Professional Documents
Culture Documents
www.emeraldinsight.com/2044-124X.htm
Suitability
Suitability of of PPP
public-private-partnership procurement
method
procurement method for road
projects in Sri Lanka 199
Abstract
Purpose – Governments of many developing countries that are unable to develop their infrastructure in
order to obtain financial resources prefer to establish public–private partnerships (PPPs) for providing the
much-required infrastructure. Time is thus opportune for Sri Lanka, which is also a developing country, to
make use of PPPs to develop its road network. The purpose of this paper is, therefore, to identify the PPP
models that suit road construction in Sri Lanka.
Design/methodology/approach – The study used a mixed approach. The characteristics of road
construction, procurement selection factors to be considered in road construction, and the different PPP
models that can be used for such procurements were identified through a comprehensive literature synthesis.
The findings were validated using expert interviews. A questionnaire survey identified the PPP models that
suit road construction in Sri Lanka. The most suitable model among them was identified by ranking the PPP
models using procurement selection factors.
Findings – Build–Own–Operate–Transfer was identified as the PPP model that best suits road construction
in Sri Lanka. However, investors may not find it attractive because of its high payback period, a result of the
low traffic volume in Sri Lanka. Therefore, a PPP model that involves road construction alone will not be
feasible in Sri Lanka. It will have to include the construction of other infrastructure as well.
Originality/value – The study identifies a PPP model that best suits the road construction projects in
Sri Lanka.
Keywords Sri Lanka, Public–private partnership (PPP), Road projects, Build–Own–Operate–Transfer (BOOT),
Overall suitability, Procurement selection factors
Paper type Research paper
1. Introduction
When the social and economic development of a country becomes rapid, there will be a
demand for investment on infrastructure (Izaguirre and Mirzagalyamova, 2008).
Governments of most developing countries face challenges when addressing the demands
made on their public infrastructure services and facilities (Babatunde et al., 2015). When
they find it difficult to self-finance these infrastructure projects, these governments prefer
public–private partnerships (PPPs) for providing the much-needed infrastructure facilities
( Jin and Doloi, 2008). Grimsey and Lewis (2002) have defined PPP as a long-term contractual
agreement between a public body and a private entity for production, management or
provision of public sector infrastructure facilities by the private entity. PPPs can be
prepared to suit the specific situations and circumstances encountered during the process
Built Environment Project and
(Efficiency Unit, 2008). Asset Management
According to the Hong Kong Institute of Surveyors (2009), many countries use PPPs to Vol. 9 No. 2, 2019
pp. 199-213
provide public facilities and services through partnerships established between their public © Emerald Publishing Limited
2044-124X
and private sectors although they still widely use the traditional approaches as well. DOI 10.1108/BEPAM-01-2018-0007
BEPAM Ibbs et al. (2009) have stated that during the last two decades, PPPs have become the main
9,2 mode of providing public facilities and services in both developed and developing countries.
Therefore, a comprehensive evaluation of the different types of available PPP models is
necessary to identify the model that best suits Sri Lanka.
2. Literature synthesis
2.1 Infrastructure development
Infrastructure of a country contributes in many ways to the sustained economic
development of that country (Sahoo and Dash, 2009). Kumaraswamy and Zhang (2001) have
stated that developing countries need to invest in infrastructure that can fulfill the basic
needs of their public. World Economic Forum (2012) is of the view that unless infrastructure
of a country is perfectly aligned with the economic, environmental, industrial and social
priorities of the country, it will be unlikely that the expected outcomes of the infrastructure
will be delivered efficiently and effectively. Low-income countries have limited public
resources for infrastructure development. The total financial commitments required for
infrastructure development by these countries could be reduced by improving the efficiency
of their public procurement processes (Estache and Iimi, 2008). Rajeh et al. (2014) have stated
that the procurement process adopted for a project is critical as it can affect the success of
that project, and that the selection of the most appropriate procurement system is a crucial
and a difficult step that has to be taken at the inception of the project.
