Article Row TSO Reviewer Comment / Question (description Category Comment / Clarification / Justification Change Status Article
number (please use as specific as possible, please) in Article Owner
email address)
All All VUEN hubert.peter@vu Abbreviation "SO GL". The Improvement SO GL and GL SO can and have both be No done all
Document Documents en.at Regulation (EU) 2017/1485 is named suggested used vice versa. NRAs did not ask to
a guideline on electricity transmission change SO GL into GL SO for already
system operation. Therefore the submitted proposals, so the drafting team
abbreviation "GL SO" seems to be also stays with SO GL in this project
more appropriate.
Response to Swissgrid cherry.yuen@sw We don’t agree to the standard Clarification “FCR has the function of a reserve of no done all
Public issgrid.ch response to stakeholders “FCR has needed last resort…" has been removed.
Consultation the function of a reserve of last resort
and has therefore to be available also
in cases where FRR is not activated
correctly”.
FCR is the “first” resort with relatively
small amount of the fast control
reserves dimensioned for the
relatively small frequency deviations
and to support other slower measures
with much bigger amount. If all
reserves are exhausted there will be
automatic load responses and forced
load shedding. Therefore FCR is by
no means “last” resort. We would also
like to point out that Swissgrid agrees
entirely what the Swiss stakeholder
EKZ has written, in particular their last
sentence “Additionally we feel the
existing grid codes for FRR are
sufficient and if enforced adequately
will render reserve mode less relevant
or obsolete altogether”. The second
part of the standard response “FCR
has the function of a reserve of last
resort…” must be removed.
We don’t agree to the standard
response to stakeholders “FCR has
the function of a reserve of last resort
and has therefore to be available also
in cases where FRR is not activated
correctly”.
FCR is the “first” resort with relatively
small amount of the fast control
reserves dimensioned for the
relatively small frequency deviations
and to support other slower measures
with much bigger amount. If all
reserves are exhausted there will be
automatic load responses and forced
load shedding. Therefore FCR is by
no means “last” resort. We would also
like to point out that Swissgrid agrees
entirely what the Swiss stakeholder
EKZ has written, in particular their last
sentence “Additionally we feel the
existing grid codes for FRR are
sufficient and if enforced adequately
will render reserve mode less relevant
or obsolete altogether”. The second
part of the standard response “FCR
has the function of a reserve of last
resort…” must be removed.
A-1 (article) 74, 78 VUEN hubert.peter@vu The calculation of "electricity Clarification The expression "electricity consumption" No done Alberto Gil
(dimensionin en.at consumption" is not defined. I assume needed is used in the Entso-e web, and used by
g rules for "total load" according to Regulation the Data Expert Group, and published in
FCR) (EU) 543/2013 Art.2(27) is meant with the Power Statistic web.
"electricity consumption".
To avoid ambiguity the calculation of
"electricity consumption" should be
clearly defined or the term "total load"
with a reference to the definition in
(EU) 543/2013 Art.2(27) should be
used.
A-1 (article) 42 50Hertz Torsten.benzin It is stated that this requires the Clarification The mentioned text (SUBMIT THE No done Alberto Gil
(dimensionin @50hertz.com approval of all NRAs, but that goes needed FOLLOWING FCR DIMENSIONING
g rules for too far. According to Art. 6 (3) (d) (ii) RULES PROPOSAL TO ALL
FCR) SO GL, the proposal under Art. 153 REGULATORY AUTHORITIES:) was
SO GL only requires the approval of provided in the original template (and is
the NRAs from the affected region, in common for all the rest A articles), if the
this case CE NRAs. That should be legal team considers necessary can be
clarified. changed, however, be aware that article
A7 has been already sent to the NRAs.
A-2 (article) 85 Terna temistocle.baffa Terna kindly requests to change the Improvement Suggestion accepted Yes done Alexander
(FCR scirocco@terna.i sentence: suggested Stimmer
additional t "shall provide technical evidence
properties) demonstrating why a longer time is
needed"
into
"shall provide technical evidence TO
THE RESPECTIVE TSO
demonstrating why a longer time is
needed"
B-9 (article) 87-88 Terna temistocle.baffa Terna kindly request to align the Improvement there was a request to allow for a direct no done Alexander
(operational scirocco@terna.i suggested approach with the currently suggested trigger in case of emergency; the Stimmer
procedure to t used procedure. In particular, it's procedure concering delayed retrofit was
reduce always the Coordination Centre to explicitly requested to be not included in
frequency trigger Stage 2 and not single TSOs B-9 but just implicitly as part of
deviations) suggesting the Coordination Centre to “Activation of additional mFRR or RR”
trigger the Stage 2. Furthermore, the (due to all this discussions and different
contents of the Additional views on the procedure…). Nevertheless,
supplementing procedure for current formulation allows to activate the
activation of reserves for delayed supplementary procedure under Stage 2
retrofit TSOs are not reflected and should therefore be in line with
explicitly in the SAFA. Should we Terna’s view
consider them included in the Stage
2?
