Professional Documents
Culture Documents
A Global Survey of Top Constru
A Global Survey of Top Constru
ABSTRACT
Construction delay is a global problem. Schedule performance was ranked higher
than budget and quality performances in judging project success. The first stage in
understanding construction delay is to pinpoint the top delay factors. To achieve an
improved schedule performance, suitable policies and actions must be implemented. A
global review of more than 200 studies reported for 59 countries/administrations is
carried out in the present study.
Are the top delay factors for different regions different? Which are the common top
delay factors globally? The aim of the present study is to address these issues. The top
construction delay factors for each region are ascertained and a comparison of the top
factors for the different regions is presented. The six regions include Africa, the Middle
East, South Asia, Southeast Asia, East Asia, and the more developed countries of
Oceania, Europe, and Americas. The findings of top delay factors for each of the regions
are useful because they highlight the main challenges faced by each region to improve
their schedule performances. Because of the high similarity level of construction
practices within each region, the bulk of the top delay factors ascertained for each of the
regions are most likely to be valid for countries within the regions where the top delay
factors have not been ascertained.
This study shows that ‘variation orders/changes of scope by owner during
construction’ and ‘late delivery/shortage of construction materials or fuel’ are among the
top delay factors for all the regions. Several top delay factors are found to be unique to
one particular region only.
INTRODUCTION
Schedule performance was ranked as the most important as compared to budget and
quality performances (Chua et al. 1999). Therefore, ascertaining the top delay factors (TDFs)
is important and the essential step in appreciating the key factors affecting schedule
performance. Suitable policies and actions should be implemented to tackle problems related
to the top delay factors identified. Construction delay is common globally. There are more
than 200 investigations to determine TDFs for 59 countries. Are the TDFs identical for these
RESEARCH METHODOLOGY
The methodology adopted for the review is encapsulated in Figure. 1.
6 Owner interference
7 Owner’s lack of experience/incompetent project team
8 Excessive bureaucracy in project-owner organization
9 Late release of site/land acquisition problems/delay or non-payment of compensation to the communities
10 Unrealistic/optimistic deadline set by client
Contractor-related factors
11 Inadequate contractor experience/incompetence contractor
12 Lack of technical professionals/incompetent project team
13 Ineffective planning and scheduling
14 Inaccurate estimating of construction materials quantities/price
15 Poor site management and supervision
16 Poor site coordination
17 Late delivery/shortage of construction materials or fuel
18 Financing by contractor
19 Subcontractor problems/mechanical and electrical works
20 Rework due to mistakes in construction/construction defects
21 Low productivity level of labors
22 Shortage of labor
23 Unqualified workforce/low skilled labor
24 Labor disputes/strikes/personal conflict among labors
25 Equipment (or operator) availability and failure
Consultants-related factors
26 Inadequate site investigation/unforeseen subsurface conditions
27 Lack of clarity in project scope
28 Poor contract management by consultants/Substandard contract
29 Mistakes and discrepancies in design documents by consultants
30 Delay in inspection and approval of works, approval of shop drawings, materials, and documents submitted by
contractor/complete design through shop drawings review
