You are on page 1of 13

REVIEW OF PILOT PLANT TESTS AT DIENG

FINAL REPORT

August 2021

P.O. Box 30-125,


Barrington,
Christchurch, 8244, NZ
kevin@geokem.co.nz
Project: Review of Pilot Plant Tests at Dieng

Status: Final Report

Prepared for: Geo Dipa Energi / ADB

Prepared by Kevin Brown

Date August 2021

Review of Pilot Plant Tests – Dieng Page | 2


TABLE OF CONTENTS

EXECUTIVE SUMMARY ................................................................................. 4


1.0 INTRODUCTION ....................................................................................... 6
2.0 TEST1 ........................................................................................................ 6
2.1 EXPERIMENTAL .................................................................................... 6
2.2 RESULTS ............................................................................................... 7
3.0 TEST 2 ....................................................................................................... 9
3.1 EXPERIMENTAL .................................................................................... 9
3.2 RESULTS ............................................................................................... 9
4.0 DISCUSSION........................................................................................... 10
5.0 RECOMMENDATIONS ............................................................................ 12

Review of Pilot Plant Tests – Dieng Page | 3


EXECUTIVE SUMMARY

Mannvit has designed and constructed a pilot plant and conducted two tests
to assess options for planned expansion developments at Dieng. GEOKEM
has been engaged to review the final report of the tests.

Two tests have been run on the pilot plant with fluid from well HCE-7C. The
tests investigated Options 1,4 and 6 from the Thermochem Indonesia (TCI)
report entitled “Silica Scale Mitigation Study for Dieng Units 2 and 3”.

The TCI report recommended acid dosing into the two-phase fluid. This was
found to cause unacceptable corrosion, and acid dosing was shifted to the
separated brine. Unfortunately, this meant that the acid was added at a
temperature below the silica saturation temperature (SST) and silica
polymerisation to form colloids had already begun. The bulky silica scaling
from geothermal brines is due to colloidal deposition and consequently it is
impossible to distinguish whether the silica scaling observed in both tests
would occur if no colloidal silica was present.

Silica scaling was observed on all coupons exposed in both of the tests.
Significant amorphous arsenic sulfide scaling was observed on coupons from
the brine after the heat exchangers in test 1. Antimony sulfide scaling was
observed in the coupon after the first heat exchanger in test 1. The sulfide
scaling would seem to tip the balance towards a steam flash plant, rather than
a binary plant. In test 2, only silica scaling was observed on the coupons.

The addition of condensate to the brine raised the pH to values where silica
polymerisation would again be expected, and negated the reason for acid
addition. Consequently, addition of condensate should not be considered if
acid dosing is utilised

The acid requirement to lower the pH to 4.6 in the separated brine is


measured as 55 – 60 ppm of 98% sulfuric acid.

Recommendations:
• That tests be conducted to determine the first stage separation
temperature above the silica saturation temperature to enable acid
addition to the brine before silica polymerisation commences. These tests
should run for a minimum of 1 week each in order to obtain conclusive
results.

• In separate tests, determine the lowest separation temperature for second


stage separation that gives acceptable operation for scaling and corrosion.
This test will also define the required pH of the HP brine to produce the
test pH in the LP brine.

• After sufficient tests have confirmed parameters for a flash development,


repeat the heat exchanger tests to find the temperature at which the
arsenic sulfide starts precipitating. Possibly with coupons in the
turnarounds in the first heat exchanger.

Review of Pilot Plant Tests – Dieng Page | 4


• Measure the silica concentration in the steam condensate at the initial
separation in order to determine likely silica concentrations that need to be
treated in the steam washing.

• Possibly investigate the acidified brine reacting with drill cuttings from the
formation in a flow-through autoclave.

• At the end of each test, flush the plant with fresh water before shutting
down to prevent silica and sulfide deposition on the coupons as the plant
is closed down and the brine cools.

