You are on page 1of 26

International Journal of Construction Project Management ISSN: 1944-1436

Volume 13, Number 1 © 2021 Nova Science Publishers, Inc.

A GLOBAL SURVEY OF TOP CONSTRUCTION


DELAY FACTORS

Yue Choong Kog, PhD


East West Engineering Consultants, Singapore

ABSTRACT
Construction delay is a global problem. Schedule performance was ranked higher
than budget and quality performances in judging project success. The first stage in
understanding construction delay is to pinpoint the top delay factors. To achieve an
improved schedule performance, suitable policies and actions must be implemented. A
global review of more than 200 studies reported for 59 countries/administrations is
carried out in the present study.
Are the top delay factors for different regions different? Which are the common top
delay factors globally? The aim of the present study is to address these issues. The top
construction delay factors for each region are ascertained and a comparison of the top
factors for the different regions is presented. The six regions include Africa, the Middle
East, South Asia, Southeast Asia, East Asia, and the more developed countries of
Oceania, Europe, and Americas. The findings of top delay factors for each of the regions
are useful because they highlight the main challenges faced by each region to improve
their schedule performances. Because of the high similarity level of construction
practices within each region, the bulk of the top delay factors ascertained for each of the
regions are most likely to be valid for countries within the regions where the top delay
factors have not been ascertained.
This study shows that ‘variation orders/changes of scope by owner during
construction’ and ‘late delivery/shortage of construction materials or fuel’ are among the
top delay factors for all the regions. Several top delay factors are found to be unique to
one particular region only.

INTRODUCTION
Schedule performance was ranked as the most important as compared to budget and
quality performances (Chua et al. 1999). Therefore, ascertaining the top delay factors (TDFs)
is important and the essential step in appreciating the key factors affecting schedule
performance. Suitable policies and actions should be implemented to tackle problems related
to the top delay factors identified. Construction delay is common globally. There are more
than 200 investigations to determine TDFs for 59 countries. Are the TDFs identical for these

 Corresponding Author’s Email: eastwestconsult@yahoo.co.uk


64 Yue Choong Kog

59 countries/administrations? Construction practices are dependent on business environment


risk, contractual arrangements, regulatory restrictions, and differences in culture and in
standards. The similarity level of the construction practices within the same region is high.
Will the top delay factors of different regions differ? Which are the global common top delay
factors? What are the TDFs for all the 59 countries/administrations? The aim of this paper is
to address these issues by a comparative study of the top delay factors identified in these
studies. A review of these studies is carried out to ascertain the TDFs in different regions, i.e.
South Asia, East Asia, Southeast Asia, the Middle East, Africa, and the more developed
countries in Oceania, Europe and Americas. Comparison of the TDFs for different regions
reveals interesting differences. The TDFs for all the 59 countries/ administrations are also
identified. No global survey of TDFs has been reported and the TDFs that are common
globally have not been identified. A comparison of TDFs of different regions has yet to be
reported in the literature. The findings of TDFs for each of the regions are useful because they
highlight the main challenges faced by each region to improve their schedule performances.
Because of the high similarity level of construction practices within each region, the bulk of
the TDFs identified for each of the regions are most likely to be the TDFs for countries within
the regions where the TDFs have not been identified.

RESEARCH METHODOLOGY
The methodology adopted for the review is encapsulated in Figure. 1.

Figure 1 Research Methodology.


A Global Survey of Top Construction Delay Factors 65

STANDARDIZED DELAY FACTORS


The standardized construction delay factors are summarized in Table 1. The category
indicates the party exerting the largest impact on the outcome of each of the factors. Factors
not influenced by the owner, consultant and contractor are placed under the category of ‘other
factors’. Construction delay factors identified by more than 200 studies are summarized in
Tables 2, 4, 6, 8, 10, and 12. Some of the studies identified slightly more than ten TDFs and
others only identified three TDFs.
As pointed out in Kog (2017a to 2017e, 2018a to 2018e, 2019a to 2019b), the naming of
delay factors were not standardized in the various studies. This was the main problem in
reviewing the TDFs reported and has to be standardized. Also, similar delay factors are
merged for consistency in this review. It is not possible to list all of them and some of them
can be found in Kog (2017a to 2017e, 2018a to 2018e, 2019a to 2019b). For example,
‘consultants endeavored to complete the design through shop drawing review’ reported by
Keen (2010) is grouped together with ‘approval of shop drawings’. Similarly, delay factors
‘late issuance of instructions’, ‘late issuance of information’, ‘late issuance of drawings’,
‘incomplete drawings’, ‘inadequate information’, ‘delay in revising design documents and
approving works’, and ‘delays in design work’ are grouped together and delay factors ‘wrong
choice of consultants’, ‘poor contract management by the consultants’ and ‘inappropriate
design by the consultants’ are grouped together.

TOP DELAY FACTORS FOR DIFFERENT REGIONS


Table 2 summarizes the TDFs identified for each of the countries in Africa. The ranking
of each of the TDFs ascertained by this study and their respective proportions of the total
number of countries are shown in Table 3. The top five delay factors, namely ‘finance and
payments of completed work by owner’, ‘financing by contractor’, ‘variation orders/changes
of scope by owner during construction’, ‘late delivery/shortage of construction materials or
fuel’, and ‘equipment (or operator) availability and failure’ are identified by more than
half of the 20 countries studied. It will be of interest to note that the followings:
‘unrealistic/optimistic deadline set by client’ and ‘staff recruitment delay’ by consultants are
unique to Kenya only and ‘natural disaster/acts of God’ is unique to Nigeria only.

Table 1. Summary of construction delay factors from existing literature

DF Construction delay factor (DF)


All project participants related factor
1 Communication problems/lack of adequate project coordination
Owner-related factors
2 Finance and payments of completed work by owner
3 Variation orders/changes of scope by owner during construction
4 Contractor selection methods (negotiation, lowest bidder)
5 Slow decisions from owner

(Table 1 continued on next page)


66 Yue Choong Kog

6 Owner interference
7 Owner’s lack of experience/incompetent project team
8 Excessive bureaucracy in project-owner organization
9 Late release of site/land acquisition problems/delay or non-payment of compensation to the communities
10 Unrealistic/optimistic deadline set by client
Contractor-related factors
11 Inadequate contractor experience/incompetence contractor
12 Lack of technical professionals/incompetent project team
13 Ineffective planning and scheduling
14 Inaccurate estimating of construction materials quantities/price
15 Poor site management and supervision
16 Poor site coordination
17 Late delivery/shortage of construction materials or fuel
18 Financing by contractor
19 Subcontractor problems/mechanical and electrical works
20 Rework due to mistakes in construction/construction defects
21 Low productivity level of labors
22 Shortage of labor
23 Unqualified workforce/low skilled labor
24 Labor disputes/strikes/personal conflict among labors
25 Equipment (or operator) availability and failure
Consultants-related factors
26 Inadequate site investigation/unforeseen subsurface conditions
27 Lack of clarity in project scope
28 Poor contract management by consultants/Substandard contract
29 Mistakes and discrepancies in design documents by consultants
30 Delay in inspection and approval of works, approval of shop drawings, materials, and documents submitted by
contractor/complete design through shop drawings review
31 Late issuance of instructions, information or drawings/incomplete drawings/inadequate information/delay in
revising design documents and approving works or materials/delays in design work/delay due to progress
payment evaluation and issuance of certificate by quantity surveyor
32 Lack of constructability reviews in design
33 Wrong choice of consultants/poor contract management by consultants/inappropriate design by consultants
requiring redesign/incompetent or inexperience staff
34 Staff recruitment delay
Other factors
35 Inclement weather
36 Rise in prices of materials
37 Economic conditions
38 Security/political situations/border closures/segmentation
39 Corruption
40 Lack of community buy-in/environmental impact/civil disturbances, youth unrest, militancy and communal
crises
41 Delays by utility agencies/relocation/inaccurate as-built utility drawings
42 Natural disaster/acts of God
43 Government regulations and permit approval
Table 2. Summary of main causes of construction delay from existing literature on Africa

