You are on page 1of 20

The current issue and full text archive of this journal is available on Emerald Insight at:

https://www.emerald.com/insight/1366-4387.htm

Toll road
Assessment of the government’s projects
role performance in public-private
partnership (PPP) toll road
projects in Indonesia 239
Mohammad Arif Rohman Received 30 July 2019
Revised 7 February 2020
Department of Civil Engineering, Construction Management Laboratory, 14 May 2020
Institut Teknologi Sepuluh Nopember, Surabaya, Indonesia 20 October 2020
5 January 2021
24 May 2021
Accepted 19 July 2021

Abstract
Purpose – This study aims to investigate the government’s role in the development of toll road projects that
adopt public-private partnership (PPP) schemes in Indonesia. In addition to investigating its role, this study also
attempts to quantitatively assess its performance as the use of quantitative analysis in this area is still fairly
limited. The analysis was developed from the perspectives of two main stakeholders involved: government and
private sectors. The findings of this study are expected to help both government and private sectors to better
understand the government’s role as well as its performance in PPP toll road projects in Indonesia.
Design/methodology/approach – The data was analysed by using statistical methods. Following the
identification of the government’s role in PPP toll road projects from the literature, a preliminary survey
involving 12 highway construction experts was conducted to verify the initial findings from the literature
review. Subsequently, the authors conducted a survey of 146 respondents from both government and
private sectors. To analyse the collected data, both descriptive and inferential statistics were used, which
include analysis of means, analysis of reliability, as well as independent T-test. T-test was used to examine
differences in perception between the two groups.
Findings – In total, 12 criteria from the literature were used to assess the government’s role and its
performance in PPP toll road projects in Indonesia. Based on the analysis, the authors find that the
government’s role in the development of PPP toll road projects can be considered moderate in its performance.
In this respect, the author argue that, instead of focusing on meeting all the criteria, it would be better for
government to focus on meeting only a number of them, which include realizing smooth land acquisition,
selecting appropriate concessionaire, offering a solution to community protests over environmental issues,
providing substantial government support, providing supervision, enforcing the law and eradicating
corruption. The results of this study provide valuable information for international parties aiming to
participate in PPP toll road projects in Indonesia, considering this country has been offering a wide
opportunity for private sectors to be involved in developing infrastructure. Meanwhile, for the host
government, the findings can be used as the basis for conducting improvements to attract private sectors’
involvement and to achieve more successful upcoming PPP toll road projects in Indonesia.
Research limitations/implications – The findings of this study might provide valuable information
for the host government to evaluate its role and performance to achieve more successful PPP toll road projects
in the future. Rather than focusing on all attributes, the improvements can be made by focusing only on the
critical ones: those ranked high on the importance and low on its performance. In addition, this finding can
also help private sectors to better understand both the role and performance of government in Indonesia as
this country offers a great opportunity for infrastructure investment through PPP schemes.
Practical implications – The findings of this study might provide valuable information for the host
government to evaluate its role and performance to achieve more successful PPP toll road projects in the future.
Journal of Financial Management
of Property and Construction
Vol. 27 No. 2, 2022
The main author thanks The Indonesian Ministry of Research, Technology and Higher Education pp. 239-258
which sponsored this research. The authors also thank all respondents who participated in the © Emerald Publishing Limited
1366-4387
interviews and questionnaire survey. DOI 10.1108/JFMPC-07-2019-0065
JFMPC Rather than focusing on all attributes, the improvements can be made by focusing only on the critical ones: those
ranked high on the importance and low on its performance. In addition, this finding can also help private sectors to
27,2 better understand both the role and performance of government in Indonesia as this country offers a great
opportunity for infrastructure investment through PPP schemes.
Social implications – Text.
Originality/value – This paper contributes to the body of knowledge on the criteria to assess the
government’s role performance in the Indonesian PPP toll road projects. Whilst there is still limited research
240 has been conducted regarding the government’s role in the PPP toll road projects in Indonesia, this study
presented the criteria of the government’s role and showed how to assess and evaluate the host government’s
performance based on these criteria in a more objective approach using quantitative method. This result can
be used as the basis for improvements to achieve a more successful PPP toll road project in Indonesia and
might be in other similar developing countries.
Keywords Project success, Toll roads, Government’s role, Indonesian infrastructure,
Public-private partnerships (PPP)
Paper type Research paper

1. Introduction
Infrastructure plays an essential role in economic development. For a developing country, it
is expected that public-private partnerships (PPP) can offer solutions in regard to the budget
limitation in developing public infrastructure by collaborating with private sectors. In
Indonesia, toll road has been a vital project, especially for these past few years, as the
Government of Indonesia (GoI) intends to develop toll roads to support the country’s
economic growth (Wibowo, 2005; Rohman, 2017). Unfortunately, the development of toll
road projects in Indonesia has not been quite successful. Even though toll roads in Indonesia
have been built since 1978 and the private sector has been involved since the 1990s
(Abednego and Ogunlana, 2006), there is only 2,000 km of toll roads under the operational
stage (Badan Pengatur Jalan Tol (BPJT), 2019; DetikFinance, 2019).
Although several factors have been reported as the causes of this problem, it is important
to note that the success of the PPP project heavily depends on the role of the government. It
is the host government’s role to ensure political and economic stability, good governance,
favourable legal and regulatory framework, transparent procurement mechanism and well-
committed public agency (Zhang, 2005a).
Previous studies have proposed the attributes of government’s role in PPP projects
(Birgonul and Ozdogan, 1998; Kumaraswamy and Zhang, 2001; Zhang, 2005a; Kwak et al.,
2009), including the critical success factors (CSF) (Chan et al., 2010; Wibowo and Alfen,
2015). However, there is still limited investigation that focuses on the attributes of the
government’s role in PPP toll road projects in Indonesia. Indonesia as a developing country
has been offering a massive opportunity to the involvement of the private sector in public
infrastructure development. Moreover, research on this topic that uses a quantitative
approach to assess stakeholders’ perceptions is still scarce.
This paper focuses on the examination of the government’s role and its performance in
PPP toll road projects in Indonesia. This study uses a quantitative approach to assess
the perceptions of two main stakeholders involved: government and private sectors. The
perceptions of these two stakeholders are essential to the comprehensive examination of
the government’s role and its performance in PPP toll road projects. The goal of this paper
can be divided into three objectives, namely, to find out the criteria or attributes to measure
government’s role in PPP toll road projects, to assess the performance of government’s
role based on stakeholders’ perceptions and to find room for improvement in government’s
role to deliver better PPP toll road implementation in Indonesia.
2. Literature review Toll road
2.1 Public-private partnerships toll road implementation in Indonesia projects
Traditionally, the government is responsible for public infrastructure provision (Tsamboulas
et al., 2012). However, infrastructure provision in developing countries is often limited by
technology as well as the budget of the government (Kumaraswamy and Zhang, 2001). PPP
concept has been widely proposed to overcome the public sector’s limitation as it is believed
that it has many advantages such as potentially using private sector’s resources, stirring up
innovation, improving productivity, providing better risk allocation, promoting value for 241
money and delivering cost-effectiveness (Ng et al., 2012).
According to Wibowo (2005), for a number of years toll road projects have become essential
PPP projects in Indonesia as the government aims to support the country’s economic growth
through either built-operate-transfer (BOT) or operation-and-maintenance-contract scheme as
parts of the PPP scheme. Badan Perencanaan Pembangunan Nasional (BAPPENAS) (2010)
explains that 17 out of 26 priorities for PPP projects between 2010 and 2014 were toll road projects.
To attract private sectors, several actions were carried out by the GoI to streamline the
process such as establishing a new policy regulation framework (Wibowo and
Kochendoerfer, 2011). However, Rostiyanti and Tamin (2010) assert that those actions have
not been entirely successful to attract the involvement of private sectors because, since 2005,
there have been insignificant changes in toll road length in the operation phase. Indeed,
attracting private sectors in infrastructure development is not as simple as it appears, as this
type of project involves a high degree of risks (Wibowo and Kochendoerfer, 2011).
Problems regarding the implementation of toll roads have been identified by Rostiyanti
and Tamin (2010). Some of them include excessive government intervention in the process,
limited support from the government, as well as complex and conflicting regulations.
Abednego and Ogunlana (2006) also point out that there are often delays in the decision-
making process which can negatively impact the smooth running of the implementation.
The literature suggests that PPP is not a panacea that can solve all problems and is
suitable for all project settings (Cheung et al., 2012). Implementing PPP is not easy work as
this concept requires certain and particular environments to be successfully implemented (Li
et al., 2005a; Chan et al., 2010; Hwang et al., 2012). In this respect, the success of PPP toll road
projects is influenced by a number of factors such as transparency of procurement process,
good governance, a reliable and good private consortium, political support, stable
macroeconomic condition, favourable legal framework, guarantee and involvement from the
government, well-organized and committed public agency, as well as appropriate risk
allocation and sharing (Li et al., 2005a; Chan et al., 2010; Hwang et al., 2012). Those
aforementioned factors are highly influenced by the role of the government as the main actor
in the PPP project (Kwak et al., 2009). Therefore, we argue that the government’s role is an
important factor for the success of this type of project.

