The document is a checklist for preparing to install a water pump. It lists 6 main tasks: 1) installing chemical anchors, 2) installing the pump skid, 3) installing the pump, 4) installing the motor, 5) aligning the skid, and 6) applying epoxy grout. For each task, it identifies required materials, tools, equipment, and documents to complete the job and notes the status or location of each item. The overall goal is to properly secure and install all pump components.
The document is a checklist for preparing to install a water pump. It lists 6 main tasks: 1) installing chemical anchors, 2) installing the pump skid, 3) installing the pump, 4) installing the motor, 5) aligning the skid, and 6) applying epoxy grout. For each task, it identifies required materials, tools, equipment, and documents to complete the job and notes the status or location of each item. The overall goal is to properly secure and install all pump components.
The document is a checklist for preparing to install a water pump. It lists 6 main tasks: 1) installing chemical anchors, 2) installing the pump skid, 3) installing the pump, 4) installing the motor, 5) aligning the skid, and 6) applying epoxy grout. For each task, it identifies required materials, tools, equipment, and documents to complete the job and notes the status or location of each item. The overall goal is to properly secure and install all pump components.
- Material Chemical Anchor Bolt MRO-029 Plastik Hitam (antisipasi cuaca) request - Tools Bor Concrete MRO-050 Mata bor 28mm (Nacy) request Kabel Extantion (Roll) 50m KM4 - Equipment Genset KM4 - Dokumen Material Verifikasi Chemical Anchor Bolt 2 Install Skid Pompa Pengambilan Skid Pompa Skid Pompa - Material - 2 unit Bekasap Ready Central Shop Duri - 2 unit Pematang - Tools Lifting Gear Ready - Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Email izin masuk Central Shop Lifting Plan Setting Skid Pompa di atas Pondasi - Material - Tools MRO-050 MRO-050 - Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Lifting Plan 3 Install Pompa Pengambilan Unit Pompa Unit Pompa - 2 unit Bekasap - Material Ready di Central Shop Duri - 2 unit Pematang - 2 unit Bangko - Tools Lifting Gear Ready - Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Email izin masuk Central Shop Lifting Plan Setting Unit Pompa di atas Skid - Material - Tools MRO-050 MRO-050 - Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Lifting Plan 4 Install Motor Pengambilan Unit Motor Unit Motor - 2 unit Bekasap - Material Ready di Central Shop Minas - 2 unit Pematang - 2 unit Bangko Checklist Persiapan Install Pompa WIP
No Pekerjaan Item Status
- Tools Lifting Gear Ready
- Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Email izin masuk Central Shop Lifting Plan Setting Motor di atas Skid - Material - Tools MRO-050 MRO-050 - Equipment Foco Truck 8 Ton Ready Trailer Ready - Dokumen Lifting Plan Pasang Cable Temporary Space Heater & Grounding - Material MRO-042 MRO-042 - Tools MRO-050 MRO-050 - Equipment Foco Truck 3 Ton Ready - Dokumen SOP Electrical (IHE) Ready Terminasi - Material MRO-042 MRO-042 - Tools MRO-050 MRO-050 - Equipment - Dokumen SOP Electrical (IHE) Ready Energize - Material MRO-042 MRO-042 - Tools MRO-050 MRO-050 - Equipment - Dokumen SOP Electrical (IHE) Ready 5 Allignment Skid - Material - - Tools Waterpass, Alat Survey Ready (existing) Kunci Torsi check di KM4 MRO-050 MRO-050 - Equipment Chainblock 3 Ton Tiang Gawangan - Dokumen - 6 Epoxy Grout - Material Epoxy Grouting MRO-030 Formwork MRO-039 - Tools Waterpass, Alat Survey Ready (existing) Tools vendor (bor, pengaduk, dsb) MRO-030 - Equipment Foco Truck 3 Ton / Pick Up Ready - Dokumen SOP Epoxy