operation of 1/Ton single AC /WH Point wiring as a desiginated circut from specified AC
DB with 2 x 4 + 1 x 2.5 sqmm multi stranded PVC insulated copper cable in cluding 20
mm dia HDP conduit.The cost shall be including modular formation industrial socket
sockets/top and their flushing GI box but including GI fish wire, cutting and filling chases
for recessed pipes as deemed as per drawing and lay out plan all complete.

4 Light Fixtures/Luminaires & Accessories


Supply, storing, assembling, installation, testing and
commissioning of wall/ceiling, surface/recessed, suspended types LED lighting fixtures
including LED Driver all fixing and connecting materials all complete. (Make - Wipro,
Philips)
9 W LED CIRCULAR Dome Light having
4.1 CRI>80,Efficiency>85%, Temperature Range 3000-4000K and die-cast aluminium 8.00 Nos 1,085.02 8,680.16
housing with white powder coated finish.
4.2 15 watt LED wall decorative Light complete set 13.00 Nos 1,085.02 14,105.26
4.3 Supply and Install 42" Ceiling Fan 4.00 4.00 4,815.05 19,260.20

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity

5 Earthing system
EARTHING SYSTEMS
Supply, installation, testing and commissioning of following
types of Maintenance Free compound earthing stations by means of 2 meter long, 50
mm dia intergrated with 100x32x6 mm terminals filled with earth enhancing coumpound
in required quantity all complete with 300 x300 x450 mm masonry enclosure with
pre cast cover. All earthing arrangements must comply with IS–3043.The resistivity
should be below 3 ohm.
5.1 Copper electrode. 1.00 No 28000 28,000.00
Total Works of C 160,116.10

D SANITARY WORKS

Supply and Install 110 mm UPVC Rainwater down pipe including Screen, Inlet and all
1 30.00 Rm 419.78 12,593.52
required fittings & accessories all complete as per engineer instruction
Supply and Install 150 mm HDP Pipe 4kgf. including required all accessories all
2 40.00 Rm 1,102.49 44,099.60
complete as per engineer instruction

Total Works of D 56,693.12

E Others Component

Providing and Fixing Chatras (placed on corners of parapets. Made up of Fibre


1 4.00 Nos. 35,000.00 140,000.00
moulding.) Diameter= 1'-6" Height= 2'-8"
Providing and Fixing Gajur (main) Placed on top of main sloped roof
2 1.00 Nos. 40,000.00 40,000.00
Diameter=0'-6" Height= 2'-6" Made up of Fibre moulding
Providing and Fixing Gajur (secondary) Placed on top of main sloped roof of secondary
3 1.00 Nos. 35,000.00 35,000.00
entrance . Diameter=0'-6" Height= 1'-6" Made up of Fibre moulding
Prepared By: Checked By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Abstract of Quantity of Main Gumba


Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
Spec./ Total
S. N. Description Unit Rate/ Unit Total Amount
Ref Quantity
Providing and Fixing Dharmachakra and 2 deers (Placed above the entry porch. Made
up of concrete moulding.) Two nos of deers placed above the entry porch. Made up of
4 Fibre moulding. Diameter= 1'-6" Height= 3'-6" Length= 2'-6" Height= 2'-0" breath= 1'-0" 1.00 Nos. 50,000.00 50,000.00

Providing and fixing Dragons Placed on corners of pagodas. Made of metal moulding
5 4.00 Nos. 10,000.00 40,000.00
Length= 1'-6" breath= 1'-0" Made up of Fibre moulding
Total Works of E 305,000.00

F Miscelleneous Works
Providing and Fixing 9 Kg BC/ABC type Dry Pouder Fire Extinguisher Attack fire Brand
1 2.00 Nos. 9,775.00 19,550.00
or equivalent
Type of Fire:BC/AB&C
Extinguishing Type:Stored Pressure
Extinguishing Media
Dry Powder:(Mono Ammonium Phospate/Sodium-bi-carbonate) IS: 4308 / IS: 14609 Pressured
with N2 Gas
Total Works of F 19,550.00

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)

Insurance premium
1 Insurance premium for the work, plant and materials damage for contract work for all risk including Riot,Strike,
Damage,Malicious damage and Terrorism for contract work for project period 12 months + 1 year Maintenance period.
Insurance with value (NRs. Rs. 3.03 per thousand Rs 15,658.85
do for Terrorism Rs. 1.49 per thousand Rs 7,700.23
Premium Rs 23,359.08
for stamp duty Rs 10.00
Premium with stamp duty Rs 23,369.08
Total Amount without VAT Rs 23,369.08

2 Insurance premium for the insurance of owner and consultant staff (named) Rs. 10,00,000.00 per person for 3 persons
with unlimited number of occurances per annum
Personnel accident of 10,00,000.00 for 20 Rs.2.00 per thousand Rs 6,000.00
Do for Terrorism Rs.0.50 per thousand Rs 1,500.00
Premium Rs 7,500.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 7,510.00
Total Amount without VAT Rs 7,510.00
Total Amount without VAT Rs 23,155.83

3 Insurance Premium for construction equipments and machines with value of Rs.20,00,000.00 for 12 months

Insurance premium of Rs. 20,00,000.00 Rs.2.03 per thousand Rs 4060.00


Do for Terrorism Rs.1.49 per thousand Rs 2980.00
Premium Rs 7040.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 7050.00
Total Amount without VAT Rs 7050.00

4 Insurance Premium for third party liability personal only per person Rs.2,00,000.00 for 3 persons for 12months

P.A. of third party 3 person=20,00,000.00 Rs. 3.03 per thousand Rs 6060.00


Do for Terrorism Rs. 1.49 per thousand Rs 2980.00
Premium Rs 9040.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 9050.00
Total Amount without VAT Rs 9050.00

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
5 Insurance Premium for Contractor's Workers(Un named) per person only Rs.2,00,000.00 for 25 persons for 12months

P.A. of third party 25 person=2,00,000.00 Rs. 3.03 per thousand Rs 15150.00


Do for Terrorism Rs. 1.49 per thousand Rs 7450.00
Premium Rs 22600.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 22610.00
Total Amount without VAT Rs 22,610.00

Grand Total 85,234.91

Prepared By: Checked By: Approved By:


sk including Riot,Strike,
hs + 1 year Maintenance period.

Per Annum

00.00 per person for 3 persons

Per Annum
Per period

00.00 for 12 months

3 persons for 12months

Prepared By: Checked By: Approved By:


00 for 25 persons for 12months

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal

Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)

ABSTRACT OF COST FOR TEST


Works- Calculation for Material Lab Test .

S.N Description Unit Quantity Rate Amount Remarks


1 Concret Test
a Cubes or Cylinder crushing nos 3.00 150.00 450.00
2 Brick Test
a Brick Crushing Test nos 3.00 100.00 300.00
b Brick water absorption Test nos 3.00 100.00 300.00
c Brick Test nos 3.00 1400.00 4200.00
3 Aggregate Test
a Aggregate Crushing Value Test nos 3.00 489.00 1467.00
b Aggregate Impact Value Test nos 3.00 350.00 1050.00
4 Sieve Analyais
a Sieve Analyais(Wet) nos 3.00 844.00 2532.00
b Sieve Analyais(Dry) nos 3.00 450.00 1350.00
5 U.T.M.Tensile Strength Test
a 8mm ø nos 1.00 1200.00 1200.00
b 10mm ø nos 1.00 1200.00 1200.00
c 12mm ø nos 1.00 1200.00 1200.00
d 16mm ø nos 1.00 1200.00 1200.00
e 20mm ø nos
f 25mm ø nos
6 Cement Test
a Cement mortar crushing test nos 1.00 1200.00 1200.00
b Initial setting and final setting nos 1.00 1200.00 1200.00

Total = 18849.00

Material Lab Test


Materials lab test Frequency of test No of test
1 Cement Test 420 Bags 6 as per source
2 Concrete cube 130 times 3,6
3 Sand source 3 as per source
4 Aggregate source 3 as per source
5 Reinforcement bar 3 times 3 as per source
6 Stone source 3 as per source
7 Brick Test source 52 per 20m3
Total

Prepared By: Checked By: Approved By:


Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
Project: Preparation of Design, Drawings, Estimate and Specifications for Monasteries Type Design
Site: Nepal (for 600 Sqft Plinth Area SS)
F/Y:- 2075/2076
ABSTRACT OF COST
Works- Calculation for As built drawing, Project Description Board, Performance bond commission .
As Built Drawing
S No Position Mandays Daily rate Amount Remarks
3 Civil Engineer / Architect Engineer 10.00 1016.67 10,166.70
5 Electrical Engineer 10.00 1016.67 10,166.70
6 Helper/Camp worker 10.00 470.00 4,700.00
7 Travel Allowance Lumpsump 10,000.00
8 Logistics Lumpsump 5,000.00
Total 40,033.40

For Project Description Board Remarks


As per District
Sign Board(8'×6' ) 15264.00 Rate
15% contractor overhead 2289.60
Total (Rs.) 17553.60

Prepared By: Checked By: Approved By:


Prepared By: Checked By: Approved By:
#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
1 Foundation Footing
F1 4.00 10.00 16.00 1.40 56.00 1.58 88.48 ###
4.00 10.00 16.00 1.40 56.00 1.58 88.48 ###
F2 4.00 14.00 16.00 2.00 112.00 1.58 176.96 ###
4.00 14.00 16.00 2.00 112.00 1.58 176.96 ###
F3 4.00 15.00 16.00 2.20 132.00 1.58 208.56 ###
4.00 15.00 16.00 2.20 132.00 1.58 208.56 ###
F 4.00 8.00 12.00 1.20 38.40 0.89 34.18 ###
4.00 8.00 12.00 1.20 38.40 0.89 34.18 ###
Total Reinforcement in Foundation Footing 1016.35 Kg
2 Foundation column
Foundation
C1 4.00 4.00 12.00 1.70 0.72 38.72 0.89 34.46
4.00 4.00 16.00 1.70 0.96 42.56 1.58 67.24
C2 4.00 4.00 16.00 1.70 0.96 42.56 1.58 67.24
4.00 4.00 16.00 1.70 0.96 42.56 1.58 67.24
C3 4.00 4.00 20.00 1.70 1.20 46.40 2.47 114.61
4.00 4.00 16.00 1.70 0.96 42.56 1.58 67.24
C 4.00 4.00 12.00 1.70 0.72 38.72 0.89 34.46
4.00 4.00 12.00 1.70 0.72 38.72 0.89 34.46
Sub-Total 486.96
Strirrups
C1 external 4.00 17.00 8.00 0.98 0.00 66.64 0.39 25.99
Internal 4.00 17.00 8.00 0.72 0.00 48.96 0.39 19.09
C2 external 4.00 17.00 8.00 0.98 0.00 66.64 0.39 25.99
Internal 4.00 17.00 8.00 0.72 0.00 48.96 0.39 19.09
C3 external 4.00 17.00 8.00 0.98 0.00 66.64 0.39 25.99
Internal 4.00 17.00 8.00 0.72 0.00 48.96 0.39 19.09
C, external 4.00 17.00 8.00 0.98 0.00 66.64 0.39 25.99
Internal 4.00 17.00 8.00 0.72 0.00 48.96 0.39 19.09
Sub-Total 180.33
Total Reinforcement in Foundation Cloumn 667.30 Kg
3 Superstructure Column
Ground Floor
C1 4.00 4.00 12.00 2.75 0.72 55.52 0.89 49.41
4.00 4.00 16.00 2.75 0.96 59.36 1.58 93.79
C2 4.00 4.00 16.00 2.75 0.96 59.36 1.58 93.79
4.00 4.00 16.00 2.75 0.96 59.36 1.58 93.79
C3 4.00 4.00 20.00 2.75 1.20 63.20 2.47 156.10
4.00 4.00 16.00 2.75 0.96 59.36 1.58 93.79
C 4.00 4.00 12.00 2.92 0.72 58.24 0.89 51.83
2.00 4.00 12.00 2.92 0.72 29.12 0.89 25.92
Sub-Total 658.42 Kg
Strirrups
C1 external 4.00 28.00 8.00 0.98 0.00 109.76 0.39 42.81
Internal 4.00 28.00 8.00 0.72 0.00 80.64 0.39 31.45
C2 external 4.00 28.00 8.00 0.98 0.00 109.76 0.39 42.81
Internal 4.00 28.00 8.00 0.72 0.00 80.64 0.39 31.45
C3 external 4.00 28.00 8.00 0.98 0.00 109.76 0.39 42.81
Internal 4.00 28.00 8.00 0.72 0.00 80.64 0.39 31.45
C, external 4.00 30.00 8.00 0.98 0.00 117.60 0.39 45.86
Internal 2.00 30.00 8.00 0.72 0.00 43.20 0.39 16.85
Sub-Total 285.48 Kg
First Floor
C1 4.00 4.00 12.00 2.63 0.72 53.60 0.89 47.70
4.00 4.00 12.00 2.63 0.72 53.60 0.89 47.70
C2 4.00 4.00 16.00 2.63 0.96 57.44 1.58 90.76

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
4.00 4.00 12.00 2.63 0.72 53.60 0.89 47.70
C3 4.00 4.00 16.00 2.63 0.96 57.44 1.58 90.76
4.00 4.00 16.00 2.63 0.96 57.44 1.58 90.76
Sub-Total 415.38 Kg
Strirrups
C1 external 4.00 27.00 8.00 0.98 0.00 105.84 0.39 41.28
Internal 4.00 27.00 8.00 0.72 0.00 77.76 0.39 30.33
C2 external 4.00 27.00 8.00 0.98 0.00 105.84 0.39 41.28
Internal 4.00 27.00 8.00 0.72 0.00 77.76 0.39 30.33
C3 external 4.00 27.00 8.00 0.98 0.00 105.84 0.39 41.28
Internal 4.00 27.00 8.00 0.72 0.00 77.76 0.39 30.33
Sub-Total 214.81 Kg
Second floor
C2 4.00 4.00 16.00 2.63 0.96 57.44 1.58 90.76
4.00 4.00 12.00 2.86 0.72 57.28 0.89 50.98
C3 4.00 4.00 16.00 2.86 0.96 61.12 1.58 96.57
4.00 4.00 16.00 2.86 0.96 61.12 1.58 96.57
Sub-Total 334.87 Kg
Strirrups
C2 external 4.00 27.00 8.00 0.98 0.00 105.84 0.39 41.28
Internal 4.00 29.00 8.00 0.72 0.00 83.52 0.39 32.57
C3 external 4.00 29.00 8.00 0.98 0.00 113.68 0.39 44.34
Internal 4.00 29.00 8.00 0.72 0.00 83.52 0.39 32.57
Sub-Total 150.76 Kg
Total Reinforcement in Super structure Cloumn 2059.71 Kg
4 Ground Floor
i Foundation Beam
Lower Tie Beam (LTB) ###
Grid A-A 1.00 6.00 12.00 13.60 0.72 85.89 0.89 76.44
Grid B-B 1.00 6.00 12.00 13.60 0.72 85.89 0.89 76.44
Grid C-C 1.00 6.00 12.00 3.70 0.72 26.49 0.89 23.58
Grid 1-1 1.00 6.00 12.00 4.90 0.72 33.69 0.89 29.98
Grid 2-2 1.00 6.00 12.00 4.90 0.72 33.69 0.89 29.98
Grid 3-3 1.00 6.00 12.00 8.40 0.72 54.69 0.89 48.67
Grid 4-4 1.00 6.00 12.00 8.40 0.72 54.69 0.89 48.67
Grid 5-5 1.00 6.00 12.00 4.90 0.72 33.69 0.89 29.98
Cantilever Beam 1.00 6.00 12.00 5.39 0.72 36.66 0.89 32.63
Sub-Total 396.39 Kg
Tie Beam (UTB)
Grid A-A 1.00 4.00 16.00 13.60 0.96 58.22 1.58 91.99
1.00 2.00 12.00 13.60 0.72 28.63 0.89 25.48
Grid B-B 1.00 4.00 16.00 13.60 0.96 58.22 1.58 91.99
1.00 2.00 12.00 13.60 0.72 28.63 0.89 25.48
Grid C-C 1.00 4.00 16.00 3.70 0.96 18.62 1.58 29.42
1.00 2.00 12.00 3.70 0.72 8.83 0.89 7.86
Grid 1-1 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00
1.00 2.00 12.00 4.90 0.72 11.23 0.89 9.99
Grid 2-2 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00
1.00 2.00 12.00 4.90 0.72 11.23 0.89 9.99
Grid 3-3 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 2.00 12.00 8.40 0.72 18.23 0.89 16.22
Grid 4-4 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 2.00 12.00 8.40 0.72 18.23 0.89 16.22
Grid 5-5 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00
1.00 2.00 12.00 4.90 0.72 11.23 0.89 9.99
Cantilever beam 1.00 4.00 16.00 5.39 0.96 25.40 1.58 40.13
1.00 2.00 12.00 5.39 0.72 12.22 0.89 10.88