2.2 Government’s role in public-private partnerships projects


Several scholars have conducted studies on the government’s role in PPP projects. Birgonul
and Ozdogan (1998) propose a framework for the Turkish Government to implement a
systematic decision-making system in the BOT project. They emphasize the importance of
setting up appropriate evaluation criteria in the procurement method to ensure the
successful implementation of this type of project.
Kumaraswamy and Zhang (2001) present evidence of unsuccessful PPP projects in
Thailand and Lao PDR due to the failure in the government’s role. Aside from that, they also
identify several aspects that need to be considered by the government to ensure
the successful implementation of the PPP scheme. Likewise, Zhang (2005a) highlights
JFMPC the attributes of the government’s role that need to be taken into account, namely, adequate
27,2 regulatory framework, capable central coordinating unit, appropriate government support
and clear responsibilities of governmental bodies (Kwak et al., 2009). In this case, the
government has crucial roles that need to be considered, which include creating favourable
investment environment, providing an adequate regulatory framework, establishing
coordinating authority and selecting an appropriate concessionaire.
242 Although several studies on this topic are readily available in the literature, they might
not apply to the Indonesian context. Similar to the success criteria which vary among
countries, sectors and projects (Muhammad and Johar, 2018), the government’s role in PPP
projects may also differ among countries. In regard to the Indonesian context, there are
several studies on PPP. Abednego and Ogunlana (2006), for instance, propose a good
governance framework for better risk allocation in the implementation of PPP toll road
projects in Indonesia. Rostiyanti and Tamin (2010) investigate several challenges on toll
road development under the PPP scheme such as problems related to legal and regulatory
frameworks. Meanwhile, Bustaman and Ramayandi (2012) examine the existing barriers of
PPP toll projects by empowering PPP central unit (P3CU). In this respect, P3CU is a PPP
unit that has several functions such as formulating policy and assessment for contingent
government support, supporting government contracting agencies for the preparation of the
projects and developing capacity within government agencies for PPP implementation
(Badan Perencanaan Pembangunan Nasional (BAPPENAS), 2010).
Nevertheless, despite several studies pertaining to PPP projects that have been conducted in
Indonesia, there is still limited attention given to the area of government’s role under the PPP
scheme, especially in toll road projects using a quantitative approach. Moreover, most studies
related to the government’s role in PPP projects only focus on the examination of the importance
of the criteria, without evaluating its performance. Meanwhile, the evaluation of the government’s
performance is necessary to identify gaps for improvement (Wibowo and Alfen, 2015). Therefore,
this research aims to fill the gaps by examining the government’s role and its performance in PPP
toll road projects in Indonesia using a quantitative approach.

3. Research design
3.1 Identification of research variables
Identification of research variables was carried out by selecting attributes from previously
published works. Studies on the government’s role in PPP projects, CSF, risks in PPP projects, as
well as barriers of PPP implementation were carefully reviewed and synthesized to generate the
attributes of the government’s role. We identified many factors related to this topic from the
literature. Nonetheless, there are a number of attributes that overlap with each other as they share
similar characteristics. Thus, we either delete them or combine them into meaningful categories.
At the final stage, we managed to identify a total of 12 attributes of the government’s role in PPP
projects. These attributes are further classified into seven major categories (Table 1).
As depicted in Table 1, there are seven major categories: selecting and planning on
appropriate PPP projects, providing favourable investment environment, developing legal
and regulatory framework, conducting competitive procurement and contractual
arrangements, providing supports and guarantees, establishing good governance in
bureaucracy and monitoring and supervising project implementation. To test the validity of
these attributes, we conducted an interview with 12 highway construction experts.

3.2 Preliminary survey


Preliminary survey involving 12 experts from the industry was conducted to validate the
12-attributes identified from the literature (Ng et al., 2010). All the experts have more than
No. Government’s role attributes Sources
Toll road
projects
I. Appropriate project selection and planning
Selection of a feasible PPP project Birgonul and Ozdogan (1998), Qiao et al. (2001);
Zhang (2005a) and Ng et al. (2012)
II. Providing a favourable investment environment
Provision of stable and conducive political Qiao et al. (2001), Kumaraswamy and Zhang
environment (2001); Li et al. (2005a); Kwak et al. (2009), Chan 243
et al. (2010) and Ng et al. (2012)
Provision of stable and conducive economic Kumaraswamy and Zhang (2001), Qiao et al.
conditions (2001); Li et al. (2005a); Kwak et al. (2009) and
Chan et al. (2010)
III. Establishment of an adequate regulatory
framework and appropriate support
Realization of the smooth land acquisition process Kumaraswamy and Zhang (2001), Wibowo and
Mohamed (2010) and Abednego and Ogunlana
(2006)
Solving community protests regarding the Ng et al. (2012) and Doloi (2012)
environmental issues
Provision of appropriate government support Qiao et al. (2001), Kumaraswamy and Zhang
(2001); Li et al. (2005a); Kwak et al. (2009) and
Chan et al. (2010)
IV. Establishment of good bureaucracy
Simplification of bureaucracy procedures Ozdoganm and Birgonul (2000); Li et al. (2005a);
Chen and Doloi (2008) and Ke et al. (2009)
Law enforcement Zhang (2005a) and Rostiyanti and Tamin (2010)
Corruption eradication Zhang (2005b) and Chan et al. (2011)
V. Selection of an appropriate concessionaire and
supervise the project implementation
Selection of the appropriate concessionaire Birgonul and Ozdogan (1998), Kumaraswamy and
Zhang (2001); Zhang (2005b); Li et al. (2005a);
Kwak et al. (2009) and Ng et al. (2012)
Appropriate supervision Qiao et al. (2001); Li et al. (2005b) and Wibowo and Table 1.
Mohamed (2010) Attributes for the
Development of good communication between Chan et al. (2011) and Doloi (2012) government’s role in
government and the private sector PPP projects