2.5 PPPs in Sri Lanka and their levels of success and failure
According to the Medium-Term Development Policy Framework (2011–2016) of the GoSL,
the government will focus on getting the private sector involved in government-owned
BEPAM business ventures to improve their management and workmanship (Finance Commission of
9,2 Sri Lanka, 2017). It considers PPP as a successful and alternative funding method that can
considerably improve the national infrastructure. Because it does not have adequate funds,
both government and foreign, to provide economic infrastructure, the government is
compelled to seek private sector participation for financing the related projects (Finance
Commission of Sri Lanka, 2017). A considerable amount of government funds that would
202 otherwise have been utilized for infrastructure development have been spent on social
capital rather than on specifically targeted groups. This has slowed down the annual
growth rate of the country. There is no legislation on PPPs in Sri Lanka. PPPs have been
implemented in the country pursuant to 1998 Guidelines on private sector infrastructure
projects (BOO/BOT/BOOT) of the Guidelines on Government Tender Procedure Part II
(Revised Edition, 1997). According to USAID (2016), although the 1998 guidelines were to be
replaced by the Government Procurement Guidelines of 2007, the latter have so far had no
force and effect as they had not been published. The USAID report also discloses that
Sri Lanka has been implementing PPPs since 1990 and that 73 PPP projects with a total
investment of over $6bn have been implemented by 2014 in several sectors.
Like in most developing countries, PPPs have been implemented in the telecommunication
and energy sectors in accordance with their tendering processes which are outside the PPP
process. Adikari (2018) states that the heavy transaction costs in Sri Lanka hinder the
popularising of PPP in the country as a procurement method, whereas this fact has been
confirmed by Chan et al. (2009) as well. Appuhami and Perera (2016), Barlow et al. (2013) and
Rufin (2012) have disclosed that in Sri Lanka it is administratively difficult to arrange and
manage PPPs because of their complexity. USAID (2016) states that GoSL has failed to
consider the negative impacts and results of implementing PPPs. Sri Lanka would need
additional resources to establish a strong and enabling PPP environment and undertake PPPs
in its critical sectors (roads, water, waste, social services, etc.).
OSS rating bands. The minimum OSS that could be scored was 8 and the highest was 200.
The OSS values could therefore fall within a range of 192 (192/5 ¼ 38.4) (Sivakumaran et al.,
2015; Rodrigo and Perera, 2017). To make the analysis of OSS values easier, the OSS range
was split into five bands as indicated below (Ahamad et al., 2013; Alaghbari et al., 2007;
Ekanayake and Perera, 2016; Kamarazaly, 2007):
(1) OSS o46.40 (8 + 38.4) – not suitable.
(2) 46.41o OSSo84.80 (46.40 + 38.40) – mildly suitable.
(3) 84.81o OSSo123.20 (84.80 + 38.40) – moderately suitable.
(4) 123.21 oOSSo 161.60 (123.20 + 8.40) – highly suitable.
(5) 161.61 oOSS – very highly suitable.
4.2 Suitability of BOOT as a PPP procurement tool for road construction in Sri Lanka
The suitability of each PPP model for procurement in road construction in Sri Lanka was
determined by getting the questionnaire survey respondents to rank procurement selection
206 factors based on their importance. The information obtained was used to calculate the MRj
of each procurement selection factor for each PPP model and the corresponding CSS was
calculated by multiplying MRi by MRj (suitability of procurement selection factors in terms
of each PPP model (MRj) × Importance of procurement selection factors related to road
projects (MRi)).
The OSS for each category was then calculated to identify the overall suitability of each
PPP model as a procurement tool for road projects in Sri Lanka. Table II presents MR and
CSS values of client-related, project-related and external environment-related procurement
selection factors along with their rankings for BOOT.
With a CSS of 17.59, “low operational and maintenance cost (C2)” becomes the most
significant client-related procurement selection factor while “type of the road project (P1)”
with a CSS of 17.62 becomes the most significant project-related procurement selection
factor related to road construction in the PPP Model BOOT. “Degree to which the projects
can get affected by government policies on infrastructure development and the financial
situation of the country (E1)” with a CSS of 14.14 becomes the most significant external
environment-related procurement selection factor.
The suitability of BOT, BOO, BTO, BLT and BT were also determined similarly and
Table III presents a summary of the overall findings.