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Sub-Total 614.90 Kg
Strirups
Lower Tie Beam (LTB)
Grid A-A 1.00 110.00 8.00 0.87 0.00 95.70 0.39 37.32 ###
Grid B-B 1.00 110.00 8.00 0.87 0.00 95.70 0.39 37.32 ###
Grid C-C 1.00 28.00 8.00 0.87 0.00 24.36 0.39 9.50 ###
Grid 1-1 1.00 38.00 8.00 0.87 0.00 33.06 0.39 12.89 ###
Grid 2-2 1.00 38.00 8.00 0.87 0.00 33.06 0.39 12.89 ###
Grid 3-3 1.00 67.00 8.00 0.87 0.00 58.29 0.39 22.73 ###
Grid 4-4 1.00 67.00 8.00 0.87 0.00 58.29 0.39 22.73 ###
Grid 5-5 1.00 38.00 8.00 0.87 0.00 33.06 0.39 12.89 ###
Cantilever beam 1.00 45.00 8.00 0.87 0.00 39.15 0.39 15.27 ###
Tie Beam (UTB)
Grid A-A 1.00 110.00 8.00 1.06 0.00 116.60 0.39 45.47 ###
Grid B-B 1.00 110.00 8.00 1.06 0.00 116.60 0.39 45.47 ###
Grid C-C 1.00 28.00 8.00 1.06 0.00 29.68 0.39 11.58 ###
Grid 1-1 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 2-2 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 3-3 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 4-4 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 5-5 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Cantilever beam 1.00 45.00 8.00 1.06 0.00 47.70 0.39 18.60 ###
Sub-Total 407.21 Kg
Total Beam for Foundation 1418.50 Kg
ii Sill Tie ###
Grid A-A 1.00 2.00 10.00 7.400 0.00 14.80 0.62 9.18 ###
Cantilever Portion 1.00 2.00 10.00 4.460 0.00 8.92 0.62 5.53 ###
Grid B-B 1.00 2.00 10.00 7.400 0.00 14.80 0.62 9.18 ###
Grid C-C 1.00 2.00 10.00 2.700 0.00 5.40 0.62 3.35 ###
Grid 1-1 1.00 2.00 10.00 3.900 0.00 7.80 0.62 4.84 ###
Grid 3-3 1.00 2.00 10.00 5.450 0.00 10.90 0.62 6.76 ###
Grid 4-4 1.00 2.00 10.00 5.900 0.00 11.80 0.62 7.32 ###
Grid B3-B4 1.00 1.00 10.00 2.700 0.00 2.70 0.62 1.67
Toilet wall 1.00 1.00 10.00 2.980 0.00 2.98 0.62 1.85
Sub-Total 49.66 Kg
iii Lintel Tie
Grid A-A 1.00 2.00 10.00 7.400 0.00 14.80 0.62 9.18 ###
Cantilever Portion 1.00 2.00 10.00 4.460 0.00 8.92 0.62 5.53 ###
Grid B-B 1.00 2.00 10.00 7.400 0.00 14.80 0.62 9.18 ###
Grid C-C 1.00 2.00 10.00 2.700 0.00 5.40 0.62 3.35 ###
Grid 1-1 1.00 2.00 10.00 3.900 0.00 7.80 0.62 4.84 ###
Grid 3-3 1.00 2.00 10.00 5.450 0.00 10.90 0.62 6.76 ###
Grid 4-4 1.00 2.00 10.00 7.100 0.00 14.20 0.62 8.80 ###
Grid B3-B4 1.00 1.00 10.00 2.700 0.00 2.70 0.62 1.67
Toilet wall 1.00 1.00 10.00 3.730 0.00 3.73 0.62 2.31
Sub-Total 51.61 Kg
iv Slab Beam
Grid A-A 1.00 4.00 16.00 13.60 0.96 58.22 1.58 91.99
1.00 1.00 12.00 13.60 0.72 14.32 0.89 12.74
Grid B-B 1.00 4.00 16.00 13.60 0.96 58.22 1.58 91.99
1.00 1.00 12.00 13.60 0.72 14.32 0.89 12.74
Grid C-C 1.00 4.00 16.00 3.70 0.96 18.62 1.58 29.42
1.00 1.00 12.00 3.70 0.72 4.42 0.89 3.93
Grid 1-1 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00 ###
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00 ###
Grid 2-2 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Grid 3-3 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11
Grid 4-4 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11 ###
Grid 5-5 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00 ###
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00
Cantilever beam 1.00 4.00 16.00 5.39 0.96 25.40 1.58 40.13
1.00 1.00 12.00 5.39 0.72 6.11 0.89 5.44 ###
Extra Bar
Grid A-A 1.00 2.00 12.00 8.58 0.00 17.16 0.89 15.27 ###
Grid B-B 1.00 2.00 12.00 8.58 0.00 17.16 0.89 15.27
Grid C-C 1.00 2.00 12.00 1.95 0.00 3.90 0.89 3.47
Grid 1-1 1.00 2.00 12.00 2.82 0.00 5.64 0.89 5.02
Grid 2-2 1.00 2.00 12.00 3.12 0.00 6.24 0.89 5.55
Grid 3-3 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Grid 4-4 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Grid 5-5 1.00 2.00 12.00 3.12 0.00 6.24 0.89 5.55
Sub-Total 619.70 Kg
v Strirups
Slab Beam
Grid A-A 1.00 110.00 8.00 1.06 0.00 116.60 0.39 45.47 ###
Grid B-B 1.00 110.00 8.00 1.06 0.00 116.60 0.39 45.47 ###
Grid C-C 1.00 28.00 8.00 1.06 0.00 29.68 0.39 11.58 ###
Grid 1-1 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 2-2 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 3-3 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 4-4 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 5-5 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Cantilever beam 1.00 45.00 8.00 1.06 0.00 47.70 0.39 18.60 ###
Sill (C- hook) ###
Grid A-A 1.00 50.00 8.00 0.350 0.00 17.50 0.39 6.83 ###
Cantilever Portion 1.00 30.00 8.00 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 50.00 8.00 0.350 0.00 17.50 0.39 6.83 ###
Grid C-C 1.00 18.00 8.00 0.350 0.00 6.30 0.39 2.46 ###
Grid 1-1 1.00 26.00 8.00 0.350 0.00 9.10 0.39 3.55 ###
Grid 3-3 1.00 37.00 8.00 0.350 0.00 12.95 0.39 5.05 ###
Grid 4-4 1.00 40.00 8.00 0.350 0.00 14.00 0.39 5.46 ###
Grid B3-B4 1.00 18.00 8.00 0.350 0.00 6.30 0.39 2.46
Toilet wall 1.00 20.00 8.00 0.350 0.00 7.00 0.39 2.73
Lintel Tie
Grid A-A 1.00 50.00 8.00 0.350 0.00 17.50 0.39 6.83 ###
Cantilever Portion 1.00 30.00 8.00 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 50.00 8.00 0.350 0.00 17.50 0.39 6.83 ###
Grid C-C 1.00 18.00 8.00 0.350 0.00 6.30 0.39 2.46 ###
Grid 1-1 1.00 26.00 8.00 0.350 0.00 9.10 0.39 3.55 ###
Grid 3-3 1.00 37.00 8.00 0.350 0.00 12.95 0.39 5.05 ###
Grid 4-4 1.00 48.00 8.00 0.350 0.00 16.80 0.39 6.55 ###
Grid B3-B4 1.00 18.00 8.00 0.350 0.00 6.30 0.39 2.46
Toilet wall 1.00 25.00 8.00 0.350 0.00 8.75 0.39 3.41
Sub-Total 304.32 Kg
Total Reinforcement in Ground Floor Beam 1025.29 Kg
vi Slab
Main Bar
Grid A1-A3-B3-B1
IN X DIRECTION
Bottom Bar 1.00 15.00 8.00 2.64 0.00 39.60 0.39 15.44
Bottom Bar 1.00 15.00 8.00 4.50 0.00 67.50 0.39 26.33

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Bottom Bar 1.00 15.00 8.00 3.57 0.00 53.55 0.39 20.88
Bottom Bar 1.00 15.00 8.00 2.94 0.00 44.10 0.39 17.20

Bottom Bar 1.00 14.00 8.00 4.84 0.00 67.76 0.39 26.43
Bottom Bar 1.00 14.00 8.00 5.67 0.00 79.31 0.39 30.93

Bottom Bar 1.00 20.00 8.00 6.20 0.00 124.00 0.39 48.36

IN Y DIRECTION
Bottom Bar 1.00 16.00 8.00 7.40 0.00 118.40 0.39 46.18
Bottom Bar 1.00 16.00 8.00 8.30 0.00 132.80 0.39 51.79

Bottom Bar 1.00 20.00 8.00 2.92 0.00 58.34 0.39 22.75
Bottom Bar 1.00 20.00 8.00 2.85 0.00 57.00 0.39 22.23

Bottom Bar 1.00 22.00 8.00 0.74 0.00 16.17 0.39 6.31
Bottom Bar 1.00 22.00 8.00 3.12 0.00 68.64 0.39 26.77

IN X DIRECTION
Top Bar 2.00 57.00 8.00 0.93 0.00 106.02 0.39 41.35

Top Bar 1.00 39.00 8.00 0.83 0.00 32.18 0.39 12.55
Top Bar 1.00 39.00 8.00 2.70 0.00 105.30 0.39 41.07
Top Bar 2.00 20.00 8.00 2.38 0.00 95.00 0.39 37.05
IN Y DIRECTION
Top Bar 1.00 31.00 8.00 0.90 0.00 27.90 0.39 10.88
Top Bar 1.00 31.00 8.00 2.70 0.00 83.70 0.39 32.64
Top Bar 1.00 31.00 8.00 1.95 0.00 60.45 0.39 23.58

Top Bar 1.00 39.00 8.00 0.75 0.00 29.25 0.39 11.41
Top Bar 1.00 25.00 8.00 1.08 0.00 27.05 0.39 10.55

Top Bar 1.00 43.00 8.00 1.69 0.00 72.46 0.39 28.26
Top Bar 1.00 43.00 8.00 0.80 0.00 34.40 0.39 13.42
Top Bar 1.00 12.00 8.00 0.90 0.00 10.80 0.39 4.21
Inclined slab
Bottom Bar 1.00 8.00 8.00 11.52 0.00 92.16 0.39 35.94
Bottom Bar 1.00 78.00 8.00 1.14 0.00 88.92 0.39 34.68
Total Reinforcement in Ground Floor Slab 699.17 Kg
5 First Floor
i Sill Tie ###
Grid A-A 1.00 2.00 10.000 7.400 0.00 14.80 0.62 9.18 ###
Cantilever Portion 1.00 2.00 10.000 4.460 0.00 8.92 0.62 5.53 ###
Grid B-B 1.00 2.00 10.000 7.400 0.00 14.80 0.62 9.18 ###
Grid C-C 1.00 2.00 10.000 2.700 0.00 5.40 0.62 3.35 ###
Grid 1-1 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid 2-2 1.00 1.00 10.000 2.900 0.00 2.90 0.62 1.80 ###
Grid 3-3 1.00 2.00 10.000 5.450 0.00 10.90 0.62 6.76 ###
Grid 4-4 1.00 2.00 10.000 6.100 0.00 12.20 0.62 7.56
Grid B3-B4 1.00 1.00 10.000 2.700 0.00 2.70 0.62 1.67
Toilet wall 1.00 1.00 10.000 2.980 0.00 2.98 0.62 1.85 ###
Account office 1.00 1.00 10.000 1.755 0.00 1.76 0.62 1.09 ###
Sub-Total 52.80 Kg
ii Lintel Tie
Ground floor
Grid A-A 1.00 2.00 10.000 7.400 0.00 14.80 0.62 9.18 ###
Cantilever Portion 1.00 2.00 10.000 4.460 0.00 8.92 0.62 5.53 ###

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Grid B-B 1.00 2.00 10.000 7.400 0.00 14.80 0.62 9.18 ###
Grid C-C 1.00 2.00 10.000 2.700 0.00 5.40 0.62 3.35 ###
Grid 1-1 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid 2-2 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid 3-3 1.00 2.00 10.000 5.450 0.00 10.90 0.62 6.76 ###
Grid 4-4 1.00 2.00 10.000 7.100 0.00 14.20 0.62 8.80
Grid B3-B4 1.00 1.00 10.000 2.700 0.00 2.70 0.62 1.67
Toilet wall 1.00 1.00 10.000 3.730 0.00 3.73 0.62 2.31 ###
Account office 1.00 1.00 10.000 2.755 0.00 2.76 0.62 1.71 ###
Sub-Total 58.16 Kg
iii Slab Beam Cantilever Portion
Grid A-A 1.00 4.00 16.00 11.70 0.96 50.62 1.58 79.98 Grid B-B
1.00 1.00 12.00 11.70 0.72 12.42 0.89 11.05 Grid C-C
Grid B-B 1.00 4.00 16.00 11.70 0.96 50.62 1.58 79.98 Grid 1-1
1.00 1.00 12.00 11.70 0.72 12.42 0.89 11.05 Grid 2-2
Grid C-C 1.00 4.00 16.00 3.70 0.96 18.62 1.58 29.42 Grid 3-3
1.00 1.00 12.00 3.70 0.72 4.42 0.89 3.93 Grid 4-4
Grid 1-1 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00 Grid B3-B4
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00 Toilet wall
Grid 2-2 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00 ount office
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00
Grid 3-3 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11
Grid 4-4 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11 ###
Cantilever beam 1.00 4.00 16.00 5.39 0.96 25.40 1.58 40.13
1.00 1.00 12.00 5.39 0.72 6.11 0.89 5.44 ###
Extra Bar
Grid A-A 1.00 2.00 12.00 7.23 0.00 14.46 0.89 12.87 ###
Grid B-B 1.00 2.00 12.00 7.23 0.00 14.46 0.89 12.87
Grid C-C 1.00 2.00 12.00 1.95 0.00 3.90 0.89 3.47
Grid 1-1 1.00 2.00 12.00 2.82 0.00 5.64 0.89 5.02
Grid 2-2 1.00 2.00 12.00 3.12 0.00 6.24 0.89 5.55
Grid 3-3 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Grid 4-4 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Sub-Total 539.94 Kg
iv Strirups
Slab Beam
Grid A-A 1.00 95.00 8.00 1.06 0.00 100.70 0.39 39.27 ###
Grid B-B 1.00 95.00 8.00 1.06 0.00 100.70 0.39 39.27 ###
Grid C-C 1.00 28.00 8.00 1.06 0.00 29.68 0.39 11.58 ###
Grid 1-1 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 2-2 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 3-3 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 4-4 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Cantilever beam 1.00 45.00 8.00 1.06 0.00 47.70 0.39 18.60 ###
Sill Tie (C- hook) ###
Grid A-A 1.00 50.00 8.000 0.350 0.00 17.50 0.39 6.83 ###
Cantilever Portion 1.00 30.00 8.000 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 50.00 8.000 0.350 0.00 17.50 0.39 6.83 ###
Grid C-C 1.00 18.00 8.000 0.350 0.00 6.30 0.39 2.46 ###
Grid 1-1 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid 2-2 1.00 20.00 8.000 0.350 0.00 7.00 0.39 2.73 ###
Grid 3-3 1.00 37.00 8.000 0.350 0.00 12.95 0.39 5.05 ###
Grid 4-4 1.00 41.00 8.000 0.350 0.00 14.35 0.39 5.60
Grid B3-B4 1.00 18.00 8.000 0.350 0.00 6.30 0.39 2.46
Toilet wall 1.00 20.00 8.000 0.350 0.00 7.00 0.39 2.73 ###

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Account office 1.00 12.00 8.000 0.350 0.00 4.20 0.39 1.64 ###
Lintel Tie
Grid A-A 1.00 50.00 8.000 0.350 0.00 17.50 0.39 6.83 ###
Cantilever Portion 1.00 30.00 8.000 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 50.00 8.000 0.350 0.00 17.50 0.39 6.83 ###
Grid C-C 1.00 18.00 8.000 0.350 0.00 6.30 0.39 2.46 ###
Grid 1-1 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid 2-2 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid 3-3 1.00 37.00 8.000 0.350 0.00 12.95 0.39 5.05 ###
Grid 4-4 1.00 48.00 8.000 0.350 0.00 16.80 0.39 6.55
Grid B3-B4 1.00 18.00 8.000 0.350 0.00 6.30 0.39 2.46
Toilet wall 1.00 25.00 8.000 0.350 0.00 8.75 0.39 3.41 ###
Account office 1.00 19.00 8.000 0.350 0.00 6.65 0.39 2.59 ###
Sub-Total 286.85 Kg
Total Reinforcement in First Floor Beam 937.75 Kg
vi Slab
Main Bar
IN X DIRECTION
Bottom Bar 1.00 17.00 8.00 2.71 0.00 46.07 0.39 17.97
Bottom Bar 1.00 17.00 8.00 6.20 0.00 105.40 0.39 41.11
Bottom Bar 1.00 17.00 8.00 4.46 0.00 75.74 0.39 29.54
Bottom Bar 1.00 17.00 8.00 4.46 0.00 75.74 0.39 29.54

Bottom Bar 1.00 16.00 8.00 4.91 0.00 78.56 0.39 30.64
Bottom Bar 1.00 16.00 8.00 6.00 0.00 96.00 0.39 37.44

IN Y DIRECTION
Bottom Bar 1.00 22.00 8.00 7.44 0.00 163.57 0.39 63.79
Bottom Bar 1.00 22.00 8.00 9.15 0.00 201.30 0.39 78.51

Bottom Bar 1.00 21.00 8.00 2.88 0.00 60.48 0.39 23.59
Bottom Bar 1.00 21.00 8.00 4.26 0.00 89.46 0.39 34.89