31 Late issuance of instructions, information or drawings/incomplete drawings/inadequate information/delay in
revising design documents and approving works or materials/delays in design work/delay due to progress
payment evaluation and issuance of certificate by quantity surveyor
32 Lack of constructability reviews in design
33 Wrong choice of consultants/poor contract management by consultants/inappropriate design by consultants
requiring redesign/incompetent or inexperience staff
34 Staff recruitment delay
Other factors
35 Inclement weather
36 Rise in prices of materials
37 Economic conditions
38 Security/political situations/border closures/segmentation
39 Corruption
40 Lack of community buy-in/environmental impact/civil disturbances, youth unrest, militancy and communal
crises
41 Delays by utility agencies/relocation/inaccurate as-built utility drawings
42 Natural disaster/acts of God
43 Government regulations and permit approval
Table 2. Summary of main causes of construction delay from existing literature on Africa
Burkina South
C Algeria Benin Botswana Cameroon Chad Egypt Ghana Kenya Libya Malawi Morocco Nigeria Rwanda Tanzania Uganda Zambia Zimbabwe
Faso Africa
R 1 2 3 4 5 76 6 3 7 8 9 10 11 3 12 13 14 15 16 17 18 19 20 21 22 23 24 25
M S S S S S S S S F F F S S S S I I F S S S S S S S S S S+P
N 18 175 18 49 150 140 84 18 - - - ? 72 18 45 33 12 - 38 142 22 75 60 247 52 26 53 27+4
T C A C B A A C C A A A A A C C A B A A A A B A A B C A A
1 X X X X X X X
2 X X X X X X X X X X X X X X X X X X X
3 X X X X X X X X X X X X X X X X
4 X X X
5 X X X X X X
7 X X X
8 X
9 X X X X X X
11 X X X X X X X X X X X
12 X X X X X
13 X X X X X X X X X X X X
14 X X X
15 X X X X X X X X X X X
16 X X X X
17 X X X X X X X X X X X X X X X X X X
18 X X X X X X X X X X X X X X X
19 X X X X X X X X X
20 X X X X X X
21 X X X
22 X X X X
Table 4 summarizes the top delay factors for each of the countries/administrations in the
Middle East. The top delay factors for the Middle East ascertained by this study
are summarized in Table 5. The seven top delay factors, namely ‘financing by
contractor’, ‘finance and payments of completed work by owner’, ‘late delivery/shortage
of construction materials or fuel’, ‘variation orders/changes of scope by owner
during construction’, ‘ineffective planning and scheduling’, ‘poor site management
and supervision’, and ‘inadequate contractor experience/incompetence contractor’ are
identified by more than half of the fourteen countries/administrations that were studied.
One top delay factor that is unique in Gaza and that was identified by Enshassi et al.
(2010a, 2010b) is ‘border closures’. Delay factor ‘corruption’ is unique to Afghanistan
only, and ‘delays by utility agencies/ relocation/inaccurate as-built utility drawings’ is
unique to Bahrain only. Corruption in construction normally serves to accelerate
the resolution of issues adversely affecting the schedule performance and provide alternatives
to shorten construction time. It is, therefore, surprising that it is one of the top delay
factors in Afghanistan. Unfortunately, no explanation was given in Niazai and Gidado
(2012).
Table 4. Major delay factors from literature on the Middle East
United
Saudi West Bank
C Afghanistan Bahrain Gaza Iran Iraq Jordan Kuwait Lebanon Oman Qatar Turkey Arab
Arabia of Palestine
Emirates
R 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 33 46 47
M S S S S F S S F S S S P P S S S+I F S S S S F S S
T A C A A A A A A B B A B B O C A A A A A A A C A
1 X X X X
2 X X X X X X X X X X X X X X X X
3 X X X X X X X X X X X X X X X X X X
4 X X X X X
5 X X X X X X X X
6 X X
7 X X X X X X X
9 X X X
10 X
11 X X X X X X X X X
12 X X
13 X X X X X X X X X X X X
15 X X X X X X X X X X
16 X X X
17 X X X X X X X X X X X X X X X X
18 X X X X X X X X X X X X X X