Burkina South
C Algeria Benin Botswana Cameroon Chad Egypt Ghana Kenya Libya Malawi Morocco Nigeria Rwanda Tanzania Uganda Zambia Zimbabwe
Faso Africa
R 1 2 3 4 5 76 6 3 7 8 9 10 11 3 12 13 14 15 16 17 18 19 20 21 22 23 24 25
M S S S S S S S S F F F S S S S I I F S S S S S S S S S S+P
N 18 175 18 49 150 140 84 18 - - - ? 72 18 45 33 12 - 38 142 22 75 60 247 52 26 53 27+4
T C A C B A A C C A A A A A C C A B A A A A B A A B C A A
1 X X X X X X X
2 X X X X X X X X X X X X X X X X X X X
3 X X X X X X X X X X X X X X X X
4 X X X
5 X X X X X X
7 X X X
8 X
9 X X X X X X
11 X X X X X X X X X X X
12 X X X X X
13 X X X X X X X X X X X X
14 X X X
15 X X X X X X X X X X X
16 X X X X
17 X X X X X X X X X X X X X X X X X X
18 X X X X X X X X X X X X X X X
19 X X X X X X X X X
20 X X X X X X
21 X X X
22 X X X X

(Table 2 continued on next page)


Burkina South
C Algeria Benin Botswana Cameroon Chad Egypt Ghana Kenya Libya Malawi Morocco Nigeria Rwanda Tanzania Uganda Zambia Zimbabwe
Faso Africa
23 X X X X X X
24 X X X X
25 X X X X X X X X X X X X X X
26 X X X X
27 X X
28 X X X
29 X X X X X
30 X
31 X X X X X X X X X
33 X X
35 X X X X
36 X X
37 X X X X X
38 X X X X X
39 X X
40 X
41 X X
43 X X X X X X
Legends: C = Country/Administration; R = Reference; M = Methodology of study; N = Number of respondents in the questionnaire survey/projects; T = Type of construction
projects studied; S = study is based on a survey of views of owners, contractors and consultants; P = study is based on actual construction projects; I = open ended interviews;
F = review of all relevant reported studies; A = Building, road, water and sewer etc. projects; B = Building projects; C = Civil engineering infrastructural projects such as
highway, water, sewer, pipeline projects; G = Ground water work projects; O = Oil and gas projects; @=not able to check this; ? = number of respondents not stated in the
reference
References: 1 = Kadry et al. (2016); 2 = Akogbe (2013); 3 = Tumi et al. (2009); 4 = Joseph (2004); 5 = Adeyemi and Masalila (2016); 76 = Bagaya and Song (2016); 6 = Akoa
(2011); 7 = Kog (2019a); 77 = Woldeyohannes et al. (2020); 8 = Kog (2017a); 9 = Kog (2018a); 10 = Mezher and Tawil (1998); 11 = Shebob et al. (2012); 12 = Kamanga
and Steyn (2013); 13 = Challal and Tkiouat (2012a); 14 = Challal and Tkiouat (2012b) ; 15 = Kog (2017b); 16 = Amandin and Kule (2016).; 17 = Mukuka (2014); 18 =
Baloyi and Bekker (2011); 19 = Adugna (2015); 20 = Kikwasi (2012); 21 = Alinaitwe et al. (2013) and Apolot et al. (2016); 22 = Muhwezi et al. (2014); 23 = Kaliba et al.
(2009); 24 = Muya et al. (2013); 25 = Shiri (2015).
A Global Survey of Top Construction Delay Factors 69

Table 3. Top construction delay factors for African countries

Construction delay factor Rank No. Proportion*

Finance and payments of completed work by owner 1 14 70%

Financing by contractor 2 11 55%

Late delivery/shortage of construction materials or fuel 2 11 55%

Variation orders/changes of scope by owner during


4 10 50%
construction

Equipment (or operator) availability and failure 4 10 50%

Ineffective planning and scheduling by contractor 6 9 45%

Late issuance of instructions, information or


drawings/incomplete drawings/inadequate
7 8 40%
information/delay in revising design documents and
approving works or materials/delays in design work

Poor site management and supervision by contractor 8 7 35%

Subcontractor problems 8 7 35%

Inadequate contractor experienceincompetence


8 7 35%
contractor
*Proportion of studies that identified the factor to be one of the top 10 delay factors.

Table 4 summarizes the top delay factors for each of the countries/administrations in the
Middle East. The top delay factors for the Middle East ascertained by this study
are summarized in Table 5. The seven top delay factors, namely ‘financing by
contractor’, ‘finance and payments of completed work by owner’, ‘late delivery/shortage
of construction materials or fuel’, ‘variation orders/changes of scope by owner
during construction’, ‘ineffective planning and scheduling’, ‘poor site management
and supervision’, and ‘inadequate contractor experience/incompetence contractor’ are
identified by more than half of the fourteen countries/administrations that were studied.
One top delay factor that is unique in Gaza and that was identified by Enshassi et al.
(2010a, 2010b) is ‘border closures’. Delay factor ‘corruption’ is unique to Afghanistan
only, and ‘delays by utility agencies/ relocation/inaccurate as-built utility drawings’ is
unique to Bahrain only. Corruption in construction normally serves to accelerate
the resolution of issues adversely affecting the schedule performance and provide alternatives
to shorten construction time. It is, therefore, surprising that it is one of the top delay
factors in Afghanistan. Unfortunately, no explanation was given in Niazai and Gidado
(2012).
Table 4. Major delay factors from literature on the Middle East

United
Saudi West Bank
C Afghanistan Bahrain Gaza Iran Iraq Jordan Kuwait Lebanon Oman Qatar Turkey Arab
Arabia of Palestine
Emirates
R 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 33 46 47

M S S S S F S S F S S S P P S S S+I F S S S S F S S

N 21 144 124 66 27 134 - 450 48 36 32 14 59 37 15+15 - 20 71 151 64 - 64 219

T A C A A A A A A B B A B B O C A A A A A A A C A

1 X X X X

2 X X X X X X X X X X X X X X X X

3 X X X X X X X X X X X X X X X X X X

4 X X X X X

5 X X X X X X X X

6 X X

7 X X X X X X X

9 X X X

10 X

11 X X X X X X X X X

12 X X

13 X X X X X X X X X X X X

15 X X X X X X X X X X

16 X X X

17 X X X X X X X X X X X X X X X X

18 X X X X X X X X X X X X X X

19 X X X X X X X
United
Saudi West Bank
C Afghanistan Bahrain Gaza Iran Iraq Jordan Kuwait Lebanon Oman Qatar Turkey Arab
Arabia of Palestine
Emirates
20 X X

