Rencana Tindakan Perbaikan/Corrective Action Plan (“CAP”)

Unimedika Sepatan Mulia Tangerang (UMST) – PT Hero Yoyo Sudarsa (HYS)

Signing: 11 October 2021

No
Finding Description Output Parameter Status
.
1 Public disclosure of the company's activities, 1. A letter of approval from UMST signed by COMPLETED
impacts, and developments is one of the the Director or Hospital Manager allowing
prerequisites for IIF financing. UMST is expected to IIF to upload UKL-UPL documents on the
produce a letter or statement of approval enabling IIF website during the period of the IIF
IIF to upload the Environmental Permit and financing facility.
Assessment Document (i.e., UKL-UPL) and other
related S&E documents on the IIF website prior to 2. Copy of UKL-UPL document uploaded on
signing the facility agreement. IIF website.
2 Based on SEDD, in terms of managing S&E aspects, 1. The UMST SEMS document that has been 1. Completed
several components of the Social and reviewed and updated (which includes a Unimedika has submitted the SEMS
Environmental Management System (SEMS) are compilation of all requested components) Document. The document is considered
already available or developed by UMST (eg S&E has been signed by the Director or adequate.
policy, an organizational structure with specialized Hospital Leader.
personnel, etc.). After the SEDD process is 2. COMPLETED
complete, UMST notifies that they have prepared 2. Documentation/proof of The SEMS dissemination was conducted
the SEMS document (which was not previously dissemination/socialization of SEMS to all through an email to all employees and a
provided during the SEDD process). Based on the workers, which can be in the form of direct approach to workers. It is evident
review of the IIF S&E team, the document can still attendance lists, photos, emails, etc. through photos and a list of participants
be further developed to complement the SEMS in who receive the dissemination.
accordance with the first IIF Social and
Environmental Principles (SEP 1).
3 Stakeholder Engagement Plan
The available SEMS documents have included 1. Stakeholder Engagement Plan Document 1. ATTENTION REQUIRED
general descriptions/guidelines related to which includes stakeholder mapping, The document has been submitted on 15
engagement with multiple stakeholders. However, plans, and programs to manage and November 2022. However, the submitted
the explanation does not include a detailed plan or maintain relationships with relevant document covering implementation of its
No
Finding Description Output Parameter Status
.
strategy regarding the form of engagement that will stakeholders. SEP. the SEP itself not found in the
be carried out with the identified stakeholders, submitted document. SED write a review
including communities potentially affected by the on the document for UMST references/
project. guidances in revising the document.

2. Annually

2. Documentation of the implementation of


stakeholder engagement (in the form of a
report).
4 Grievance Mechanism
In terms of employment, UMST does not yet have a 1. Worker grievance mechanism for UMST 1. ATTENTION REQUIRED
formal procedure for handling worker complaints. employees The document submitted by Unimedika
Complaints are usually submitted directly to the only contains grievance procedures for
worker's supervisor without any documentation or the community and patient, while it
reports of complaints handling actions and the 2. Records of patient, community, and should also include the grievance
status of their resolution. worker complaints with completion mechanism for their own workers. A
status. document was submitted on 31 August
2022, but it does not reflect a procedure
Note: For workers' complaint records, UMST related to the grievance mechanism for
only needs to convey the type of complaint UMST employees. The document only
and the status of the settlement, without the informs coordination meetings related to
need to disclose confidential data from grievances, issues, and communication
workers. related to Hospital operations. UMST
may refer to UMSB procedure for the
workers grievance mechanism.
Therefore, UMST is still required to
submit the Grievance Mechanism for
workers. By email, UMST confirmed that
will submit the document on Dec 2022
No
Finding Description Output Parameter Status
.
2. Annually
5 Management Program
During the construction phase, UMST shall identify 1. Updated Contractor Management Plan or 1. COMPLETED
and develop the S&E risk management measures SOP regarding safety procedures during UMST has prepared a document
that the contractor will require, which can be done renovation and construction that is consisting of direction for the contractor
by developing a “Contractor Management Plan” acceptable to IIF to conduct the construction phase. It
includes contractor’s responsibility to
(CMP) or “Contractor S&E Requirements”. The CMP
provide reporting to UMST, proper
should describe the various S&E considerations and
facility to conduct the work, regular
mitigations, controls, and commitments associated coordination meeting with UMST, work
with the contractor's main activities and clearly permit, dedicated OHS personnel,
define responsibilities, performance measurements, availability and diligence to use PPE,
and reporting requirements. Based on the document coordination with UMST regarding
review, UMST already has safety procedures during mobility of construction material,
renovation and construction (SPO/UMST/FMS- workers medical check-up, and
K3RS/001). However, we note that these continuous coordination and
socialization with community or related
procedures are general requirements and can be
stakeholders prior and during the
updated or improved in accordance with IIF
construction activities. The document
standards. has been agreed and signed by the
2. The Construction Monitoring Report is Contractor (i.e. PT Cipta Dimensi Baja
During the operations phase, UMSTs need to accompanied by evidence or Nusantara).
identify and develop programs related to the S&E documentation of the implementation of
aspects they will implement, which may include S&E management during construction 2. ATTENTION REQUIRED
programs, performance indicators, targets, (e.g., provision of traffic safety signs in HYS submitted several documents in
evidence, resource estimates, etc. the project area, sanitation area, order to comply with CAP 5.2
hazardous materials management, etc.) requirements:
 Pengarahan tim proyek UMST
terkait SOP Pelaksanaan Proyek
signed by Contractor and HYS;
 HSE Report Feb 2022;
No
Finding Description Output Parameter Status
.
 Elemen 2: Manajemen Program;
 Standar Pelaksanaan K3 PT Cipta
Dimensi Baja Nusantara.
SED has reviewed all above documents
and did not find monitoring report that
covers provision of traffic safety signs,
3. S&E Management Program during the
sanitation area, hazardous material, and
operational phase
hazardous waste management.
Mohon dapat mengirimkan dokumen
HSE Report Q1-Q3 (Januari – September
2022)