19 X X X X X X X
United
Saudi West Bank
C Afghanistan Bahrain Gaza Iran Iraq Jordan Kuwait Lebanon Oman Qatar Turkey Arab
Arabia of Palestine
Emirates
20 X X
21 X X X
22 X X X X X X
23 X X X
25 X X X X X
26 X
29 X X
30 X X X X
31 X X X
33 X X X
35 X X
36 X X X X X
37 X X
38 X X X X
39 X
40 X
41 X X
43 X X X X
References : 26 = Niazai and Gidado (2012); 27 = Hasan et al. (2014); 28 = Enshassi et al. (2009) and Al-Najjar(2008); 29 = Enshassi et al. (2010a) and Enshassi et al. (2010b);
30 = Kog (2017c); 31 = Hindawi and Awad (2007); 32 = Bekr (2015); 33 = Kog (2017e); 34 = Koushki et al. (2005); 35 = Al-Tabtabai (2002); 36 = Tumi et al. (2009);
37 = Alnuaimi and Mohsin (2013); 38 = Ruqaishi and Bashir (2013); 39 = Emam et al. (2015); 40 = Al-Jurf and Beheiry (2010); 41 = Kog (2018b); 42 = Arditi et al. (1985);
43 = Kazaz et al. (2012); 44 = Cülfik et al. (2014); 45 = Gündüz et al. (2013); 46 = Mahamid et al. (2012) and Mahamid (2013); 47 = Albatsh (2015)
72 Yue Choong Kog
Table 5. Top construction delay factors for the Middle East countries
Table 6 summarizes the TDFs for each of the countries in South Asia. The TDFs for
South Asia ascertained by this study are summarized in Table 7. The seven TDFs, namely
‘finance and payments of completed work by owner’, ‘late delivery/shortage of construction
materials or fuel’, ‘poor site management and supervision’, ‘equipment (or operator)
availability and failure’, ‘variation orders/changes of scope by owner during construction’,
‘ineffective planning and scheduling by contractor’, and ‘government regulation and permit
approval’ are identified by more than half of the five countries studied. The top delay factors
unique to some countries are as follows. ‘Communication problems/lack of adequate project
coordination’ among the project participants, ‘poor site co-ordination’ and ‘unqualified
workforce/low skilled labor’ are unique to India only. ‘Excessive bureaucracy in project-
owner organization’ and ‘late release of site/land acquisition problems/delay or non-payment
of compensation to the communities’ and ‘staff recruitment delay’ by consultants are unique
to Bangladesh only. Contractor’s ‘lack of technical professionals/incompetent project team’ is
unique to Nepal only. ‘Shortage of labor’ is unique to Sri Lanka only.
Table 8 summarizes the TDFs for each of the countries/administrations in East Asia. The
TDFs for East Asia found by this review are summarized in Table 9. All the TDFs found by
this review are identified by more than half of the four countries/administrations studied.
‘Finance and payments of completed work by owner’ and ‘staff recruitment delay’ by
consultants are unique to China. This is because the TDFs of China are identified based
on infrastructural projects of the Asian Development Bank. ‘Inadequate contractor
experience/incompetence contractor’, ‘lack of technical professionals/incompetent project
team’, ‘ineffective planning and scheduling’ by the contractor, ‘poor site management
and supervision’, ‘late issuance of instructions, information or drawings/incomplete
drawings/inadequate information/delay in revising design documents and approving works or
74 Yue Choong Kog
Table 10 summarizes the TDFs reported for each of the countries in Southeast Asia. The
TDFs for Southeast Asian countries identified by this study are summarized in Table 11. The
seven TDFs, namely, ‘finance and payments of completed work by owner’, ‘variation
orders/changes of scope by owner during construction’, ‘ineffective planning and scheduling
by contractor’, ‘late delivery/shortage of construction materials’, ‘inadequate contractor
experience/incompetence contractor’, ‘poor site management and supervision’, and ‘shortage
of labor’ are identified by more than half of the seven countries/administrations studied.