B-9 (article) 129 Terna temistocle.baffa Terna asks to change the sentence Improvement "record" replaced by "take note" yes done Alexander
(operational scirocco@terna.i "The Coordination Centre shall record suggested Stimmer
procedure to t the information…". In particular,
reduce substitute the word "record" with "take
frequency note" or something similar. Otherwise
deviations) the term "record" paves the way to
many interpretations. For instance,
what kind of recording is to be
performed by the Coordination
Centre? written recording? Phone
recording? Other?
B-9 (article) 165 Elia bernard.campio for consistency with B3, "SGSF" Editorial done yes done Alexander
(operational n@elia.be should be replaced by "synchronous change Stimmer
procedure to area monitor according to B3"
reduce
frequency
deviations)
B-9 (article) 168 Elia bernard.campio For TSOs taking part to the cross- Clarification Real time ACE has been deleted yes done Alexander
(operational n@elia.be border aFRR energy exchange, the needed Stimmer
procedure to ajusted ACE taking into account the
reduce activations for cross-border purposes
frequency might not be known in real-time.
deviations) Moreover, this value might be a bit
approximative
B-10 (article) 144 PSE robert.trebski@p Is the duration of the trail phase Clarification replaced "All TSOs" by "The relevant yes done Jan
(roles and se.pl included in the duration of the whole needed TSO" Cernohors
responsibiliti process? Since the trial phase covers ky
es of "All TSO .." and not "Each TSO",
Imbalance there is a real risk that the trial phase
Netting and will last a long time due to the still
cross-border attaching TSO
FRR and RR)
B-10 (article) 154 PSE robert.trebski@p We are asking for clarification Clarification yes, the task is valid for each TSO no done Jan
(roles and se.pl regarding the reporting process: needed individually Cernohors
responsibiliti should any individual TSO be ky
es of reported? If so, see the previous note.
Imbalance
Netting and
cross-border
FRR and RR)
B-10 (article) 151 PSE robert.trebski@p We are asking for clarification of Clarification yes, this is a process other than no done Jan
(roles and se.pl exactly what Additional Process is. Is needed mentioned earlier. Every new process Cernohors
responsibiliti this a process other than mentioned with cross-border relevance should have ky
es of earlier? been notified to CSO as current practice
Imbalance before implementation
Netting and
cross-border
FRR and RR)
B-10 (article) 86 Terna temistocle.baffa Terna would like to point out that Improvement Operational Security Analysis is a SOGL yes done Jan
(roles and scirocco@terna.i limiting to write "Operational Security suggested definition and is therefore used. Cernohors
responsibiliti t Analysis " is very generic. Therefore, Reference to SO GL definition has been ky
es of we propose to better specify by listing added to article
Imbalance what has to be contained (at least a
Netting and condensed description of the
cross-border minimum contents).
FRR and RR)
B-10 (article) 128 Terna temistocle.baffa The sentence is unclear. Affected Improvement Wording changed in a way that limits can yes done Jan
(roles and scirocco@terna.i TSO should be able to define limits suggested be requested in general Cernohors
responsibiliti t for the exchange and sharing of ky
es of reserves of other LFC Areas/Blocks
Imbalance (mostly neighbouring TSO of Affecting
Netting and TSOs should declare themselves as
cross-border Affected TSOs) , since it's the
FRR and RR) exchange and sharing of reserves of
other TSOs that has an impact on the
Affected TSO. Therefore, Terna asks
to check if the proposed formulation is
valid.
B-10 (article) 137-138 Terna temistocle.baffa The terms "new process proposal" Clarification yes, this is a process other than no done Jan
(roles and scirocco@terna.i are not clear. Is this referring only to needed mentioned earlier. Every new process Cernohors
responsibiliti t "Additional processes" as reported in with cross-border relevance should have ky
es of rows 103-112 and 151-157 or is been notified to CSO as current practice
Imbalance referring also to processes as before implementation
Netting and Imbalance Netting, Cross-border
cross-border activation of reserves, Exchange and
FRR and RR) Sharing of reserves?
For the sake of clarity, we kindly ask
to clearly state that the new process
proposal in line 137 does not refer to
Imbalance Netting, Cross-border
activation of reserves, Exchange and
Sharing of reserves.
B-10 (article) 101 RTE julien.gaudin@rt to add "at least" three months in Improvement "at least" added yes done Jan
(roles and e-France.com advance suggested Cernohors
responsibiliti ky
es of
Imbalance
Netting and
cross-border
FRR and RR)
B-10 (article) 132 RTE julien.gaudin@rt to replace SGSF by synchronous Improvement replaced SG SF by Synchronous Area yes done Jan
(roles and e-France.com area monitor suggested Monitor Cernohors
responsibiliti ky
es of
Imbalance
Netting and
cross-border
FRR and RR)
B-10 (article) 161 RTE julien.gaudin@rt the sentence is not clear if we shall Clarification general change of all article 4 of all B yes done Jan
(roles and e-France.com publish the proposal without undue needed articles according to guidace of legal Cernohors
responsibiliti delay or if we shall list and publish the expert team ky
es of roles and responsibilities of TSOs
Imbalance already performing imbalance
Netting and netting,…
cross-border proposal is to rephrase clearly: "The
FRR and RR) TSO shall publish this proposal of
roles and responsibilities of..."
