ASSIGNMENT 7
Create operational planning includes:
1. Plan of Activity
● Development of proposal (Result, Discussion, and Conclusion)
● Trials of the product
● Share the google form to the cohort group and friends
● Senosry evaluation (9-point hedonic scale)
● Data collection and analysis
2. Plan of Human Resources
● Need 30 semi-trained panelists
● Panelists perform a sensory test for approx. 10 minutes
● The panel leader need to understand the concept of the product
3. Plan of Equipment and Materials
Materials
a. 500 mL UHT full cream
b. 500 g Soybean
c. 2 sachets of Yogurt starter
d. 1500 mL water
Equipment
a. Cheesecloth
b. Temperature
c. Refrigerator
d. Grinder
e. Bowl
f. Stove
g. Saucepan
h. Jars
i. pH meter
j. Viscometer
k. Whisk
4. Plan of Time Schedule

Date Activity

27 October MidTerm Paper Submission

22 - 25 Nov 2022 Product Trial

28 Nov 2022 Product Manufacturing

28 - 30 Nov 2022 Sensory Evaluation

28 Nov - 12 Dec 2022 Physicochemical Observations

12 - 16 Dec 2022 Data Collection and Completion of


Clarica (21010004), Edelin N. (20010103), Gabriella E.K.M (21010005) November 16th, 2022

Paper

5. Plan of Budget

No Description Unit Price per unit Total Price per unit

1 Commercial Milk 1 Rp17.000 Rp17.000

2 Soybeans 500 g Rp10.000 Rp10.000

3 Yogurt Starter 2 Rp6.000 Rp12.000

4 Water 1500 mL Rp6.500 Rp6.500

TOTAL Rp45.500

6. Statement of Assumptions
● All team members will done their task as expected
● Laboratory room and equipment must be borrowed from 1-2 weeks before use
● All budgets need to be used carefully
● The temperature of yogurt need to remains stable during the bacteria
development
● Soy milk will be made using soybeans from the market
● The bacteria used are in a package or referred as yogurt starter
● All of the equipment used need to be as aseptic as possible in order to avoid
contamination
7. Plan of Monitoring
● The progress stick to the proposal
● All of the members are responsible for time schedule agreed
● Accordance to budget plan