21 X X X

22 X X X X X X

23 X X X

25 X X X X X

26 X

29 X X

30 X X X X

31 X X X

33 X X X

35 X X

36 X X X X X

37 X X

38 X X X X

39 X

40 X

41 X X

43 X X X X
References : 26 = Niazai and Gidado (2012); 27 = Hasan et al. (2014); 28 = Enshassi et al. (2009) and Al-Najjar(2008); 29 = Enshassi et al. (2010a) and Enshassi et al. (2010b);
30 = Kog (2017c); 31 = Hindawi and Awad (2007); 32 = Bekr (2015); 33 = Kog (2017e); 34 = Koushki et al. (2005); 35 = Al-Tabtabai (2002); 36 = Tumi et al. (2009);
37 = Alnuaimi and Mohsin (2013); 38 = Ruqaishi and Bashir (2013); 39 = Emam et al. (2015); 40 = Al-Jurf and Beheiry (2010); 41 = Kog (2018b); 42 = Arditi et al. (1985);
43 = Kazaz et al. (2012); 44 = Cülfik et al. (2014); 45 = Gündüz et al. (2013); 46 = Mahamid et al. (2012) and Mahamid (2013); 47 = Albatsh (2015)
72 Yue Choong Kog

Table 5. Top construction delay factors for the Middle East countries

Construction delay factor Rank No. Proportion


Financing by contractor 1 11 78.6%
Finance and payments of completed work by owner 2 10 71.4%
Variation orders/changes of scope by owner during construction 2 10 71.4%
Late delivery/shortage of construction materials or fuel 2 10 71.4%
Ineffective planning and scheduling 5 9 64.3%
Poor site management and supervision by contractor 6 8 57.1%
Inadequate contractor experience/incompetence contractor 7 7 50%
Slow decisions from owner 8 6 42.9%
Owner’s lack of experience/incompetent project team 9 5 35.7%
Subcontractor problems/mechanical and electrical works 9 5 35.7%
Shortage of labor 9 5 35.7%

Table 6. Major delay factors from literature on South Asia

C Bangladesh India Nepal Pakistan Sri Lanka


R 48 49 50 51 33 33
M A F S+I P F F
N 31 - 10+5 22 - -
T C A B C A A
2 X X X X X
3 X X X
5 X X
7 X
8 X
9 X
11 X X
12 X X
13 X X X X
15 X X X X X
16 X
17 X X X X X
18 X X X
20 X X
21 X
22 X
23 X
25 X X X X
31 X
33 X X
34 X
35 X X
42 X X
43 X X X X
References: 33 = Kog (2017e); 48 = Ahsan and Gunawan (2010); 49 = Kog (2018c); 50 = Koirala (2014); 51 = Manavazhi
and Adhikari (2002).
A Global Survey of Top Construction Delay Factors 73

Table 6 summarizes the TDFs for each of the countries in South Asia. The TDFs for
South Asia ascertained by this study are summarized in Table 7. The seven TDFs, namely
‘finance and payments of completed work by owner’, ‘late delivery/shortage of construction
materials or fuel’, ‘poor site management and supervision’, ‘equipment (or operator)
availability and failure’, ‘variation orders/changes of scope by owner during construction’,
‘ineffective planning and scheduling by contractor’, and ‘government regulation and permit
approval’ are identified by more than half of the five countries studied. The top delay factors
unique to some countries are as follows. ‘Communication problems/lack of adequate project
coordination’ among the project participants, ‘poor site co-ordination’ and ‘unqualified
workforce/low skilled labor’ are unique to India only. ‘Excessive bureaucracy in project-
owner organization’ and ‘late release of site/land acquisition problems/delay or non-payment
of compensation to the communities’ and ‘staff recruitment delay’ by consultants are unique
to Bangladesh only. Contractor’s ‘lack of technical professionals/incompetent project team’ is
unique to Nepal only. ‘Shortage of labor’ is unique to Sri Lanka only.

Table 7. Top construction delay factors for South Asian countries

Construction delay factor Rank No. Proportion


Finance and payments of completed work by owner 1 5 100%
Late delivery/shortage of construction materials or fuel 1 5 100%
Poor site management and supervision by contractor 3 4 80%
Equipment (or operator) availability and failure 3 4 80%
Variation orders/changes of scope by owner during construction 5 3 60%
Ineffective planning and scheduling by contractor 5 3 60%
Government regulation and permit approval 5 3 60%
Slow decisions from owner 8 2 40%
Inadequate contractor experience/incompetence contractor 8 2 40%
Financing by contractor 8 2 40%
Rework due to mistakes in construction/construction defects 8 2 40%
Wrong choice of consultants/poor contract management by consultants/inappropriate
8 2 40%
design by consultants requiring redesign/incompetent or inexperience staff
Inclement weather 8 2 40%
Natural disaster/acts of God 8 2 40%

Table 8 summarizes the TDFs for each of the countries/administrations in East Asia. The
TDFs for East Asia found by this review are summarized in Table 9. All the TDFs found by
this review are identified by more than half of the four countries/administrations studied.
‘Finance and payments of completed work by owner’ and ‘staff recruitment delay’ by
consultants are unique to China. This is because the TDFs of China are identified based
on infrastructural projects of the Asian Development Bank. ‘Inadequate contractor
experience/incompetence contractor’, ‘lack of technical professionals/incompetent project
team’, ‘ineffective planning and scheduling’ by the contractor, ‘poor site management
and supervision’, ‘late issuance of instructions, information or drawings/incomplete
drawings/inadequate information/delay in revising design documents and approving works or
74 Yue Choong Kog

materials/delays in design work’ and ‘wrong choice of consultants/poor contract management


by consultants/inappropriate design by consultants requiring redesign/incompetent or
inexperience staff’ are unique to Hong Kong only.

Table 8. Major delay factors from literature on East Asia

C China Hong Kong Korea Taiwan


R 48 52 53 54 R 48
M P F P S M P
N 30 - 3 450 N 30
T C A C B T C
2 X 2 X
3 X X X X 3 X
5 X X 5 X
6 6
7 X X 7
8 X 8 X
9 X X X 9 X
10 X 10
11 X 11
12 X 12
13 X 13
15 X 15
17 X 17 X
18 X 18
19 X X X 19
20 X 20
23 X 23
26 X X X 26
29 X 29
31 X 31
33 X 33
34 X 34 X
36 36
40 X X 40
41 41
43 X X X 43 X
References: 48 = Ahsan and Gunawan (2010); 52 = Kog (2018d); 53 = Han et al. (2009); 54 = Acharya et al. (2006); 55 =
Yang and Liao (2008); 56 = Yang et al. (2010).