B-10 (article) 132 Elia bernard.campio for consistency with B3, "SGSF" Editorial replaced SG SF by Synchronous Area yes done Jan
(roles and n@elia.be should be replaced by "synchronous change Monitor Cernohors
responsibiliti area monitor according to B3" ky
es of
Imbalance
Netting and
cross-border
FRR and RR)
B-11 (article) 69-70 Terna temistocle.baffa Terna would like to stress that with Improvement Good remark. This hot-stand-backup is yes done Bernard
(requirement scirocco@terna.i the establishment in the following suggested indeed necessary. It is foreseen in the Campion
s concerning t years of the European Platforms for PICASSO project.
the the activation of reserves (aFRR, I adapted the Article in order to take your
availability, mFRR, RR) pursuant to EB GL, the suggestion into account: "The Frequency
reliability hot-stand-by-backup system should Restoration Controller of aFRR shall be
and be foreseen for these Platforms. operated on-line and shall have a very
redundancy Therefore we suggest to change the high reliability. The tools for activation of
of the following sentence: mFRR and RR shall be operated on-line
technical "A hot-stand-by-backup system must and shall have a very high reliability as
infrastructur be available to take over the control well. A hot-stand-by-backup system must
e) function in case of an outage or fault be available to take over the control
of the main system." function in case of an outage or fault of
into the main system. This requirement
"A hot-stand-by-backup system must applies as well for all European
be available for all European Platform Platform performing a cross-border
performing a cross-border FRR and FRR and RR activation process."
RR activation process, to take over
the control function in case of an
outage or fault of the main system."
B-11 (article) 119-121 Terna temistocle.baffa Terna would like to ask why TSOs Clarification Solution found via bilateral agreeement no done Bernard
(requirement scirocco@terna.i "shall publish the requirements needed between Terna and Bernard. No change Campion
s concerning t concerning the availability, reliability in article.
the and redundancy of the technical
availability, infrastructure proposal". Unless an
reliability already existing obligation is force, we
and suggest not to publish such sensible
redundancy information and then to remove the
of the lines from 119 to 121.
technical
infrastructur
e)
B-11 (article) 90-91 VUEN hubert.peter@vu The text "Substitute measurements Clarification Formulation of MLA OH was used. yes done Bernard
(requirement en.at and reserve equipment shall be needed Measurement requirements have been Campion
s concerning available in parallel to the primary precised.
the measurement and substitute
availability, measurements." is a tightening of
reliability the requirements compared to the
and existing OH Policy 1 where substitute
redundancy measurements are obligatory for all
of the TIE-LINES with significant impact to
technical SECONDARY CONTROL. Is this
infrastructur intentional and in any case feasible,
e) eg. in case of lower voltage tie-lines
(< 110 kV)?
Furthermore the meaning of
"...available in parallel to the primary
measurement and substitute
measurement" is unclear. Does that
mean it is required to have a primary
measurement with a substitute
measurment and reserve equipment
and a further substitute measurement
also with primary and subtitute
measurement and reserve
equipment?
I propose to delete "and substitute
measurements" at the end of the
sentence to avoid misunderstandings.
B-11 (article) 77 RTE julien.gaudin@rt to adapt "frequency measurements Improvement Good proposal. The sentence online 76- yes done Bernard
(requirement e-France.com available in real time from at least two suggested 77 was modified as follows: "For each Campion
s concerning different geographical locations LFC Area of CE synchronous Area, the
the available within the LFC area" related TSO shall have frequency
availability, measurements from at least two
reliability different geographical locations
and available within this LFC Area."
redundancy
of the
technical
infrastructur
e)
B-12 (article) 65 RTE julien.gaudin@rt the sentence is not clear. Maybe to Improvement suggestion implemented yes done Alexander
(common e-France.com split the sentence into two phrases: suggested Stimmer
rules for the All common rules for the operation in
operation in Normal State and Alert State reflect
normal state the target of load-frequency-control to
and alert reduce frequency deviations. Those
state) rules refer to the operational
procedures to reduce frequency
deviation according to B-9
Operational Procedures to Reduce
Frequency Deviation.
B-16 (article) 57 ESO IKezhov@ndc.b I didn't find the word "compensation" Clarification Formulation was missleading and has yes done David
(technical g about the providing synchronous area needed been adjusted according to wording in Whitley
design of the neither in 173(3), nor in 153. Could article 173(3)
frequency you please to comment what has to
coupling be compensated (is this some back-
process) up process)?