Review of Pilot Plant Tests – Dieng Page | 5


1.0 INTRODUCTION

Geo Dipa Energi (GDE) is considering an expansion to its current operation at


Dieng. The proposal is for two new 55 MW power plants. The brine from
Dieng wells is very saline and has a high silica content due to the high
temperature in the reservoir. Current operation has a number of scaling
problems due mainly to the high silica content.

Mannvit was engaged to design and construct a pilot plant and to conduct two
initial tests to investigate the likelihood and severity of silica and other scaling
in different conditions. GEOKEM was engaged to review the results of these
pilot plant tests.

Documents available to GEOKEM were:

• Design, construction and testing Final Report. Mannvit. Document


Number: 5692127-000-MRP-0006

• Test 1. Results of Measurements. Mannvit. Document Number


5692127-000-MRP-0004

• Test 2. Results of Measurements. Mannvit. Document Number


5692127-000-MRP-0005

2.0 TEST1
2.1 EXPERIMENTAL
The first pilot plant test was for Options 1 and 4 from the original proposal.

Option 1 was to test a single flash and separation at a pressure of ~ 21 bara


(215°C) and a standard condensing turbine. Acid addition is into the two-phase
fluid before separation. Option 1 corresponds to Line 2 in the Mannvit PFD.

Option 4 was to test a single flash and separation at a pressure of ~ 21 bara


(215°C), followed by ORC bottoming of the steam and brine, with condensate
addition and acid dosing into the two-phase fluid. Option 4 corresponds to Line 1
in the Mannvit PFD.

As with setting up any pilot plant, there were some problems at the start of this
test:
• There was solid material being produced from the well causing pressure
variation
• The acid dosing into two-phase fluid was found to be causing severe
corrosion and so dosing was then shifted into the brine after the separator
• A pressure transducer was found to be wrongly calibrated and the
separator was therefore operated at well below target
pressure/temperature.

The pressure transducer error was corrected after three days and the test was
restarted with replacement coupons, but the formation rock chips in the holdup
vessels were not replaced.
Review of Pilot Plant Tests – Dieng Page | 6
The automatic pH measurement system rapidly became inoperable due to sulfide
scaling and was replaced by manual periodic pH measurement. Brine from
various sample points was collected during the test. The test ran for 13 days. At
the conclusion of the test, coupons were withdrawn and analysed and the rock
chips in the holdup vessels were also analysed.

2.2 RESULTS
General
Unfortunately, the data records could not be recovered from the datalogger.
However, pressures, temperatures and pH from the screenshot data were
reasonably constant throughout the test, although it appears that the acid dosing
was halted for ~ 12 hours between the dates of 1st and 2nd of May due to dosing
pump problems.

Shifting the acid dosing to the separated brine from the two-phase fluid meant
that the acid was then dosed at a pressure of ~ 21 bara (215°C). With a silica
concentration of 1130 - 1145 ppm, the separated brine is already oversaturated
with respect to amorphous silica and silica polymerisation to colloidal silica will
probably have commenced. As the voluminous silica scaling is due to colloidal
silica, and the acid is added to delay silica polymerisation, the acid needs to be
added to the brine before silica polymerisation commences. The silica saturation
temperature (SST) is the temperature at which the silica concentration in the
separated brine just reaches amorphous silica solubility. The SST for HCE-7C is
estimated to be 222°C from TFT and chemical data collected in September 2020.
The difference in concentration between the total silica (1145 ppm) and the
monomeric silica (1062 ppm) also indicates that the silica has already
polymerised. As well, the operational data shows that although the separated
brine was initially at 215°C, for much of the latter testing the temperature of the
separated brine was below 210°C, further increasing the silica saturation.

From the test data, assuming a dose rate of 2.5 vol% sulfuric acid of 7 litres/hour,
the calculated dose rate of 98% sulfuric acid required for a 25°C pH of 4.6 is
calculated to be 59 gms of 98% sulfuric acid per tonne of brine. This dose rate is
dependent on the chemistry of the brine and particularly on the bicarbonate
concentration in the separated brine.