4.3 PPP model most suitable for road construction projects in Sri Lanka
Using the information presented in Table III, the OSS for client’s requirements (OSS–CR),
project characteristics (OSS–PC) and external environment (OSS–EE) were derived for each
PPP model and the average OSS for each PPP model was calculated to determine its
suitability for road construction in Sri Lanka. Table IV presents the results.
The OSS of the client’s requirements was very much higher than the OSSs of other
categories probably because of the adverse effects that client-related factors can have on a
project. However, project-specific factors and external factors were not found to be of that
importance probably because project type and size will not be of importance to investors
who in general are well off financially. According to Table IV, BOOT with an average
suitability score of 130.83 is the most suitable PPP procurement model for road construction
in Sri Lanka. It has the highest ranking in relation to client’s requirements, project
characteristics and external environment. With its overall suitability band falling in the
range, 123.21–161.60, which corresponds to a “highly suitable” model, BOOT becomes the
PPP procurement model most suitable for road construction in Sri Lanka.
As can be seen from Table IV, BOT with an average suitability score of 129.75 is the
second most suitable PPP procurement model. It can be considered as “highly suitable” for
road construction in Sri Lanka as its OSS falls in the range, 123.21–161.60.
Hong Kong, People’s Republic of China and South Asia have successfully implemented
BOT/BOOT projects (Kumaraswamy and Morris, 2002). In Pakistan, BOT/BOOT projects
have been found to be suitable for the transportation sector of its mega cities (Mubin and
Ghaffar, 2008; Noor et al., 2012). Indonesia has used BOT in its toll road projects (Wibowo et al.,
2012). India too has adopted BOT in its national highway projects (Gupta et al., 2013).
Because of various bottlenecks that are encountered when mobilizing public funds and foreign
debt, developing countries have become more interested in implementing infrastructure
projects through BOT schemes (Kumaraswamy and Zhang, 2001). Efficiency Unit (2003)
BOOT BOT BOO
Suitability
PCF MRj MRi CSS Rank MRj MRi CSS Rank MRj MRi CSS Rank of PPP
Suitability of PPP Models in respect of clients’ requirement-related procurement selection factors
procurement
C2 4.13 4.26 17.59 1 3.92 4.26 16.70 6 4.08 4.26 17.38 1 method
C7 4.20 4.15 17.43 2 4.13 4.15 17.14 2 3.95 4.15 16.39 3
C4 4.11 4.15 17.06 3 4.23 4.15 17.55 1 3.21 4.15 13.32 10
C1
C12
3.92
4.20
4.30
4.00
16.86
16.80
4
5
3.92
4.23