The TDFs unique to some countries are discussed as follows. ‘Owner’s lack of
experience/incompetent project team’, ‘poor contract management by consultants/
substandard contract’, and ‘government regulations and permit approval’ are unique to
Thailand only. ‘Unrealistic/optimistic deadline set by client’ and ‘natural disaster/
acts of God’, are unique to Cambodia only. ‘Mistakes and discrepancies in design
documents by consultants’ is unique to Brunei only. ‘Wrong choice of consultants/poor
contract management by consultants/inappropriate design by consultants requiring
redesign/incompetent or inexperience staff’ is unique to Malaysia only. ‘Inaccurate estimating
76 Yue Choong Kog
Table 11. Top construction delay factors for Southeast Asian countries
Table 12 summarizes the TDFs identified for Australia, New Zealand, Portugal, Norway,
Slovenia, UK, Chile, Canada, and US. The respective TDFs for these countries ascertained by
this study are summarized in Table 13. The eight TDFs, namely, ‘late issuance of instructions,
information or drawings/incomplete drawings/inadequate information/delay in revising and
approving design documents/delays in design work’, ‘variation orders/changes of scope by
owner during construction’, ‘slow decisions from owner’, ‘mistakes and discrepancies in
design documents by consultants’, ‘communication problems by all project participants’,
‘ineffective planning and scheduling by contractor’, ‘subcontractor problems/mechanical and
electrical works’, and ‘inadequate site investigation/unforeseen subsurface conditions’ are
identified by more than half of the nine countries/administrations studied. The TDFs that
are unique to some countries are discussed as follows. ‘Contractor selection methods
(negotiation, lowest bidder)’ is unique to New Zealand only. ‘Low productivity level of
labors’, ‘equipment (or operator) availability and failure’ and ‘natural disaster/acts of God’
are unique to Chile only. ‘Poor contract management by consultants/substandard contract’ is
unique to Slovenia only. Keen (2010) is the only study among the more than 200 studies on
construction delay factors that identified that the consultants in Canada ‘completed design
through shop drawings review’ as a TDF.
A Global Survey of Top Construction Delay Factors 77
Table 12. Major delay factors from literature on Australia, New Zealand,
Europe, and Americas
New
C Australia Canada Chile Norway Portugal Slovenia UK US
Zealand
R 64 65 66 67 68 69 70 71 72 73 74 75 74 74
M S P+S I P P S P S S S F S F F
N 32 33+33 ? 175 24 87 16 28 143 202 - 62 - -
T A B C B A O B A A A A A A A
1 X X X X X X X
2 X X X
3 X X X X X X X X X
4 X
5 X X X X X X
7 X X X
9 X X
10 X X X
11 X X X
12 X
13 X X X X X X X X
14 X
15 X X X X X
16 X X X
17 X X X X X
19 X X X X X
20 X X
21 X X
22 X X
23 X X X
25 X
26 X X X X X X
27 X
28 X
29 X X X X X X X
30 X X X
31 X X X X X X X X X X
32 X X
33 X X X X
35 X X X
42 X
43 X X X X
Reference: 64 = Wong and Vimonsatit (2002); 65 = Walker(1995); 66 = Orangi et al. (2011); 67 = Keen (2010); 68 =
Semple et al. (1994); 69 = Jergeas and Ruwanpura (2010) and Ruwanpura and Jergeas (2010); 70 = Alarcón et al.
(2008); 71 = Lessing et al. (2017); 72 = Zidane et al. (2015); 73 = Eik-Andresen et al. (2015); 74 = Kog (2018e); 75 =
Srdić and Šelih (2015).
78 Yue Choong Kog
The ten TDFs for 59 countries/administrations ascertained by this study are summarized
in Table 14. The four TDFs, namely, ‘finance and payments of completed work by
owner’, ‘variation orders/changes of scope by owner during construction’, ‘late
delivery/shortage of construction materials or fuel’, ‘ineffective planning and scheduling’, and
‘financing by contractor’ are identified by more than half of the 59 countries/administrations
studied.