Table 9. Top construction delay factors for East Asian countries/administrations

Construction delay factor Rank No. Proportion


Variation orders/changes of scope by owner during construction 1 4 100%
Inadequate site investigation/unforeseen subsurface conditions 2 3 75%
Government regulation and permit approval 2 3 75%
Slow decisions from owner 4 2 50%
Owner’s lack of experience/incompetent project team 4 2 50%
Excessive bureaucracy in project-owner organization 4 2 50%
Late release of site/land acquisition problems 4 2 50%
A Global Survey of Top Construction Delay Factors 75

Table 10. Major delay factors from literature on Southeast Asia

C Brunei Cambodia Indonesia Malaysia Singapore Thailand Vietnam


R 57 58 59 60 60 61 62 63 60 60
M S S S F F S S P F F
N 75 153 48 - - 66 36 - - -
T B C A A A B B B A A
1 X X X
2 X X X X X X X
3 X X X X X X X X
5 X X
7 X
9 X X X
10 X
11 X X X X X
12 X
13 X X X X X X
14 X X
15 X X X X X
16 X X
17 X X X X X X X X
18 X X X X
19 X X X
20 X X
22 X X X X X X
23 X X
25 X X X
28 X
29 X
31 X X X X
33 X
35 X X X X
42 X
43 X
References: 57 = Salleh (2009); 58 = Santoso and Soeng (2016); 59 = Durdyev et al. (2017); 60 = Kog (2019b);
61=Ayudhya (2011); 62 = Hwang et al. (2013); 63 = Kog (2017d).

Table 10 summarizes the TDFs reported for each of the countries in Southeast Asia. The
TDFs for Southeast Asian countries identified by this study are summarized in Table 11. The
seven TDFs, namely, ‘finance and payments of completed work by owner’, ‘variation
orders/changes of scope by owner during construction’, ‘ineffective planning and scheduling
by contractor’, ‘late delivery/shortage of construction materials’, ‘inadequate contractor
experience/incompetence contractor’, ‘poor site management and supervision’, and ‘shortage
of labor’ are identified by more than half of the seven countries/administrations studied.
The TDFs unique to some countries are discussed as follows. ‘Owner’s lack of
experience/incompetent project team’, ‘poor contract management by consultants/
substandard contract’, and ‘government regulations and permit approval’ are unique to
Thailand only. ‘Unrealistic/optimistic deadline set by client’ and ‘natural disaster/
acts of God’, are unique to Cambodia only. ‘Mistakes and discrepancies in design
documents by consultants’ is unique to Brunei only. ‘Wrong choice of consultants/poor
contract management by consultants/inappropriate design by consultants requiring
redesign/incompetent or inexperience staff’ is unique to Malaysia only. ‘Inaccurate estimating
76 Yue Choong Kog

of construction materials quantities/price’ is unique to Vietnam only. ‘Lack of technical


professionals/incompetent project team’ by the contractor is unique to Singapore only even
though this TDF was pinpointed by only one study of Singapore and not the other two. ‘Slow
decisions from owner’ is unique to Brunei and Thailand only. ‘Poor site coordination’ by the
contractor is unique to Singapore and Thailand only. ‘Financing by contractor’ is unique to
Malaysia and Thailand only. ‘Rework due to mistakes in construction/construction defects’ is
unique to Indonesia and Malaysia only. ‘Unqualified workforce/low skilled labor’ is unique to
Cambodia and Indonesia only. ‘Equipment (or operator) availability and failure’ is unique to
Indonesia and Thailand only.

Table 11. Top construction delay factors for Southeast Asian countries

Construction delay factor Rank No. Proportion


Finance and payments of completed work by owner 1 7 100%
Variation orders/changes of scope by owner during construction 1 7 100%
Ineffective planning and scheduling by contractor 3 6 86%
Late delivery/shortage of construction materials or fuel 3 6 86%
Inadequate contractor experience/incompetence contractor 5 5 71%
Poor site management and supervision by contractor 5 5 71%
Shortage of labor 5 5 71%
Communication problems by all project participants 8 3 43%
Late release of site/land acquisition problems/delay or non-payment of compensation to
8 3 43%
the communities
Financing by contractor 8 3 43%
Subcontractor problems 8 3 43%
Late issuance of instructions, information or drawings/incomplete drawings/inadequate
8 3 43%
information/delay in revising and approving design documents/delays in design work
Inclement weather 8 3 43%

Table 12 summarizes the TDFs identified for Australia, New Zealand, Portugal, Norway,
Slovenia, UK, Chile, Canada, and US. The respective TDFs for these countries ascertained by
this study are summarized in Table 13. The eight TDFs, namely, ‘late issuance of instructions,
information or drawings/incomplete drawings/inadequate information/delay in revising and
approving design documents/delays in design work’, ‘variation orders/changes of scope by
owner during construction’, ‘slow decisions from owner’, ‘mistakes and discrepancies in
design documents by consultants’, ‘communication problems by all project participants’,
‘ineffective planning and scheduling by contractor’, ‘subcontractor problems/mechanical and
electrical works’, and ‘inadequate site investigation/unforeseen subsurface conditions’ are
identified by more than half of the nine countries/administrations studied. The TDFs that
are unique to some countries are discussed as follows. ‘Contractor selection methods
(negotiation, lowest bidder)’ is unique to New Zealand only. ‘Low productivity level of
labors’, ‘equipment (or operator) availability and failure’ and ‘natural disaster/acts of God’
are unique to Chile only. ‘Poor contract management by consultants/substandard contract’ is
unique to Slovenia only. Keen (2010) is the only study among the more than 200 studies on
construction delay factors that identified that the consultants in Canada ‘completed design
through shop drawings review’ as a TDF.
A Global Survey of Top Construction Delay Factors 77

Table 12. Major delay factors from literature on Australia, New Zealand,
Europe, and Americas

New
C Australia Canada Chile Norway Portugal Slovenia UK US
Zealand
R 64 65 66 67 68 69 70 71 72 73 74 75 74 74
M S P+S I P P S P S S S F S F F
N 32 33+33 ? 175 24 87 16 28 143 202 - 62 - -
T A B C B A O B A A A A A A A
1 X X X X X X X
2 X X X
3 X X X X X X X X X
4 X
5 X X X X X X
7 X X X
9 X X
10 X X X
11 X X X
12 X
13 X X X X X X X X
14 X
15 X X X X X
16 X X X
17 X X X X X
19 X X X X X
20 X X
21 X X
22 X X
23 X X X
25 X
26 X X X X X X
27 X
28 X
29 X X X X X X X
30 X X X
31 X X X X X X X X X X
32 X X
33 X X X X
35 X X X
42 X
43 X X X X
Reference: 64 = Wong and Vimonsatit (2002); 65 = Walker(1995); 66 = Orangi et al. (2011); 67 = Keen (2010); 68 =
Semple et al. (1994); 69 = Jergeas and Ruwanpura (2010) and Ruwanpura and Jergeas (2010); 70 = Alarcón et al.
(2008); 71 = Lessing et al. (2017); 72 = Zidane et al. (2015); 73 = Eik-Andresen et al. (2015); 74 = Kog (2018e); 75 =
Srdić and Šelih (2015).
78 Yue Choong Kog

The ten TDFs for 59 countries/administrations ascertained by this study are summarized
in Table 14. The four TDFs, namely, ‘finance and payments of completed work by
owner’, ‘variation orders/changes of scope by owner during construction’, ‘late
delivery/shortage of construction materials or fuel’, ‘ineffective planning and scheduling’, and
‘financing by contractor’ are identified by more than half of the 59 countries/administrations
studied.
Table 13. Top construction delay factors for Oceania
and European and American countries