IN X DIRECTION
Top Bar 2.00 62.00 8.00 1.75 0.00 216.38 0.39 84.39

Top Bar 1.00 30.00 8.00 3.22 0.00 96.45 0.39 37.62
Top Bar 1.00 30.00 8.00 1.09 0.00 32.70 0.39 12.75
IN Y DIRECTION
Top Bar 1.00 43.00 8.00 1.72 0.00 73.75 0.39 28.76
Top Bar 1.00 43.00 8.00 2.70 0.00 116.10 0.39 45.28
Top Bar 1.00 43.00 8.00 1.95 0.00 83.85 0.39 32.70

Top Bar 1.00 41.00 8.00 1.02 0.00 41.62 0.39 16.23
Top Bar 1.00 41.00 8.00 1.38 0.00 56.66 0.39 22.10

Inclined slab
Bottom Bar 1.00 8.00 8.00 34.87 0.00 278.96 0.39 108.79
Bottom Bar 1.00 233.00 8.00 1.14 0.00 265.62 0.39 103.59

Total Reinforcement in First Floor Slab 879.21 Kg


6 Second Floor
i Sill Tie ###
Grid A-A 1.00 2.00 10.000 3.700 0.00 7.40 0.62 4.59 ###
Cantilever Portion 1.00 2.00 10.000 4.460 0.00 8.92 0.62 5.53 ###
Grid B-B 1.00 2.00 10.000 3.700 0.00 7.40 0.62 4.59 ###

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Grid 2-2 1.00 2.00 10.000 2.900 0.00 5.80 0.62 3.60 ###
Grid 3-3 1.00 2.00 10.000 2.900 0.00 5.80 0.62 3.60 ###
Grid 4-4 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid B3-B4 1.00 2.00 10.000 1.700 0.00 3.40 0.62 2.11 ###
Sub-Total 28.84 Kg
ii Lintel Tie
Grid A-A 1.00 2.00 10.000 3.700 0.00 7.40 0.62 4.59 ###
Cantilever Portion 1.00 2.00 10.000 4.460 0.00 8.92 0.62 5.53 ###
Grid B-B 1.00 2.00 10.000 3.700 0.00 7.40 0.62 4.59 ###
Grid 2-2 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid 3-3 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid 4-4 1.00 2.00 10.000 3.900 0.00 7.80 0.62 4.84 ###
Grid B3-B4 1.00 2.00 10.000 2.700 0.00 5.40 0.62 3.35 ###
Sub-Total 32.56 Kg
iii Slab Beam Cantilever Portion
Grid A-A 1.00 4.00 16.00 7.70 0.96 34.62 1.58 54.70 Grid B-B
1.00 1.00 12.00 7.70 0.72 8.42 0.89 7.49 Grid C-C
Grid B-B 1.00 4.00 16.00 7.70 0.96 34.62 1.58 54.70 Grid 1-1
1.00 1.00 12.00 7.70 0.72 8.42 0.89 7.49 Grid 2-2
Grid 2-2 1.00 4.00 16.00 4.90 0.96 23.42 1.58 37.00 ount office
1.00 1.00 12.00 4.90 0.72 5.62 0.89 5.00
Grid 3-3 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11
Grid 4-4 1.00 4.00 16.00 8.40 0.96 37.42 1.58 59.12
1.00 1.00 12.00 8.40 0.72 9.12 0.89 8.11 Grid A-A
Cantilever beam 1.00 4.00 16.00 5.39 0.96 25.40 1.58 40.13 ver Portion
1.00 1.00 12.00 5.39 0.72 6.11 0.89 5.44 Grid B-B
Extra Bar Grid 2-2
Grid A-A 1.00 2.00 12.00 4.50 0.00 9.00 0.89 8.01 Grid 3-3
Grid B-B 1.00 2.00 12.00 4.50 0.00 9.00 0.89 8.01 Grid 4-4
Grid 2-2 1.00 2.00 12.00 3.12 0.00 6.24 0.89 5.55
Grid 3-3 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Grid 4-4 1.00 2.00 12.00 5.82 0.00 11.64 0.89 10.36
Sub-Total 388.71 Kg
iv Strirups
Slab Beam
Grid A-A 1.00 62.00 8.00 1.06 0.00 65.72 0.39 25.63 ###
Grid B-B 1.00 62.00 8.00 1.06 0.00 65.72 0.39 25.63 ###
Grid 2-2 1.00 38.00 8.00 1.06 0.00 40.28 0.39 15.71 ###
Grid 3-3 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Grid 4-4 1.00 67.00 8.00 1.06 0.00 71.02 0.39 27.70 ###
Cantilever beam 1.00 45.00 8.00 1.06 0.00 47.70 0.39 18.60 ###

Sill Tie (C-hook) ###


Grid A-A 1.00 25.00 8.000 0.350 0.00 8.75 0.39 3.41 ###
Cantilever Portion 1.00 30.00 8.000 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 25.00 8.000 0.350 0.00 8.75 0.39 3.41 ###
Grid 2-2 1.00 20.00 8.000 0.350 0.00 7.00 0.39 2.73 ###
Grid 3-3 1.00 20.00 8.000 0.350 0.00 7.00 0.39 2.73 ###
Grid 4-4 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid B3-B4 1.00 12.00 8.000 0.350 0.00 4.20 0.39 1.64 ###
Lintel Tie
Grid A-A 1.00 25.00 8.000 0.350 0.00 8.75 0.39 3.41 ###
Cantilever Portion 1.00 30.00 8.000 0.350 0.00 10.50 0.39 4.10 ###
Grid B-B 1.00 25.00 8.000 0.350 0.00 8.75 0.39 3.41 ###
Grid 2-2 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid 3-3 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate of Steel work

#REF!

#REF!
Lap
Total L Unit
S.N Item of Work Number Nos. Dia Length length@6 Total/kg Remarks
in m Weight
0d
Grid 4-4 1.00 26.00 8.000 0.350 0.00 9.10 0.39 3.55 ###
Grid B3-B4 1.00 18.00 10.000 0.350 0.00 6.30 0.39 2.46 ###
Sub-Total 186.56 Kg
Total Reinforcement in Second Floor Beam 636.67 Kg
v Slab
IN X DIRECTION
Bottom Bar 1.00 31.00 8.00 3.70 0.00 114.61 0.39 44.70
Bottom Bar 1.00 31.00 8.00 3.70 0.00 114.61 0.39 44.70
IN Y DIRECTION
Bottom Bar 1.00 22.00 8.00 6.98 0.00 153.63 0.39 59.91
Bottom Bar 1.00 22.00 8.00 6.98 0.00 153.63 0.39 59.91
IN X DIRECTION
Top Bar 2.00 61.00 8.00 2.38 0.00 289.75 0.39 113.00
IN Y DIRECTION
Top Bar 2.00 43.00 8.00 2.32 0.00 199.09 0.39 77.65
Top Bar 1.00 43.00 8.00 2.33 0.00 100.19 0.39 39.07
Inclined slab
Bottom Bar 1.00 8.00 8.00 30.53 0.00 244.24 0.39 95.25
Bottom Bar 1.00 204.00 8.00 1.14 0.00 232.56 0.39 90.70
Total Reinforcement in Second Floor Slab 624.89 Kg
7 Staircase
Slab buttom+Waist slab top 4.00 8.00 12.00 2.53 0.00 80.96 0.89 72.05
Slab buttom+Waist slab top 4.00 17.00 10.00 1.20 0.00 81.60 0.62 50.59
Junction(R+T) 4.00 9.00 10.00 1.20 0.00 43.20 0.62 26.78

Waist slab Buttom+slab top 4.00 8.00 12.00 5.80 0.00 185.54 0.89 165.13
Waist slab Buttom+slab top 4.00 39.00 10.00 1.20 0.00 187.20 0.62 116.06

Slab buttom+Waist slab top 4.00 8.00 12.00 1.65 0.00 52.90 0.89 47.08
Slab buttom+Waist slab top 4.00 12.00 10.00 1.20 0.00 57.60 0.62 35.71

Total Reinforcement inStaircase 513.41 Kg

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate (Sanitary)

#REF!
#REF!
S. N. Description No Length Breadth Height Quantity Remarks

Supplying and Fixing Porcelain clay Indian Pattern


Comode, Porcelain clay Cistern and seat cover with
1
pipe connector all complete set.(Hindware,
Parryware, or equivalent ).

Indian pattern Comode,Seat cover with low level


flushing cistern.
Ground Floor 12.00 12.00
Total 12.00 Set

Supplying and fixing White glaze Porcelain clay


wash basin/Oval 50X40Cm with pedestal, Mixture
brackets 32mm dia. p trap, 32mm CP waste
coupling with CP chain and rubber plug,
2
15mmx450mm long c.p. pipe connector etc all
complete.(Sanitaryware:-Hindware,parryware or
equivalent).Valve:- jaquar,ark,Ess Ess or
equivalent)

Indian pattern White glazed wash basin 50X40cm


with basin mixture all complete set.
Ground Floor 10.00 10.00
Total 10.00 Set

Supplying and fixing White glaze Porcelain clay


46.5x35.5x26.5cm flat back White glazed Urinal
with sensor valve, brackets 32mm dia. p trap, 32mm
CP waste coupling with CP chain and rubber plug,
3
15mmx450mm long c.p. pipe connector etc all
complete.(Sanitaryware:-Hindware,parryware or
equivalent).Valve:- jaquar,ark,Ess Ess or
equivalent)

46.5x35.5x26.5 cm flat back White glazed Urinal all


complete set.
Ground Floor 8.00 8.00
Total 8.00 Set
68 X 30 Cm white glazed urinal Partation with all
complete set
` 7.00 7.00
Total 7.00 Set

Supplying and Fixing Pvc roof water tank With


4 cover including drain hole ,inlet outlet, over flow
etc.all complete set .Hill take, Roof top or equivalent

1000 litres PVC overhead tank 2.00 2.00 Nos.

Supplying and Fixing Electric moter Pump single or


5 three phase phase with base, nut and bolts all
complete set (Kirloskar, Compton, Servo, Sharp,)

2 HP Electric motor Pump monoblock.(crompton) 1.00 1.00


Total 1.00 Nos.
Supplying and Fixing Indian pattern C.P. valves with
6
wall flange Including c.p. nipple all complete set.
15mm CP bib cock Cock ordinary type
Ground Floor 21.00 21.00
Total 21.00 Set
C.P. 15mm dia Angle valve.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate (Sanitary)

#REF!
#REF!
S. N. Description No Length Breadth Height Quantity Remarks
Ground Floor 29.00 29.00
Total 29.00 Nos.
15 mm comode CP water spray with 1.2mt. Long
flexiable pipe.
Ground Floor 12.00 12.00
Total 12.00 Nos.
Stainless steel shower wth sliding bar and complete
set
Ground Floor 12.00 12.00
Total 12.00 Nos.
CP Wall mixture
Ground Floor 4.00 4.00
Total 4.00 Nos.
7 Valves with all complete accessories.
GM Gate valve 50 mm dia. 1.00 1.00
Total 1.00 Nos.
(G.M.) check valve 50 mm dia 1.00 1.00
Total 1.00 Nos.
Supplying and Fixing UPVC pipe all complete set as
8 per specification and instruction. (Panchakanya ,
Prince,Supreme )
75mm PVC pipe of 6 kg/cm2
Ground Floor 130.00 130.00
Total 130.00 Rm
110mm PVC pipe of 6 kg/cm2
Ground Floor 80.00 80.00
Total 80.00 Rm

Supplying and fixing PPR and GI Pipe. or


equivalent with fittings/ specials (Tees, elbows,
Unions etc) clamps(m.s plate with nut and bolt with
hexagonal screws for clamp in ceiling,wall), nails,
9 including jointing materials,installation of pipes and
specials including making holes on walls or floor
and repairing the same to its original finish,cleaning
of the system, testing and ready for operation,. all
complete set as per specification and instruction.

15 mm dia P.P.R pipe


Ground Floor 45.00 45.00
Total 45.00 RM
20 mm dia P.P.R pipe
Ground Floor 145.00 145.00
Total 145.00 RM
25 mm dia P.P.R pipe
Ground Floor 10.00 10.00
Total 10.00 RM
50 mm dia P.P.R pipe
70.00 70.00
Total 70.00 RM
Supplying and Fixing UPVC specials with O ring
rubber washer,Pvc liquid(Solvent cement), Pvc
10
cream, all complete set as per specification and
instruction. (Panchakanya,Prince,Supreme )
75 mm dia UPVC vent cowl 1.00 1.00 Nos.
75 mm dia UPVC plain/door Tee.
Ground Floor 18.00 18.00

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate (Sanitary)

#REF!
#REF!
S. N. Description No Length Breadth Height Quantity Remarks
Total 18.00 Nos.
75 mm dia UPVC 90 degree bend.
Ground Floor 7.00 7.00
Total 7.00 Nos.
75 mm dia UPVC Y bend.
Ground Floor 5.00 5.00
Total 5.00 Nos.
75 mm dia UPVC 45˚ bend.
Ground Floor 4.00 4.00
Total 4.00 Nos.
75 mm dia UPVC pipe clip
Ground Floor 110.00 110.00
Total 110.00 Nos.
110 mm dia UPVC plain /door Tee.
Ground Floor 6.00 6.00
Total 6.00 Nos.
110 mm dia UPVC 90 degree bend
Ground Floor 8.00 8.00
Total 8.00 Nos.
110 mm dia UPVC Y bend.
Ground Floor 10.00 10.00
Total 10.00 Nos.
110 mm dia UPVC 45˚ bend.
Ground Floor 8.00 8.00
Total 8.00 Nos.
110 mm dia UPVC pipe clip
Ground Floor 55.00 55.00
Total 55.00 Nos.
PVC floor trap 11x7.5 cm.
Ground Floor 18.00 18.00
Total 18.00 Nos.
Supplying and Fixing Indian pattern bathroom
11
accessories all complete set.
Modi guard bevelled float mirror 6mm thick with
stainfree 0.45x0.60m and bracket all compete set.
Ground Floor 14.00 14.00
Total 14.00 Nos.
Chrome plate type toilet paper holder.
Ground Floor 12.00 12.00
Total 12.00 Nos.
Chrome plated soap tray.
Ground Floor 12.00 12.00
Total 12.00 Nos.
CP 15mm dia x450mm long towel rod.
Ground Floor 11.00 11.00
Total 11.00 Nos.
Kitchen sink 37" long and 8"deep with sink cock all
completed set
Ground Floor 1.00 1.00
Total 1.00 Nos.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantity Estimate (Sanitary)

#REF!
#REF!
S. N. Description No Length Breadth Height Quantity Remarks

Fire pump:-20H.P.x2set or 40H.P. (Head-


70.0mtr.,Discharge-2400Lpm)Fire pump set with
5.0h.p Stainless steel verticle jockey pump,(Main
12 pump start Automatically If jockey pump pressure
drop) including control panel board,Required
Cable,Stairner for both pump,pressure
switches,pressure guage all complete set,

1.00 1.00
Total 1.00 Set

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantiy Estimate of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. Remarks
1.Wiring of light/fan & power points:
1.10 Supply of materials and wiring with PVC Insulated copper wire
in NS Approved HDP conduit without any joint in middle of the
span with necessary connecting, fixing, insulating and jointing
materials as per drawing and specification complete (wire:
Trishakti, Pioneer, Litmus)
1.1 Light/ Fan Points
{a} Light and Fan point with 2x1.5 Sq. mm from point to
switches and 2x2.5+1.1.5 as Light circuit laying from Switch to
DB NS mark cu multistrand cable Including all necessary items
i.e. bends, circular & Junction boxes etc.
point 111
{b} 2 Way light point with 3x1.5 Sq. mm from point to switches
and 2x2.5+1.1.5 as Light circuit laying from Switch to DB NS
mark cu multistrand cable Including all necessary items i.e.
bends, circular & Junction boxes etc. point 4
{c} High and Medium bay, Flood Light point with 2x2.5 sq.
mm/equivalent cu cable, bends, circular & junction Boxes point 71
1.2 Power Points
{a} 5/6 pin 6 x 16 A general outlet point with 2x 4+1x2.5 sq. mm
/ equivalent cu cable, bends, circular & Junction Boxes point 40
1.3 Outdoor Light Points
{a} Outdoor Street Pole Light point with 3x4.0 Sq. mm Armored
cu cable, bends, circular & Junction boxes point 4
{b} Outdoor Post top Light point with 3x2.5 Sq. mm cu cable,
bends, circular & Junction boxes with civil foundation point 2
2. Light Fixtures:
Supply of light fixtures, fixing, interconnection, testing and
commissioning complete with Holders, CFL, FTL, GLS,
electronic ballast, capacitor with all required mounting and
2.1 fixing accessories as per drawing
Brands: Philips,Wipro or Equivalent.
Indoor Lighting
{a} 2x36 Watt FTL Mirror optics fixture with EB Ballast surface
mounted (LT CS 001 HFB2) set 43
{b} Ceiling Dome Light with 11 watt CFL (CG 80 630) set 36
{c} Dust and jet proof 250W Integral enclosed type HPSV
Medium bay Light (BGEMB 250 SV) set 41
{d} Dust and jet proof 150W Integral enclosed type HPSV
Medium bay Light (BGEMB 150 SV) set 12
{e} Dust and jet proof 70W Integral enclosed type HPSV low
bay Light (BGELB 70 SV) set 14
{f} Black Powder coated Integral, die-cast housing 400W HPSV
Light (LT F1 004) set 4
{g} 14 Watt T8 FTL Picture/Mirror Light Fixture (as per
selection) set 8
{h} Weather proof half-head Light with 11 watt CFL (as per
selection) set 4
2.2 Outdoor Lighting
{a} 9 meter high street light metal pole with required civil works
complete set 4

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantiy Estimate of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. Remarks
{b} 70 watt HPSV dia cast sheet aluminum housing with lamp,
Ballast, Control gear, goose neck arm and 3x4 sqmm Cu Ar.
Cable as per drawing and specification (Philips- SRP 48/70(E),
CROMPTON- SSP1207 IH/WI, BAJAJ- BGEST 70 SV DD/02
70 SV or equivalent) set 4
{c} Post top Light fixture with 300 mm Unbreakable Clear Glass
with 18 W CFL Light and 1200 mm SS Stand with required Civil
works (LT GL 105) set 2
3. Fan Fixtures:
3.1 Supply of fan fixtures, fixing, interconnection, testing and
commissioning all complete as per drawing, specification and
instruction
Brands: Crompton, Bajaj or equivalent
220 v, 50 Hz, ceiling fan with J Hook and accessories,
capacitor 1200 mm dia, Heavy duty set 20
4. Switches and Sockets
4.10 Supply of switches, sockets as mentioned below, 18 SWG GI
metal boxes , screw, and other necessary materials with its
Installation, Interconnection and commissioning including civil
works as per drawing , specification all complete

Brands: C&S, Legrand, Schneider Clipsal (with prior approval


by designer)
{a} 10 A 1 Gang 1 way switch set 4
{b} 10 A 2 Gang 2 way switch set
{c} 10 A 2 Gang 1 way switch set 10
{d} 10 A 3 Gang 1 way switch set 6
{e} 10 A 4 Gang 1 way switch set 10
{f} 200 Watt 5 step Fan rider set 20
{g} 10 A 6 Gang 1 way switch set 2
{h} 5/6 pin 6/16 A switch socket set 40
5. Power Cable
5.10 Supply, delivery, laying and connecting of the following
Armoured/unarmoured power cable including cable sockets,
pull boxes and necessary materials. chiselling of wall/ floors
and redoing the chiselled area with cement &sand mortar as
per drawing and site condition all complete.