Line 1 results
The acidified brine was passed through two heat exchangers, which Mannvit
called a Vaporizer and Preheater. After the two heat exchangers, condensate
was added to the brine. This setup is simulating a bottoming plant. The
temperature was reduced to ~ 100 °C in the ‘vaporiser’ and further to ~ 80°C in
the ‘preheater’. Condensate was added to the brine and then passed through the
holdup vessels. After exiting the holdup vessels, the temperature was ~ 70°C.

From the coupon data at C04 before the first heat exchanger, there is some silica
scaling just after acid dosing. The scaling rate is estimated as 0.5 – 1.4
mm/year. This may be due to the amount of polymerised silica present
throughout the test as mentioned above, or it could also be due to the increased
likelihood of silica polymerisation and scaling while the acid dosing pump was not
in service during the test. The SEM photomicrograph (Appendix D9 in test 1
report) is characteristic of spherical colloidal silica. The aluminium content in the

Review of Pilot Plant Tests – Dieng Page | 7


silica is high at this point. There is also some arsenic sulfide present. This would
not be expected at the temperature of the coupon and may be due to cooling and
deposition during shutdown. The morphology of the scaling (Appendix D7 in Test
1 report) is typical of colloidal silica scaling.

The scaling on the coupon (C05) exiting the first heat exchanger showed the
presence of silica (87wt%), antimony sulfide(10wt%) and arsenic sulfide (3wt%).
The reddish colour of the scale indicates that the antimony sulfide was present as
amorphous antimony sulfide, rather than crystalline stibnite. The exit
temperature of this heat exchanger was ~ 100°C. The antimony sulfide
concentration was ~ 3 times the arsenic sulfide concentration as expected due to
the lesser solubility of the antimony sulfide. From the photomicrograph Appendix
D11 Test 1 report), it appears that the bulk of the sample is large colloidal silica
spheres. Once again, it is difficult to tell whether the silica that is deposited is
due to the amount of polymerisation throughout the test, or to deposition during
the period of no acid addition. The small sulfide colloids on the surface of the
larger silica colloids would probably have been precipitated during plant
shutdown. This could be avoided by flushing the plant with fresh water before
shutting down. From the SEM analysis, there is no alumimium present in the
scale. This is expected from many previous experiments, where the initial silica
deposition quantitatively removes nearly all of the aluminium.

The scaling on the coupon (C06) exiting the second heat exchanger also showed
the presence of silica (51wt%), arsenic sulfide (46wt%) and antimony sulfide
(3wt%). The deposit had the typical yellow/orange colour of arsenic sulfide. The
exit temperature was 76 – 80 °C and the amount of scale was significant which
would severely impact regular electricity production from a bottoming plant with
these temperatures.

Scaling on the coupon (C07) after the holdup vessels showed only the presence
of silica (81wt%), and arsenic sulfide (19wt%). The amount of scaling was
significant. Slightly cooler condensate was added to the brine before entering the
holdup vessels. Although this dilutes the silica and reduces the SSI from ~4.6 to
~2.9 at 80°C, it has the effect of raising the pH and negating the purpose of
adding the acid to halt silica polymerisation. For a lot of the time, it also reduced
the temperature to ~70°C where the SSI is increased to ~3.3.

Line 2 results
Line 2 was testing Option 1 and this was simply separating at high
temperature/pressure and acidifying the brine. The coupon (C08) immediately
after acid dosing was composed of silica (79wt%), with some alumina (4 wt%)
and some corrosion products or background metal from the coupon. The amount
of scale deposited is similar to that observed in Line 1 before cooling.

The scale on the coupon (C09) after the holdup vessels was composed of silica
(66 wt%) and iron oxide (34%). Measured thickness was greater than that
observed before holdup. However, the degree of silica polymerisation (the
difference between total and monomeric silica) is the same within experimental
error between before and after holdup.