4.30
4.00
16.86
16.92
4
3
3.28
4.08
4.30
4.00
14.10
16.32
8
4
207
C11 4.07 4.07 16.56 6 4.11 4.07 16.73 5 4.04 4.07 16.44 2
C8 3.80 4.22 16.04 7 3.92 4.22 16.54 7 3.68 4.22 15.53 5
C6 3.73 4.22 15.74 8 3.61 4.22 15.23 8 3.58 4.22 15.11 6
C3 3.67 4.11 15.08 9 3.58 4.11 14.71 9 3.37 4.11 13.85 9
C13 3.82 3.85 14.71 10 3.80 3.85 14.63 10 3.86 3.85 14.86 7
C5 3.42 4.19 14.33 11 3.33 4.19 13.95 11 2.90 4.19 12.15 11
C9 3.73 3.56 13.28 12 3.83 3.56 13.63 12 3.39 3.56 12.07 12
C10 1.67 3.52 5.88 13 1.79 3.52 6.30 13 1.83 3.52 6.44 13
Suitability of PPP models in respect of project characteristics-related procurement selection factors
P1 4.07 4.33 17.62 1 3.98 4.33 17.23 1 3.58 4.33 15.50 1
P2 3.94 4.00 15.76 2 3.86 4.00 15.44 2 3.52 4.00 14.08 2
P7 3.52 4.26 15.00 3 3.52 4.26 15.00 3 3.18 4.26 13.55 4
P4 3.95 3.74 14.77 4 3.80 3.74 14.21 5 3.55 3.74 13.28 6
P3 3.77 3.81 14.36 5 3.73 3.81 14.21 4 3.52 3.81 13.41 5
P6 3.27 4.15 13.57 6 3.24 4.15 13.45 6 3.30 4.15 13.70 3
P5 3.02 4.04 12.20 7 3.06 4.04 12.36 7 2.72 4.04 10.99 7
P8 3.30 3.56 11.75 8 3.21 3.56 11.43 8 3.03 3.56 10.79 8
Suitability of PPP models in respect of external environment-related procurement selection factors
E1 4.11 3.44 14.14 1 4.04 3.44 13.90 1 3.37 3.44 11.59 1
E2 3.67 3.44 12.62 2 3.70 3.44 12.73 2 2.68 3.44 9.22 6
E6 3.46 3.56 12.32 3 3.30 3.56 11.75 3 2.72 3.56 9.68 4
E3 2.99 3.85 11.51 4 2.97 3.85 11.43 4 2.93 3.85 11.28 2
E7 3.24 3.30 10.69 5 3.12 3.30 10.30 5 2.99 3.30 9.87 3
E4 2.87 3.33 9.56 6 2.93 3.33 9.76 6 2.81 3.33 9.36 5
E5 2.66 3.48 9.26 7 2.63 3.48 9.15 7 2.44 3.48 8.49 7
BTO BT BLT
PCF MRj MRi CSS Rank MRj MRi CSS Rank MRj MRi CSS Rank
Suitability of PPP models in respect of clients’ requirement-related procurement selection factors
C2 3.24 4.26 13.81 10 1.98 4.26 8.41 13 2.66 4.26 11.32 12
C7 3.73 4.15 15.49 4 3.61 4.15 14.97 6 3.70 4.15 15.36 3
C4 3.46 4.15 14.35 6 3.43 4.15 14.21 8 3.06 4.15 12.69 10
C1 3.33 4.30 14.33 8 2.59 4.30 11.14 11 2.78 4.30 11.93 11
C12 4.08 4.00 16.30 1 4.29 4.00 17.17 1 3.92 4.00 15.67 1
C11 3.83 4.07 15.57 3 3.77 4.07 15.33 4 3.61 4.07 14.69 5
C8 3.73 4.22 15.75 2 3.92 4.22 16.53 2 3.70 4.22 15.61 2
C6 3.49 4.22 14.73 5 3.68 4.22 15.51 3 3.52 4.22 14.84 4
C3 3.30 4.11 13.56 11 3.46 4.11 14.21 9 3.49 4.11 14.35 6
C13 3.70 3.85 14.25 9 3.73 3.85 14.37 7 3.55 3.85 13.67 8
C5 3.43 4.19 14.35 7 3.61 4.19 15.12 5 3.30 4.19 13.83 7
C9 3.55 3.56 12.64 12 3.61 3.56 12.85 10 3.68 3.56 13.08 9
C10 2.90 3.52 10.21 13 3.06 3.52 10.77 12 2.01 3.52 7.07 13
Suitability of PPP models in respect of project characteristics-related procurement selection factors
P1 3.21 4.33 13.89 2 2.75 4.33 11.91 3 2.99 4.33 12.95 2 Table III.