Armoured/ Unarmored cable


{a} 3.5 core 50 sq. mm aluminium armored cable laying
underground with PVC conduit (cable from NEA's kWH meter rm 60
and DG set to changeover, from changeover to main panel)

{b} 4x10+1x4 -E sq. mm copper Cable laying underground with


rm 60
PVC conduit [cable from Main panel Board to FDB-1/4
{c} 4x6+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [cable from Main Panel Board to FDB-2/3; FDB- rm 120
1/4 to SDB -1/4; Main Panel to Switch Panel-1/2
{d} 2x6+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [from Main Panel Board to Guard blocks and rm 291
fountain, switch panel interconnection]

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantiy Estimate of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. Remarks
6. Earthing System
6.10 Supply of materials and Installation of loke copper plate
(600x600x3.14 mm), salt, charcoal dust, 10 mm2 bare copper
cable with solid CAD weld ( Brazing) & watering 32 mm dia
PVC pipe & its installation in a whole of 90x90x250 cm with the
layers of Earthing materials as per standard, specification,
drawing and refilling the ground all complete
set 3
6.20 Supply and installation of 25*3 mm Copper Strip from roof trus
to Earthing station as Lightening protection and bonding of
metal roof to the earthing system kg 30
6.30 Supply and installation of 10 sq. mm bare copper wire with
necessary copper lugs and copper nut bolts connection with
Earthing system on each Electrical Closet as described on the
drawing rm 135
7. Electrical Panel & Distribution Boards
Supply, Delivery, Installation and Commissioning of the
following Distribution Board Including following equipment
housed in lockable, Double Door enclosure made from 16
SWG HRCA Sheet metal and the enclosure shall be finished at
least of two coats of red oxide metal primer and other two coats
of final epoxy enamel paint as per drawing and site condition
(shop drawing of all Distribution Boards shall submit to the
Consultant and get approval before starting the job)

Breaker: Schneider, Legrand


Fabricator: Himalaya/ Hyonjan
7.10 Main Panel Board - MPB set 1
100 Amp Panel Board with copper busabr and hardwrae - 1 set

100 A, TP MCCB - 1 set


Electronic Digital Volt Meter with 7 position Selector - 1 set
Electronic Digital Load Meter with 4 position Selector & CTs - 1
set
Indication LED Light with 2 A MCB - 3 set
40 A TP MCCB - 5 set
32 A TP MCB - 5 set
200 A TPNE copper Busbar with all required 1100 Volt Grade
bus Insulator, Colour Bus Sleeve, Power and Control cable,
Cable Lugs/Socket, Terminal Block, Panel wiring materials etc.
all complete
7.20 DBs - 1,2,3 & 4 [12 Way TPN DB Double Cover 30"x26"x6"] set 4
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
6 A SP MCB - 12 set
16 A SP MCB - 12 set
7.30 External Lighting Panel set 1
32 A, TP MCB -1 set
16 A SP MCB - 6 set
6 A SP MCB - 6 set
7.40 16A DP MCB in Enclosure for Guard House (Only Provision) set 1
7.50 Switch Panel - 1 set 1
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
20 A SP MCB - 6 set
Prepared By: Checked By: Approved By:
#REF!
#REF!
#REF!
#REF!

Quantiy Estimate of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. Remarks
32 A DP Switch - 9 set

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Quantiy Estimate of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. Remarks
7.60 Switch Panel - 2 set 1
40 A, TP MCCB -1 set
20 A, TP MCB -1 set
16 A SP MCB - 3 set
6 A SP MCB - 5 set
16 A DP Switch - 9 set
7.70 100A TPN 4 pole manual chnageover switch within metal
enclosure set-LS 1
8 Telephone System:
8.10 Supply of materials and wiring in NS approved 10 kg cm2 HDP
conduit concealed without any joint in middle of the span as per
drawing, specification all complete
{a} Telephone points with 3 Pair UTP Telephone cable point 6
8.20 Supply, installation and interconnection of Telephone/TV CDF
with 8 way Power pass booster, splitter for Coaxial and Solder
less crone for RJ-11 as per drawing, specifications all complete
with require power supply for Amplifier

{b} Telephone CDF 400x500mm with hinge door and lockable


system including 1 set Solder less telephone cable termination
module 10 pair set 1
8.30 RJ-11 cable
{a} 10 pairs UTP Telephone cable (for CDF interconnection) rm 46
8.40 Supply, installation & interconnection of sockets of approved
make using proper tools in appropriate GI metal boxes
including civil works & accessories as per drawing and
specification complete. Make: C&S, Legrand, Schneider or
equivalent

{a} RJ 11 Telephone socket set 6


9 NEA Intake:
1.10 400 Volt, 3 Phase Energy Meter with 63 A MCCB and Metal
enclosure as per NEA's standard (complete with kWH, MCCB,
Metal meter box, Coordination with NEA etc.)
LS 1
1.20 3.5 core 50 sq. mm aluminium armored cablefrom NEA Tap
poin to kwh meter rm 30
10 Diesel Generator - cummins, jackson or equivalent
1.10 Supply, Installation, testing, commissioning and erection of
Fully Enclosed type 40 KVA, 400 Volt, 3 Phase, 50 Hz standby
Diesel Generator set of approved make with all ancillary
equipments [base frame coupling, coupling guard, AMF,
Control panel, exhaust pipe with arrangements, Piping system,
Day tank, canopy, battery its charger RCC Pad & dampers etc.]
for the DG set
set 1

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Civil) Upto Plinth Level

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
A CIVIL WORKS
Site clearance before and after completion of work including
desposing the remaining construction materials & plants &
1 Job 1.00 50,000.00 50,000.00
making the site in working condition all complete as per
instruction of site Engineer.
Earthwork in excavation in Boulder mixed and hard soil in
foundation, trenches including timbering and shoring & 30m
2 Cum #REF! 492.75 #REF!
Lead and 1.5 m. lift all complete as per design, drawing,
specification and instruction of site Engineer.
Earthwork backfilling in 150 mm layers by ramming & watering
at required places as per instruction & disposing all surplus
3 Cum #REF! 301.01 #REF!
excavated materials within the site as per design, drawing,
specification and instruction of site Engineer all complete.
Supplying and filling in foundations and the area wherever
required below ground level and sides of the foundation and
walls with approved gravel sand (40:60) mixture in layers not
4 exceeding 150 mm thick, including well watering and Cum #REF! 3,583.11 #REF!
consolidation, leveling, loading, unloading and transportation
etc. complete, and as per specification, drawing and
instructions of Site Engineer.
Providing and laying machine mixed plain cement concrete
(1:3:6) using crushed coarse aggregates of 25 mm and down
size in foundation and under floors, steps, walls, platform etc.
including laying in layers of thickness not exceeding 150 mm
5 Cum #REF! 11,229.99 #REF!
and in alternative bays not exceeding 10 sqm including setting
out, mixing, compacting, curing and finishing etc. to approved
level, lines and dimension all complete as per specification,
drawing and instruction of Site Engineer.
Brickwork in cement sand mortar (1:4) in foundation up to plinth
level with approved quality first class chimney burnt bricks, with
minimum compressive strength of 70 k.g. per sq. cm., in perfect
6 line and level including soaking bricks in water, provision for Cum #REF! 13,229.50 #REF!
recesses, openings, toothings, packing the joints and curing the
work in all types and thickness of wall as per specification,
drawing and instruction of Site Engineer, all complete.
7 RCC Works
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M20 grade for R.C.C. works in slab, beam
etc in any form, size, shape and level with cement, sand and
7.1 crushed coarse aggregates of 20 mm/ 13 mm gauge including Cum #REF! 14,371.37 #REF!
setting out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing
and instruction of Site Engineer.
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M25 grade for R.C.C. works in column in
any form, size, shape and level with cement, sand and crushed
7.2 coarse aggregates of 20 mm/ 13 mm gauge including setting Cum #REF! 18,101.49 #REF!
out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing
and instruction of Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Civil) Upto Plinth Level

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Providing, straightening, cleaning, cutting, fabricating, bending
and placing TMT Thermex steel reinforcement bars and binding
the bars with 18 gauge annealed wire for tying them at each
junction as per design and details for all types of RCC elements
7.3 including all waste and cut pieces, provision for spacers, chairs, Kg #VALUE! 113.39 #VALUE!
providing and placing cement mortar (1:1) cover blocks to keep
the bars in the intended position at all levels as per design,
drawing, specification and instruction of site engineer all
complete.
Formwork, centering and shuttering with 19 mm thick
waterproof plywood for all kinds of R.C.C. works of any shape,
size and at any level with necessary propping, scaffolding,
staging, supporting, cutting holes for utilization works, etc.
7.4
including providing final surface in correct and perfect line, level,
cleaning the surface and applying form oil and removal of forms
all complete as per specification, drawing and instruction of Site
Engineer.
Column Sqm #REF! 1,405.30 #REF!
Beam Sqm #REF! 958.71 #REF!
8 Flooring Works
Earth filling in 300 mm thick layer, watering, ramming including
8.1 supply of filling materials all complete as per design, drawing, Cu.m #REF! 301.01 #REF!
specification and instruction of Site Engineer
Sand filling in flooring including supply of filling materials,
8.2 watering, ramming etc. all complete as per design, drawing, Cu.m #REF! 3,583.11 #REF!
specification and instruction of site Engineer
Providing and laying one layer of flat brick soling in foundation
and floor with approved quality chimney burnt bricks in perfect
8.3 sqm #REF! 1,078.41 #REF!
line and level, including filling the voids with sand as per design,
drawing, specification and instruction of site Engineer
75mm thick P.C.C. (1:2:4) for flooring with approved quality of
cement & sand and crushed stone aggregate including mixing,
8.4 Sq. m #REF! 1,037.26 #REF!
laying and compacting and curing etc all complete as per
design, drawing, specification and instruction of site Engineer
38 mm thick P.C.C. (1:2:4) for flooring with approved quality of
cement & sand and crushed stone aggregate including mixing,
laying and compacting including rubbing with steel trowel to a
8.5 Sqm #REF! 609.26 #REF!
hard, smooth and shining surface and curing etc all complete as
per design, drawing, specification and instruction of site
Engineer
3 mm thick cement sand punning on floor, skriting, dado etc,
including mixing laying and rubbing with steel trowel to a hard,
8.6 Sqm #REF! 237.37 #REF!
smooth and shining surface and curing all complete as per
design, drawing, specification and instruction of site Engineer
Providing and laying 8 mm thick non slip ceramic tiles (Spartek,
Kajaria, or approved equivalent) of approved colour, shade and
size on floor in perfect line and level on 20 mm thick base
8.7 Sqm #REF! 3,954.66 #REF!
cement sand mortar (1:4) and jointed with white cement slurry
mixed with pigment to match the shade of the tile complete as
per specification, drawing and instruction of Site Engineer.
Total #REF!

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Civil) Super Structure

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
A CIVIL WORKS
Brickwork in cement sand mortar (1:4) in foundation above plinth
level with approved quality first class chimney burnt bricks, with
minimum compressive strength of 70 k.g. per sq. cm., in perfect
1 line and level including soaking bricks in water, provision for Cum #VALUE! 13,537.47 #VALUE!
recesses, openings, toothings, packing the joints and curing the
work in all types and thickness of wall as per specification,
drawing and instruction of Site Engineer, all complete.
2 RCC Works
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M20 grade for R.C.C. works in slab, beam
etc in any form, size, shape and level with cement, sand and
2.1 crushed coarse aggregates of 20 mm/ 13 mm gauge including Cum #VALUE! 14,371.37 #VALUE!
setting out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing and
instruction of Site Engineer.
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M25 grade for R.C.C. works in column in
any form, size, shape and level with cement, sand and crushed
2.2 coarse aggregates of 20 mm/ 13 mm gauge including setting Cum #VALUE! 18,101.49 #VALUE!
out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing and
instruction of Site Engineer.
Providing, straightening, cleaning, cutting, fabricating, bending
and placing TMT Thermex steel reinforcement bars and binding
the bars with 18 gauge annealed wire for tying them at each
junction as per design and details for all types of RCC elements
2.3 including all waste and cut pieces, provision for spacers, chairs, Kg #VALUE! 113.39 #VALUE!
providing and placing cement mortar (1:1) cover blocks to keep
the bars in the intended position at all levels as per design,
drawing, specification and instruction of site engineer all
complete.
Formwork, centering and shuttering with 19 mm thick waterproof
plywood for all kinds of R.C.C. works of any shape, size and at
any level with necessary propping, scaffolding, staging,
supporting, cutting holes for utilization works, etc. including
2.4
providing final surface in correct and perfect line, level, cleaning
the surface and applying form oil and removal of forms all
complete as per specification, drawing and instruction of Site
Engineer.
Column Sqm #VALUE! 1,405.30 #VALUE!
Beam Sqm #VALUE! 958.71 #VALUE!
Slab Sqm #REF! 758.04 #REF!
3 Plaster Works
12.5mm thick cement sand plaster in (1:4) ratio on ceiling with
good finish including supplying of approved quality of cement &
sand, chiping the concrete surface, wetting the surfaces &
3.1 Sqm #REF! 381.90 #REF!
curing the work all complete including necessary single or
multiple stage scaffolding at all heights. as per the design,
drawing, specification and instruction of site engineer.
12.5mm thick cement sand plaster in (1:4) ratio on wall with
good finish including supplying of approved quality of cement &
sand, racking the joint, Chiping the concerte surface, wetting of
3.2 Sqm #VALUE! 332.97 #VALUE!
surfaces & curing the work all complete including necessary
single or multiple stage scaffolding at all heights. as per the
design, drawing, specification and instruction of site engineer.
4 Aluminium Door / Windows