five years of field experience and were involved in at least three toll road projects. Semantic
scale from 1 (not very relevant) to 5 (very relevant) was used to measure experts’ opinions.
Mean and standard deviation (SD) were used to analyse the relevancy and importance of
the attributes. As stated before, this study adopted Rohman and Wiguna (2019), who use the
middle score (3.00) as the cut-off to determine the relevance of the attributes. Thus,
attributes with a mean higher than 3.00 are considered relevant to be included in the
measurement of the government’s role. Experts’ opinion regarding the 12-attributes from the
preliminary survey is presented in Table 2.
As shown in Table 2, the mean of all attributes identified from the literature is
larger than the cut-off point (3.00). Majority of them (9 out of 12) even have a higher
mean score than 4.00 and only three attributes have an average score of slightly lower
than 4.00. Therefore, the overall attributes were considered to be relevant in the
measurement of the government’s role in PPP toll road projects in Indonesia.
The rank of the five most important attributes, listed from the most relevant to the least
relevant, is as follows: realization of the smooth land acquisition process (mean 4.83),
JFMPC
27,2 No. Government’s role attributes Mean SD

1 Realization of smooth land acquisition process 4.83 0.389


2 Selection of the appropriate concessionaire 4.75 0.452
3 Solving community protests regarding environmental issues 4.58 0.515
4 Provision of appropriate government support 4.58 0.669
244 5 Appropriate supervision 4.58 0.515
6 Simplification of bureaucracy procedure 4.33 0.888
7 Law enforcement 4.25 0.622
Table 2.
8 Selection of a feasible PPP project 4.17 0.835
Experts’ survey 9 Development good communication between the government and the concessionaire 4.17 0.718
results for the 10 Provision of stable economic condition 3.92 0.669
government’s role 11 Corruption eradication 3.92 1.240
attributes’ relevancy 12 Provision of the stable political condition 3.83 0.555

selection of the appropriate concessionaire (4.75), solving community aspiration regarding


the environmental problems (4.58), provision of appropriate government support (4.58) and
appropriate supervision (4.58).

3.3 Main survey


To assess the performance of the government’s role, a survey was conducted by administering a
questionnaire. We use the questionnaire in the main survey as it covers a wider geographical
distribution of the population (Kumar, 1997). To keep the main questionnaire simple and
understandable to the respondents, it was designed in the form of a plain language system. We
use a five-point Likert Scale, namely, 1 (strongly disagree), 2 (disagree), 3 (neutral), 4 (agree) and 5
(strongly agree). The design used positive statements expressing respondents’ agreement. If the
respondents were satisfied, the score should be at least 4.00 (agree).
However, before the main survey was conducted, a pilot test was performed to make sure
that the questionnaire was fully understood by the respondents (Ng et al., 2010). In this pilot
test, 11 respondents were involved in the pilot test and after that, the questionnaire was
considered ready to be used in the main survey. Hand, postal and email deliveries were used
to distribute the questionnaire.
In this survey, stakeholders in PPP toll roads were targeted as respondents. According to
Yuan et al. (2010), there were four types of stakeholders in PPP projects: public sector
(government), private sector (designers, consultants, contractors, sub-contractors and
suppliers), general public and research group. However, Ng et al. (2012) only categorized the
stakeholders into three categories, namely, government, private sector and community
directly and/or indirectly affected by the implementation of PPP toll road projects.
The targeted respondents in this study include government and private sectors as they
are considered as the main actors in the PPP model. Whilst the former involves government
staff from national to village levels, the latter includes toll road operator staff, consultants,
contractors and sub-contractors. The criteria involve individuals who have prior experience
in the development of toll road projects, thus they have a comprehensive understanding of
how the project is built and performed during the operation stage. The main survey was
conducted from April to June 2014 for eight toll road projects under study.

3.4 Research objects selection


This study focused on toll roads that were developed after 1998 and, at the time of the
survey, are currently in the operational stage. Eight projects were selected as the research
objects that fulfill the requirements, namely, more than 5 km and are already in the Toll road
operational stage. Toll roads that had lengths less than 5 km were considered unfinished projects
projects because they were parts of a full toll road path (have not been fully operated).
Meanwhile, the operational project was selected to comprehensively understand the
government’s role performance during the overall project life cycles.
The eight toll road projects under study are located in Waru-Juanda, Kanci-Pejagan,
Semarang-Ungaran, Ulujami-Serpong, Cipularang, Jakarta Outer Ring Road (JORR) W1, 245
JORR E1 and JORR E2. All of those toll roads are located in Java Island, which is the densest
population in Indonesia (Badan Pusat Statistik (BPS), 2010). Therefore, the above toll roads
are considered suitable to represent the Indonesian context as most of those toll roads are
located in Java Island.

4. Result analysis
The main survey was conducted following the primary survey and the pilot test through
questionnaire distribution across eight selected toll road projects in Indonesia under the PPP
scheme. A total of 146 samples were obtained from the main survey and explained in the
next section.

4.1 Data preparation


The samples were cleaned to ensure that they were ready to be analysed using the statistical
method. According to the analysis, the data fulfill all the requirements and they can be
classified as a normal distribution.

4.2 Respondents’ background


There were 73 samples (50%) from the government and 73 samples (50%) from the private
sector. Table 3 provides the characteristics of the respondents. The majority of respondents
are from Waru-Juanda (54.800%), whilst only a number of them are from Kanci-Pejagaan
(0.700%). Most of the respondents also have bachelor’s degrees (50.000%) and are from
engineering majors (76.000%).

4.3 Reliability test


The sample’s reliability is a necessary investigation and is commonly measured using
Cronbach’s alpha coefficient (Hair et al., 2010). Field (2005) claims 0.700 as the cut-off for an
acceptable result. The sample has excellent reliability since, based on the analysis, the
Cronbach’s alpha coefficient was 0.810, meaning so high and above 0.700.