Construction delay factor Rank No. Proportion

Late issuance of instructions, information or drawings/incomplete drawings/inadequate


1 8 88.9%
information/delay in revising and approving design documents/delays in design work

Variation orders/changes of scope by owner during construction 2 7 77.8%


Slow decisions from owner 3 6 66.7%
Mistakes and discrepancies in design documents by consultants 3 6 66.7%
Communication problems by all project participants 5 5 55.6%
Ineffective planning and scheduling by contractor 5 5 55.6%
Subcontractor problems/mechanical and electrical works 5 5 55.6%
Inadequate site investigation/unforeseen subsurface conditions 5 5 55.6%
Late delivery/shortage of construction materials or fuel 9 4 44.4%

Wrong choice of consultants/poor contract management by consultants/inappropriate


9 4 44.4%
design by consultants requiring redesign/incompetent or inexperience staff

Government regulations and permit approval 9 4 44.4%

Table 14. Top 10 construction delay factors of 59 countries/administrations

Countries/Administrations
Construction delay factor Rank
No. Proportion

Finance and payments of completed work by owner 1 43 72.9%


Variation orders/changes of scope by owner during construction 2 37 62.7%
Late delivery/shortage of construction materials or fuel 2 37 62.7%
Ineffective planning and scheduling 4 32 54.2%
Financing by contractor 5 29 49.2%
Poor site management and supervision by contractor 6 27 45.8%
Inadequate contractor experience/incompetence contractor 7 25 42.4%
Equipment (or operator) availability and failure 8 23 39%
Slow decisions by owner 8 23 39%
Late issuance of instructions, information or drawings/incomplete drawings/
inadequate information/delay in revising and approving design documents/ 10 22 37.3%
delays in design work
A Global Survey of Top Construction Delay Factors 79

Table 15. Top construction delay factors for different regions

South Oceania,
South East Middle
Construction delay factor East Europe and Africa All
Asia Asia East
Asia Americas
Finance and payments of completed
1 1 10 2 12 1 1
work by owner
Variation orders/changes of scope
1 5 1 2 2 4 2
by owner during construction
Poor site management and supervision
5 3 10 6 12 8 6
by contractor
Late delivery/shortage of
3 1 4 2 9 2 2
construction materials or fuel
Financing by contractor 8 8 10 1 30 2 5
Mistakes and discrepancies in
14 25 10 22 3 21 17
design documents by consultants
Communication problems by
8 13 27 22 5 21 14
all project participants
Owner’s lack of experience/
21 13 4 9 18 28 17
incompetent project team
Excessive bureaucracy in project-owner
29 13 4 37 30 40 37
organization
Inadequate contractor experience/
5 8 10 7 12 8 7
incompetence contractor
Ineffective planning and scheduling
3 5 10 5 5 6 4
by contractor
Shortage of labor 5 13 27 9 18 15 12
Equipment (or operator) availability
14 3 27 14 24 4 8
and failure
Late issuance of instructions, information or
drawings/incomplete drawings/ inadequate
8 13 10 22 1 7 10
information/delay in revising and approving
design documents/delays in design work
Wrong choice of consultants/poor contract
management by consultants/inappropriate
21 8 10 14 9 28 17
design by consultants requiring
redesign/incompetent or inexperience staff
Inclement weather 8 8 27 22 12 13 13
Slow decisions from owner 14 8 4 8 3 11 8
Subcontractor problems 8 25 4 9 5 8 11
Inadequate site investigation/unforeseen
21 25 2 31 5 28 23
subsurface conditions
Government regulation and permit approval 21 5 2 22 9 15 16
Late release of site/land acquisition
8 13 4 14 18 11 13
problems
Natural disaster/acts of God 21 8 27 37 24 36 25

COMPARISON OF THE TOP DELAY FACTORS


FOR DIFFERENT REGIONS

Table 15 summarizes the TDFs found by this review for Africa, the Middle East, South
Asia, East Asia, Southeast Asia, and the grouping of Oceania, Europe and Americas
representing the relatively more developed countries. Delay factors ‘variation orders/changes
of scope by owner during construction’ and ‘late delivery/shortage of construction materials
80 Yue Choong Kog

or fuel’ are among the TDFs for all regions. The delay factor ‘ineffective planning and
scheduling’ by contractor is a TDF for all regions except East Asia. There are some delay
factors that are the TDF unique to one particular region only. For example, ‘natural
disaster/acts of God’ is unique to South Asia and ‘mistakes and discrepancies in design
documents by consultants’ is unique to the grouping of Oceania, Europe and Americas.
Many suggestions were made in Kog (2017a to 2017e, 2018a to 2018e, 2019a to 2019b)
on measures that could be taken to address various delay factors to improve schedule
performance. If such suggestions can be implemented rigorously in a sustained manner, the
schedule performance of construction projects can definitely be improved and construction
delay can be reduced substantially. The adverse impact of variation orders to the construction
schedule performance is well known. Why are architects in building projects and civil
engineers in civil engineering projects persisted in issuing variation orders after the
commencement of construction? Unfortunately, there is no study reported on the underlying
reasons on the issuance of variation orders. The present study highlights the importance that
future research should be undertaken so that appropriate actions are taken to curtail the
issuance of variation orders after the commencement of construction. Similarly, there is no
study reported on the underlying reasons for the late delivery/shortage of construction
materials or fuel. Shortage of fuel is confined to the region of Africa. According to Table 15,
‘late delivery/shortage of construction materials’ is a TDF for the grouping of Oceania,
Europe and Americas representing the relatively more developed countries. How much of
‘late delivery/shortage of construction materials’ can be attributed to the local logistics system
and other causes? Future research should be undertaken so that suitable policies and actions
are taken to tackle this important delay factor.

CONCLUSION
A review of more than 200 studies for 59 countries/administrations shows that the TDFs
are ‘finance and payments of completed work by owner’, ‘variation orders/changes of
scope by owner during construction’, ‘late delivery/shortage of construction materials or
fuel’, ‘ineffective planning and scheduling’, ‘financing by contractor’, ‘poor site management
and supervision’, ‘inadequate contractor experience/incompetence contractor’, ‘equipment
(or operator) availability and failure’, ‘late issuance of instructions, information or
drawings/incomplete drawings/ inadequate information/delay in revising and approving
design documents/delays in design work’, and ‘slow decisions from owner’.
Comparison of the TDFs for the different regions shows that ‘variation orders/changes of
scope by owner during construction’ and ‘late delivery/shortage of construction materials or
fuel’ are among the TDFs for all regions. On the other hand, ‘natural disaster/acts of God’ as
a top delay factor is unique to South Asia only, and ‘mistakes and discrepancies in design
documents by consultants’ is unique to the grouping of Oceania, Europe and Americas only.
The findings of TDFs for each of the regions are useful because they highlight the main
challenges faced by each region to improve their schedule performances. The practical
implications of the present study are that appropriate measures must be taken to address the
TDFs of ‘variation orders/changes of scope by owner during construction’ and ‘late
delivery/shortage of construction materials or fuel’ and other TDFs unique to each region to
improve the schedule performance of construction projects.
A Global Survey of Top Construction Delay Factors 81

Because of the high similarity level of construction practices within each region, the bulk
of the TDFs identified for each of the regions are most likely to be the TDFs for countries
within the regions where the TDFs have not been identified. The present study highlights the
importance that future research should be undertaken so that appropriate actions are taken to
curtail the issuance of variation orders after the commencement of construction and the late
delivery/shortage of construction materials. As a practitioner for more than forty years, it is
clear that the frequent issuances of variation order are often related to the level of
professionalism of the project participants and the fast track nature of many construction
projects particularly the civil engineering projects. For fast track projects, some stakeholders
do not have sufficient time to finalize their requirements. It is also not possible to obtain all
the necessary approvals from the relevant authorities before calling tender. Variations may be
required to comply with the authorities’ requirements and the stakeholders’ finalized
requirements during construction. The number of variation orders will definitely be reduced if
appropriate measures, such as allowing more time for project participants to finalize the
design and obtaining authorities’ approvals before calling the construction tender, are
implemented.