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Civil) Super Structure

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Providing and fixing aluminium doors, windows and ventilators
assembled using colour anodized sections manufactured by
"AGRANI" or equivalent, fabricated as per drawings and fixed at
all levels, elevations and heights. The aluminium extruded
sections shall be anodized of approved colour with anodic film of
not less than 20 microns. Rate shall include to provide 5.0 mm
thick clear float glass/ tinted coloured glass/ milky glass of
approved make and 9 mm thick both side melamine laminated
high pressure particle board wherever required with snap fit
aluminium colour anodized beading with special water proof
cascades, neoprene etc. complete, as per specification, drawing
and instruction of Site Engineer.
Single/Double panel casement hinge door of section 101*45*1.5
4.1 Sq.m #VALUE! 7,553.38 #VALUE!
with 5mm glass
Sliding cum fix window of section 101*45*1.5 with 5mm glass
4.2 Sqm #VALUE! 6,465.58 #VALUE!
with net shutter
Supplying and fixing of MS grill of 4.5x20mm MS plate frame
and 12x12mm solid core square rod including metal primer paint
5 Sqm #VALUE! 2,564.62 #VALUE!
all complete as per design, drawing and instruction of site
engineer.
6 Flooring Works
38 mm thick P.C.C. (1:2:4) for flooring with approved quality of
cement & sand and crushed stone aggregate including mixing,
6.1 laying and compacting including rubbing with steel trowel to a Sqm #REF! 609.26 #REF!
hard, smooth and shining surface and curing etc all complete as
per drawing, specification in approval of site engineer
Providing and laying 8 mm thick glazed ceramic tiles (Spartek,
Kajaria, or approved equivalent) of approved shade, size and
pattern on wall in perfect line and level on 12.5 mm thick base
6.2 cement sand mortar (1:4) and jointed with cement slurry mixed Sqm #REF! 3,954.66 #REF!
with pigment to match the shade of the tile including adhesive
chemical all complete as per specification, drawing and
instruction of Site Engineer.
Providing and laying 16 mm thick granite from Rajasthan, India
of approved quality on wash basin with 30 mm thick cement
6.3 mortar (1:4) including cutting to the required shape, moulding Sqm #REF! 4,315.46 #REF!
and polishing all complete, as per specification, drawing and
instruction of Site Engineer.
Providing and laying 16 mm thick marble from Rajasthan, India
of approved quality on floors, staircase, parapet etc. with 30 mm
6.4 thick cement mortar (1:4) including cutting to the required shape, Sqm #VALUE! 4,315.46 #VALUE!
moulding and polishing all complete, as per specification,
drawing and instruction of Site Engineer.
6.5 Parqueting Sqm #REF! 3,000.00 #REF!
6 Painting Works
Providing and applying two coats of plastic emulsion paint of
approved brand and colour with one coat of primer including
preparation of surface through cleaning as per specification and
6.1 Sqm #VALUE! 269.63 #VALUE!
making good all small holes of nails, open joints and minor
defects of every kind after application of primer coat as per
specification and instruction of Site Engineer.
Providing and applying two coats of weather proof exterior
emulsion paint of approved brand and colour on the external
facade with one coat of primer including preparation of surface
6.2 through cleaning as per specification and making good all small Sqm #VALUE! 288.95 #VALUE!
holes of nails, open joints and minor defects of every kind after
application of primer coat as per specification and instruction of
Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Civil) Super Structure

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
7 Stainless Steel Railing Works
Providing and fixing stainless steel railing of 50mm dia vertical
post and hand rail, 25mm dia three layer horizontal pipe all
Rm #VALUE! 3831.04 #VALUE!
complete as per specification, drawing and instruction of Site
Engineer.
8 Roofing Works -
8.1 Truss Kg #REF! 154.72 #REF!
Providing, laying and fixing carbon fiber UPVC roofing sheet
with necessary bolts, J hooks, washers, including necessary
8.2 Sqm #REF! 1600.00 #REF!
overlaps, all complete as per specification, drawing and
instruction of Site Engineer. (5-5.5 Kg/sqm)
Total #VALUE!

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Soak pit)

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Earthwork in excavation in Boulder mixed and hard soil in
foundation, trenches including timbering and shoring &
1 Cum 2.47 492.75 1,217.10
30m Lead and 1.5 m. lift all complete as per design,
drawing, specification and instruction of site engineer.
Flat brick soling work in foundation with supplying of
approved quality of stone laying, ramming and levelling
2 Sq.m. 1.15 1078.41 1,240.18
including filling in the joints with sand as per design,
drawing, specification and instruction of site engineer
Brick masonry work in 1:4 C/S mortar with approved
quality of hammer dressed bond/block stone in perfect line,
layer, plumb and finishing including racking the joints and
3 Cu.m. 1.43 13229.50 18,918.19
curing the work for at least 7 days etc.all complete as per
design, drawing, specification and instruction of site
engineer.
Sand filling in side of wall including supply of filling
4 materials, watering, ramming etc. all complete as per Cu.m. 0.70 3583.11 2,508.18
drawing, specification in approval of site engineer
5 RCC Work
Plain cement Concrete (PCC) in 1:1.5:3 ratio (M20) for
RCC works in counter slab etc. with approved quality of
cement and sand and stone aggregate including mixing,
5.1 Cum 0.113 14371.37 1,619.24
laying, compacting and curing etc all complete as per
design, drawing, specification and instruction of site
engineer.
Steel reinforcement bar of Fe 415/500 grade including
straightening, cleaning, cutting, bending, placing in position
6 and binding with annealed binding wire all complete as per kg 17.69 113.39 2,005.87
design, drawing, specification and instruction of site
engineer.
Formwork, shuttering, centering with 19mm thick
waterproof ply board and steel post necessary propping,
scaffolding, staging, supporting inclusive of wedging and
7 Sqm 3.50 758.04 2,651.97
cutting holes for utilization till the support if fully unyielding
nett as per drawing, specification in approval of site
engineer
Total 30,160.73

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract of Cost (Septic Tank)

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Earthwork in excavation in Boulder mixed and hard soil in
foundation, trenches including timbering and shoring & 30m Lead
1 and 1.5 m. lift all complete as per design, drawing, specification Cu.m 7.53 492.75 3,710.41
and instruction of site engineer.
Flate brick soling work in foundation with supplying of approved
quality of stone laying, ramming and levelling including filling in the
2 Sq m 4.03 1078.41 4,346.00
joints with sand as per design, drawing, specification and
instruction of site engineer
3 RCC Works
Plain cement Concrete (PCC) in 1:1.5:3 ratio (M20) for RCC works
in counter slab etc. with approved quality of cement and sand and
3.1 stone aggregate including mixing, laying, compacting and curing Cu.m 0.84 14371.37 12,071.96
etc all complete as per design, drawing, specification and
instruction of site engineer.
Steel reinforcement bar of Fe 415/500 grade including
straightening, cleaning, cutting, bending, placing in position and
4 kg 59.28 113.39 6,721.76
binding with annealed binding wire all complete as per design,
drawing, specification and instruction of site engineer.
Formwork, shuttering, centering with 19mm thick waterproof ply
board and steel post necessary propping, scaffolding, staging,
5 supporting inclusive of wedging and cutting holes for utilization till Sqm 4.22 758.04 3,198.93
the support if fully unyielding nett as per drawing, specification in
approval of site engineer
Brick masonry work in 1:4 C/S mortar with approved quality of
hammer dressed bond/block stone in perfect line, layer, plumb and
6 finishing including racking the joints and curing the work for at Cu.m 2.58 13229.50 34,132.11
least 7 days etc.all complete as per design, drawing, specification
and instruction of site engineer.
12.5mm thick cement sand plaster in (1:4) ratio on wall with good
finish including supplying of approved quality of cement & sand,
7 racking the joint, Chiping the concerte surface, wetting of surfaces Sqm 9.60 332.97 3,196.52
& curing the work all complete as per the design, drawing,
specification and instruction of site engineer.
3 mm thick cement sand punning on floor, skriting, dado etc,
including mixing laying and rubbing with steel trowel to a hard,
8 Sqm 9.60 237.37 2,278.76
smooth and shining surface and curing all complete as per
drawing, specification in approval of site engineer
Total 69,656.45

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost (Manhole)

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Earthwork in excavation in Boulder mixed and hard soil in
foundation, trenches including timbering and shoring & 30m
1 Lead and 1.5 m. lift all complete as per design, drawing, Cu.m 48.240 492.75 23,770.26
specification and instruction of site engineer.
Flat brick soling work in foundation with supplying of approved
quality of stone laying, ramming and levelling including filling in
2 the joints with sand as per design, drawing, specification and Sq m 2.670 1,078.41 2,879.36
instruction of site engineer
Plain cement Concrete (PCC) in 1:3:6 ratio for foundations
with supplying approved quality of cement, sand and stone
3 aggregate including mixing, laying, copmacting and curing etc Cu.m 0.27 11,229.99 3,032.10
all complete as per design, drawing, specification and
instruction of site
4 RCC Works
Plain cement Concrete (PCC) in 1:1.5:3 ratio (M20) for RCC
works in counter slab etc. with approved quality of cement and
4.1 sand and stone aggregate including mixing, laying, compacting Cu.m 0.090 14,371.37 1,293.43
and curing etc all complete as per design, drawing,
specification and ins
Steel reinforcement bar of Fe 415/500 grade including
straightening, cleaning, cutting, bending, placing in position
5 and binding with annealed binding wire all complete as per Kg 9.00 113.39 1,020.51
design, drawing, specification and instruction of site engineer.

Formwork, shuttering, centering with 19mm thick waterproof


ply board and steel post necessary propping, scaffolding,
6 staging, supporting inclusive of wedging and cutting holes for Sq m 5.76 758.04 4,366.32
utilization till the support if fully unyielding nett as per drawing,
spec
Brick masonry work in 1:4 C/S mortar with approved quality of
hammer dressed bond/block stone in perfect line, layer, plumb
7 and finishing including racking the joints and curing the work Cu.m 0.54 13,229.50 7,143.93
for at least 7 days etc.all complete as per design, drawing,
specif
12.5mm thick cement sand plaster in (1:4) ratio on wall with
good finish including supplying of approved quality of cement
8 & sand, racking the joint, Chiping the concerte surface, wetting Sq m 26.43 332.97 8,800.40
of surfaces & curing the work all complete as per the design,
dra

3 mm thick cement sand punning on floor, skriting, dado etc,


including mixing laying and rubbing with steel trowel to a hard,
9 smooth and shining surface and curing all complete as per Sq m 26.43 237.37 6,273.69
drawing, specification in approval of site engineer

Total 58,580.00

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Water Tank

#REF!
#REF!
SN Particulars Unit Quantity Rate Amount Remarks
Earthwork in excavation in Boulder mixed and hard
soil in foundation, trenches including timbering and
1 shoring & 30m Lead and 1.5 m. lift all complete as Cum 28.13 492.75 13,861.06
per design, drawing, specification and instruction of
site engineer.
Earthwork backfilling in 150 mm layers by ramming &
watering at required places as per instruction &
2 Cum 8.44 301.01 2,540.52
disposing all surplus excavated materials within the
site all complete.
Flat brick soling work in foundation with supplying of
approved quality of stone laying, ramming and
3 levelling including filling in the joints with sand as per Sqm 14.78 1,078.41 15,938.90
design, drawing, specification and instruction of site
engineer
4 PCC Works
Plain cement Concrete (PCC) in 1:3:6 ratio for
foundations with supplying approved quality of
cement, sand and stone aggregate including mixing,
4.1 Cum 1.11 11,229.99 12,465.29
laying, copmacting and curing etc all complete as per
design, drawing, specification and instruction of site
engineer
5 RCC Works

Plain cement Concrete (PCC) in 1:1.5:3 ratio (M20)


for RCC works in column, beam etc. with approved
quality of cement, sand and stone aggregate
5.1 Cum 7.28 14,371.37 104,623.57
including mixing, laying, compacting and curing etc
all complete as per design, drawing, specification and
instruction of site engineer.

Steel reinforcement bar of Fe 415/500 grade


including straightening, cleaning, cutting, bending,
6 placing in position and binding with annealed binding Kg 869.88 113.39 98,635.24
wire all complete as per design, drawing,
specification and instruction of site engineer.
Formwork, shuttering, centering with waterproof ply
wood and wooden post necessary propping,
7 scaffolding, staging, supporting all complete in Sqm 45.18 758.04 34,248.25
perfect line and level as per drawing, specification
and instruction of site engineer
8 Plaster Works

12.5mm thick cement sand plaster in (1:4) ratio on


wall and floor with good finish including supplying of
approved quality of cement & sand, racking the joint,
8.1 Sqm 57.73 332.97 19,222.36
Chiping the concerte surface, wetting of surfaces &
curing the work all complete as per the design,
drawing, specification and instruction of site engineer.

3 mm thick cement sand punning on floor, skriting,


dado etc, including mixing laying and rubbing with
8.2 steel trowel to a hard, smooth and shining surface Sqm 57.73 237.37 13,703.37
and curing all complete as per drawing, specification
in approval of site engineer
Total 315,238.56

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
1.0 Wiring of light/fan & power points:
Supply of materials and wiring with PVC Insulated copper wire
in NS Approved HDP conduit without any joint in middle of the
span with necessary connecting, fixing, insulating and jointing
materials as per drawing and specification complete (wire:
Trishakti, Pioneer, Litmus)

1.1 Light/ Fan Points

{a} Light and Fan point with 2x1.5 Sq. mm from point to
switches and 2x2.5+1.1.5 as Light circuit laying from Switch to
DB NS mark cu multistrand cable Including all necessary items
i.e. bends, circular & Junction boxes etc.
point 111 1,309.82 145,389.66
{b} 2 Way light point with 3x1.5 Sq. mm from point to switches
and 2x2.5+1.1.5 as Light circuit laying from Switch to DB NS
mark cu multistrand cable Including all necessary items i.e.
bends, circular & Junction boxes etc. point 4 1,583.44 6,333.74
{c} High and Medium bay, Flood Light point with 2x2.5 sq.
mm/equivalent cu cable, bends, circular & junction Boxes point 71 1,745.22 123,910.41
1.2 Power Points
{a} 5/6 pin 6 x 16 A general outlet point with 2x 4+1x2.5 sq. mm
/ equivalent cu cable, bends, circular & Junction Boxes
point 40 1,950.92 78,036.70
1.3 Outdoor Light Points
{a} Outdoor Street Pole Light point with 3x4.0 Sq. mm Armored
cu cable, bends, circular & Junction boxes point 4 5,505.33 22,021.30

{b} Outdoor Post top Light point with 3x2.5 Sq. mm cu cable,
bends, circular & Junction boxes with civil foundation
point 2 2,388.00 4,776.00
Sub Total 380,467.81
2.0 Light Fixtures:
Supply of light fixtures, fixing, interconnection, testing and
commissioning complete with Holders, CFL, FTL, GLS,
electronic ballast, capacitor with all required mounting and
2.1 fixing accessories as per drawing

Brands: Philips,Wipro or Equivalent.


Indoor Lighting
{a} 2x36 Watt FTL Mirror optics fixture with EB Ballast surface
mounted (LT CS 001 HFB2) set 43 5,502.46 236,605.89
{b} Ceiling Dome Light with 11 watt CFL (CG 80 630) set 36 948.57 34,148.38
{c} Dust and jet proof 250W Integral enclosed type HPSV
Medium bay Light (BGEMB 250 SV) set 41 15,283.94 626,641.42
{d} Dust and jet proof 150W Integral enclosed type HPSV
Medium bay Light (BGEMB 150 SV) set 12 14,094.26 169,131.14

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
{e} Dust and jet proof 70W Integral enclosed type HPSV low
bay Light (BGELB 70 SV) set 14 9,403.41 131,647.77
{f} Black Powder coated Integral, die-cast housing 400W HPSV
Light (LT F1 004) set 4 26,710.34 106,841.35
{g} 14 Watt T8 FTL Picture/Mirror Light Fixture (as per
selection) set 8 3,315.97 26,527.74
{h} Weather proof half-head Light with 11 watt CFL (as per
selection) set 4 885.71 3,542.83
2.2 Outdoor Lighting
{a} 9 meter high street light metal pole with required civil works
complete set 4 18,977.76 75,911.04
{b} 70 watt HPSV dia cast sheet aluminum housing with lamp,
Ballast, Control gear, goose neck arm and 3x4 sqmm Cu Ar.
Cable as per drawing and specification (Philips- SRP 48/70(E),
CROMPTON- SSP1207 IH/WI, BAJAJ- BGEST 70 SV DD/02
70 SV or equivalent) set 4 15,161.68 60,646.72
{c} Post top Light fixture with 300 mm Unbreakable Clear Glass
with 18 W CFL Light and 1200 mm SS Stand with required Civil
works (LT GL 105) set 2 7,802.08 15,604.17
Sub Total 1,487,248.44
3.0 Fan Fixtures:
3.1 Supply of fan fixtures, fixing, interconnection, testing and
commissioning all complete as per drawing, specification and
instruction
Brands: Crompton, Bajaj or equivalent
220 v, 50 Hz, ceiling fan with J Hook and accessories,
capacitor 1200 mm dia, Heavy duty set 20 4,137.30 82,745.95
Sub Total 82,745.95
4.0 Switches and Sockets
4.1 Supply of switches, sockets as mentioned below, 18 SWG GI
metal boxes , screw, and other necessary materials with its
Installation, Interconnection and commissioning including civil
works as per drawing , specification all complete

Brands: C&S, Legrand, Schneider Clipsal (with prior approval


by designer)
{a} 10 A 1 Gang 1 way switch set 4 387.41 1,549.65
{b} 10 A 2 Gang 2 way switch set 0 516.76 0.00
{c} 10 A 2 Gang 1 way switch set 10 379.88 3,798.80
{d} 10 A 3 Gang 1 way switch set 6 442.97 2,657.81
{e} 10 A 4 Gang 1 way switch set 10 715.45 7,154.50
{f} 200 Watt 5 step Fan rider set 20 911.84 18,236.70
{g} 10 A 6 Gang 1 way switch set 2 1,054.38 2,108.76

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
{h} 5/6 pin 6/16 A switch socket set 40 713.15 28,525.98
Sub Total 64,032.18

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
5.0 Power Cable
5.1 Supply, delivery, laying and connecting of the following
Armoured/unarmoured power cable including cable sockets,
pull boxes and necessary materials. chiselling of wall/ floors
and redoing the chiselled area with cement &sand mortar as
per drawing and site condition all complete.