4.4 Attributes’ performance ranking and comparison


The mean data analysis is presented in Table 4 where every attribute is written using the
notation of government role (GR) from GR 1 to GR 12. According to the overall sectors
(combination of the two respondents’ perception), the five highest attributes of government’s
role are the selection of a feasible PPP project (4.089), the provision of stable political
condition (3.966), the provision of stable economic condition (3.893), the provision of
appropriate government support (3.822) and the development of good communication
between the government and the concessionaire (3.747). Meanwhile, the five lowest
attributes performance were the realization of the smooth land acquisition process (3.096),
appropriate supervision (3.381), corruption eradication (3.411), the selection of appropriate
concessionaire (3.432) and simplification of bureaucratic procedure (3.610).
JFMPC Respondent’s Percent Percent
27,2 Group category Group type frequency (%) (cumulative)

Sector Government 73 50.00 50.00


Private 73 50.00 100.00
Toll road name Cipularang 20 13.70 13.70
Jakarta Outer Ring Road (JORR 3 2.10 15.80
246 E1)
Jakarta Outer Ring Road (JORR 1 0.70 16.50
E2)
Jakarta Outer Ring Road (JORR 10 6.80 23.30
W1)
Kanci-Pejagan 14 9.60 32.90
Semarang-Ungaran 17 11.60 44.50
Ulujami-Serpong 1 0.70 45.20
Waru-Juanda 80 54.80 100.00
Education level Doctorate 2 1.37 1.40
Master 49 33.56 34.93
Bachelor 73 50.00 84.93
Diploma 3 2.06 86.99
Senior high school 13 8.90 95.89
Junior high school 3 2.06 97.95
Primary school 1 0.69 98.63
Table 3. Missing data 2 1.37 100.00
Respondents Education Engineering 111 76.00 76.00
background category Non-engineering 35 24.00 100.00

Overall sector Government Private


No. Attributes Mean Ranking Mean Ranking Mean Ranking

GR12 Selection of a feasible PPP project 4.089 1 4.068 1 4.110 1


GR1 Provision of the stable political condition 3.966 2 3.877 5 4.055 2
GR2 Provision of stable economic condition 3.893 3 3.877 4 3.909 3
GR11 Provision of appropriate government 3.822 4 3.932 2 3.712 4
support
GR8 Development of good communication 3.747 5 3.822 6 3.671 5
between government and the concessionaire
GR7 Solving community protests regarding the 3.733 6 3.808 7 3.658 6
environmental issues
GR3 Simplification of bureaucracy procedure 3.705 7 3.904 3 3.507 9
GR5 Law enforcement 3.610 9 3.726 8 3.493 10
GR10 Selection of the appropriate concessionaire 3.432 8 3.342 10 3.521 8
(transparent tender)
GR4 Corruption eradication 3.411 10 3.644 9 3.178 11
Table 4. GR9 Appropriate supervision 3.381 11 3.123 12 3.639 7
Mean analysis for the GR6 Realization of the smooth land acquisition 3.096 12 3.219 11 2.973 12
government’s role process
attributes Mean 3.657 3.695 3.619

Selection of a feasible PPP project was the attribute ranked the highest among other
attributes (4.089), as well as from the perceptions of government (4.068) and private sector
(4.110). This finding indicates that all parties share the view of this attribute being a good
measure of government’s performance.
The provision of stable political conditions (mean 3.966) and the establishment of stable Toll road
economic conditions (mean 3.893) are placed in the second and third positions, respectively. projects
Nevertheless, the government has a different view of these two attributes. The government
ranks the provision of stable economic condition in fifth place (mean 3.877), whilst the
private sector ranks this attribute in second place (mean 4.055). Meanwhile, the provision of
the stable economic condition is ranked fourth (mean 3.877) from the government
perspective whilst the private sector places this attribute in the third position (mean 3.909).
The fourth position of the government’s role performance was the provision of
247
appropriate government support (mean 3.822). Again, the government shared a different
perception with the private sector as this attribute was ranked in second place (mean 3.932).
However, according to the private sector’s view, this attribute was positioned in fourth place
(mean 3.712). Good communication between the government and the private sector ranked
fifth among the overall attributes (mean 3.747). Nevertheless, this attribute was placed in the
sixth position according to the government (mean 3.822) and fifth position according to the
private sector. The realization of the smooth land acquisition process was ranked the lowest
among the overall government’s role performance attributes (3.096). Even though the
government ranked this attribute in the 11th position, the private sector placed this attribute
in the lowest position, namely, the 12th position.
The highest difference in perception between the two sectors was regarding the
appropriate supervision attribute (0.516). In this case, those who belong to the private sector
perceived that they had already been supervised sufficiently by the government (mean
3.639), even though the government did not have a similar perception about it (mean 3.123).
The second-highest difference perception between the government and the private sector
was related to the corruption eradication attribute (0.466). The government perceived that
they had already performed corruption eradication (mean 3.644), whilst the private sector
gave a lower score about it (mean 3.178). The third highest difference perception between the
government and the private sector was on the simplification bureaucracy procedure (0.397).
In this case, the government scored this attribute higher (mean 3.904) compared to the
private sector (mean 3.507). Meanwhile, for the other nine attributes, the difference in means
ranged between 0.032 and 0.023.
Table 4 also showed that the overall sector performances were still below the satisfactory
level (4.000) or called sub-optimal. Only one attribute obtained a score above 4.000 from a
total of 12 attributes. Meanwhile, 11 other attributes had scores under 4.000. The average
score from the 12 GR’s attributes was 3.657 (below 4.000). The attributes scored between
3.000 (neutral) and 4.000 (agree). It can be said that the performance is still not optimal
because, as explained in research design Section 3.3, to be considered having good
performance, the minimum score for an attribute should be more than 4.000 (agree) because
the questionnaire was designed as positive statements to represent the respondents’
agreement (Rohman et al., 2017). Therefore, the score should be at least 4.000 (agree) if the
respondents are satisfied with the attributes’ performance.

4.5 Attributes performance classification


To assess the attributes’ performance easily, the 12 attributes’ scores were classified into
several groups (Rohman and Wiguna, 2019). Based on the performance classification, the
attributes that had means between 4.000 and 5.000 were considered “good performance”.
Secondly, the ones that had means between 3.000 and 4.000 were considered “moderate
performance”. Finally, the ones that had means between 0.000 and 2.990 were considered
“poor performance”.
JFMPC Referring to the classification above, the results can be classified into two levels: “good”
27,2 and “moderate”. However, only one attribute can be classified as having “good
performance”, which is the selection of feasible PPP projects. Most of the attributes (11
attributes) are categorized as “moderate performance” with means between 3.996 and 3.096,
namely, provision of a stable political condition, provision of appropriate government
support, development of good communication between government and the private sector,
248 solving community protest regarding the environmental issues, simplification of
bureaucracy procedure, law enforcement, selection of the appropriate concessionaire,
corruption eradication, appropriate supervision and realization of the smooth land
acquisition process.

4.6 Independent sample t-test


According to the attribute ranking comparison in Section 4.4, it seems that there were
different perceptions between the government and the private sector. However, it still cannot
be concluded that there was a difference in perceptions between the two sectors unless it
was validated by statistical analysis. Therefore, an independent t-test was needed to find out
the difference between the two sectors’ means (Field, 2005).
Independent t-test is part of the parametric statistical analysis which can be used to
analyse any different perceptions between the two sectors (Ng et al., 2012; Cheung et al.,
2012). This test was selected because the data were categorized as normal distribution as
stated in Section 4.1. In this independent t-test, a significant variation is detected between
the government and private sectors if the significance level is below 0.050 as the threshold.
Table 5 shows the results of the independent t-test analysis for all the GR attributes.
Based on Table 5, most of the p-values for the attributes were larger than 0.050. Only did
three attributes that have p-values smaller than 0.050, namely, GR3 simplification of
bureaucracy procedure, GR4 corruption eradication and GR9 appropriate supervision.
According to the result, it can be concluded that the difference in perception between the two
sectors was overall quite significant based on the independent t-test result. Out of the 12
attributes, only in three attributes that the government and private sector perceptions’ differ.
Meanwhile, the government had similar (did not differ statistically significant) perceptions
with the private sector in the rest nine attributes.
The reason for the significant differences in the three attributes is likely because these
attributes are related to the problem, namely, the lack of a regulatory framework that the
private sector still faces. As revealed by Rostiyanti and Tamin (2010), there is a condition
where there are still many regulations that exist in every level of bureaucracy, which may be
ambiguous and sometimes conflicting with each other. The difficulty in coordination
between any government bodies involved (Wibowo and Alfen, 2015) could happen due to
the lack of a regulatory problem. Indeed, unclear procedures and regulations can potentially
cause corruption to act as many problems must proceed behind the door (Zhang, 2005b).
Finally, the lack of standard can also cause ambiguity between any parties involved
regarding how the project supervision should be conducted.
However, based on the independent t-test result in general, it can be concluded that the
two sectors did not have different opinions on most of the attributes. Accordingly, it can be
concluded that the questionnaire was valid for the analysis (Cheung et al., 2012). The result
is also supported by the reliability test, showing that the questionnaire was reliable.