P2 3.08 4.00 12.33 4 2.75 4.00 11.00 5 2.87 4.00 11.47 5 Suitability of PPP
models in relation
to procurement
(continued ) selection factors
BEPAM P7 3.30 4.26 14.06 1 3.15 4.26 13.42 1 3.30 4.26 14.06 1
9,2 P4 3.39 3.74 12.68 3 2.84 3.74 10.63 6 3.21 3.74 12.00 4
P3 2.97 3.81 11.30 7 2.66 3.81 10.13 7 2.75 3.81 10.48 7
P6 2.93 4.15 12.17 5 2.99 4.15 12.42 2 2.93 4.15 12.17 3
P5 2.84 4.04 11.48 6 2.81 4.04 11.35 4 2.78 4.04 11.21 6
P8 2.93 3.56 10.44 8 2.81 3.56 10.00 8 2.78 3.56 9.88 8
208 Suitability of PPP models in respect of external environment-related procurement selection factors
E1 3.24 3.44 11.15 3 2.66 3.44 9.14 6 3.15 3.44 10.84 3
E2 3.43 3.44 11.78 1 3.06 3.44 10.52 2 3.24 3.44 11.15 2
E6 2.87 3.56 10.21 4 2.66 3.56 9.46 4 2.68 3.56 9.55 5
E3 2.99 3.85 11.52 2 2.97 3.85 11.42 1 2.93 3.85 11.29 1
E7 2.97 3.30 9.79 6 2.84 3.30 9.38 5 2.81 3.30 9.27 6
E4 3.03 3.33 10.07 5 3.12 3.33 10.38 3 3.03 3.33 10.07 4
Table III. E5 2.66 3.48 9.25 7 2.59 3.48 9.02 7 2.59 3.48 9.02 7
and Shen et al. (1996) have also identified BOT as a suitable procurement approach as in these
projects the private sector partner who does not have the legal ownership of the infrastructure
facility has to transfer the operation of the facility to the government at the end of its contract
with the government. The literature thus validates the research findings.
Because of its political instability, Sri Lanka is considered as a high-risk country for
investments. Thus, projects implemented in the country require proper contractual
arrangements. For Sri Lanka, BOOT is found to be better than BOT since in BOOT projects
the ownership rests with the investor until he hands over the project to the public sector. Political
risks of these projects are considerably less, as the public sector controlled by the government
cannot have much influence over them which makes them suitable for a country like Sri Lanka.
Interviewees disclosed that PPP-based investments and beneficiary contributions could
be obtained for maintaining public assets. According to them, PPP has not been very
successful and popular among the stakeholders in Sri Lanka since the existing laws and
regulations discourage organizations from entering into agreements, particularly on the
alienation of lands. Re-negotiation of contracts, a common feature in PPP, creates problems
in government projects as the tender procedures of the GoSL do not encourage such
practices. According to the experts, Sri Lanka should follow countries like India, Pakistan
and South Africa, which have taken institutional measures to promote PPP as an alternative
financing mechanism, and also the USA, which is adopting this approach in its social
infrastructure sector, if it is to provide an efficient service to the country.
References
Adair, A., Berry, J., Gulati, M., Haran, M., Hutchison, N.E., Kashyap, A., McCord, M., McGreal, S.,
Oyedele, J. and Tiwari, P. (2011), The Future of Private Finance Initiative and Public Private
Partnership, RICS, London.
Adikari, W. (2018), “Potential mitigation strategies for higher transaction cost of PPP context”,
unpublished thesis (BSc), University of Moratuwa.
BEPAM Ahamad, M.H.S., Perera, B.A.K.S. and Illankoon, I.M.C.S. (2013), “In house versus outsourcing facilities
9,2 management: a framework for value added selection in Sri Lankan commercial buildings”, in
Senevirathne, L.D.I.P. and Sandanayake, Y.G. (Eds), Proceedings of the Second World
Construction Symposium on Planning, Designing and Building for Tomorrow, Ceylon Institute of
Builders, Colombo, pp. 298-306.
Alaghbari, W., Kadir, M.P.A., Salim, A. and Ernawati (2007), “The significance factors causing delay of
building construction projects in Malaysia”, Engineering, Construction and Architectural
210 Management, Vol. 14 No. 2, pp. 192-206, available at: www.emeraldinsight.com/doi/pdfplus/10.
1108/09699980710731308
Ameyaw, E.E. and Chan, A.P. (2015), “Risk ranking and analysis in PPP water supply infrastructure
projects: an international survey of industry experts”, Facilities, Vol. 33 No. 7, pp. 428-453.
Appuhami, R. and Perera, S. (2016), “Management controls for minimising risk in public private
partnerships in a developing country: evidence from Sri Lanka”, Journal of Accounting &
Organizational Change, Vol. 12 No. 3, pp. 408-431.
Babatunde, S.O., Perera, S., Udeaja, C. and Zhou, L. (2015), “Drivers for adopting public private
partnership for infrastructure projects in developing countries: an empirical assessment”, RICS
COBRA AUBEA, Royal Institution of Chartered Surveyors (RICS), Sydney, available at: www.
rics.org/cobra (accessed July 13, 2017).