Review of Pilot Plant Tests – Dieng Page | 8


Again, it is difficult to tell whether the silica that is deposited in line 2 is due to the
amount of polymerisation throughout the test due to acidification after
polymerisation may been commenced, or to deposition during the period of no
acid addition.

3.0 TEST 2
3.1 EXPERIMENTAL
This test was to investigate Option 6 and a variation of Option 6. The target
conditions were an initial separation at 215°C followed by a second flash and
separation at 127°C. In Line 1, cold condensate was added to the brine and it
was then passed through the holdup vessels. The two heat exchangers in Line 1
were not connected. In line 2, no condensate was added and the brine was just
passed through the holdup vessels.

After four days, suspected severe scaling at the inlet to the second separator
caused the test to be halted.

3.2 RESULTS
General
Flows through Line 1 and Line 2 were reasonably constant throughout the test.
The pH varied a small amount but was always below pH = 5.0. The target
second flash temperature of 127°C became 132 – 139 °C. There seemed to be
a significant temperature drop through the holdup vessels in Line 2.

The two-phase brine was again separated at 215°C, which is below the silica
saturation temperature. Consequently, a significant proportion of the silica had
polymerised before acid was added to the brine, as witnessed by the difference
between the total silica and monomeric silica analyses. This difference is greater
than that measured in Test 1.

The pH is measured in the HP brine before the second flash. When the HP brine
is flashed to 132 °C, some CO2 is lost from the brine fraction and the pH
increases slightly. From the information in Table 4 in the Test 2 report, the pH
rises from 4.5 to 5.0. Consequently, the target pH in the brine to be tested is
greater than the target pH.

From the data given, the required dose rate of 98% sulfuric acid is calculated to
be 55 gms of 98% sulfuric acid per tonne of brine, which is similar to that
calculated for Test 1.

Line 1 results
Unfortunately, no chemical samples were taken of the undiluted brine at 137°C in
either line 1 or line 2. The calculated total silica concentration is 1354 ppm in
the brine from the LP separator. The brine at 137°C was then diluted by ~ 45%
with condensate at 47°C. This reduced the Silica Saturation Index (SSI) from
2.47 at 137°C to 2.36 at 95°C. However, once again, in the process of dilution,
the pH was raised from ~ 5.0 to ~6.3. This rise in pH allows the silica to start
polymerising and silica to deposit in the holdup vessels. Consequently, the
addition of the condensate is having a detrimental effect on silica scaling.

Review of Pilot Plant Tests – Dieng Page | 9


The scaling on the coupon in the 137°C brine (C04) consisted of almost 100%
silica, as did the coupon after the holdup vessels (C07). However, the amount of
scaling after the holdup vessels was much greater than that on the C04 coupon.
From the SEM photomicrographs, the silica colloids deposited after the holdup
vessels are ~ 50% of the diameter of those deposited on coupon C04 before
condensate was added. This indicates a more rapid silica polymerisation after
the condensate was added – presumably due to the pH increase.

Analyses of the brine before and after the packed bed in Line 1 (Table 9 in test 2
report) show that there has been a significant deposition of silica onto the
formation material in the bed.

Line 2 results
The analysis of the separator sample from S01 shows a large difference between
the total silica and monomeric silica analyses, which indicates significant silica
polymerisation. There is even greater silica polymerisation shown in the sample
from the outlet (S24). The difference probably occurs due to growth of the silica
particles in the holdup vessels. The energy required for a silica monomer to
attach to a colloid is much less than that required to form a nucleus of a new
colloid. On both the inlet (C08) and outlet (C09) coupons, the scale consists of
essentially pure silica. The amount of scale on each coupon would probably be
prohibitive in a production scenario. The morphology of the surface in the C08
coupons is very typical of colloidal silica deposition. The SEM photomicrographs
confirm the colloidal nature of the scale on both the input and output coupons.

There were no brine analyses for the inlet and outlet of the packed bed in Line 2.
From the photos of the packed bed, it appears that most of the silica was
deposited on the bottom of the packed bed.