Armoured/ Unarmored cable


{a} 3.5 core 50 sq. mm aluminium armored cable laying
underground with PVC conduit (cable from NEA's kWH meter rm 60 1,270.68 76,240.86
and DG set to changeover, from changeover to main panel)

{b} 4x10+1x4 -E sq. mm copper Cable laying underground with


rm 60 788.45 47,306.86
PVC conduit [cable from Main panel Board to FDB-1/4
{c} 4x6+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [cable from Main Panel Board to FDB-2/3; FDB- rm 120 504.04 60,484.94
1/4 to SDB -1/4; Main Panel to Switch Panel-1/2
{d} 2x6+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [from Main Panel Board to Guard blocks and rm 291 299.67 87,204.21
fountain, switch panel interconnection]

Sub Total 271,236.87


6.0 Earthing System
6.1 Supply of materials and Installation of loke copper plate
(600x600x3.14 mm), salt, charcoal dust, 10 mm2 bare copper
cable with solid CAD weld ( Brazing) & watering 32 mm dia
PVC pipe & its installation in a whole of 90x90x250 cm with the
layers of Earthing materials as per standard, specification,
drawing and refilling the ground all complete
set 3 22,678.47 68,035.41
6.2 Supply and installation of 25*3 mm Copper Strip from roof trus
to Earthing station as Lightening protection and bonding of
metal roof to the earthing system kg 30 1,086.75 32,602.50
6.3 Supply and installation of 10 sq. mm bare copper wire with
necessary copper lugs and copper nut bolts connection with
Earthing system on each Electrical Closet as described on the
drawing rm 135 117.29 15,834.15
Sub Total 116,472.06
7.0 Electrical Panel & Distribution Boards

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
Supply, Delivery, Installation and Commissioning of the
following Distribution Board Including following equipment
housed in lockable, Double Door enclosure made from 16
SWG HRCA Sheet metal and the enclosure shall be finished at
least of two coats of red oxide metal primer and other two coats
of final epoxy enamel paint as per drawing and site condition
(shop drawing of all Distribution Boards shall submit to the
Consultant and get approval before starting the job)

Breaker: Schneider, Legrand


Fabricator: Himalaya/ Hyonjan
7.1 Main Panel Board - MPB set 1 96,586.51 96,586.51
100 Amp Panel Board with copper busabr and hardwrae - 1 set

100 A, TP MCCB - 1 set


Electronic Digital Volt Meter with 7 position Selector - 1 set
Electronic Digital Load Meter with 4 position Selector & CTs - 1
set
Indication LED Light with 2 A MCB - 3 set
40 A TP MCCB - 5 set
32 A TP MCB - 5 set
200 A TPNE copper Busbar with all required 1100 Volt Grade
bus Insulator, Colour Bus Sleeve, Power and Control cable,
Cable Lugs/Socket, Terminal Block, Panel wiring materials etc.
all complete
7.2 DBs - 1,2,3 & 4 [12 Way TPN DB Double Cover 30"x26"x6"] set 4 28,574.20 114,296.79
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
6 A SP MCB - 12 set
16 A SP MCB - 12 set
7.3 External Lighting Panel set 1 11,186.45 11,186.45
32 A, TP MCB -1 set
16 A SP MCB - 6 set
6 A SP MCB - 6 set
7.4 16A DP MCB in Enclosure for Guard House (Only Provision) set 1 1,066.05 1,066.05
7.5 Switch Panel - 1 set 1 23,571.01 23,571.01
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
20 A SP MCB - 6 set
32 A DP Switch - 9 set
7.6 Switch Panel - 2 set 1 24,988.17 24,988.17
40 A, TP MCCB -1 set
20 A, TP MCB -1 set

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
16 A SP MCB - 3 set
6 A SP MCB - 5 set
16 A DP Switch - 9 set
7.7 100A TPN 4 pole manual chnageover switch within metal
enclosure set-LS 1 12,112.37 12,112.37
Sub Total 283,807.35

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT
8.0 Telephone System:
8.1 Supply of materials and wiring in NS approved 10 kg cm2 HDP
conduit concealed without any joint in middle of the span as per
drawing, specification all complete
{a} Telephone points with 3 Pair UTP Telephone cable point 6 1,736.43 10,418.59
8.2 Supply, installation and interconnection of Telephone/TV CDF
with 8 way Power pass booster, splitter for Coaxial and Solder
less crone for RJ-11 as per drawing, specifications all complete
with require power supply for Amplifier

{b} Telephone CDF 400x500mm with hinge door and lockable


system including 1 set Solder less telephone cable termination
module 10 pair set 1 4,081.68 4,081.68
8.3 RJ-11 cable
{a} 10 pairs UTP Telephone cable (for CDF interconnection) rm 46 149.80 6,890.75
8.4 Supply, installation & interconnection of sockets of approved
make using proper tools in appropriate GI metal boxes
including civil works & accessories as per drawing and
specification complete. Make: C&S, Legrand, Schneider or
equivalent

{a} RJ 11 Telephone socket set 6 506.95 3,041.73


Sub Total 24,432.75
9.0 NEA Intake:
9.1 400 Volt, 3 Phase Energy Meter with 63 A MCCB and Metal
enclosure as per NEA's standard (complete with kWH, MCCB,
Metal meter box, Coordination with NEA etc.)
LS 1 75,000.00 75,000.00
9.2 3.5 core 50 sq. mm aluminium armored cablefrom NEA Tap
poin to kwh meter rm 30 1,270.68 38,120.43
Sub Total 113,120.43
10.0 Diesel Generator - cummins, jackson or equivalent
10.1 Supply, Installation, testing, commissioning and erection of
Fully Enclosed type 40 KVA, 400 Volt, 3 Phase, 50 Hz standby
Diesel Generator set of approved make with all ancillary
equipments [base frame coupling, coupling guard, AMF,
Control panel, exhaust pipe with arrangements, Piping system,
Day tank, canopy, battery its charger RCC Pad & dampers etc.]
for the DG set
set 1 1,156,528.67 1,156,528.67
Sub Total 1,156,528.67

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Cost of Electrical Works

#REF!
###
S.No. DESCRIPTION OF WORKS UNIT QTY. RATE AMOUNT

Summary of Costing (Electrical and Allied works)

1. Wiring of light/fan & power points 380,467.81


2. Light Fixtures 1,487,248.44
3. Fan Fixtures 82,745.95
4. Switches and sockets 64,032.18
5. Power Cable 271,236.87
6. Earthing system 116,472.06
7. Electrical Panel & Distribution Boards 283,807.35
8. Telephone System 24,432.75
9. NEA Intake 113,120.43
10. Diesel Generator (40 KVA) 1,156,528.67
TOTAL 3,980,092.51

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Abstract Costs of sanitary

#REF!
#REF!
SN Particulars Quantity Unit Rate Amount Remarks
Supplying and Fixing Porcelain clay Indian Pattern Comode,
Rate
1 Porcelain clay Cistern and seat cover with pipe connector all 12.00 Set 26,057.85 312,694.20
Kathmandu
complete set.(Hindware, Parryware, or equivalent ).
Supplying and fixing White glaze Porcelain clay wash
basin/Oval 50X40Cm with pedestal, Mixture brackets 32mm
dia. p trap, 32mm CP waste coupling with CP chain and rubber
2 10.00 Set 10,550.10 105,501.00 "
plug, 15mmx450mm long c.p. pipe connector etc all complete.
(Sanitaryware:-Hindware,parryware or equivalent).Valve:-
jaquar,ark,Ess Ess or equivalent)
Supplying and fixing White glaze Porcelain clay
46.5x35.5x26.5cm flat back White glazed Urinal with sensor
valve, brackets 32mm dia. p trap, 32mm CP waste coupling
3
with CP chain and rubber plug, 15mmx450mm long c.p. pipe
connector etc all complete.(Sanitaryware:-Hindware,parryware
or equivalent).Valve:- jaquar,ark,Ess Ess or equivalent)
46.5x35.5x26.5 cm flat back White glazed Urinal all complete
8.00 Set 18,901.40 151,211.20 "
set.
68 X 30 Cm white glazed urinal Partation with all complete set 7.00 Set 2,910.65 20,374.55 "
Supplying and Fixing Pvc roof water tank With cover including
4 drain hole ,inlet outlet, over flow etc.all complete set .Hill take,
Roof top or equivalent
1000 litres PVC overhead tank 2.00 Nos. 18,771.45 37,542.90 "
Supplying and Fixing Electric moter Pump single or three phase
5 phase with base, nut and bolts all complete set (Kirloskar,
Compton, Servo, Sharp,)
2 HP Electric motor Pump monoblock.(crompton) 1.00 Nos. 32,190.80 32,190.80 "
Supplying and Fixing Indian pattern C.P. valves with wall flange
6
Including c.p. nipple all complete set.
15mm CP bib cock Cock ordinary type 21.00 Set 1,674.57 35,165.97 "
C.P. 15mm dia Angle valve. 29.00 Nos. 1,540.02 44,660.58 "
15 mm comode CP water spray with 1.2mt. Long flexiable pipe.
12.00 Nos. 1,690.73 20,288.76 "

Stainless steel shower wth sliding bar and complete set 12.00 Nos. 3,750.66 45,007.92 "
CP Wall mixture 4.00 Nos. 6,359.67 25,438.68 "
7 Valves with all complete accessories.
GM Gate valve 50 mm dia. 1.00 Nos. 2,068.04 2,068.04 "
(G.M.) check valve 50 mm dia 1.00 Nos. 5,151.36 5,151.36 "
Supplying and Fixing UPVC pipe all complete set as per
8
specification and instruction. (Panchakanya , Prince,Supreme )
75mm PVC pipe of 6 kg/cm2 130.00 Rm 473.80 61,594.00 "
110mm PVC pipe of 6 kg/cm2 80.00 Rm 875.20 70,016.00 "
Supplying and fixing PPR and GI Pipe. or equivalent with
fittings/ specials (Tees, elbows, Unions etc) clamps(m.s plate
with nut and bolt with hexagonal screws for clamp in
ceiling,wall), nails, including jointing materials,installation of
9
pipes and specials including making holes on walls or floor and
repairing the same to its original finish,cleaning of the system,
testing and ready for operation,. all complete set as per
specification and instruction.
15 mm dia P.P.R pipe 45.00 RM 118.45 5,330.25 "
20 mm dia P.P.R pipe 145.00 RM 118.45 17,175.25 "
25 mm dia P.P.R pipe 10.00 RM 162.80 1,628.00 "

Checked by
Prepared by Approved by
#REF!
#REF!
#REF!
#REF!

Abstract Costs of sanitary

#REF!
#REF!
SN Particulars Quantity Unit Rate Amount Remarks
50 mm dia P.P.R pipe 70.00 RM 510.10 35,707.00 "
Supplying and Fixing UPVC specials with O ring rubber
washer,Pvc liquid(Solvent cement), Pvc cream, all complete set
10
as per specification and instruction.
(Panchakanya,Prince,Supreme )
75 mm dia UPVC vent cowl 1.00 Nos. 232.12 232.12 "
75 mm dia UPVC plain/door Tee. 18.00 Nos. 418.81 7,538.58 "
75 mm dia UPVC 90 degree bend. 7.00 Nos. 310.14 2,170.98 "
75 mm dia UPVC Y bend. 5.00 Nos. 382.59 1,912.95 "
75 mm dia UPVC 45˚ bend. 4.00 Nos. 285.99 1,143.96 "
75 mm dia UPVC pipe clip 110.00 Nos. 39.85 4,383.50 "
110 mm dia UPVC plain /door Tee. 6.00 Nos. 742.13 4,452.78 "
110 mm dia UPVC 90 degree bend 8.00 Nos. 538.06 4,304.48 "
110 mm dia UPVC Y bend. 10.00 Nos. 734.88 7,348.80 "
110 mm dia UPVC 45˚ bend. 8.00 Nos. 487.35 3,898.80 "
110 mm dia UPVC pipe clip 55.00 Nos. 50.72 2,789.60 "
PVC floor trap 11x7.5 cm. 18.00 Nos. 504.44 9,079.92 "
Supplying and Fixing Indian pattern bathroom accessories all
11
complete set.
Modi guard bevelled float mirror 6mm thick with stainfree
14.00 Nos. 2,052.11 28,729.54 "
0.45x0.60m and bracket all compete set.
Chrome plate type toilet paper holder. 12.00 Nos. 1,223.77 14,685.24 "
Chrome plated soap tray. 12.00 Nos. 741.92 8,903.04 "
CP 15mm dia x450mm long towel rod. 11.00 Nos. 851.34 9,364.74 "
Kitchen sink 37" long and 8"deep with sink cock all completed
1.00 Nos. 7,644.05 7,644.05 "
set
Fire pump:-20H.P.x2set or 40H.P. (Head-70.0mtr.,Discharge-
2400Lpm)Fire pump set with 5.0h.p Stainless steel verticle
jockey pump,(Main pump start Automatically If jockey pump
12 1.00 Set 640,561.50 640,561.50 "
pressure drop) including control panel board,Required
Cable,Stairner for both pump,pressure switches,pressure
guage all complete set,
Total 1,787,891.04

Checked by
Prepared by Approved by
#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
1.0 General Works
Site clearance before and after completion of work including desposing the remaining
1.1 construction materials & plants & making the site in working condition all complete as Job 1.00 1.00
per instruction of site Engineer.
2.0 Earthworks
Earthwork in excavation in Boulder mixed and hard soil in foundation, trenches
2.1 including timbering and shoring & 30m Lead and 1.5 m. lift all complete as per design, Cum #REF! 7.53 2.47 48.24 28.13 #REF!
drawing, specification and instruction of site Engineer.
Earthwork backfilling in 150 mm layers by ramming & watering at required places as per
2.2 instruction & disposing all surplus excavated materials within the site as per design, Cum #REF! 8.44 #REF!
drawing, specification and instruction of site Engineer all complete.
Supplying and filling in foundations and the area wherever required below ground level
and sides of the foundation and walls with approved gravel sand (40:60) mixture in
2.3 layers not exceeding 150 mm thick, including well watering and consolidation, leveling, Cum #REF! #REF!
loading, unloading and transportation etc. complete, and as per specification, drawing
and instructions of Site Engineer.
3.0 PCC Works
Providing and laying machine mixed plain cement concrete (1:3:6) using crushed coarse
aggregates of 25 mm and down size in foundation and under floors, steps, walls,
platform etc. including laying in layers of thickness not exceeding 150 mm and in
3.1 Cum #REF! 0.27 1.11 #REF!
alternative bays not exceeding 10 sqm including setting out, mixing, compacting, curing
and finishing etc. to approved level, lines and dimension all complete as per
specification, drawing and instruction of Site Engineer.
4.0 Brick Works
Brickwork in cement sand mortar (1:4) in foundation up to plinth level with approved
quality first class chimney burnt bricks, with minimum compressive strength of 70 k.g.
per sq. cm., in perfect line and level including soaking bricks in water, provision for
4.1 Cum #REF! 2.58 1.43 0.54 #REF!
recesses, openings, toothings, packing the joints and curing the work in all types and
thickness of wall as per specification, drawing and instruction of Site Engineer, all
complete.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
Brickwork in cement sand mortar (1:4) in foundation above plinth level with approved
quality first class chimney burnt bricks, with minimum compressive strength of 70 k.g.
per sq. cm., in perfect line and level including soaking bricks in water, provision for
4.2 Cum #VALUE!
recesses, openings, toothings, packing the joints and curing the work in all types and
thickness of wall as per specification, drawing and instruction of Site Engineer, all
complete.
5.0 PCC for RCC Works
Providing and laying machine mixed/ batch plant mixed plain cement concrete of M20
grade for R.C.C. works in slab, beam etc in any form, size, shape and level with cement,
5.1 sand and crushed coarse aggregates of 20 mm/ 13 mm gauge including setting out, Cum #REF! #VALUE! 0.84 0.11 0.09 7.28 #REF!
mixing, compacting, curing, finishing and providing construction / expansion joints, as
per specification, drawing and instruction of Site Engineer.
Providing and laying machine mixed/ batch plant mixed plain cement concrete of M25
grade for R.C.C. works in column in any form, size, shape and level with cement, sand
5.2 and crushed coarse aggregates of 20 mm/ 13 mm gauge including setting out, mixing, Cum #REF! #VALUE! #REF!
compacting, curing, finishing and providing construction / expansion joints, as per
specification, drawing and instruction of Site Engineer.
Providing, straightening, cleaning, cutting, fabricating, bending and placing TMT
Thermex steel reinforcement bars and binding the bars with 18 gauge annealed wire for
tying them at each junction as per design and details for all types of RCC elements
5.3 Kg #VALUE! #VALUE! 59.28 17.69 9.00 869.88 #VALUE!
including all waste and cut pieces, provision for spacers, chairs, providing and placing
cement mortar (1:1) cover blocks to keep the bars in the intended position at all levels
as per design, drawing, specification and instruction of site engineer all complete.
Formwork, centering and shuttering with 19 mm thick waterproof plywood for all kinds of
R.C.C. works of any shape, size and at any level with necessary propping, scaffolding,
staging, supporting, cutting holes for utilization works, etc. including providing final
5.4
surface in correct and perfect line, level, cleaning the surface and applying form oil and
removal of forms all complete as per specification, drawing and instruction of Site
Engineer.
Column Sqm #REF! #VALUE! #REF!