Barlow, J., Roehrich, J. and Wright, S. (2013), “Europe sees mixed results from public private partnerships
for building and managing health care facilities and services”, Health Affairs, Vol. 31 No. 1,
pp. 146-154.
Broadbent, J. and Laughlin, R. (2003), “Public private partnerships: an introduction”, Accounting,
Auditing and Accountability Journal, Vol. 16 No. 3, pp. 332-341.
Central Bank of Sri Lanka (2016), “CBSL Annual report 2016: economic infrastructure”, Central Bank of
Sri Lanka.
Chan, A.P., Lam, P.T., Chan, D.W., Cheung, E. and Ke, Y. (2009), “Potential obstacles to successful
implementation of public–private partnerships in Beijing and the Hong Kong Special
Administrative Region”, Journal of Management in Engineering, Vol. 26 No. 1, pp. 30-40.
Du Toit, J.L. and Mouton, J. (2013), “A typology of designs for social research in the built environment”,
International Journal of Social Research Methodology, Vol. 16 No. 2, pp. 125-139.
Eaton, D., Akbiyikli, R., de Lemos, T., Gunnigan, L., Kutanis, R.O., Casensky, M., Ladra, J. and
El-Sawalhi, N. (2007), “An examination of the suitability of a UK PFI model within the Czech
Republic, the Republic of Ireland, Palestine (Gaza–West Bank), Portugal and Turkey”,
Construction Innovation, Vol. 7 No. 1, pp. 122-142.
Efficiency Unit (2008), An Introductory Guide to Public Private Partnerships (PPPs), 3rd ed., Efficiency Unit,
Hong Kong.
Ekanayake, E.M.K. and Perera, B.A.K.S. (2016), “Appropriate delay analysis techniques to analyse
delays in road construction projects in Sri Lanka”, Built Environment Project and Asset
Management, Vol. 6 No. 5, pp. 521-534.
Estache, A. and Iimi, A. (2008), Procurement Efficiency for Infrastructure Development and Financial
Needs Reassessed, World Bank Group, available at: https://openknowledge.worldbank.org/
bitstream/handle/10986/6854/WPS4662.pdf?sequence=1&isAllowed=y
Farquharson, E. and Yescombe, E.R. (2011), Defining Public-Private Partnerships. How to Engage with
the Private Sector in Public-Private Partnerships in Emerging Markets, The World Bank,
Washington, available at: https://doi.org/10.1596/9780821378632_CH02 (accessed May 22, 2017).
Fellows, R.F. and Liu, A.M.M. (2015), Research Methods for Construction, 4th ed., John Wiley & Sons,
New York, NY.
Finance Commission of Sri Lanka (2017), “Public–private partnership approach: theory and practice”,
available at: http://fincom.gov.lk/public-private-partnership-approach-theory-and-practice/
(accessed July 3, 2017).
Grimsey, D. and Lewis, M.K. (2002), “Evaluating the risks of public–private partnerships for Suitability
infrastructure projects”, International Journal of Project Management, Vol. 20 No. 2, pp. 107-118. of PPP
Gupta, A.K., Trivedi, M.K. and Kansal, R. (2013), “Risk variation assessment of Indian road PPP projects”, procurement
International Journal of Science, Environment and Technology, Vol. 2 No. 5, pp. 1017-1026.
method
Hall, D., De La Motte, R. and Davies, S. (2003), “Terminology of public-private partnerships (PPPs)”,
Public Services International Research Unit, London.
Henjewele, C., Sun, M. and Fewings, P. (2014), “Comparative performance of healthcare and transport 211
PFI projects: empirical study on the influence of key factors”, International Journal of Project
Management, Vol. 32 No. 1, pp. 77-87.
Hong Kong Institute of Surveyors (2009), Practical Guide to Public Private Partnership (PPP) Projects,
Hong Kong Institute of Surveyors, Hong Kong.
Ibbs, C.W., Kwak, Y.H., Chih, Y. and Ibbs, C.W. (2009), “Towards a comprehensive understanding of
public private partnerships for infrastructure development”, California Management Review,
Vol. 51 No. 2, pp. 51-79.