4.0 DISCUSSION

Unfortunately, neither Test 1 and Test 2 are valid tests of pH modification to


delay silica polymerisation. Acid needs to be added to the brine before silica
polymerisation commences, that is before the brine reaches its silica saturation
temperature (SST). Thermochem data for a complete TFT and brine and steam
sampling for HCE-7C are available for samples collected on 20/9/2020. Using
this data, the calculated SST for HCE-7C is 222°C (24 bara). In future pilot plant
tests, it would be prudent to allow a slightly greater separation temperature than
222°C to allow for variations in the chemical data, variations in the operation of
the plant and the possibility of alumino-silicate deposition. This latter can cause
an aluminium rich silica scale at temperatures above the silica saturation
temperature.

HCE-7C has a calculated quartz geothermometer temperature of between 320°C


and 330°C for the reservoir brine. The recent TFT and chemical sampling on
29/9/20 gave a calculated quartz geothermometer temperature of 328°C.
However, this does not equate to the measured TFT discharge enthalpy of 1426
kJ/kg measured at the same time, instead of 1511 kJ/kg for liquid water at 328°C.
Regardless, at these temperatures the silica concentration in the reservoir liquid
is close to a maximum value. Consequently, testing at HCE-7C is close to a

Review of Pilot Plant Tests – Dieng Page | 10


worst possible case for silica scaling. Other wells that may be included in the
Unit 2 and 3 development may have lesser silica concentrations.

Addition of condensate to the acid treated brines caused a rise in pH to a value


where silica polymerisation is likely. This probably led to an increase in silica
scaling by colloidal silica. The brine dilution gave only a very small reduction in
the silica saturation index, as the temperature was also reduced. It cannot be
recommended for a flash operation, as it would normally contain oxygen unless a
surface condenser is utilised. The introduction of oxygen can cause corrosion in
carbon steel and can also oxidise Fe2+ to Fe3+. The ferric ion (Fe3+) greatly
increases silica scaling as it causes coagulation of silica colloids.

In a dual flash arrangement when the brine is flashed from HP to LP, acid gases
are lost to the vapour phase and the pH of the resultant LP brine is raised.
Consequently, in order to maintain a pH of 4.6 in the LP brine, the pH of the HP
brine after acid addition will need to be lower than 4.6. Alternatively, two-stage
acid dosing in both HP and LP brine may be utilised. A calculation shows that in
order for a pH25 of 4.6 in the LP brine at 150°C, a pH25 of ~ 4.4 is required in the
HP brine before flashing.

As expected, when the acidified brine is conductively cooled, arsenic and


antimony amorphous sulfides are precipitated. The arsenic concentration in the
brine is relatively high and the arsenic sulfide scaling could be significant in a
conventional ORC binary plant. Antimony sulfide scaling normally occurs before
arsenic sulfide scaling, as it did in these pilot plant tests. However, it appears
that the antimony concentration is relatively low in the Dieng brines, and the bulk
of the sulfide scaling is due to arsenic. The fact that only a small amount of
arsenic sulfide scaling is present on the coupon after the first heat exchanger
where the temperature is ~ 100°C, could mean that raising the temperature to
say 120°C would eliminate the voluminous arsenic sulfide scale.

Because arsenic and antimony sulfides are precipitated from cooled acidified
brine, sampling of acidified brine for arsenic and antimony can be difficult. As
suggested previously, the samples for As and Sb analysis should have been
preserved in caustic solution. As well, the samples should be collected at as high
a temperature as possible while still preventing flashing, and at a high flow rate.
Samples collected during tests 1 and 2 will return arsenic and antimony analyses
that are incorrect due to incorrect sampling and preservation.

As pH measurement is restricted to low temperatures, sulfide scaling can be


expected in the conditioning line prior to pH measurement, and on the pH
electrodes. In a production scenario, dual pH meters are utilised, where each
electrode swaps between a duty cycle and a wash and clean cycle.