3. COMPLETED
4. S&E Management Program The company had submitted S&E
Implementation Report management programs, which are part
of their SEMS

4. Annually

6 Emergency Preparedness and Response Plan


An internal Emergency Preparedness and Response 1. The updated Emergency Response 1. ATTENTION REQUIRED
Plan (ERP) document has been developed for the Procedure includes the items mentioned in HYS has submitted several documents
operations phase. However, the aspects covered in the corrective action plan column. related to ERP:
the emergency response plan are only limited to the  Laporan Training K3 RS;
fire evacuation plan. In-house training on this  Training K3 RS on earthquake
subject has been conducted annually. In addition, simulation;
UMST does not yet have/include emergency  Prosedur Penanggulanan
response procedures for affected communities. Bencana Kebakaran di Dalam
Rumah Sakit
In 2019 UMST received a letter of recommendation
(36/SPO/K3/RSIASM/XII/20).
from the Regional Disaster Management Agency
To fulfill CAP 6.1 requirement, HYS
(BPBD) regarding technical plans for existing
No
Finding Description Output Parameter Status
.
shall establish SOP related to
buildings and expansion buildings. The
earthquake and flood.
recommendation letter states that BPBD will visit
UMST to check the compliance stated in the letter
2. BPBD Visit Report and Fire Protection
related to fire safety requirements, once
System Feasibility Certificate 2. COMPLETED
construction is complete.
The BPBD visit has been conducted and
the Fire Protection System Eligibility
Certificate has been received
7 Company regulations and standard operating A statement or policy regarding the COMPLETED
procedures owned by UMST do not include the freedom of workers to form or join workers' UMST has submitted the statement letter
freedom to form or join workers' organizations and organizations and no forced labor is signed signed by the CEO of Unimedika Hospital
the statement that there is no forced labor. by the Director or Hospital Management. Group on 31 August 2022 stating that the
Statement Letter is applicable to all hospital
under Unimedika Group. The document is
considered adequate and fulfill the CAP.
8 Based on the UKL-UPL Implementation and 1. SOP or program for monitoring and 1. COMPLETED
Monitoring report, UMST has conducted a monthly evaluating the performance of Unimedika has submitted the
program for monitoring wastewater. Referring to wastewater treatment plants (WWTP). Wastewater Management Procedure,
2019 (Semester 1 and 2) and 2020 (Semester 1) also Emergency Response Procedure
reports, several wastewater parameters are above for WTP. The document is considered
the quality standard (e.g., Total Coliform, TSS, complied.
Ammonia, BOD, and COD, Nitrate, Detergents such 2. WWTP Performance Evaluation Report
as MBAS, Fluoride, and Nickel). 2. COMPLETED
WTP evaluation report for the 2021
Recommendations for technical assessment period has been submitted. The report
requirements from the Tangerang Environmental 3. A copy of the application for a is considered adequate.
Agency No. 658.31/04-DLHK (January 2020) have wastewater disposal permit (IPLC) after 3. COMPLETED
provided several requirements for UMST to treat the expansion of the WWTP, which is Unimedika has been obtained Technical
wastewater (page 5). In accordance with the accompanied by the design of the Recommendation (Pertek) for
No
Finding Description Output Parameter Status
.
requirements, UMST must develop a formalized expansion WWTP. Wastewater Discharge to Waterbody.
wastewater monitoring program in the form of a
document. 4. Renewed wastewater disposal permits 4. COMPLETED
and include recommendations for Surat Kelayakan Operasional No:
However, we also received information that UMST technical assessment requirements 658.31/05-DLHK dated 23 June 2022.
plans to expand and/or increase its WWTP capacity. from the Environment Agency.
Thus, UMST needs to request a renewal of the
wastewater disposal permit in accordance with the
increase in capacity.
9 Hazardous and Domestic Waste
Improvements to facilities and specifications for 1. Updated B3 waste management 1. COMPLETED
Temporary Storage Places (TPS) for hazardous procedures, especially regarding labeling The procedure for hazardous waste
waste at UMST locations are still needed to meet management has been submitted and
the criteria of Government Regulation no. 14 of 2. Procedures for managing domestic waste is considered adequate.
2014. (non-hazardous and/or non-infectious
waste) during the construction and 2. COMPLETED
As for domestic waste, based on the SEDD report, operational stages. The procedure for domestic waste has
domestic waste is only categorized as non- been submitted and is considered
infectious waste. To achieve better environmental 3. Documentation of the implementation of adequate.
sustainability, it is necessary to carry out additional the household waste management plan,
management of domestic waste. including the amount of recycled and non- 3. BI-annually
recyclable waste collected and/or photo Documentation of hazardous waste
documentation. This can be included as management
part of the UKL-UPL implementation report
during the construction and operational
stages or submitted to IIF as a separate
document.
10 Hazardous Material
Based on SEDD, it was found that several gas 1. Updated hazardous materials 1. COMPLETED
cylinders in the gas chamber were placed unbound. management procedures, to include Unimedika has submitted the procedure
No
Finding Description Output Parameter Status
.
High-pressure gas cylinders must be strapped to operating safety associated with placing for hazardous material management
prevent them from falling and exploding. compressed gas cylinders in storage procedure. The document is considered
rooms or during use to comply with IIF requirements.