5. Discussion
According to the analysis result, it is found that the existing government’s role performance
in PPP toll road projects in Indonesia is still not quite satisfying (moderate level) where the
Levene’s test for
equality of variances t-test for equality of means
95% confidence interval
of the difference
Sth.
Sig. Mean error
F Sig. t df (two-tailed) difference difference Lower Upper

GR1 Equal variances 1.008 0.317 1.429 144 0.155 0.17808 0.12465 0.42447 0.06831
assumed
Equal variances not 1.429 134.167 0.155 0.17808 0.12465 0.42462 0.06846
assumed
GR2 Equal variances 0.418 0.519 0.268 144 0.789 0.03237 0.12058 0.27071 0.20596
assumed
Equal variances not 0.268 143.471 0.789 0.03237 0.12058 0.27072 0.20597
assumed
GR3 Equal variances 4.533 0.035 2.816 144 0.006* 0.39726 0.14105 0.11846 0.67607
assumed
Equal variances not 2.816 143.798 0.006* 0.39726 0.14105 0.11845 0.67607
assumed
GR4 Equal variances 0.172 0.679 2.923 144 0.004* 0.46575 0.15933 0.15083 0.78068
assumed
Equal variances not 2.923 143.477 0.004* 0.46575 0.15933 0.15082 0.78069
assumed
GR5 Equal variances 3.096 0.081 1.619 144 0.108 0.23288 0.14385 0.05146 0.51721
assumed
Equal variances not 1.619 143.277 0.108 0.23288 0.14385 0.05147 0.51723
assumed
GR6 Equal variances 0.015 0.901 1.403 144 0.163 0.24658 0.17580 0.10090 0.59406
assumed
Equal variances not 1.403 143.988 0.163 0.24658 0.17580 0.10090 0.59406
assumed
GR7 Equal variances 6.628 0.011 1.308 144 0.193 0.15068 0.11520 0.07702 0.37839
assumed
1.308 137.535 0.193 0.15068 0.11520 0.07711 0.37848
(continued)

role attributes
Toll road

Table 5.

the government’s
249

Independent t-test for


projects
27,2

250

Table 5.
JFMPC

Levene’s test for


equality of variances t-test for equality of means
95% confidence interval
of the difference
Sth.
Sig. Mean error
F Sig. t df (two-tailed) difference difference Lower Upper

Equal variances not


assumed
GR8 Equal variances 2.014 0.158 1.134 144 0.259 0.15068 0.13287 0.11195 0.41332
assumed
Equal variances not 1.134 143.804 0.259 0.15068 0.13287 0.11195 0.41332
assumed
GR9 Equal variances 56.095 0.000 3.617 144 0.000* 0.51596 0.14265 0.79791 0.23400
assumed
Equal variances not 3.617 105.307 0.000* 0.51596 0.14265 0.79879 0.23312
assumed
GR10 Equal variances 0.481 0.489 1.089 144 0.278 0.17808 0.16359 0.50143 0.14526
assumed
Equal variances not 1.089 142.997 0.278 0.17808 0.16359 0.50145 0.14528
assumed
GR11 Equal variances 19.026 0.000 1.679 144 0.095 0.21918 0.13058 0.03892 0.47727
assumed
Equal variances not 1.679 127.443 0.096 0.21918 0.13058 0.03920 0.47756
assumed
GR12 Equal variances 0.148 0.701 0.385 144 0.701 0.04110 0.10665 0.25189 0.16970
assumed
Equal variances not 0.385 142.776 0.701 0.04110 0.10665 0.25191 0.16972
assumed

