No
Finding Description Output Parameter Status
.
1 Public disclosure of the company's activities, 1. A letter of approval from UMST signed by COMPLETED
impacts, and developments is one of the the Director or Hospital Manager allowing
prerequisites for IIF financing. UMST is expected to IIF to upload UKL-UPL documents on the
produce a letter or statement of approval enabling IIF website during the period of the IIF
IIF to upload the Environmental Permit and financing facility.
Assessment Document (i.e., UKL-UPL) and other
related S&E documents on the IIF website prior to 2. Copy of UKL-UPL document uploaded on
signing the facility agreement. IIF website.
2 Based on SEDD, in terms of managing S&E aspects, 1. The UMST SEMS document that has been 1. Completed
several components of the Social and reviewed and updated (which includes a Unimedika has submitted the SEMS
Environmental Management System (SEMS) are compilation of all requested components) Document. The document is considered
already available or developed by UMST (eg S&E has been signed by the Director or adequate.
policy, an organizational structure with specialized Hospital Leader.
personnel, etc.). After the SEDD process is 2. COMPLETED
complete, UMST notifies that they have prepared 2. Documentation/proof of The SEMS dissemination was conducted
the SEMS document (which was not previously dissemination/socialization of SEMS to all through an email to all employees and a
provided during the SEDD process). Based on the workers, which can be in the form of direct approach to workers. It is evident
review of the IIF S&E team, the document can still attendance lists, photos, emails, etc. through photos and a list of participants
be further developed to complement the SEMS in who receive the dissemination.
accordance with the first IIF Social and
Environmental Principles (SEP 1).
3 Stakeholder Engagement Plan
The available SEMS documents have included 1. Stakeholder Engagement Plan Document 1. ATTENTION REQUIRED
general descriptions/guidelines related to which includes stakeholder mapping, The document has been submitted on 15
engagement with multiple stakeholders. However, plans, and programs to manage and November 2022. However, the submitted
the explanation does not include a detailed plan or maintain relationships with relevant document covering implementation of its
No
Finding Description Output Parameter Status
.
strategy regarding the form of engagement that will stakeholders. SEP. the SEP itself not found in the
be carried out with the identified stakeholders, submitted document. SED write a review
including communities potentially affected by the on the document for UMST references/
project. guidances in revising the document.
2. Annually
3. COMPLETED
4. S&E Management Program The company had submitted S&E
Implementation Report management programs, which are part
of their SEMS
4. Annually
2. COMPLETED
The evidence (photograph) has been
submitted to IIF.
2. Evidence of improved hazardous
materials management (can be provided
in the form of photos)
11 Based on UKL-UPL, UMST is required to measure Measurements of air quality and noise levels COMPLETED
ambient air quality and noise once during the within hospitals, construction areas, and Unimedika has conducted monitoring for
construction phase. Bore pile or foundation work sensitive receptor areas (i.e., community ambient air quality and noise level at the
has been carried out since the end of 2020. settlements) have been included as part of the construction area and community
However, based on the latest UKL-UPL UKL-UPL implementation report during the
settlement. No parameters exceed the
implementation report in July-September 2020, construction and operational stages or
threshold value.
there is no information regarding the noise level. Air submitted to IIF as a separate document.
quality measurements were carried out in July 2020
in the Nurse Station and the operating room, but
these areas do not reflect the air quality in the
construction area. In accordance with IIF standards,
UMST should also consider air quality and noise
measurements in sensitive receptor areas, such as
residential areas of communities adjacent to
construction areas.
12 Based on flood and technical recommendations Documentation or evidence of the COMPLETED
issued by the Department of Highways and Water construction of drainage canals and infiltration Unimedika has constructed the drainage as
Resources of Tangerang No. wells at the UMST location a recommendation from the Department of
614/191/DBMSDA/2020 (January 2020), UMST is Highways and Water Resources Tangerang.
required to provide ponds or infiltration wells to
The infiltrations well also have been
avoid runoff/discharge of rainwater directly into
No
Finding Description Output Parameter Status
.
surface water. UMST is also required to provide a constructed in the hospital area.
study or analysis of the drainage system. However,
based on the SEDD report, drainage channels
equipped with infiltration wells are not yet available
at the UMST location.