Table 13. Top construction delay factors for Oceania
and European and American countries
Countries/Administrations
Construction delay factor Rank
No. Proportion
South Oceania,
South East Middle
Construction delay factor East Europe and Africa All
Asia Asia East
Asia Americas
Finance and payments of completed
1 1 10 2 12 1 1
work by owner
Variation orders/changes of scope
1 5 1 2 2 4 2
by owner during construction
Poor site management and supervision
5 3 10 6 12 8 6
by contractor
Late delivery/shortage of
3 1 4 2 9 2 2
construction materials or fuel
Financing by contractor 8 8 10 1 30 2 5
Mistakes and discrepancies in
14 25 10 22 3 21 17
design documents by consultants
Communication problems by
8 13 27 22 5 21 14
all project participants
Owner’s lack of experience/
21 13 4 9 18 28 17
incompetent project team
Excessive bureaucracy in project-owner
29 13 4 37 30 40 37
organization
Inadequate contractor experience/
5 8 10 7 12 8 7
incompetence contractor
Ineffective planning and scheduling
3 5 10 5 5 6 4
by contractor
Shortage of labor 5 13 27 9 18 15 12
Equipment (or operator) availability
14 3 27 14 24 4 8
and failure
Late issuance of instructions, information or
drawings/incomplete drawings/ inadequate
8 13 10 22 1 7 10
information/delay in revising and approving
design documents/delays in design work
Wrong choice of consultants/poor contract
management by consultants/inappropriate
21 8 10 14 9 28 17
design by consultants requiring
redesign/incompetent or inexperience staff
Inclement weather 8 8 27 22 12 13 13
Slow decisions from owner 14 8 4 8 3 11 8
Subcontractor problems 8 25 4 9 5 8 11
Inadequate site investigation/unforeseen
21 25 2 31 5 28 23
subsurface conditions
Government regulation and permit approval 21 5 2 22 9 15 16
Late release of site/land acquisition
8 13 4 14 18 11 13
problems
Natural disaster/acts of God 21 8 27 37 24 36 25
Table 15 summarizes the TDFs found by this review for Africa, the Middle East, South
Asia, East Asia, Southeast Asia, and the grouping of Oceania, Europe and Americas
representing the relatively more developed countries. Delay factors ‘variation orders/changes
of scope by owner during construction’ and ‘late delivery/shortage of construction materials
80 Yue Choong Kog
or fuel’ are among the TDFs for all regions. The delay factor ‘ineffective planning and
scheduling’ by contractor is a TDF for all regions except East Asia. There are some delay
factors that are the TDF unique to one particular region only. For example, ‘natural
disaster/acts of God’ is unique to South Asia and ‘mistakes and discrepancies in design
documents by consultants’ is unique to the grouping of Oceania, Europe and Americas.
Many suggestions were made in Kog (2017a to 2017e, 2018a to 2018e, 2019a to 2019b)
on measures that could be taken to address various delay factors to improve schedule
performance. If such suggestions can be implemented rigorously in a sustained manner, the
schedule performance of construction projects can definitely be improved and construction
delay can be reduced substantially. The adverse impact of variation orders to the construction
schedule performance is well known. Why are architects in building projects and civil
engineers in civil engineering projects persisted in issuing variation orders after the
commencement of construction? Unfortunately, there is no study reported on the underlying
reasons on the issuance of variation orders. The present study highlights the importance that
future research should be undertaken so that appropriate actions are taken to curtail the
issuance of variation orders after the commencement of construction. Similarly, there is no
study reported on the underlying reasons for the late delivery/shortage of construction
materials or fuel. Shortage of fuel is confined to the region of Africa. According to Table 15,
‘late delivery/shortage of construction materials’ is a TDF for the grouping of Oceania,
Europe and Americas representing the relatively more developed countries. How much of
‘late delivery/shortage of construction materials’ can be attributed to the local logistics system
and other causes? Future research should be undertaken so that suitable policies and actions
are taken to tackle this important delay factor.
CONCLUSION
A review of more than 200 studies for 59 countries/administrations shows that the TDFs
are ‘finance and payments of completed work by owner’, ‘variation orders/changes of
scope by owner during construction’, ‘late delivery/shortage of construction materials or
fuel’, ‘ineffective planning and scheduling’, ‘financing by contractor’, ‘poor site management
and supervision’, ‘inadequate contractor experience/incompetence contractor’, ‘equipment
(or operator) availability and failure’, ‘late issuance of instructions, information or
drawings/incomplete drawings/ inadequate information/delay in revising and approving
design documents/delays in design work’, and ‘slow decisions from owner’.