REFERENCES
Acharya, N. K., Im, H. M. and Lee, Y. D. (2006). Investigating delay factors in construction
industry: A Korean perspective. Korean Journal of Construction Engineering and
Management, Korea Institute of Construction Engineering and Management, Seoul,
Korea, 7(5), 177-190.
Adeyemi, A.Y. and Masalila, K. (2016). Delay factors and time-cost performance of
construction projects in Gaborone City Council, Botswana. Journal for the Advancement
of Performance Information & Value, 8(1), 4-1 to 4-18.
Adugna, N. T. (2015). A study of causes of delay and cost overrun in office construction
projects in the eThekwini Municipal Area, South Africa, Master of Technology
(Construction Management) thesis, Durban University of Technology, Durban, South
Africa, June, 136p.
Ahsan, K. and Gunawan, I. (2010). Analysis of cost and schedule performance of
international development projects. International Journal of Project Management,
Elsevier, Oxford, U.K., 28(1), 68–78.
Akoa B. B. (2011). Cost overruns and time delays in highway and bridge projects in
developing countries experiences from Cameroon, Master of Science thesis, Michigan
State University, Michigan, U.S.A., 241p.
Akogbe, R. K. T. M., Feng, X. and Zhou, J. (2013). Importance and ranking evaluation of
delay factors for development construction projects in Benin. KSCE Journal of Civil
Engineering, Springer and Korean Society of Civil Engineers, Seoul, South Korea, Vol.
17, 1213-1222.
Alarcón, L. F., Diethelm, S., Rojo, O. and Calderon, R. (2008). Assessing the impacts
of implementing lean construction. Revista ingeniería de construcción, Pontificia
Universidad Católica de Chile, Departamento de Ingeniería y Gestión de la Construcción,
Santiago, Chile 23(1), 26-33.
82 Yue Choong Kog

Albatsh, N. J. (2015). Assessment of delay causes of construction projects in Palestine.


Master of Engineering Management thesis, An-Najah National University, Nablus, West
Bank of Palestine, 255p.
Alinaitwe, H., Apolot, R. and Tindiwensi, D. (2013). Investigation into the causes of delays
and cost overruns in Uganda's public sector construction projects. Journal of
Construction in Developing Countries, Penerbit Universiti Sains Malaysia, Pulau Pinang,
Malaysia, 18(2), 33–47.
Al-Jurf, N. and Beheiry, S. (2010). Qatar residential construction projects. Procs. Second
International Conference on Engineering Systems Management and Its Applications
(ICESMA 2010), 30th March to 1st Apr, Sharjah, United Arab Emirates, IEEE,
Piscataway, N.J., 1-6.
Al-Najjar, J. (2008). Factors influencing time and cost overruns on construction projects in
the Gaza Strip, Master degree thesis, Islamic University, Gaza.
Alnuaimi, A. S. and Mohsin, M., (2013). Causes of delay in completion of construction
projects in Oman. Proceedings International Conference on Innovations in Engineering
and Technology, International Institute of Engineers, December 25-26, Bangkok,
Thailand, 267-270.
AI-Tabtabai, H. M. (2002). Causes for delays in construction projects in Kuwait. Engineering
Journal of the University of Qatar, Vol. 15, 19-37.
Amandin, M. M. and Kule, J. W. (2016). Project delays on cost overrun risks: a study of
Gasabo district construction projects Kigali, Rwanda. ABC Journal of Advanced
Research, i-Proclaim, Puchong, Malaysia, 5(1), 21-34.
Apolot, R., Alinaitwe, H. and Tindiwensi, D. (2011). An investigation into the causes of
delay and cost overrun in Uganda's public sector construction projects. Procs. Second
International Conference on Advances in Engineering and Technology, 305-311.
Arditi, D., Akan, G. T., and Gurdamar, S. (1985). Reasons for delays in public projects in
Turkey. Construction Management and Economics, Taylor Francis, U.K., London, 3(2),
171-181.
Ayudhya, B. I. N. (2011). Evaluation of common delay causes of construction projects in
Singapore. Journal of Civil Engineering and Architecture, David Publishing, New York,
N.Y., U.S.A., 5(11), 1027-1034.
Bagaya, O. and Song, J. B. (2016), Empirical Study of Factors Influencing Schedule Delays
of Public Construction Projects in Burkina Faso, Journal of Management in Engineering,
32(5), American Society of Civil Engineers, https://doi.org/10.1061/(ASCE)ME.1943-
5479.0000443, 05016014-1 to 05016014-10
Baloyi, L., and Bekker, M. (2011). Causes of construction cost and time overruns: The 2010
FIFA World Cup stadia in South Africa. Acta Structilia, University of the Free State,
Bloemfontein, South Africa, 18(1), 51-67.
Bekr, G. A., (2015). Causes of delay in public construction projects in Iraq. Jordan Journal of
Civil Engineering, Jordan University of Science and Technology, Irbid, Jordan 9(2), 149-
162.
Challal, A. and Tkiouat, M. (2012a). Identification of the causes of deadline slippage in
construction projects: state of the art and application. Journal of Service Science and
Management, Scientific Research Publishing, Delaware, United States, 5(2), 151-159,
http//doi: 10.4236/jssm.2012.52019.
A Global Survey of Top Construction Delay Factors 83