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
Beam Sqm #REF! #VALUE! #REF!
Slab Sqm #REF! 4.22 3.50 5.76 45.18 #REF!
6.0 Flooring Works
Earth filling in 300 mm thick layer, watering, ramming including supply of filling materials
6.1 Cum #REF! #REF!
all complete as per design, drawing, specification and instruction of Site Engineer
Sand filling in flooring including supply of filling materials, watering, ramming etc. all
6.2 Cum #REF! 0.70 #REF!
complete as per design, drawing, specification and instruction of site Engineer
Providing and laying one layer of flat brick soling in foundation and floor with approved
6.3 quality chimney burnt bricks in perfect line and level, including filling the voids with sand Sqm #REF! 4.03 1.15 2.67 14.78
as per design, drawing, specification and instruction of site Engineer
75mm thick P.C.C. (1:2:4) for flooring with approved quality of cement & sand and
6.4 crushed stone aggregate including mixing, laying and compacting and curing etc all Sqm #REF! #REF!
complete as per design, drawing, specification and instruction of site Engineer
38 mm thick P.C.C. (1:2:4) for flooring with approved quality of cement & sand and
crushed stone aggregate including mixing, laying and compacting including rubbing with
6.5 Sqm #REF! #REF! #REF!
steel trowel to a hard, smooth and shining surface and curing etc all complete as per
design, drawing, specification and instruction of site Engineer
3 mm thick cement sand punning on floor, skriting, dado etc, including mixing laying and
6.6 rubbing with steel trowel to a hard, smooth and shining surface and curing all complete Sqm #REF! 9.60 26.43 57.73 #REF!
as per design, drawing, specification and instruction of site Engineer
7.0 Painting Works
Providing and applying two coats of plastic emulsion paint of approved brand and colour
with one coat of primer including preparation of surface through cleaning as per
7.1 specification and making good all small holes of nails, open joints and minor defects of Sqm #VALUE! #VALUE!
every kind after application of primer coat as per specification and instruction of Site
Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
Providing and applying two coats of weather proof exterior emulsion paint of approved
brand and colour on the external facade with one coat of primer including preparation of
7.2 surface through cleaning as per specification and making good all small holes of nails, Sq.m. #VALUE! #VALUE!
open joints and minor defects of every kind after application of primer coat as per
specification and instruction of Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
8.0 Plaster Works
12.5mm thick cement sand plaster in (1:4) ratio on ceiling with good finish including
supplying of approved quality of cement & sand, chiping the concrete surface, wetting
8.1 the surfaces & curing the work all complete including necessary single or multiple stage Sq. m #REF! 26.43 #REF!
scaffolding at all heights. as per the design, drawing, specification and instruction of
site engineer.
12.5mm thick cement sand plaster in (1:4) ratio on wall with good finish including
supplying of approved quality of cement & sand, racking the joint, Chiping the concerte
8.2 surface, wetting of surfaces & curing the work all complete including necessary single or Sq. m #VALUE! 9.60 57.73 #VALUE!
multiple stage scaffolding at all heights. as per the design, drawing, specification and
instruction of site engineer.
9.0 Aluminium Door / Windows
Providing and fixing aluminium doors, windows and ventilators assembled using colour
anodized sections manufactured by "AGRANI" or equivalent, fabricated as per drawings
and fixed at all levels, elevations and heights. The aluminium extruded sections shall be
anodized of approved colour with anodic film of not less than 20 microns. Rate shall
include to provide 5.0 mm thick clear float glass/ tinted coloured glass/ milky glass of
approved make and 9 mm thick both side melamine laminated high pressure particle
board wherever required with snap fit aluminium colour anodized beading with special
water proof cascades, neoprene etc. complete, as per specification, drawing and
instruction of Site Engineer.
9.1 Single/Double panel casement hinge door of section 101*45*1.5 with 5mm glass Sqm #VALUE! #VALUE!
9.2 Sliding cum fix window of section 101*45*1.5 with 5mm glass with net shutter Sqm #VALUE! #VALUE!
Supplying and fixing of MS grill of 4.5x20mm MS plate frame and 12x12mm solid core
9.3 square rod including metal primer paint all complete as per design, drawing and Sqm #VALUE! #VALUE!
instruction of site engineer.
10.0 Floor Finishing Works

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summery of Quantity (Civil Works)

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water
Sub- Super- Manhole Quantity
tank Pit Tank
Structure Structure
Providing and laying 8 mm thick non slip ceramic tiles (Spartek, Kajaria, or approved
equivalent) of approved colour, shade and size on floor in perfect line and level on 20
10.1 mm thick base cement sand mortar (1:4) and jointed with white cement slurry mixed with Sq. m #REF! #REF!
pigment to match the shade of the tile complete as per specification, drawing and
instruction of Site Engineer.
Providing and laying 8 mm thick glazed ceramic tiles (Spartek, Kajaria, or approved
equivalent) of approved shade, size and pattern on wall in perfect line and level on 12.5
mm thick base cement sand mortar (1:4) and jointed with cement slurry mixed with Sq.m #REF! #REF!
pigment to match the shade of the tile including adhesive chemical all complete as per
10.2 specification, drawing and instruction of Site Engineer.
Providing and laying 16 mm thick granite from Rajasthan, India of approved quality on
wash basin with 30 mm thick cement mortar (1:4) including cutting to the required
10.3 Sq.m #REF! #REF!
shape, moulding and polishing all complete, as per specification, drawing and instruction
of Site Engineer.
Providing and laying 16 mm thick marble from Rajasthan, India of approved quality on
floors, staircase, parapet etc. with 30 mm thick cement mortar (1:4) including cutting to
Sq.m #VALUE!
the required shape, moulding and polishing all complete, as per specification, drawing
10.4 and instruction of Site Engineer. #VALUE!
10.5 Parqueting Sq.m #REF! #REF!
11.0 Railing Works
Providing and fixing stainless steel railing of 50mm dia vertical post and hand rail, 25mm
11.1 dia three layer horizontal pipe all complete as per specification, drawing and instruction R.m #VALUE!
of Site Engineer. #VALUE!
12.0 Roofing Works
12.1 Truss Kg #REF! #REF!
Providing, laying and fixing carbon fiber UPVC roofing sheet with necessary bolts, J
12.2 hooks, washers, including necessary overlaps, all complete as per specification, drawing Sq.m #REF!
and instruction of Site Engineer. (5-5.5 Kg/sqm) #REF!

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
1 General Works
Site clearance before and after completion of work including
desposing the remaining construction materials & plants &
1.1 Job 1.00 1.00 50,000.00 50,000.00
making the site in working condition all complete as per
instruction of site Engineer.
2 Earthworks
Earthwork in excavation in Boulder mixed and hard soil in
foundation, trenches including timbering and shoring & 30m
2.1 Cum #REF! 7.53 2.47 48.24 28.13 #REF! 492.75 #REF!
Lead and 1.5 m. lift all complete as per design, drawing,
specification and instruction of site Engineer.
Earthwork backfilling in 150 mm layers by ramming & watering
at required places as per instruction & disposing all surplus
2.2 Cum #REF! 8.44 #REF! 301.01 #REF!
excavated materials within the site as per design, drawing,
specification and instruction of site Engineer all complete.
Supplying and filling in foundations and the area wherever
required below ground level and sides of the foundation and
walls with approved gravel sand (40:60) mixture in layers not
2.3 exceeding 150 mm thick, including well watering and Cum #REF! #REF! 3,583.11 #REF!
consolidation, leveling, loading, unloading and transportation
etc. complete, and as per specification, drawing and
instructions of Site Engineer.
3 PCC Works
Providing and laying machine mixed plain cement concrete
(1:3:6) using crushed coarse aggregates of 25 mm and down
size in foundation and under floors, steps, walls, platform etc.
including laying in layers of thickness not exceeding 150 mm
3.1 Cum #REF! #REF! 11,229.99 #REF!
and in alternative bays not exceeding 10 sqm including setting
out, mixing, compacting, curing and finishing etc. to approved
level, lines and dimension all complete as per specification,
drawing and instruction of Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
4 Brick Works
Brickwork in cement sand mortar (1:4) in foundation up to plinth
level with approved quality first class chimney burnt bricks, with
minimum compressive strength of 70 k.g. per sq. cm., in perfect
4.1 line and level including soaking bricks in water, provision for Cum #REF! 0.27 1.11 #REF! 13,229.50 #REF!
recesses, openings, toothings, packing the joints and curing the
work in all types and thickness of wall as per specification,
drawing and instruction of Site Engineer, all complete.
Brickwork in cement sand mortar (1:4) in foundation above
plinth level with approved quality first class chimney burnt
bricks, with minimum compressive strength of 70 k.g. per sq.
cm., in perfect line and level including soaking bricks in water,
4.2 Cum #VALUE! #VALUE! 13,537.47 #VALUE!
provision for recesses, openings, toothings, packing the joints
and curing the work in all types and thickness of wall as per
specification, drawing and instruction of Site Engineer, all
complete.
5 PCC for RCC Works
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M20 grade for R.C.C. works in slab, beam
etc in any form, size, shape and level with cement, sand and
5.1 crushed coarse aggregates of 20 mm/ 13 mm gauge including Cum #REF! #VALUE! #REF! 14,371.37 #REF!
setting out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing
and instruction of Site Engineer.
Providing and laying machine mixed/ batch plant mixed plain
cement concrete of M25 grade for R.C.C. works in column in
5.2 any form, size, shape and level with cement, sand and crushed Cum #REF! #VALUE! 2.58 1.43 0.54 #REF! 18,101.49 #REF!
coarse aggregates of 20 mm/ 13 mm gauge including setting
out, mixing, compacting, curing, finishing and providing
construction / expansion joints, as per specification, drawing
and instruction of Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
Providing, straightening, cleaning, cutting, fabricating, bending
and placing TMT Thermex steel reinforcement bars and binding
5.3 the bars with 18 gauge annealed wire for tying them at each Kg #VALUE! #VALUE! #VALUE! 113.39 #VALUE!
junction as per design and details for all types of RCC elements
including all waste and cut pieces, provision for spacers, chairs,
providing and placing cement mortar (1:1) cover blocks to keep
Formwork, centering
the bars in the intended and shuttering
position with 19
at all levels as permmdesign,
thick
drawing, plywood
waterproof specification
for alland
kinds
instruction
of R.C.C. ofworks
site ofengineer
any shape,
all
complete.
size and at any level with necessary propping, scaffolding,
staging, supporting, cutting holes for utilization works, etc.
5.4
including providing final surface in correct and perfect line,
level, cleaning the surface and applying form oil and removal of
forms all complete as per specification, drawing and instruction
of Site Engineer.
Column Sqm #REF! #VALUE! 0.84 0.11 0.09 7.28 #REF! 1,405.30 #REF!
Beam Sqm #REF! #VALUE! #REF! 958.71 #REF!
Slab Sqm #REF! #REF! 758.04 #REF!
6 Flooring Works
Earth filling in 300 mm thick layer, watering, ramming including
6.1 supply of filling materials all complete as per design, drawing, Cum #REF! #REF! 301.01 #REF!
specification and instruction of Site Engineer
Sand filling in flooring including supply of filling materials,
6.2 watering, ramming etc. all complete as per design, drawing, Cum #REF! #REF! 3,583.11 #REF!
specification and instruction of site Engineer
Providing and laying one layer of flat brick soling in foundation
and floor with approved quality chimney burnt bricks in perfect
6.3 Sqm #REF! #REF! 1,078.41 #REF!
line and level, including filling the voids with sand as per design,
drawing, specification and instruction of site Engineer

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
75mm thick P.C.C. (1:2:4) for flooring with approved quality of
cement & sand and crushed stone aggregate including mixing,
6.4 Sqm #REF! 4.22 3.49845 5.76 45.18 #REF! 1,037.26 #REF!
laying and compacting and curing etc all complete as per
design, drawing, specification and instruction of site Engineer
38 mm thick P.C.C. (1:2:4) for flooring with approved quality of
cement & sand and crushed stone aggregate including mixing,
laying and compacting including rubbing with steel trowel to a
6.5 Sqm #REF! #REF! #REF! 609.26 #REF!
hard, smooth and shining surface and curing etc all complete
as per design, drawing, specification and instruction of site
Engineer
3 mm thick cement sand punning on floor, skriting, dado etc,
including mixing laying and rubbing with steel trowel to a hard,
6.6 Sqm #REF! #REF! 237.37 #REF!
smooth and shining surface and curing all complete as per
design, drawing, specification and instruction of site Engineer
7 Painting Works
Providing and applying two coats of plastic emulsion paint of
approved brand and colour with one coat of primer including
7.1 preparation of surface through cleaning as per specification and Sqm #VALUE! #VALUE! 269.63 #VALUE!
making good all small holes of nails, open joints and minor
defects of every kind after application of primer coat as per
Providing and
specification andapplying twoof coats
instruction of weather proof exterior
Site Engineer.
emulsion paint of approved brand and colour on the external
facade with one coat of primer including preparation of surface
7.2 through cleaning as per specification and making good all small Sq.m. #VALUE! #VALUE! 288.95 #VALUE!
holes of nails, open joints and minor defects of every kind after
application of primer coat as per specification and instruction of
Site Engineer.
8 Plaster Works

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
12.5mm thick cement sand plaster in (1:4) ratio on ceiling with
good finish including supplying of approved quality of cement &
sand, chiping the concrete surface, wetting the surfaces &
8.1 Sq. m #REF! #REF! 381.90 #REF!
curing the work all complete including necessary single or
multiple stage scaffolding at all heights. as per the design,
drawing, specification and instruction of site engineer.
12.5mm thick cement sand plaster in (1:4) ratio on wall with
good finish including supplying of approved quality of cement &
8.2 sand, racking the joint, Chiping the concerte surface, wetting of Sq. m #VALUE! #VALUE! 332.97 #VALUE!
surfaces & curing the work all complete including necessary
single or multiple stage scaffolding at all heights. as per the
9 Aluminium
design, Door specification
drawing, / Windows and instruction of site engineer.
Providing and fixing aluminium doors, windows and ventilators
assembled using colour anodized sections manufactured by
"AGRANI" or equivalent, fabricated as per drawings and fixed
at all levels, elevations and heights. The aluminium extruded
sections shall be anodized of approved colour with anodic film
Single/Double
of not less than panel casement
20 microns. hinge
Rate shall doorto of
include section
provide 5.0
9.1 Sqm #VALUE! #VALUE! 7,553.38 #VALUE!
101*45*1.5 withfloat
mm thick clear 5mmglass/
glass tinted coloured glass/ milky glass of
approved
Sliding cummake and 9 mm
fix window thick both
of section side melamine
101*45*1.5 laminated
with 5mm glass
9.2 Sqm #VALUE! 26.43 #VALUE! 6,465.58 #VALUE!
high net
with pressure
shutter particle board wherever required with snap fit
aluminium
Supplying andcolour anodized
fixing beading
of MS grill with special
of 4.5x20mm MS water proof
plate frame
cascades, neoprene etc. complete, as per
and 12x12mm solid core square rod including metal primer specification,
9.3 drawing and instruction of Site Engineer. Sqm #VALUE! 9.6 57.73 #VALUE! 2,564.62 #VALUE!
paint all complete as per design, drawing and instruction of site
engineer.
10 Floor Finishing Works
Providing and laying 8 mm thick non slip ceramic tiles (Spartek,
Kajaria, or approved equivalent) of approved colour, shade and
size on floor in perfect line and level on 20 mm thick base
10.1 Sq. m #REF! #REF! 3,954.66 #REF!
cement sand mortar (1:4) and jointed with white cement slurry
mixed with pigment to match the shade of the tile complete as
per specification, drawing and instruction of Site Engineer.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Summary of Cost of Civil work

#REF!
#REF!
Quantity
Covered Hall Total
S. N. Description Unit Septic Soak Water Rate Amount Remarks
Sub- Super- Manholes Quantity
tank Pit Tank
Structure Structure
Providing and laying 8 mm thick glazed ceramic tiles (Spartek,
Kajaria, or approved equivalent) of approved shade, size and
pattern on wall in perfect line and level on 12.5 mm thick base
10.2 cement sand mortar (1:4) and jointed with cement slurry mixed Sq.m #REF! #REF! 3,954.66 #REF!
with pigment to match the shade of the tile including adhesive
chemical all complete as per specification, drawing and
instruction of Site Engineer.
Providing and laying 16 mm thick granite from Rajasthan, India
of approved quality on wash basin with 30 mm thick cement
10.3 mortar (1:4) including cutting to the required shape, moulding Sq.m #REF! #REF! 4,315.46 #REF!
and polishing all complete, as per specification, drawing and
instruction of Site Engineer.
Providing and laying 16 mm thick marble from Rajasthan, India
of approved quality on floors, staircase, parapet etc. with 30
10.4 mm thick cement mortar (1:4) including cutting to the required Sq.m #VALUE! #VALUE! 4,315.46 #VALUE!
shape, moulding and polishing all complete, as per
specification, drawing and instruction of Site Engineer.
10.5 Parqueting Sq.m #REF! #REF! 3,000.00 #REF!
11 Railing Works
Providing and fixing stainless steel railing of 50mm dia vertical
post and hand rail, 25mm dia three layer horizontal pipe all
11.1 R.m #VALUE! #VALUE! 3,831.04 #VALUE!
complete as per specification, drawing and instruction of Site
Engineer.
12 Roofing Works
12.1 Truss Kg #REF! #REF! 154.72 #REF!
Providing, laying and fixing carbon fiber UPVC roofing sheet
with necessary bolts, J hooks, washers, including necessary
12.2 Sq.m #REF! #REF! 1,600.00 #REF!
overlaps, all complete as per specification, drawing and
instruction of Site Engineer. (5-5.5 Kg/sqm)
Total #REF!