Note: *Italic bold means there are significant different perceptions between the two sectors
attributes mean are still below 4.000 (four) score as the minimum score which shows the Toll road
respondent’s agreement related to good attribute performance. This study confirmed a projects
previous study that revealed that the performance of PPP success factors related to the
government is still somewhat below moderate (Wibowo and Alfen, 2015). Perhaps, this is
the reason for the quite unsuccessful implementation of the existing toll road projects in
Indonesia.
The above result should become the reason for the host government to perform some
improvements on its role in the PPP scheme. The GoI should perform its role better to
251
achieve more successful PPP toll road projects. Indeed, the success or failure of any PPP
project heavily depends on the government’s role (Kumaraswamy and Zhang, 20010). PPP is
not a panacea that can be implemented in all project environments. There are some
prerequisites for the successful implementation of this scheme where several of them only
can be provided by the host government. The willingness of the private sectors to be
involved in these projects greatly depends on the government’s role performance in the host
country (Zhang, 2005b). It happens where the government can provide a conducive
environment to support business operations.
Based on the government’s role evaluation, it was found that most of the attributes need
improvement as 11 out of 12 attributes scored lower than 4.000 as the minimum score.
However, rather than the overall attributes, the improvement could be focused on solely some
of them which were considered critical (Rohman and Wiguna, 2019). This is conducted by
selecting attributes which performances are not quite satisfying (score is lower than 4.000) but
considered very important attributes (score is higher than 4.000). Eight critical attributes can be
included as the focus on the improvement, namely, the realization of the smooth land
acquisition, appropriate supervision, selection of the appropriate concessionaire, law
enforcement, simplification of bureaucratic procedure, solving community protest regarding
the environmental issues, development of good communication between the government and
the concessionaire and provision of appropriate government support.
Firstly, the realization of a smooth land acquisition process becomes the priority that
should be improved by the government. This research finding is confirmed by Tamin et al.
(2011), revealing that land acquisition still becomes one of the main challenges in Indonesian
toll road development. Indeed, there is an improvement in this aspect of the current toll road
development. However, the process still needs to be improved to provide certainty for the
investor. Land acquisition is a complicated issue in PPP projects as many projects are
delayed or even cancelled because of this issue (Kumaraswamy and Zhang, 2001). This
problem also happened in several BOT road projects in Bangkok, Thailand and Guangzhou,
China, causing project delays (Chen and Doloi, 2008). Therefore, it is the role of the host
government to smooth the land acquisition process which prevents time delay and cost
overruns. In Indonesia, the land is owned by the community and, without the community’s
permission, it cannot be used for public infrastructure. The government should plan
appropriate approaches for the community to ensure a smooth land acquisition process. The
government that is represented by Land Provision Committee (P2T) is the main actor in the
land acquisition process (Tamin et al., 2011). It is difficult for the private sector to deal with
this issue without the government’s support and involvement. The government should
provide clear and adequate procedures for the land acquisition process as well as they need
to be consistent in implementing them. This process is usually related to the simplification
of the regulation and bureaucratic system as well as the law enforcement. Recently, the
government published Peraturan Presiden (Presidential Decree) No. 66 in 2020 which is
expected can smooth and simplify the land acquisition process (PP No. 66, 2020).
JFMPC Secondly, appropriate supervision should also be improved. This is needed because it is
27,2 not enough for the government to only select the private sector and then transfer as many
risks as possible to them without being actively involved in the process. The government
needs to supervise the project implementation to ensure that the project is executed within
the allocated time, budget and also meets the specification. Therefore, proper supervision
(Li et al., 2005a) at each stage of the project must be carried out to ensure that the design and
252 planning are appropriately implemented. Appropriate supervision should be performed in
the overall project lifecycle to ensure that the project is implemented as expected. In the
construction stage, the government has to ensure that the project execution meets the project
objective and success criteria. Meanwhile, in the operational stage, the government needs to
ensure that the toll roads service quality is achieved or meets the target. Good service
quality is one of the main objectives in applying PPP schemes, that is to achieve better value
for money (Grimsey and Lewis, 2005).
Thirdly, the selection of an appropriate concessionaire should also be conducted in this
PPP scheme. Appropriate selection of the developer or concessionaire can increase the
chance of successful PPP projects (Rohman et al., 2015). It can be achieved when the
government conducts a fair and competitive bidding process (Zhang, 2005b). Through this
process, a concessionaire that best meets the criteria can be selected. Zhang (2005a) also
added that not only giving competitive tendering but also providing a clear contract that can
accommodate appropriate risk allocation. In the existing practice, the government usually
selects the private concessionaire which provides the most attractive financial consideration.
However, as the need to implement the sustainable construction concept in the context of
PPP, competitive procurement should also consider the sustainability performance
(Koppenjan, 2015). This sustainability practice should balance the three components,
namely, economic, environmental and social aspects. Indeed, integrating the sustainability
concept in PPP implementation is essential, considering that this type of project has a long
project life cycle (Kumaraswamy et al., 2007). As such, competitive procurement in PPP
should motivate the private sector to present an innovation (Verweij et al., 2019) that
improves sustainability achievement.
Fourthly, law enforcement is also very important. Providing legal certainty is needed by
the private sector to run the business. All regulations that have been issued should be
strictly enforced (Zhang, 2005a). Corruption is usually happened due to the incomplete or
unclear regulatory framework combined with the weak of law enforcement. Indonesia has
various types of law and regulation at different levels, yet has problems regarding its
enforcement (Wibowo and Alfen, 2015). An example of the importance of this law
enforcement is in the case of the land acquisition process above. In the current practice, the
land acquisition process in Indonesian PPP still cannot be executed optimally and is often
delayed because of the weakness of this aspect’s implementation (Rostiyanti and Tamin,
2010). Therefore, the process of land acquisition should be implemented through a
transparent and fair procedure based on the regulation to minimize the action of land
speculators or otherwise, this process is complicated to be timely implemented (Rostiyanti
and Tamin, 2010).
Fifthly, simplification of bureaucratic procedure should also be improved as this is
usually related to regulation and law enforcement issues as has been explained previously.
Several variables have been identified as barriers to PPP projects: bureaucratic procedures,
too many institutional players and risks due to poor local governmental administration and
corruption (Zhang, 2005a). The bureaucratic and regulation problems were considered to be
a hindrance in the process of land acquisition (Rostiyanti and Tamin, 2010). It is, therefore,
very important for the host government to establish a simple and easy bureaucratic system,
which can eradicate corruption and to make sure every person has an equal position under Toll road
the law. By establishing a reliable bureaucracy, a smooth and fast approval process can be projects
executed for time and budget efficiency. Conversely, too many problems in the bureaucratic
system could make every step longer, which could finally lead to budget increase and time
extension of the project completion. The problem in the bureaucratic system can also
influence the private sector’s interest to have less trust in the government. These
bureaucratic problems also increase opportunities for corruption. Owusu et al. (2019) argued
253
that corruption has adverse effects in lowering the construction work quality and distort the
entire process of procurement. The private sector is possibly reluctant to get involved in the
PPP scheme because of the corruption that happened in the host country (Zhang, 2005a),
making the business risk higher.
Sixthly, solving the community protest regarding the environmental issues is also needed as
the construction of toll road projects play role in the life of the surrounding environment and
community. As the result, the community protests the toll road development which often causes a
delay in the project. Regarding this, the government should manage this process with an
appropriate approach. Indeed, community support is very important for a successful
infrastructure project development. A failure to accommodate the community’s aspirations as
part of the project would cause stakeholders’ opposition that potentially results in project failure
(El-Gohary et al., 2006; Li et al., 2013). Woltjer (2002) highlighted that using an appropriate
approach to solve the community’s aspirations is vital to reduce social problems. Referring to
that, the best way to accommodate the community’s needs in the decision-making process is by
involving their perspective in a PPP scheme (Rohman et al., 2017). It is believed that stakeholder
consultation can be a good channel to solve any public issues on PPP implementations. Solving
social issues might minimize stakeholders’ opposition and gradually improve the chances of
success of this project. On the other hand, this project might not work and stakeholders’
opposition can happen due to the failure of responding and fulfilling the community expectations
(Majamaa et al., 2008).
Seventhly, the development of good communication between the government and the
concessionaire. This is very important and one of the PPP success factors as this type of project is
a long concession period partnership between the public and private sectors that involve many
stakeholders and types of risks in its implementation. Maintaining good communication between
these two parties can lead to better project coordination which affects the project performance.
Kumaraswamy and Zhang (2001) pointed that poor project coordination is one of the reasons
why several PPP projects in the area of energy and transportation were unsuccessful. Good
project coordination may happen where there is good communication between any parties
involved in the project implementation, especially between the government and the
concessionaire. Potential disputes between any parties involved can be reduced if good
communication can be realized between these two main parties (Kwak et al., 2009).
Eightly, the provision of the private sector that needs government support should also be
improved, as some risks on political and economic conditions in PPP projects can occur. The
government should provide appropriate and adequate support. PPP projects have higher
risks than traditional projects so the private sector could be thinking very carefully about
investing in PPP projects. To attract private sector involvement, the host government needs
to provide support or a guarantee to minimize the private sector’s risk. Therefore, an
appropriate and adequate support of the government is needed to minimize the private
party’s risks (Kumaraswamy and Zhang, 2001). According to Osei-Kyei and Chan (2017),
government support is one of the CSF in PPP projects which is applied in many countries,
even though its manifestation can be different among jurisdictions. The government
JFMPC support can be realized by providing tax relief, exchanging rate differences and being
27,2 flexible in toll tariff adjustment (Kwak et al., 2009)