Challal, A. and Tkiouat, M. (2012b). Qualitative approach risk period in construction


projects. Journal of Financial Risk Management, 1(3), 42-51, http://dx.doi.org/10.4236/
jfrm.2012.130 08.
Chua, D. K. H., Kog, Y. C. and Loh, P. K. (1999). Critical success factors for different
project objectives. Journal of Construction Engineering and Management, ASCE,
125(3), 142-150.
Cülfik, M., Sarikaya, Ö. and Altun, H. (2014). Causes of delays in construction projects in
Turkey. Procs. 11th International congress on advances in civil engineering, organized
by Istanbul Technical University, 21st to 25th Oct, Istanbul, Turkey.
Durdyev, S., Omarov, M. and Ismail, S., (2017). Causes of delay in residential construction
projects in Cambodia. Cogent Engineering, Taylor and Francis, U.K., 4(1), 1291117.
Eik-Andresena, P., Haji-Kazemib, A. L. S., Johansenc, A. and Andersenb, B. (2015).
Remedies for managing bottlenecks and time-thieves in Norwegian construction
projects–public vs private sector. Procs. 29th International Project Management
Association (IPMA) World Congress, organized by the Asociatión Panameńa de
Gestion de Proyectos (APGP), Panama City, Panama, 28th-30th September.
Emam, H., Farrell, P., and Abdelaal, M. (2015). Causes of delay on infrastructure projects in
Qatar. Procs 31st Annual ARCOM Conference, Raidén, A. B. and Aboagye-Nimo, E.
(eds), 7-9 September 2015, Lincoln, U.K., Association of Researchers in Construction
Management, 773-782.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. M. (2009). delays and cost overruns in the
construction projects in the Gaza strip. Journal of Financial Management of Property
and Construction, Emerald Publishing Ltd, Bingley, U.K., 14(2), 126-151.
Enshassi, A., Kumaraswamy, M. and Jomah, A. N. (2010a). Significant factors causing time
and cost overruns in construction projects in the Gaza strip: Contractors' perspective.
International Journal of Construction Management, Taylor Francis and the Chinese
Research Institute of Construction Management, Hong Kong, 10(1), 35-60.
Enshassi, A., Kumaraswamy, M. and Al-Najjar, J. (2010b). Factors influencing time and cost
overruns in construction projects in the Gaza strip: Consultant's view. International
Journal of Construction Project Management, Nova Science Publishers, Inc., United
States, 2(1), 73-89.
Gündüz, M., Nielsen, Y. and Özdemir, M. (2013). Quantification of delay factors using the
relative importance index method for construction projects in Turkey. Journal of
Management in Engineering, ASCE, 29(2), 133-139.
Hasan, R., Suliman, S. M. and Malki, Y. (2014). An investigation into the delays in road
projects in Bahrain. International Journal of Research in Engineering and Science, 2(2),
38-47.
Hindawi, G. and Awad, H. (2007). Causes of delay in Iraq construction projects. Master
degree thesis, University of Baghdad, Baghdad.
Han, S. H., Yun, S., Kim, H., Kwak, Y. H., Park, H. K. and Lee, S. H. (2009). Analyzing
schedule delay of mega project: Lessons learned from Korea train express. IEEE
Transactions on Engineering Management, The Institute of Electrical and Electronics
Engineers, New York, U.S.A., 56(2), 243-256.
Hwang, B. G., Zhao, X. and Ng, S. Y. (2013). Identifying the critical factors affecting
schedule performance of public housing projects. Habitat International, Elsevier, Oxford,
U.K., Vol. 38, April, 214-221, https://doi.org/10.1016/j.habitatint.2012.06.008.
84 Yue Choong Kog

Jergeas, G. F. and Ruwanpura, J. (2010). Why cost and schedule overruns on mega oil sands
projects?. Practice Periodical on Structural Design and Construction, ASCE, 15(1), 40-
43, https://doi.org/10.1061/(ASCE)SC.1943-5576.0000024.
Joseph, M. (2004). Delays in completion of building construction projects in the Botswana
public sector by medium to large category C, D and E contractors, Master of Science
(Project Management) thesis, University of Pretoria, Hatfield, South Africa.
Kadry, M., Osman, H. and Georgy, M. (2016). Causes of construction delays in countries
with high geopolitical risks. Journal of Construction Engineering and Management,
ASCE, 04016095-1 to 04016095-11, https://doi.org/10.1061/(ASCE)CO.1943-7862.000
1222.
Kaliba, C., Muya, M. and Mumba, K., (2009). Cost escalation and schedule delays in road
construction projects in Zambia. International Journal of Project Management, Elsevier,
U.K., Oxford, 27(5), 522-531.
Kamanga, M. J. and Steyn, W. J. (2013). Causes of delay in road construction projects in
Malawi. Journal of the South African Institution of Civil Engineering, Johannesburg,
South Africa, 55(3), 79-85.
Kazaz, A., Ulubeyli, S. and Avcioglu, N. (2012). Causes of delays in construction projects in
Turkey. Journal of Civil Engineering and Management, Taylor Francis and Vilnius
Gediminas Technical University, 18(3), 426–35.
Keen, B. (2010). The pitfalls of incomplete contract documents. British Columbia
Construction Association, 29(1), March, Victoria, British Columbia, Canada, 6p.
Kikwasi, J. G. (2012). Causes and effects of delays and disruptions in construction projects in
Tanzania. Australasian Journal of Construction Economics and Building Conference
Series, 1(2), 52-59.
Kog, Y. C., (2017a). Major Delay factors for Construction Projects in Ghana. Journal for the
Advancement of Performance Innovation and Value, 9(1), CIB Performance Based
Studies Research Group, Arizona State University, 96-105.
Kog, Y. C. (2017b). Major delay factors for construction projects in Nigeria. International
Journal of Architecture, Engineering and Construction, 6(2), International Association
for Sustainable Development and Management (IASDM), Toronto, Ontario, Canada, 46-
54.
Kog, Y. C. (2017c). Major delay factors for construction projects in Iran. International
Journal of Construction Project Management, 9(2), Nova Science Publishers Inc., New
York, N.Y., U.S.A., 86-97.
Kog, Y. C. (2017d). Project management and delay factors of public housing construction.
Practice Periodical on Structural Design and Construction, 23(1), ASCE, 04017028-1 to
04017028-8, https://doi.org/10.1061/(ASCE)SC.1943-5576.0000350.
Kog, Y. C. (2017e). Major construction delay factors of Jordan, UAE, Pakistan, Sri Lanka.
International Journal of Architecture, Engineering and Construction, 6(4), International
Association for Sustainable Development and Management (IASDM), Toronto, Ontario,
Canada, 13-25, http://dx.doi.org/10.7492/IJAEC.2017.020
Kog, Y. C. (2018a). Top construction delay factors of Kenya. Journal for the Advancement of
Performance Innovation and Value, 10(4), CIB Performance Based Studies Research
Group, Arizona State University, 120-129.
Kog, Y. C. (2018b). Major construction delay factors of Saudi Arabia. International Journal
of Architecture, Engineering and Construction, 7(2), International Association for
A Global Survey of Top Construction Delay Factors 85