2. COMPLETED
The evidence (photograph) has been
submitted to IIF.
2. Evidence of improved hazardous
materials management (can be provided
in the form of photos)

11 Based on UKL-UPL, UMST is required to measure Measurements of air quality and noise levels COMPLETED
ambient air quality and noise once during the within hospitals, construction areas, and Unimedika has conducted monitoring for
construction phase. Bore pile or foundation work sensitive receptor areas (i.e., community ambient air quality and noise level at the
has been carried out since the end of 2020. settlements) have been included as part of the construction area and community
However, based on the latest UKL-UPL UKL-UPL implementation report during the
settlement. No parameters exceed the
implementation report in July-September 2020, construction and operational stages or
threshold value.
there is no information regarding the noise level. Air submitted to IIF as a separate document.
quality measurements were carried out in July 2020
in the Nurse Station and the operating room, but
these areas do not reflect the air quality in the
construction area. In accordance with IIF standards,
UMST should also consider air quality and noise
measurements in sensitive receptor areas, such as
residential areas of communities adjacent to
construction areas.
12 Based on flood and technical recommendations Documentation or evidence of the COMPLETED
issued by the Department of Highways and Water construction of drainage canals and infiltration Unimedika has constructed the drainage as
Resources of Tangerang No. wells at the UMST location a recommendation from the Department of
614/191/DBMSDA/2020 (January 2020), UMST is Highways and Water Resources Tangerang.
required to provide ponds or infiltration wells to
The infiltrations well also have been
avoid runoff/discharge of rainwater directly into
No
Finding Description Output Parameter Status
.
surface water. UMST is also required to provide a constructed in the hospital area.
study or analysis of the drainage system. However,
based on the SEDD report, drainage channels
equipped with infiltration wells are not yet available
at the UMST location.
13 UMST does not yet have a Security Management Security Management Plan COMPLETED
Plan. The security management plan aims to ensure Unimedika has submitted the Security
that the safeguarding of personnel and property is Management Plan and the content is
carried out in accordance with relevant human considered adequate.
rights principles and in a manner or practice that
avoids or minimizes risks to society.
14 In 2020, two out of three incidents were related to 1. Updated Work Incident Reporting 1. COMPLETED
needle sticks. The incident report does not explain Unimedika has submitted the updated
the root cause and corrective action is limited to procedure and is considered adequate.
consulting a doctor and undergoing certain
laboratory tests. There is no detailed preventive 2. Investigation report (two reports) 2. COMPLETED
action to prevent and minimize the incident from HYS submitted below documents to SED:
recurring. It is very important for UMST to prevent  Formulir Laporan Insiden Klinis
nosocomial infections through needle stick No: LIK/UMST/QR/002;
puncture.  Penanganan Tertusuk Jarum dan
Terpapar Cairan Tubuh Pasien
No: SPO/UMST/PPI/020 dated 4
December 2021;
 Laporan Pajanan 23 Januari
2021;
Above submitted documents
considered adequate.