13 UMST does not yet have a Security Management Security Management Plan COMPLETED
Plan. The security management plan aims to ensure Unimedika has submitted the Security
that the safeguarding of personnel and property is Management Plan and the content is
carried out in accordance with relevant human considered adequate.
rights principles and in a manner or practice that
avoids or minimizes risks to society.
14 In 2020, two out of three incidents were related to 1. Updated Work Incident Reporting 1. COMPLETED
needle sticks. The incident report does not explain Unimedika has submitted the updated
the root cause and corrective action is limited to procedure and is considered adequate.
consulting a doctor and undergoing certain
laboratory tests. There is no detailed preventive 2. Investigation report (two reports) 2. COMPLETED
action to prevent and minimize the incident from HYS submitted below documents to SED:
recurring. It is very important for UMST to prevent Formulir Laporan Insiden Klinis
nosocomial infections through needle stick No: LIK/UMST/QR/002;
puncture. Penanganan Tertusuk Jarum dan
Terpapar Cairan Tubuh Pasien
No: SPO/UMST/PPI/020 dated 4
December 2021;
Laporan Pajanan 23 Januari
2021;
Above submitted documents
considered adequate.
15 The lowest salary level at UMST is for cleaning A sample copy of salary/pay slip (cleaning COMPLETED
services which are known to be below the minimum service) Unimedika has submitted the payslip for one
wage regulated in Tangerang Regency. This of their cleaning services.
No
Finding Description Output Parameter Status
.
cleaning service is rented directly by UMST.
However, the Human Resources (HR) department
has proposed a wage adjustment that refers to the
Tangerang regional regulation and the adjustment
was approved by the President Director of
Unimedika in March 2021.
Persyaratan Pelaporan Reguler (Bagian dari Rencana Tindakan Perbaikan)
3 Laporan Tahunan Perlindungan Sosial dan Pemantauan Lingkungan yang terdiri dari, namun tidak terbatas December 2022
pada:
a. Implementasi program pengelolaan Sosial dan Lingkungan
b. Pencatatan dan pelaporan keluhan masyarakat, pasien, dan karyawan, dilengkapi dengan status
penyelesaiannya;
c. Dokumentasi rencana pelibatan pemangku kepentingan;
No Laporan Reguler Status
d. Dokumentasi pelatihan tanggap darurat dan pelaksanaan simulasi (drill);
e. Pelaksanaan rencana pelatihan pekerja;
f. Pengelolaan (atau manifes) Limbah B3 dan Non B3 termasuk catatan kuantitasnya;
g. Dokumentasi pengelolaan bahan berbahaya dan beracun (misalnya MSDS, daftar bahan, dll);
h. Catatan/laporan pengukuran kinerja K3;
i. Laporan atau dokumentasi dari setiap inspeksi atau kunjungan HSE & Sosial yang dilakukan oleh otoritas
lokal; dan
j. Laporan Monitoring dan Evaluasi IPAL
Laporan tahunan diserahkan kepada IIF maksimal pada tanggal 31 Desember setiap tahun, dimulai satu tahun
setelah penandatanganan Facility Agreement. Template pelaporan akan disediakan oleh IIF
Apabila terjadi kecelakaan yang mengakibatkan korban jiwa dan/atau kecelakaan lain yang bersifat material
4 (berdampak pada aspek sosial dan lingkungan), UMST harus segera memberitahukan kepada IIF dalam waktu No report
1x24 jam, dan dilanjutkan dengan penyampaian laporan detail hasil investigasi paling lama 3 (tiga) bulan.
Jika ada pergantian personel yang bertanggung jawab dalam mengelola aspek S&E, UMST harus
5 None
menginformasikan kepada IIF dalam waktu seminggu untuk memudahkan proses komunikasi (pelaporan).