Comparison of the TDFs for the different regions shows that ‘variation orders/changes of
scope by owner during construction’ and ‘late delivery/shortage of construction materials or
fuel’ are among the TDFs for all regions. On the other hand, ‘natural disaster/acts of God’ as
a top delay factor is unique to South Asia only, and ‘mistakes and discrepancies in design
documents by consultants’ is unique to the grouping of Oceania, Europe and Americas only.
The findings of TDFs for each of the regions are useful because they highlight the main
challenges faced by each region to improve their schedule performances. The practical
implications of the present study are that appropriate measures must be taken to address the
TDFs of ‘variation orders/changes of scope by owner during construction’ and ‘late
delivery/shortage of construction materials or fuel’ and other TDFs unique to each region to
improve the schedule performance of construction projects.
A Global Survey of Top Construction Delay Factors 81
Because of the high similarity level of construction practices within each region, the bulk
of the TDFs identified for each of the regions are most likely to be the TDFs for countries
within the regions where the TDFs have not been identified. The present study highlights the
importance that future research should be undertaken so that appropriate actions are taken to
curtail the issuance of variation orders after the commencement of construction and the late
delivery/shortage of construction materials. As a practitioner for more than forty years, it is
clear that the frequent issuances of variation order are often related to the level of
professionalism of the project participants and the fast track nature of many construction
projects particularly the civil engineering projects. For fast track projects, some stakeholders
do not have sufficient time to finalize their requirements. It is also not possible to obtain all
the necessary approvals from the relevant authorities before calling tender. Variations may be
required to comply with the authorities’ requirements and the stakeholders’ finalized
requirements during construction. The number of variation orders will definitely be reduced if
appropriate measures, such as allowing more time for project participants to finalize the
design and obtaining authorities’ approvals before calling the construction tender, are
implemented.
REFERENCES
Acharya, N. K., Im, H. M. and Lee, Y. D. (2006). Investigating delay factors in construction
industry: A Korean perspective. Korean Journal of Construction Engineering and
Management, Korea Institute of Construction Engineering and Management, Seoul,
Korea, 7(5), 177-190.
Adeyemi, A.Y. and Masalila, K. (2016). Delay factors and time-cost performance of
construction projects in Gaborone City Council, Botswana. Journal for the Advancement
of Performance Information & Value, 8(1), 4-1 to 4-18.
Adugna, N. T. (2015). A study of causes of delay and cost overrun in office construction
projects in the eThekwini Municipal Area, South Africa, Master of Technology
(Construction Management) thesis, Durban University of Technology, Durban, South
Africa, June, 136p.
Ahsan, K. and Gunawan, I. (2010). Analysis of cost and schedule performance of
international development projects. International Journal of Project Management,
Elsevier, Oxford, U.K., 28(1), 68–78.
Akoa B. B. (2011). Cost overruns and time delays in highway and bridge projects in
developing countries experiences from Cameroon, Master of Science thesis, Michigan
State University, Michigan, U.S.A., 241p.
Akogbe, R. K. T. M., Feng, X. and Zhou, J. (2013). Importance and ranking evaluation of
delay factors for development construction projects in Benin. KSCE Journal of Civil
Engineering, Springer and Korean Society of Civil Engineers, Seoul, South Korea, Vol.
17, 1213-1222.
Alarcón, L. F., Diethelm, S., Rojo, O. and Calderon, R. (2008). Assessing the impacts
of implementing lean construction. Revista ingeniería de construcción, Pontificia
Universidad Católica de Chile, Departamento de Ingeniería y Gestión de la Construcción,
Santiago, Chile 23(1), 26-33.
82 Yue Choong Kog
Jergeas, G. F. and Ruwanpura, J. (2010). Why cost and schedule overruns on mega oil sands
projects?. Practice Periodical on Structural Design and Construction, ASCE, 15(1), 40-
43, https://doi.org/10.1061/(ASCE)SC.1943-5576.0000024.
Joseph, M. (2004). Delays in completion of building construction projects in the Botswana
public sector by medium to large category C, D and E contractors, Master of Science
(Project Management) thesis, University of Pretoria, Hatfield, South Africa.