15 The lowest salary level at UMST is for cleaning A sample copy of salary/pay slip (cleaning COMPLETED
services which are known to be below the minimum service) Unimedika has submitted the payslip for one
wage regulated in Tangerang Regency. This of their cleaning services.
No
Finding Description Output Parameter Status
.
cleaning service is rented directly by UMST.
However, the Human Resources (HR) department
has proposed a wage adjustment that refers to the
Tangerang regional regulation and the adjustment
was approved by the President Director of
Unimedika in March 2021.
Persyaratan Pelaporan Reguler (Bagian dari Rencana Tindakan Perbaikan)

No Laporan Reguler Status


Laporan Pelaksanaan UKL-UPL, meliputi pengukuran dan evaluasi air limbah, udara ambien, dan kebisingan.
1 UMST has submitted RKL-RPL for Semester 2 2021 period
Laporan Implementasi RKL-RPL diserahkan kepada IIF maksimal 6 bulan setelah periode pelaporan.
ATTENTION REQUIRED
Similar to CAP No 5.2 above, HYS submitted several
documents in order to comply with CAP 5.2
requirements:
 Pengarahan tim proyek UMST terkait SOP
Pelaksanaan Proyek signed by Contractor and
HYS;
 HSE Report Feb 2022;
Pemantauan HSE dan Sosial Selama Tahap Konstruksi dan Operasional (Laporan Pelaksanaan K3RS)  Elemen 2: Manajemen Program;
 Standar Pelaksanaan K3 PT Cipta Dimensi Baja
2
Nusantara.
Laporan diserahkan kepada IIF maksimal 3 bulan setelah periode pelaporan
SED has reviewed all above documents and did not find
monitoring report that covers provision of traffic safety
signs, sanitation area, hazardous material, and hazardous
waste management

Mohon dapat mengirimkan dokumen HSE Report Q1-Q3


(Januari – September 2022)

3 Laporan Tahunan Perlindungan Sosial dan Pemantauan Lingkungan yang terdiri dari, namun tidak terbatas December 2022
pada:
a. Implementasi program pengelolaan Sosial dan Lingkungan
b. Pencatatan dan pelaporan keluhan masyarakat, pasien, dan karyawan, dilengkapi dengan status
penyelesaiannya;
c. Dokumentasi rencana pelibatan pemangku kepentingan;
No Laporan Reguler Status
d. Dokumentasi pelatihan tanggap darurat dan pelaksanaan simulasi (drill);
e. Pelaksanaan rencana pelatihan pekerja;
f. Pengelolaan (atau manifes) Limbah B3 dan Non B3 termasuk catatan kuantitasnya;
g. Dokumentasi pengelolaan bahan berbahaya dan beracun (misalnya MSDS, daftar bahan, dll);
h. Catatan/laporan pengukuran kinerja K3;
i. Laporan atau dokumentasi dari setiap inspeksi atau kunjungan HSE & Sosial yang dilakukan oleh otoritas
lokal; dan
j. Laporan Monitoring dan Evaluasi IPAL

Laporan tahunan diserahkan kepada IIF maksimal pada tanggal 31 Desember setiap tahun, dimulai satu tahun
setelah penandatanganan Facility Agreement. Template pelaporan akan disediakan oleh IIF
Apabila terjadi kecelakaan yang mengakibatkan korban jiwa dan/atau kecelakaan lain yang bersifat material
4 (berdampak pada aspek sosial dan lingkungan), UMST harus segera memberitahukan kepada IIF dalam waktu No report
1x24 jam, dan dilanjutkan dengan penyampaian laporan detail hasil investigasi paling lama 3 (tiga) bulan.
Jika ada pergantian personel yang bertanggung jawab dalam mengelola aspek S&E, UMST harus
5 None
menginformasikan kepada IIF dalam waktu seminggu untuk memudahkan proses komunikasi (pelaporan).