Unfortunately, coupons were not installed in the turnarounds in the first heat
exchanger as recommended. Consequently, it is not defined at what
temperature the arsenic and antimony sulfides started to deposit. The
geochemical thermodynamic data for the amorphous antimony and arsenic
sulfides are not well defined, and consequently, the temperature at which they
might start to deposit cannot be reliably calculated. This becomes important if
subsequent flashes of acidified brine are contemplated.

Review of Pilot Plant Tests – Dieng Page | 11


The data from the packed bed is equivocal and difficult to interpret in regard to
how the brine will react with the injection formation. Unfortunately, there is only
one set of brine analyses before and after the packed bed that includes a silica
analysis (Test 2 Packed Bed 1 - Table 9). From the appearance of the rock
samples where the brine initially meets the packed bed, there definitely seems to
be some silica precipitation. What this means in terms of the useful life of a
reinjection well is hard to determine. However, acidified brine will probably
eventually react with the formation and injectivity will decline. The only question
is how long it takes before the injection well requires treatment or replacement.
The acidification of the brine only delays the silica polymerisation. If the brine
can penetrate a large distance into the formation from the well before the silica
polymerises, then the injectivity decline may be slow. However, it will then be
more difficult to recover the injectivity with, for instance, hot caustic dissolution of
the silica deposited. As well as the kinetics of the silica polymerisation and
deposition, the acidified brine can also react with the rocks in the formation to
neutralise the acid and allow silica polymerisation. This reaction can be quite
rapid if calcite is present. Consequently, pH modification is not a completely risk-
free option. The only risk-free option would be separation at a temperature above
the SST where no silica or alumino-silica deposition is occurring, followed by hot
injection of the brine without further temperature loss. However, this approach
reduces the thermal efficiency of the plant compared with dual flash or binary
options.

If the initial separation temperature is at or above 222°C, then there will be a


small but significant silica concentration dissolved in the steam phase. This is
due to the distribution of silicic acid into the vapour phase and is independent of
the separator efficiency. This silica can cause silica deposition on the turbine
blades, which can lead to failure of the turbine. Unfortunately, silica was not
analysed in the condensate sample during the tests. The relatively high
concentrations of silica in the produced fluid and the high separation temperature
mean that some form of steam-wash facility will be required to condition steam
before entering the steam turbine.

Acid consumption for HCE-7C brine separated at ~ 215°C is calculated to be 55


– 60 ppm of 98% sulfuric acid. The amount of acid required for other wells is
dependent mainly on the bicarbonate concentration of the well, and may be
different to HCE-7C.

The testing proved that acid injection into the two-phase line is not feasible due to
severe corrosion.

5.0 RECOMMENDATIONS
The severity of the arsenic sulfide scaling would appear to make a conventional
ORC binary plant less desirable than a conventional flash plant. Consequently,
future pilot plant testing should initially concentrate on defining possible flash
plant operation parameters.

It is recommended that tests be conducted to determine the first stage separation


temperature above the SST to enable acid addition to the brine before silica

Review of Pilot Plant Tests – Dieng Page | 12


polymerisation commences. These tests should run for at least one week in
order to obtain conclusive results.

In separate experiments, determine the lowest separation temperature for


second stage separation of acidified brine that gives acceptable operation for
scaling and corrosion. This test will also define the required pH of the HP brine
to produce the test pH in the LP brine.

After sufficient tests have confirmed parameters for a flash development, repeat
the heat exchanger tests to find the temperature at which the arsenic sulfide
starts precipitating. Possibly with coupons in the turnarounds in the first heat
exchanger.

Measure the silica concentration in the steam condensate at the initial separation

There is a technique available where the acidified brine is reacted with drill
cuttings from the formation in a flow-through autoclave. This technique can
possibly clarify interaction with the formation, but will not categorically define the
life of a reinjection well. This may be worth investigating in place of the packed
bed experiments.

It is recommended that at the end of each test, the plant is flushed with water to
prevent silica and sulfide deposition on the coupons as the plant is closed down.

Review of Pilot Plant Tests – Dieng Page | 13

You might also like