Muelle dela Industria Cor. Numancia and Prensa Sts., Binondo, Manila
III. Mechanical/Plumbing
1. All stub-outs must be properly enclosed when chipping or tile laying.
2. Split type wall mounted Air-condition drain should be properly tapped/connected to the air-
con drain provision of the unit. Coordinate to admin & building contractor for any
changes/alteration of the drain.
3. Used standard PPR pipes for water lines inside the unit and conduct pressure test (leak test) in
water system with in the unit.
V. Architectural Works
1. Drilling works especially on kitchen and T&B room walls must be carefully done to minimized
damages in embedded utilities such as electrical pipes and water lines.
2. Installation of aluminium grills outside of windows and balcony are not allowed to maintain
the architectural design of the building.
VI. Others
1. Provide at least 1-10lbs fire extinguisher inside the unit during renovation.
Other Comments:
Four Season Riviera
Muelle dela Industria Cor. Numancia and Prensa Sts., Binondo, Manila
__________________________________________________________________________________________
__________________________________________________________________________________________
__________________________________________________________________________________________