Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


MASBATE 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE V
Dimasalang, Masbate

May 25, 2022

MEMORANDUM

FOR : GERRYLIN M. CANTILLEP


OIC-District Engineer
DPWH Masbate 3rd District Engineering Office
Dimasalang, Masbate

SUBJECT : INSPECTION REPORT FOR PARTIAL BILLING

CONTRACT ID : 22FJ0001 (P00606435LZ)


PROJECT NAME AND LOCATION : OO1: Ensure Safe and Reliable National Road System
- Network Development Program - Road Widening -
Secondary Roads - Buenavista-Kawayan Rd -
K0044+000-K0044+672
CONTRACT PRICE : Php 23,751,459.04
CONTRACTOR : JOLAC'S CONSTRUCTION
DATE OF INSPECTION : May 24, 2022

I. FINDINGS

1. The actual length of the completed PCCP, was measured to be 559.4 meters with
3.35-meter width. PCCP thickness was noted 280mm, which conforms to plan.
2. The measured length of lined canal during inspection was 48.7 meters.
3. Actual length of accomplished grouted riprap was measured to be 82.1 meters.
4. Total work accomplishment during inspection was found to be 43.44% (see attached
computation).

II. RECOMMENDATIONS

1. Recommended for 40.06% first partial billing, as per contractor’s request

RUEL Y. GALLARES HILARIO A. MANLANGIT


Chief, Maintenance Section Chief, Quality Control Section

RIZALINA V. VERDIDA
Assistant District Engineer
Head, District Inspectorate Team

JONATHAN D. SELLAR FLORANTE U. ZURBITO


Chief, Planning and Design Section Chief, Construction Section