Izaguirre, A.K. and Mirzagalyamova, A. (2008), “Investment commitments in Europe and Central Asia
doubled in 2007”, available at: https://openknowledge.worldbank.org/handle/10986/11001
(accessed August 19, 2017).
Jin, X.H. and Doloi, H. (2008), “Interpreting risk allocation mechanism in public–private partnership
projects: an empirical study in a transaction cost economics perspective”, Construction
Management and Economics, Vol. 26 No. 7, pp. 707-721.
Johnson, J.W. and LeBreton, J.M. (2004), “History and use of relative importance indices in
organizational research”, Organizational Research Methods, Vol. 7, pp. 238-257.
Kakabadse, N.K., Kakabadse, A.P. and Summers, N. (2007), “Effectiveness of private finance initiatives
(PFI): study of private financing for the provision of capital assets for schools”, Public Administration
and Development, Vol. 27 No. 1, pp. 49-61.
Kamarazaly, M.A. (2007), “A mature profession of quantity surveying in Sri Lanka”, unpublished
MPhil thesis, University of Messay, Wellington.
Kothari, C.R. (2004), Research Methodology: Methods and Techniques, 2nd ed., New Age International,
New Delhi.
Kumaraswamy, M.M. and Dissanayaka, S.M. (2001), “Developing a decision support system for
building project procurement”, Building and Environment, Vol. 36 No. 3, pp. 337-349.
Kumaraswamy, M.M. and Morris, D.A. (2002), “Build-operate-transfer-type procurement in Asian
megaprojects”, Journal of Construction Engineering and Management, Vol. 28 No. 2, pp. 93-102.
Kumaraswamy, M.M. and Zhang, X.Q. (2001), “Governmental role in BOT-led infrastructure
development”, International Journal of Project Management”, Vol. 19 No. 4, pp. 195-205.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005), “Perceptions of positive and negative
factors influencing the attractiveness of PPP/PFI procurement for construction projects in the
UK: findings from a questionnaire survey”, Engineering, Construction and Architectural
Management, Vol. 12 No. 2, pp. 125-148.
Love, P.E., Edwards, D.J., Irani, Z. and Sharif, A. (2011), “Participatory action research approach to
public sector procurement selection”, Journal of Construction Engineering and Management,
Vol. 138 No. 3, pp. 311-322.
Lund, T. (2012), “Combining qualitative and quantitative approaches: some arguments for mixed
methods research”, Scandinavian Journal of Educational Research, Vol. 56 No. 2, pp. 155-165.
Mathonsi, M. and Thwala, W. (2012), “Selection of procurement systems in the South African
construction industry: an exploratory study”, African Journal of Business Management, Vol. 12
No. 10, pp. 13-26.
Mayer Brown JSM (2009), “New Decree on BOT, BTO and BT contracts (Decree No. 108/2009/ND-CP)”,
Mayer Brown Practices, available at: www.mayerbrown.com/publications/new-decree-on-bot-
bto-and-bt-contracts-12-09-2009/ (accessed January 29, 2018).
BEPAM Mubin, S. and Ghaffar, A. (2008), “BOT contracts: applicability in Pakistan for infrastructure
9,2 development”, Pakistan Journal of Engineering and Applied Science, Vol. 3, pp. 33-46.
Neuman, W.L. (2011), Social Research Methods: Qualitative and Quantitative Approaches, 7th ed.,
Pearson, Boston, MA.
Noor, M.A., Khalfan, M.M.A. and Maqsood, T. (2012), “Methods used to procure infrastructure projects
in Pakistan: an overview”, International Journal of Procurement Management, Vol. 5 No. 6,
212 pp. 733-752.
Qiang, M., Wen, Q., Jiang, H. and Yuan, S. (2015), “Factors governing construction project delivery selection:
a content analysis”, International Journal of Project Management, Vol. 33 No. 8, pp. 1780-1794.
