Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


MASBATE 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE V
Dimasalang, Masbate

ACTUAL PHYSICAL ACCOMPLISHMENT


From June 1 - June 15, 2022

21FJ0032- Local Program: Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects, Construction of Concrete Road -
PROJECT NAME :
Construction of Antipolo - Miabas Road, Palanas, Masbate Sta. 0+355.00 - 3+255.00

LOCATION : Palanas, Masbate


CONTRACTOR : EJ CANTORIA CONSTRUCTION & SUPPLY

ORIGINAL ACCOMPLISHMENT ACTUAL ACCOMPLISHMENT %


ITEM Decription Unit
QTY. UNIT COST AMOUNT % WT. QUANTITY AMOUNT % WT. Complete
PART B Other General Requirements
B.5 Project Billboard / Signboard each 2.00 4,336.50 8,673.00 0.02 2.00 8,673.00 0.02 100.00%
B.7(1) Occupational Safety & Health Program month 4.77 36,288.00 173,093.76 0.38 2.39 86,546.88 0.19 1/2
B.8(1) Traffic Management month 4.77 73,710.00 351,596.70 0.77 2.39 175,798.35 0.39 1/2
B.9 Mobilization / Demobilization L-S 1.00 315,318.36 315,318.36 0.69 0.50 157,659.18 0.35 50.00%
PART C EARTHWORKS
101(4)a1 Removal of Actual Structures/Obstruction (610mm dia. RCPC) l.m. 6.00 4,275.58 25,653.48 0.06 - - - 0.00%
102(1) Unsuitable Excavation cu.m. 12,912.57 388.91 5,021,827.60 11.01 4,303.76 1,673,775.14 3.67 33.33%
104(2)a Embankment from borrow (Common Soil) cu.m. 3,436.01 958.24 3,292,522.22 7.22 1,145.22 1,097,397.66 2.41 33.33%
105(1)a Subgrade Preparation (Common Material) sq.m. 23,200.00 32.68 758,176.00 1.66 7,732.56 252,700.06 0.55 33.33%
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 7,156.45 1,120.38 8,017,943.45 17.57 2,385.24 2,672,380.55 5.86 33.33%
PART E SURFACE COURSE
311(1)b1 Portland Cement Concrete Pavement (Unreinforced, 200mm, 14 days) sq.m. 14,500.00 1,762.58 25,557,410.00 56.02 4,832.85 8,518,284.75 18.67 33.33%
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
506(1) Stone Masonry cu.m. 9.96 8,736.45 87,015.04 0.19 - - - 0.00%
500(1)a3 Pipe Culvert, 910mmø l.m. 10.00 9,507.47 95,074.70 0.21 - - - 0.00%
PART H MISCELLANEOUS STRUCTURE
612(1) Refectorized Thermoplastic Pavement Markings (White) sq.m. 725.45 919.47 667,029.51 1.46 - - - 0.00%
612(2) Refectorized Thermoplastic Pavement Markings (Yellow) sq.m. 497.18 1,034.97 514,566.38 1.13 - - - 0.00%
624(8) Solar LED Street Light each 5.00 147,839.96 739,199.80 1.62 - - - 0.00%

TOTAL TOTAL (Php) 45,625,100.00 100.00 14,643,215.57 32.09

WE HEREBY CERTIFY THAT THE STATEMENT OF WORK ACCOMPLISHED


ON THIS PAGE IS TRUE AND CORRECT

Prepared by: Checked by: Submitted by:

JOEL P. MONSALES / CESAR P. MISSION ALBERTO B. VALDEMORO FLORANTE U. ZURBITO


Project Inspector / Resident Engineer Project Engineer Chief, Construction Section