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Bill Of Quantities (Sanitary Work)


#REF!
#REF!
Rate
SN Particulars Quantity Unit
In Figure In Words
Supplying and Fixing Porcelain clay Indian Pattern Comode, Porcelain
1 clay Cistern and seat cover with pipe connector all complete set.
(Hindware, Parryware, or equivalent ).
Indian pattern Comode,Seat cover with low level flushing cistern. 12.0 Set
Supplying and fixing White glaze Porcelain clay wash basin/Oval
50X40Cm with pedestal, Mixture brackets 32mm dia. p trap, 32mm CP
2 waste coupling with CP chain and rubber plug, 15mmx450mm long c.p.
pipe connector etc all complete.(Sanitaryware:-Hindware,parryware or
equivalent).Valve:- jaquar,ark,Ess Ess or equivalent)
Indian pattern White glazed wash basin 50X40cm with basin mixture all
10.0 Set
complete set.
Supplying and fixing White glaze Porcelain clay 46.5x35.5x26.5cm flat
back White glazed Urinal with sensor valve, brackets 32mm dia. p trap,
32mm CP waste coupling with CP chain and rubber plug,
3
15mmx450mm long c.p. pipe connector etc all complete.
(Sanitaryware:-Hindware,parryware or equivalent).Valve:-
jaquar,ark,Ess Ess or equivalent)
46.5x35.5x26.5 cm flat back White glazed Urinal all complete set. 8.0 Set
68 X 30 Cm white glazed urinal Partation with all complete set 7.0 Set
Supplying and Fixing Pvc roof water tank With cover including drain
4 hole ,inlet outlet, over flow etc.all complete set .Hill take, Roof top or
equivalent
1000 litres PVC overhead tank 2.0 Nos.
Supplying and Fixing Electric moter Pump single or three phase phase
5 with base, nut and bolts all complete set (Kirloskar, Compton, Servo,
Sharp,)
2 HP Electric motor Pump monoblock.(crompton) 1.0 Nos.
Supplying and Fixing Indian pattern C.P. valves with wall flange
6
Including c.p. nipple all complete set.
15mm CP bib cock Cock ordinary type 21.0 Set
C.P. 15mm dia Angle valve. 29.0 Nos

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Bill Of Quantities (Sanitary Work)


#REF!
#REF!
Rate
SN Particulars Quantity Unit
In Figure In Words
15 mm comode CP water spray with 1.2mt. Long flexiable pipe. 12.0 Nos
Stainless steel shower wth sliding bar and complete set 12.0 Nos
CP Wall mixture 4.0 Nos
7 Valves with all complete accessories.
GM Gate valve 50 mm dia. 1.0 Nos.
(G.M.) check valve 50 mm dia 1.0 Nos.
Supplying and Fixing UPVC pipe all complete set as per specification
8
and instruction. (Panchakanya , Prince,Supreme )
75mm PVC pipe of 6 kg/cm2 130.0 Rm
110mm PVC pipe of 6 kg/cm2 80.0 Rm
Supplying and fixing PPR and GI Pipe. or equivalent with fittings/
specials (Tees, elbows, Unions etc) clamps(m.s plate with nut and bolt
with hexagonal screws for clamp in ceiling,wall), nails, including jointing
9 materials,installation of pipes and specials including making holes on
walls or floor and repairing the same to its original finish,cleaning of the
system, testing and ready for operation,. all complete set as per
specification and instruction.
20 mm dia P.P.R pipe 145.0 Rm
25 mm dia P.P.R pipe 10.0 Rm
50 mm dia P.P.R pipe 70.0 Rm
Supplying and Fixing UPVC specials with O ring rubber washer,Pvc
10 liquid(Solvent cement), Pvc cream, all complete set as per specification
and instruction. (Panchakanya,Prince,Supreme )
75 mm dia UPVC vent cowl 1.0 Nos.
75 mm dia UPVC plain/door Tee. 18.0 Nos.
75 mm dia UPVC 90 degree bend. 7.0 Nos.
75 mm dia UPVC Y bend. 5.0 Nos.
75 mm dia UPVC 45˚ bend. 4.0 Nos.
75 mm dia UPVC pipe clip 110.0 Nos.
110 mm dia UPVC plain /door Tee. 6.0 Nos.
110 mm dia UPVC 90 degree bend 8.0 Nos.
110 mm dia UPVC Y bend. 10.0 Nos.

Prepared By: Checked By: Approved By:


#REF!
#REF!
#REF!
#REF!

Bill Of Quantities (Sanitary Work)


#REF!
#REF!
Rate
SN Particulars Quantity Unit
In Figure In Words
110 mm dia UPVC 45˚ bend. 8.0 Nos.
110 mm dia UPVC pipe clip 55.0 Nos.
PVC floor trap 11x7.5 cm. 18.0 Nos.
Supplying and Fixing Indian pattern bathroom accessories all complete
11
set.
Modi guard bevelled float mirror 6mm thick with stainfree 0.45x0.60m
Nos.
and bracket all compete set. 14.0
Chrome plate type toilet paper holder. 12.0 Nos.
Chrome plated soap tray. 12.0 Nos.
CP 15mm dia x450mm long towel rod. 11.0 Nos.
Kitchen sink 37" long and 8"deep with sink cock all completed set 1.0 Nos.
Fire pump:-20H.P.x2set or 40H.P. (Head-70.0mtr.,Discharge-
2400Lpm)Fire pump set with 5.0h.p Stainless steel verticle jockey
12 pump,(Main pump start Automatically If jockey pump pressure drop) Set
including control panel board,Required Cable,Stairner for both
pump,pressure switches,pressure guage all complete set, 1.0

Prepared By: Checked By: Approved By:


Total Amaount

Prepared By: Checked By: Approved By:


Total Amaount

Prepared By: Checked By: Approved By:


Total Amaount

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
1.Wiring of light/fan & power points:
1.1 Supply of materials and wiring with PVC Insulated copper wire
in NS Approved HDP conduit without any joint in middle of the
span with necessary connecting, fixing, insulating and jointing
materials as per drawing and specification complete (wire:
Trishakti, Pioneer, Litmus)

1.1 Light/ Fan Points


{a} Light and Fan point with 2x1.5 Sq. mm from point to
switches and 2x2.5+1.1.5 as Light circuit laying from Switch to
DB NS mark cu multistrand cable Including all necessary items
i.e. bends, circular & Junction boxes etc.
point 111
{b} 2 Way light point with 3x1.5 Sq. mm from point to switches
and 2x2.5+1.1.5 as Light circuit laying from Switch to DB NS
mark cu multistrand cable Including all necessary items i.e.
bends, circular & Junction boxes etc. point 4
{c} High and Medium bay, Flood Light point with 2x2.5 sq.
mm/equivalent cu cable, bends, circular & junction Boxes point 71
1.2 Power Points
{a} 5/6 pin 6 x 16 A general outlet point with 2x 4+1x2.5 sq. mm
/ equivalent cu cable, bends, circular & Junction Boxes
point 40
1.3 Outdoor Light Points
{a} Outdoor Street Pole Light point with 3x4.0 Sq. mm Armored
cu cable, bends, circular & Junction boxes point 4

{b} Outdoor Post top Light point with 3x2.5 Sq. mm cu cable,
bends, circular & Junction boxes with civil foundation
point 2
2. Light Fixtures:
supply of light fixtures, fixing, interconnection, testing and
commissioning complete with Holders, CFL, FTL, GLS,
electronic ballast, capacitor with all required mounting and
2.1 fixing accessories as per drawing

Brands: Philips,Wipro or Equivalent.

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
2.1 RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
Indoor Lighting
{a} 2x36 Watt FTL Mirror optics fixture with EB Ballast surface
mounted (LT CS 001 HFB2) set 43
{b} Ceiling Dome Light with 11 watt CFL (CG 80 630) set 36
{c} Dust and jet proof 250W Integral enclosed type HPSV
Medium bay Light (BGEMB 250 SV) set 41
{d} Dust and jet proof 150W Integral enclosed type HPSV
Medium bay Light (BGEMB 150 SV) set 12
{e} Dust and jet proof 70W Integral enclosed type HPSV low
bay Light (BGELB 70 SV) set 14
{f} Black Powder coated Integral, die-cast housing 400W HPSV
Light (LT F1 004) set 4
{g} 14 Watt T8 FTL Picture/Mirror Light Fixture (as per
selection) set 8
{h} Weather proof half-head Light with 11 watt CFL (as per
selection) set 4
2.2 Outdoor Lighting
{a} 9 meter high street light metal pole with required civil works
complete set 4
{b} 70 watt HPSV dia cast sheet aluminum housing with lamp,
Ballast, Control gear, goose neck arm and 3x4 sqmm Cu Ar.
Cable as per drawing and specification (Philips- SRP 48/70(E),
CROMPTON- SSP1207 IH/WI, BAJAJ- BGEST 70 SV DD/02
70 SV or equivalent) set 4
{c} Post top Light fixture with 300 mm Unbreakable Clear Glass
with 18 W CFL Light and 1200 mm SS Stand with required Civil
works (LT GL 105) set 2
3. Fan Fixtures:
3.1 Supply of fan fixtures, fixing, interconnection, testing and
commissioning all complete as per drawing, specification and
instruction
Brands: Crompton, Bajaj or equivalent
220 v, 50 Hz, ceiling fan with J Hook and accessories,
capacitor 1200 mm dia, Heavy duty set 20

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
4. Switches and Sockets
4.1 Supply of switches, sockets as mentioned below, 18 SWG GI
metal boxes , screw, and other necessary materials with its
Installation, Interconnection and commissioning including civil
works as per drawing , specification all complete

Brands: C&S, Legrand, Schneider Clipsal (with prior approval


by designer)
{a} 10 A 1 Gang 1 way switch set 4
{b} 10 A 2 Gang 2 way switch set 0
{c} 10 A 2 Gang 1 way switch set 10
{d} 10 A 3 Gang 1 way switch set 6
{e} 10 A 4 Gang 1 way switch set 10
{f} 200 Watt 5 step Fan rider set 20
{g} 10 A 6 Gang 1 way switch set 2
{h} 5/6 pin 16 A switch socket set 40
5. Power Cable
5.1 Supply, delivery, laying and connecting of the following
Armoured/unarmoured power cable including cable sockets,
pull boxes and necessary materials. chiselling of wall/ floors
and redoing the chiselled area with cement &sand mortar as
per drawing and site condition all complete.
Armoured/ Unarmored cable
{a} 3.5 core 50 sq. mm aluminium armored cable laying
underground with PVC conduit (cable from NEA's kWH meter
and DG set to changeover, from changeover to main panel) rm 60

{b} 4x10+1x4 -E sq. mm copper Cable laying underground with


rm 60
PVC conduit [cable from Main panel Board to FDB-1/4
{c} 4x6+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [cable from Main Panel Board to FDB-2/3; FDB- rm 120
1/4 to SDB -1/4; Main Panel to Switch Panel-1/2

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
{d} 2x4+1x2.5 -E sq. mm copper Cable laying underground with
PVC conduit [from Main Panel Board to Guard blocks and rm 291
fountain, switch panel interconnection]
6. Earthing system
6.1 Supply of materials and Installation of loke copper plate
(600x600x3.14 mm), salt, charcoal dust, 10 mm2 bare copper
cable with solid CAD weld ( Brazing) & watering 32 mm dia
PVC pipe & its installation in a whole of 90x90x250 cm with the
layers of Earthing materials as per standard, specification,
drawing and refilling the ground all complete
set 3
6.2 Supply and installation of 25*3 mm Copper Strip from roof trus
to Earthing station as Lightening protection and bonding of
metal roof to the earthing system kg 30
6.3 Supply and installation of 10 sq. mm bare copper wire with
necessary copper lugs and copper nut bolts connection with
Earthing system on each Electrical Closet as described on the
drawing rm 135
7. Electrical Panel & Distribution Boards
Supply, Delivery, Installation and Commissioning of the
following Distribution Board Including following equipment
housed in lockable, Double Door enclosure made from 16
SWG HRCA Sheet metal and the enclosure shall be finished at
least of two coats of red oxide metal primer and other two coats
of final epoxy enamel paint as per drawing and site condition
(shop drawing of all Distribution Boards shall submit to the
Consultant and get approval before starting the job)

Breaker: Schneider, Legrand


Fabricator: Himalaya/ Hyonjan
7.1 Main Panel Board - MPB set 1
100 Amp Panel Board with copper busabr and hardwrae - 1 set

100 A, TP MCCB - 1 set


Electronic Digital Volt Meter with 7 position Selector - 1 set

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
Electronic Digital Load Meter with 4 position Selector & CTs - 1
set
Indication LED Light with 2 A MCB - 3 set
40 A TP MCCB - 5 set
32 A TP MCB - 5 set
200 A TPNE copper Busbar with all required 1100 Volt Grade
bus Insulator, Colour Bus Sleeve, Power and Control cable,
Cable Lugs/Socket, Terminal Block, Panel wiring materials etc.
all complete
7.2 DBs - [12 Way TPN DB Double Cover 30"x26"x6"] set 4
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
6 A SP MCB - 12 set
16 A SP MCB - 12 set
7.3 External Light Panel [8 wayTPN DB Double Cover 18"x20"x5"]
set 1
32 A, TP MCB -1 set
16 A SP MCB - 6 set
6 A SP MCB - 6 set
7.4 16A DP MCB in Enclosure for Guard House (Only Provision) set 1
7.5 Switch Panel - 1 set 1
40 A, TP MCCB -1 set
32 A TP MCB - 1 set
20 A SP MCB - 6 set
32 A DP Switch - 9 set
7.6 Switch Panel - 2 set 1
40 A, TP MCCB -1 set
20 A, TP MCB -1 set
16 A SP MCB - 3 set
6 A SP MCB - 5 set
16 A DP Switch - 4 set
7.7 100A TPN 4 pole manual chnageover switch within metal
enclosure set 1
8 Telephone system

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
8.1 Supply of materials and wiring in NS approved 10 kg cm2 HDP
conduit concealed without any joint in middle of the span as per
drawing, specification all complete
{a} Telephone points with 3 Pair UTP Telephone cable point 6
8.2 Supply, installation and interconnection of Telephone/TV CDF
with 8 way Power pass booster, splitter for Coaxial and Solder
less crone for RJ-11 as per drawing, specifications all complete
with require power supply for Amplifier

{b} Telephone CDF 400x500mm with hinge door and lockable


system including 1 set Solder less telephone cable termination
module 10 pair set 1
8.3 RJ-11 cable
{a} 10 pairs UTP Telephone cable (for CDF interconnection) rm 46
8.4 Supply, installation & interconnection of sockets of approved
make using proper tools in appropriate GI metal boxes
including civil works & accessories as per drawing and
specification complete. Make: C&S, Legrand, Schneider or
equivalent

{a} RJ 11 Telephone socket set 6


9 NEA Intake
9.1 400 Volt, 3 Phase Energy Meter with 63 A MCCB and Metal
enclosure as per NEA's standard (complete with kWH, MCCB,
Metal meter box, Coordination with NEA etc.)
LS 1
9.2 3.5 core 35 sq. mm aluminium armored cablefrom NEA Tap
poin to kwh meter rm 30
10 Diesel Generator - cummins, jackson or equivalent

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Youth and Sports
National Sports Council
Tripureshwor, Kathmandu

Bill Of Quantities (Electrical)

#REF!
###
RATE
S.No. DESCRIPTION OF WORKS UNIT QUANTITY AMOUNT
In Figure In Word
10.1 Supply, Installation, testing, commissioning and erection of
Fully Enclosed type 40 KVA, 400 Volt, 3 Phase, 50 Hz standby
Diesel Generator set of approved make with all ancillary
equipments [base frame coupling, coupling guard, AMF,
Control panel, exhaust pipe with arrangements, Piping system,
Day tank, canopy, battery its charger RCC Pad & dampers etc.]
for the DG set
set 1

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


REMARKS

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Summary of Cost Estimate

Project Name:- Construction of Convention hall


Location:- Tanahun FY: 073/74

S No Description of work Amount Remarks


A Main Building 167,453,495.97
B Site Development (Landscaping) 5,516,584.26
C Inspection Tank10+10 Nos 248,539.22
D 2 Nos Septic tank 325,977.02
E Water Tank 2,450,213.15
F Soakpit 2 Nos 148,729.63
G Quarter 12,464,398.71
H Sanitary Installation 6,649,620.30
I Electrical Installation 37,278,841.09
J Provisional (Insurance and etc..) 3,805,519.09
K Sum without Vat and contingencies 236,341,918.44 Bid Amount
L Contingencies @ 5% of K 11,817,095.92
M Sum with contingencies (K+L) 248,159,014.36
N VAT @ 13% of M 32,260,671.87
O Sum with Vat (M+N) 280,419,686.23
For Budget Provision
P Physical Contingency @10% of M 24,815,901.44
Q Price Adjustment Contingencies @10% of M 24,815,901.44
Grand Total Cost (O+P+Q) 330,051,489.11

Prepared by- Checked by- Recommended by- Approved by-