Sustainable Development and Management (IASDM), Toronto, Ontario, Canada, 27-32,


http:// dx.doi.org/10.7492/IJAEC.2018.010
Kog, Y. C. (2018c). Major construction delay factors of India, International Journal of
Construction Project Management, 10(2), Nova Science Publishers Inc., New York,
N.Y., U.S.A., 111-122.
Kog, Y. C. (2018d). Major construction delay factors of Hong Kong, International Journal of
Architecture, Engineering and Construction, 7(3), International Association for
Sustainable Development and Management (IASDM), Toronto, Ontario, Canada, 35-40.
Kog, Y. C. (2018e). “Major construction delay factors of Portugal, UK and US”, Practice
Periodical on Structural Design and Construction, ASCE, 23(4), 04018024-1 to
04018024-8, https://doi.org/10.1061/(ASCE)SC.1943-5576.0000389
Kog, Y. C. (2019a). A structured approach for questionnaire survey of construction delay.
Journal for the Advancement of Performance Innovation and Value, 11(1), CIB
Performance Based Studies Research Group, Arizona State University, 21-33.
Kog, Y. C. (2019b). Major delay factors for construction projects in Indonesia, Malaysia,
Thailand and Vietnam, Practice Periodical on Structural Design and Construction,
American Society of Civil Engineers, 24(3), 04019013-1 to 04019013-12, https://
doi.org/10.1061/(ASCE)SC.1943-5576.0000434.
Koirala, M. K. (2014). Risks in Housing and Real Estate Construction Project. Journal of the
Institute of Engineering, 10(1), Nepal, 34-44, http://dx.doi.org/10.3126/jie.v10i1.10876
Koushki, P.A., Al-Rashid, K., and Kartam, N. (2005). Delays and cost increases in the
construction of private residential projects in Kuwait. Construction Management and
Economics, Taylor Francis, London, U.K., 23(3), 285-294.
Lessing, B., Thurnell, D. and Durdyev, S. (2017). Main factors causing delays in large
construction projects: evidence from New Zealand. Journal of Management, Economics,
and Industrial Organization, Torain Publishing Limited, Cambodia, 1(2), 63-82.
Mahamid, I., Bruland, A., and Dmaidi N. (2012), Causes of Delay in Road Construction
Projects”, Journal of Management in Engineering, ASCE, http//doi:10.1061/(ASCE)
ME.1943-5479.0000096, 300-310.
Mahamid, I. (2013). Contributors to schedule delays in public construction projects in Saudi
Arabia: owners' perspective. Journal of Construction Project Management and
Innovation, University of Johannesburg Department of Construction and Quantity
Surveying, South Africa, 3(2), 608-619.
Manavazhi, M. R. and Adhikari, D. K. (2002). Material and equipment procurement delays in
highway projects in Nepal. International Journal of Project Management, Elsevier,
Oxford, U.K., 20(8), 627-632.
Mezher, T.M. and Tawil, W. (1998). Causes of delays in the construction industry in
Lebanon. Engineering Construction and Architectural Management, Emerald Publishing
Ltd, Bingley, U.K., 5(3), 252-260.
Muhwezi, L., Acai, J., and Otim, G. (2014). An assessment of the factors causing delays on
building construction projects in Uganda. International Journal of Construction
Engineering and Management, Scientific and Academic Publishing, Rosemead,
California, USA, 3(1), 13-23.
Mukuka, M. J. (2014). Cost and schedule overruns on construction projects in South Africa,
Master of Technology (Construction Management) thesis, University of Johannesburg,
South Africa, December, 130p.
86 Yue Choong Kog

Muya, M., Kaliba, C., Sichombo, B. and Shakantu, W. (2013). Cost escalation, schedule
overruns and quality shortfalls on construction projects: The case of Zambia.
International Journal of Construction Management, Taylor Francis and the Chinese
Research Institute of Construction Management, Hong Kong, 13(1), 53-68.
Niazai, G. A. and Gidado, K. (2012). Causes of project delay in the construction industry in
Afghanistan. Proc. International Conference on Engineering, Project and Production
Management (EPPM) Conference, organized by Association of Engineering, Project, and
Production Management and University of Brighton, 10-11 September, Brighton, U.K.
Olawale, Y. and Sun M. (2010). Cost and time control of construction projects: Inhibiting
factors and mitigating measures in practice. Construction Management and Economics,
28 (5), 509 – 526
Orangi, A., Palaneeswaran, E. and Wilson, J. (2011). Exploring delays in Victoria-based
Australian pipeline projects. Procedia Engineering, 14, 874-881.
Ruqaishi, M. and Bashir, H. A. (2013). Causes of delay in construction projects in the oil and
gas industry in the gulf cooperation council countries: a case study. Journal of
Management in Engineering, ASCE, 31(3), 05014017-1 to 05014017-8.
Ruwanpura, J. and Jergeas, G. (2010). Why cost and schedule overruns on mega oils sands
projects?. Cost Engineering, AACE International, Morgantown, West Virginia, U.S.A.,
16(1), 24-27.
Salleh, R. (2009). Critical success factors of project management for Brunei construction
projects: improving project performance. Ph.D. thesis, Queensland University of
Technology, 309p.
Santoso, D.S. and Soeng, S. (2016). Analyzing delays of road construction projects in
Cambodia: causes and effects. Journal of Management in Engineering, ASCE, 32(6),
05016020-1 to05016020-11, https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.
Semple, C., Hartman, F. T., and Jergeas, G. (1994). Construction claims and disputes: Causes
and cost/time overruns, Journal of Construction Engineering and Management, ASCE,
120(4), 785-795, https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(785).
Shebob, A., Dawood, N., Shah, R. K. and Xu, Q. (2012). Comparative study of delay factors
in Libyan and the UK construction industry. Engineering, Construction and Architectural
Management, Emerald Publishing, Bingley, U.K., 19 (6), 688 – 712.
Shiri, T. (2015). An investigation of the causes and effects of construction delays on
Zimbabwean construction projects. Bachelor of Quantity Surveying (Honours) Degree
Thesis, Department of Quantity Surveying, Faculty of the Built Environment, National
University of Science and Technology, Bulawayo, Zimbabwe, 68p.
Srdić, A. and Šelih, J. (2015). Delays in construction projects: Causes and mitigation.”,
Organization, Technology and Management in Construction - an International Journal,
7(3), University of Zagreb, Faculty of Civil Engineering, Croatia, 1383-1389.
Tumi, S. A. H., Omran, A., and Pakir, A. H. K. (2009). Causes of delay in construction
industry in Libya. Proc. Int. Conf. Administration and Business, Univ. Bucharest,
Romania, 14-15th November, 265-272.
Walker, D. H. T. (1995). An investigation into construction time performance. Construction
Management and Economics, Taylor Francis, London, U.K., 13(3), 263-274.
Woldeyohannes, B., Fekadu, A. and Zeray, A. (2020). Investigation of contributing factors
for smart parking development projects Delay: The Case of Addis Ababa, Ethiopia.
A Global Survey of Top Construction Delay Factors 87

International Journal of African and Asian Studies, Academic Hosting & Event
Management Solutions, 67, 9-22.
Wong, K. and Vimonsatit, V. (2012). A study of the factors affecting construction time in
Western Australia. Scientific Research and Essays, Ebène, Mauritius, 7(40), 3390-3398.
Yang, J. B. and Liao, P. Y. (2008). Analysis of delay causes for pipeline projects in sewage
system: Taiwan cases. Proc. of the ASCE International Pipelines Conference, Pipelines
2008: Pipeline Asset Management: Maximizing Performance of our Pipeline
Infrastructure, Gokhale, S. and Rahman, S. (eds.), Pipeline Division of the ASCE,
Atlanta, Georgia, July 22nd-27th, 1-10.
Yang, J. B., Yang, C. C. and Kao, C. K. (2010). Evaluating schedule delay causes for private
participating public construction works under the Build-Operate-Transfer model.
International Journal of Project Management, Elsevier, Oxford, U.K., 28(6), 569-579.
Zidane, Y.J., Johansen, A., Andersen, B. and Hoseini, E. (2015). Time-thieves and
bottlenecks in the Norwegian construction projects. Procedia Economics and Finance,
Elservier, Oxford, U.K., 21, 486-493.
Reproduced with permission of copyright owner. Further reproduction
prohibited without permission.

You might also like