Kadry, M., Osman, H. and Georgy, M. (2016). Causes of construction delays in countries
with high geopolitical risks. Journal of Construction Engineering and Management,
ASCE, 04016095-1 to 04016095-11, https://doi.org/10.1061/(ASCE)CO.1943-7862.000
1222.
Kaliba, C., Muya, M. and Mumba, K., (2009). Cost escalation and schedule delays in road
construction projects in Zambia. International Journal of Project Management, Elsevier,
U.K., Oxford, 27(5), 522-531.
Kamanga, M. J. and Steyn, W. J. (2013). Causes of delay in road construction projects in
Malawi. Journal of the South African Institution of Civil Engineering, Johannesburg,
South Africa, 55(3), 79-85.
Kazaz, A., Ulubeyli, S. and Avcioglu, N. (2012). Causes of delays in construction projects in
Turkey. Journal of Civil Engineering and Management, Taylor Francis and Vilnius
Gediminas Technical University, 18(3), 426–35.
Keen, B. (2010). The pitfalls of incomplete contract documents. British Columbia
Construction Association, 29(1), March, Victoria, British Columbia, Canada, 6p.
Kikwasi, J. G. (2012). Causes and effects of delays and disruptions in construction projects in
Tanzania. Australasian Journal of Construction Economics and Building Conference
Series, 1(2), 52-59.
Kog, Y. C., (2017a). Major Delay factors for Construction Projects in Ghana. Journal for the
Advancement of Performance Innovation and Value, 9(1), CIB Performance Based
Studies Research Group, Arizona State University, 96-105.
Kog, Y. C. (2017b). Major delay factors for construction projects in Nigeria. International
Journal of Architecture, Engineering and Construction, 6(2), International Association
for Sustainable Development and Management (IASDM), Toronto, Ontario, Canada, 46-
54.
Kog, Y. C. (2017c). Major delay factors for construction projects in Iran. International
Journal of Construction Project Management, 9(2), Nova Science Publishers Inc., New
York, N.Y., U.S.A., 86-97.
Kog, Y. C. (2017d). Project management and delay factors of public housing construction.
Practice Periodical on Structural Design and Construction, 23(1), ASCE, 04017028-1 to
04017028-8, https://doi.org/10.1061/(ASCE)SC.1943-5576.0000350.
Kog, Y. C. (2017e). Major construction delay factors of Jordan, UAE, Pakistan, Sri Lanka.
International Journal of Architecture, Engineering and Construction, 6(4), International
Association for Sustainable Development and Management (IASDM), Toronto, Ontario,
Canada, 13-25, http://dx.doi.org/10.7492/IJAEC.2017.020
Kog, Y. C. (2018a). Top construction delay factors of Kenya. Journal for the Advancement of
Performance Innovation and Value, 10(4), CIB Performance Based Studies Research
Group, Arizona State University, 120-129.
Kog, Y. C. (2018b). Major construction delay factors of Saudi Arabia. International Journal
of Architecture, Engineering and Construction, 7(2), International Association for
A Global Survey of Top Construction Delay Factors 85
Muya, M., Kaliba, C., Sichombo, B. and Shakantu, W. (2013). Cost escalation, schedule
overruns and quality shortfalls on construction projects: The case of Zambia.
International Journal of Construction Management, Taylor Francis and the Chinese
Research Institute of Construction Management, Hong Kong, 13(1), 53-68.
Niazai, G. A. and Gidado, K. (2012). Causes of project delay in the construction industry in
Afghanistan. Proc. International Conference on Engineering, Project and Production
Management (EPPM) Conference, organized by Association of Engineering, Project, and
Production Management and University of Brighton, 10-11 September, Brighton, U.K.
Olawale, Y. and Sun M. (2010). Cost and time control of construction projects: Inhibiting
factors and mitigating measures in practice. Construction Management and Economics,
28 (5), 509 – 526
Orangi, A., Palaneeswaran, E. and Wilson, J. (2011). Exploring delays in Victoria-based
Australian pipeline projects. Procedia Engineering, 14, 874-881.