6. Conclusion
Even though PPP research has been widely explored in published literature, there are still
limited works that have been conducted which focuses on investigating the attributes of the
254 government’s role in PPP toll road projects in Indonesia based on a quantitative approach.
This paper presents attributes to measure the government’s role as well as assess its
performance in PPP toll road projects in Indonesia using statistical analysis from the
stakeholders’ perception, namely, the government and the private sector. According to the
result, it was found that 12 attributes were considered relevant or important to be used to
assess the government’s role performance in PPP toll road projects in Indonesia.
The research also found that the performance of the GoI role in toll road development can be
categorized as a “moderate” one, meaning that there should be an improvement on the current
government’s role performance to achieve more successful project implementation. In this
research, the government and private sector mostly did not have quite significantly different
perceptions regarding the government’s role attributes. This means that the questionnaire was
valid for the analysis, which complemented the reliability test in this research.
The above result can be used as the basis for the current PPP toll road projects
implementation in which the GoI should improve its roles to achieve a more successful toll
road projects implementation, considering that this country is intensively attracting the
private sector in developing toll roads through PPP scheme. The improvement should be
focused on seven attributes that are considered critical, namely, the ones which are very
important, yet have low performance in the existing practice. Those critical attributes are
the realization of the smooth land acquisition, appropriate supervision, selection of the
appropriate concessionaire, law enforcement, simplification of bureaucracy procedure,
solving community protest related to the environmental issues, development of good
communication between the government and the concessionaire and provision of
appropriate government support.
This study contributes to the body of knowledge by providing an understanding of the
government’s role attributes and its performance in PPP toll road projects in Indonesia or even in
other developing countries that have similar characteristics to Indonesia. These findings can be
used as a guide for the host government as the most powerful stakeholder to improve its
performance in implementing the PPP model successfully. This study can also help the private
sector understand the PPP environment in a developing country such as Indonesia which offers a
large opportunity for private involvement in toll road projects development.

7. Study limitation and future research


Even though this study has been conducted rigorously, several limitations remain. Firstly, this
research only involves eight toll roads located in Java. However, as most of the toll roads are
located in Java as the densest population in Indonesia, this result could still be considered
representing the Indonesian context. Future research can be carried out by involving toll road
projects outside Java to understand Indonesian toll roads more holistically. Secondly, this study is
only suitable for the Indonesian context. Therefore, it would be interesting to conduct similar
studies in other developing countries to obtain another perspective on the role of government in
PPP projects. Nevertheless, despite the study limitation, the result may still be relevant to be used
for other developing countries that have similar characteristics and problems to Indonesia.
Thirdly, this study has another limitation as it was based on data series collected in 2014. This
means the analysis can explain the condition during that time and few years after that time.
However, as there is limited research conducted on this issue, this paper still contributes to filling Toll road
the research gap by providing a better understanding regarding the government’s role in PPP toll projects
road projects in Indonesia and the assessment of the attributes performance as well as the
improvement based on the limitation. Future research which has similar nature based on an
updated data collection can be performed to obtain the current condition of the issue in this
particular area.
255
References
Abednego, M.P. and Ogunlana, S.O. (2006), “Good project governance for proper risk allocation in
public–private partnerships in Indonesia”, International Journal of Project Management, Vol. 24
No. 7, pp. 622-634.
Badan Pengatur Jalan Tol (BPJT) (2019), available at: http://bpjt.pu.go.id/konten/progress/beroperasi
Badan Perencanaan Pembangunan Nasional (BAPPENAS) (2010), Indonesian Ministry of National
Development Planning, Public-private partnerships: infrastructure projects in Indonesia.
Badan Pusat Statistik (BPS) (2010), “Hasil sensus penduduk: data agregat per provinsi”, available at:
www.bps.go.id/linkTabelStatis/view/id/1267
Birgonul, M.T. and Ozdogan, I. (1998), “A proposed framework for governmental organization in the
implementation of build-operate transfer (BOT) model”, Proceeding of 14th Annual Conference
ARCOM, Reading, 517-526.
Bustaman, A. and Ramayandi, A. (2012), “An evaluation on institution for public private partnership
(PPP) in Indonesia”, Working Paper in Economics and Development Studies, Department of
Economics Padjadjaran University, Indonesia.
Chan, A.P.C., Lam, P.T.I., Chan, D.W.M., Cheung, E. and Ke, Y. (2010), “Critical success factors for PPPs
in infrastructure developments: Chinese perspective”, Journal of Construction Engineering and
Management, Vol. 136 No. 5, pp. 484-494.
Chan, A.P.C., Yeung, J.F.Y., Yu, C.C.P., Wang, S.Q. and Ke, Y. (2011), “Empirical study of risk
assessment and allocation of public-private partnership projects in China”, Journal of
Management in Engineering, Vol. 27 No. 3, pp. 136-148.
Chen, C. and Doloi, H. (2008), “BOT application in China: driving and impeding factors”, International
Journal of Project Management, Vol. 26 No. 4, pp. 388-398.
Cheung, E., Chan, A.P.C. and Kajewski, S. (2012), “Factors contributing to successful public private
partnerships projects”, Journal of Facilities Management, Vol. 10 No. 1, pp. 45-58.
DetikFinance (2019), available at: https://finance.detik.com/infrastruktur/d-4543799/ada-806-km-tol-
beroperasi-tahun-2019-ini-jadwalnya
Doloi, H. (2012), “Understanding impacts of time and correlated construction risks on operational
performance of PPP projects”, International Journal of Strategic Property Management, Vol. 16
No. 3, pp. 316-337.
El-Gohary, N., M., Osman, H. and El-Diraby, T.E. (2006), “Stakeholder management for public private
partnerships”, International Journal of Project Management, Vol. 24 No. 7, pp. 595-604.
Field, A. (2005), Discovering Statistics Using SPSS, Sage Publication Ltd., London.
Grimsey, D. and Lewis, M.K. (2005), “Are public private partnerships value for money? evaluating
alternative approaches and comparing academic and practitioner views”, Accounting Forum,
Vol. 29, pp. 345-378.
Hair, J.F., Black, W.C., Barin, B.J. and Anderson, R.E. (2010), Multivariate Data Analysis, a Global
Perspective, NJ, Pearson.
JFMPC Hwang, B.G., Zhao, X. and Gay, M.J.S. (2012), “Public private partnership projects in Singapore: factors,
critical risks and preferred risk allocation from the perspective of contractors”, International
27,2 Journal of Project Management, Vol. 31 No. 3.
Ke, Y., Wang, S.Q., Chan, A.P.C. and Lam, P.T.I. (2009), “Preferred risk allocation in China’s public-
private partnership”, International Journal of Project Management p. 28.
Koppenjan, J.F.M. (2015), “Public–private partnerships for green infrastructures: tensions and
challenges”, In: Current Opinion in Environmental Sustainability, Vol. 12, pp. 30-35.
256
Kumar, R. (1997), “Research methodology: a step-by-step guide for beginners”, Longman.
Kumaraswamy, M.M., Ling, F.Y.Y., Anvuur, A.M. and Rahman, M.M. (2007), “Targeting relationally
integrated teams for sustainable PPPs”, Engineering, Construction and Architectural
Management, Vol. 14 No. 6, pp. 581-595.
Kumaraswamy, M.M. and Zhang, X.Q. (2001), “Governmental role in BOT-led infrastructure
development”, International Journal of Project Management, Vol. 19 No. 4, pp. 195-205.
Kwak, Y.H., Chih, Y. and Ibbs, C.W. (2009), “Towards a comprehensive understanding of public private
partnerships for infrastructure development”, California Management Review, Vol. 51 No. 2,
pp. 51-78.
Li, T.H., Ng, S.T. and Skitmore, M. (2013), “Evaluating stakeholder satisfaction during public
participation in major infrastructure and construction projects: a fuzzy approach”, Automation
in Construction, Vol. 29, pp. 123-135.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005a), “Critical success factors for PPP/PFI
projects in the UK construction industry”, Construction Management and Economics, Vol. 23
No. 5, pp. 459-471.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005b), “The allocation of risk in PPP/PFI
construction projects in the UK”, International Journal of Project Management, Vol. 23 No. 1,
pp. 23-35.
Majamaa, W., Junnila, S., Doloi, H. and Niemistö, E. (2008), “End-user oriented public-private
partnerships in real estate industry”, International Journal of Strategic Property Management,
Vol. 12 No. 1, pp. 1-17.
Muhammad, Z. and Johar, F. (2018), “Critical success factors of public-private partnership projects: a
comparative analysis of the housing sector between Malaysia and Nigeria”, International
Journal of Construction Management, Vol. 19 No. 3.
Ng, S.T., Wong, Y.M.W. and Wong, J.M.W. (2010), “A structural equation model of feasibility
evaluation and project success for public–private partnerships in Hong Kong. Engineering
management”, IEEE Transactions, Vol. 57, pp. 310-322.
Ng, S.T., Wong, Y.M.W. and Wong, M.W. (2012), “Factors influencing the success of PPP at feasibility stage – a
tripartite comparison study in Hong Kong”, Habitat International, Vol. 36 No. 4, pp. 423-432.
Osei-Kyei, R. and Chan, A.P.C. (2017), “Implementing public–private partnership (PPP) policy for
public construction projects in Ghana: critical success factors and policy implications”,
International Journal of Construction Management, Vol. 17 No. 2, pp. 113-123.
Owusu, E.K., Chan, A.P.C. and Darko, A. (2019), “Thematic overview of corruption in
infrastructure procurement process”, Journal of Infrastructure Systems, Vol. 25 No. 2,
pp. 02519001-02519001-7.
Qiao, L., Wang, S.Q., Tiong, R.L.K. and Chan, T.S. (2001), “Framework for critical success factors of
BOT projects in China”, The Journal of Project Finance, pp. 53-61.
Ozdoganm, I.D. and Birgonul, M.T. (2000), “A decision support framework for project sponsors in the
planning stage of build-operate-transfer (BOT) project”, Construction Management and
Economics, Vol. 18, pp. 343-353.
Rohman, M.A. and Wiguna, I.P.A. (2019), “Evaluation of road design performance in delivering Toll road
community project social benefits in Indonesian PPP”, International Journal of Construction
Management. projects
Rohman, M.A., Doloi, H. and Heywood, C.A. (2017), “Success criteria of toll road projects from a community
societal perspective”, Built Environment Project and Asset Management, Vol. 7 No. 1, pp. 32-44.
Rohman, M.A., Doloi, H. and Heywood, C. (2015), “Government’s roles in public private partnership toll
road projects”, International Conference on Construction and Project Management (ICCEPM),
Busan, Korea, pp. 381-385. 257
Rostiyanti, S.F. and Tamin, R.Z. (2010), “Identification of challenges in public private partnerships
implementation for Indonesian toll road”, First Makassar International Conference on Civil
Engineering (MICCE 2010), Makassar, pp. 1131-1135.
Tamin, R.Z., Marzuki, P.F. and Rostiyanti, S.F. (2011), “Complex and uncertain land acquisition:
one of major obstacle in toll road public private partnership project in Indonesia”, Society
for Social Management Systems Internet Journal, pp. 1-8, Kochi University of Technology,
Japan.
Tsamboulas, D., Verma, A. and Moraiti, P. (2012), “Transport infrastructure provision and operation:
why should governments choose private-public partnership?”, Research in Transportation
Economics, Vol. 38 No. 1.
Verweij, S., Loomans, O. and Leendertse, A. (2019), “The role of the public partner in innovation in
transport infrastructure PPPs: a qualitative comparative analysis of nine dutch DBFM projects.
Public”, Works Management and Policy, pp. 1-28.
Wibowo, A. (2005), “Estimating general threshold traffic levels of typical build, operate, and transfer
toll road projects in Indonesia”, Construction Management and Economics, Vol. 23 No. 6,
pp. 621-630.
Wibowo, A. and Alfen, H.W. (2015), “Government-led critical success factors in PPP
infrastructure development”, Built Environment Project and Asset Management, Vol. 5
No. 1, pp. 35-51.
Wibowo, A. and Kochendoerfer, B. (2011), “Selecting BOT/PPP infrastructure projects for government
guarantee portfolio under conditions of budget and risk in the Indonesian context”, Journal of
Construction Engineering and Management, Vol. 137 No. 7, pp. 512-522.
Wibowo, A. and Mohamed, S. (2010), “Risk criticality and allocation in privatized water supply projects
in Indonesia”, International Journal of Project Management, Vol. 28 No. 5, pp. 504-513.
Woltjer, J. (2002), “The ‘public support machine’: notions of the function of participatory planning by
Dutch infrastructure planners”, Planning Practice and Research, Vol. 17 No. 4, pp. 437-453.
Yuan, J., Skibniewski, M.J., Li, Q. and Zheng, L. (2010), “Performance objectives selection model in
public-private partnership projects based on the perspective of stakeholders”, Journal of
Management in Engineering, Vol. 26, pp. 89-104.
Zhang, X. (2005a), “Paving the way for public–private partnerships in infrastructure development”,
Journal of Construction Engineering and Management, Vol. 31 No. 1, pp. 71-80.
Zhang, X. (2005b), “Critical success factors for public – private partnerships in infrastructure
development”, Journal of Construction Engineering and Management, Vol. 131 No. 1,
pp. 3-14.