Rajeh, M.A., Tookey, J. and Rotimi, J. (2014), “Procurement selection model: development of a
conceptual model based on transaction costs”, Australasian Journal of Construction Economics
and Building-Conference Series, Vol. 2 No. 2, pp. 56-63, available at: https://doi.org/10.5130/ajceb-
cs.v2i2.3889
Ratnasabapathy, S. and Rameezdeen, R. (2007), “A decision support system for the selection of best
procurement system in construction”, Built-Environment Sri Lanka, Vol. 7 No. 2, pp. 43-53.
Ratnasabapathy, S., Rameezdeen, R. and Gamage, I. (2006), “Macro level factors affecting the
construction procurement selection: a multi-criteria model”, The Joint International Conference
on Construction Culture, Innovation and Management (CCIM), pp. 581-591.
Rodrigo, M.N.N. and Perera, B.A.K.S. (2017), “Criteria for selecting nominated subcontractors in
commercial building construction”, Built Environment Journal, Vol. 14 No. 1, pp. 39-47.
Rufin, C. (2012), “Between commonweal and competition: understanding the governance of
public–private partnerships”, Journal of Management, Vol. 38 No. 5, pp. 1634-1654.
Sahoo, P. and Dash, R.K. (2009), “Infrastructure development and economic growth in India”, Journal of
the Asia Pacific Economy, Vol. 14 No. 4, pp. 351-365.
Shediac, R., Abouchakra, R., Hammami, M. and Najjar, M.R. (2008), Public–Private Partnerships: A New
Catalyst for Economic Growth, Booz and Company.
Shen, L., Lee, R. and Zhang, Z. (1996), “Application of BOT system for infrastructure projects in China”,
Journal of Construction Engineering and Management, Vol. 122 No. 4, pp. 319-332.
Sivakumaran, S., Perera, B.A.K.S. and Perera, K.T.P.K. (2015), “Construction management as a suitable
procurement method for hotel building construction in Sri Lanka”, Proceedings of the 19th
Pacific Association of Quantity Surveyors Congress, Pacific Association of Quantity Surveyors,
May 28-June 1.
Tawiah, P.A. and Russell, A.D. (2008), “Assessing infrastructure project innovation potential as a
function of procurement mode”, Journal of Management in Engineering, Vol. 24 No. 3, pp. 173-186.
Teddlie, C. and Tashakkori, A. (2003), “Major issues and controversies in the use of mixed methods in
the social and behavioral sciences”, in Tashakkori, A. and Teddlie, C. (Eds), Handbook of Mixed
Methods in Social and Behavioral Research, Sage, Thousand Oaks, CA, pp. 3-50.
United Nations (2012), “Country report for the third Asia Pacific Ministerial Conference on public
private partnership for infrastructure development. Tehran, Islamic Republic of Iran”, available
at: www.unescap.org/sites/default/files/3-SriLanka-Country-report.pdf (accessed June 12, 2017).
USAID (2016), “Report on Sri Lanka’s current PPP environment and recommendations for future PPP
strategy”, AID-OAA-I-12-00039, USAID.
Wibowo, A., Permana, A., Kochendörfer, B., Kiong, R.T.L., Jacob, D. and Neunzehn, D. (2012),
“Modeling contingent liabilities arising from government guarantees in Indonesian BOT/PPP
toll roads”, Journal of Construction Engineering and Management, Vol. 138 No. 12, pp. 1403-1410.
World Economic Forum (2012), “Strategic infrastructure-steps to prioritize and deliver infrastructure
effectively and efficiently”, available at: www.weforum.org (accessed May 3, 2017).
Zangoueinezhad, A. and Azar, A. (2014), “How public–private partnership projects impact infrastructure
industry for economic growth”, International Journal of Social Economics, Vol. 41 No. 10, pp. 994-1010.
Zhang, S., Gao, Y., Feng, Z. and Sun, W. (2015), “PPP application in infrastructure development in Suitability
China: institutional analysis and implications”, International Journal of Project Management, of PPP
Vol. 33 No. 3, pp. 497-509.
Zou, W., Kumaraswamy, M., Chung, J. and Wong, J. (2014), “Identifying the critical success factors for procurement
relationship management in PPP projects”, International Journal of Project Management, Vol. 32 method
No. 2, pp. 265-274.
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com