Ruqaishi, M. and Bashir, H. A. (2013). Causes of delay in construction projects in the oil and
gas industry in the gulf cooperation council countries: a case study. Journal of
Management in Engineering, ASCE, 31(3), 05014017-1 to 05014017-8.
Ruwanpura, J. and Jergeas, G. (2010). Why cost and schedule overruns on mega oils sands
projects?. Cost Engineering, AACE International, Morgantown, West Virginia, U.S.A.,
16(1), 24-27.
Salleh, R. (2009). Critical success factors of project management for Brunei construction
projects: improving project performance. Ph.D. thesis, Queensland University of
Technology, 309p.
Santoso, D.S. and Soeng, S. (2016). Analyzing delays of road construction projects in
Cambodia: causes and effects. Journal of Management in Engineering, ASCE, 32(6),
05016020-1 to05016020-11, https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.
Semple, C., Hartman, F. T., and Jergeas, G. (1994). Construction claims and disputes: Causes
and cost/time overruns, Journal of Construction Engineering and Management, ASCE,
120(4), 785-795, https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(785).
Shebob, A., Dawood, N., Shah, R. K. and Xu, Q. (2012). Comparative study of delay factors
in Libyan and the UK construction industry. Engineering, Construction and Architectural
Management, Emerald Publishing, Bingley, U.K., 19 (6), 688 – 712.
Shiri, T. (2015). An investigation of the causes and effects of construction delays on
Zimbabwean construction projects. Bachelor of Quantity Surveying (Honours) Degree
Thesis, Department of Quantity Surveying, Faculty of the Built Environment, National
University of Science and Technology, Bulawayo, Zimbabwe, 68p.
Srdić, A. and Šelih, J. (2015). Delays in construction projects: Causes and mitigation.”,
Organization, Technology and Management in Construction - an International Journal,
7(3), University of Zagreb, Faculty of Civil Engineering, Croatia, 1383-1389.
Tumi, S. A. H., Omran, A., and Pakir, A. H. K. (2009). Causes of delay in construction
industry in Libya. Proc. Int. Conf. Administration and Business, Univ. Bucharest,
Romania, 14-15th November, 265-272.
Walker, D. H. T. (1995). An investigation into construction time performance. Construction
Management and Economics, Taylor Francis, London, U.K., 13(3), 263-274.
Woldeyohannes, B., Fekadu, A. and Zeray, A. (2020). Investigation of contributing factors
for smart parking development projects Delay: The Case of Addis Ababa, Ethiopia.
A Global Survey of Top Construction Delay Factors 87
International Journal of African and Asian Studies, Academic Hosting & Event
Management Solutions, 67, 9-22.
Wong, K. and Vimonsatit, V. (2012). A study of the factors affecting construction time in
Western Australia. Scientific Research and Essays, Ebène, Mauritius, 7(40), 3390-3398.
Yang, J. B. and Liao, P. Y. (2008). Analysis of delay causes for pipeline projects in sewage
system: Taiwan cases. Proc. of the ASCE International Pipelines Conference, Pipelines
2008: Pipeline Asset Management: Maximizing Performance of our Pipeline
Infrastructure, Gokhale, S. and Rahman, S. (eds.), Pipeline Division of the ASCE,
Atlanta, Georgia, July 22nd-27th, 1-10.
Yang, J. B., Yang, C. C. and Kao, C. K. (2010). Evaluating schedule delay causes for private
participating public construction works under the Build-Operate-Transfer model.
International Journal of Project Management, Elsevier, Oxford, U.K., 28(6), 569-579.
Zidane, Y.J., Johansen, A., Andersen, B. and Hoseini, E. (2015). Time-thieves and
bottlenecks in the Norwegian construction projects. Procedia Economics and Finance,
Elservier, Oxford, U.K., 21, 486-493.
Reproduced with permission of copyright owner. Further reproduction
prohibited without permission.