Further reading
Heywood (1999), Political Theory: An Introduction, Macmillan Press Ltd.
Neuman, W.L. (2012), Basic of Social Research: qualitative and Quantitative Approaches, Pearson.
Ng, S.T., Wong, J.M.W. and Wong, K.K.W. (2013), “A public private people partnerships (P4)
process framework for infrastructure development in Hong Kong”, Cities, Vol. 31,
pp. 370-381.
JFMPC Osei-Kyei, R., Chan, A.P.C., Javed, A.A. and Ameyaw, E.E. (2017), “Critical success criteria for public–
private partnership (PPP) projects: International experts’ opinion”, International Journal of
27,2 Strategic Property Management, Vol. 21 No. 1, pp. 87-100.
Oxford Dictionary (2016), Available at: http://oxforddictionaries.com/
Peraturan Presiden (PP) Nomor 66 Tahun (2020), “Pendanaan pengadaan tanah bagi pembangunan
untuk kepentingan umum dalam rangka pelaksanaan proyek strategis nasional”.
258 Sanghi, A., Hankinson, D. and Sundakov, A. (2007). “Designing and using public-private partnership
units in infrastructure: lessons from case studies around the world”.
Shen, L., Tam, V.W.Y., Gan, L., Ye, K. and Zhao, Z. (2016), “Improving sustainability performance for
Public-Private-Partnerships (”, Sustainability, Vol. 8 No. 3, p. 289.

Corresponding author
Mohammad Arif Rohman can be contacted at: arif@ce.its.ac.id and arif.its@gmail.com

For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com

You might also like