ASH RAE Guideline 1.

4-2014


roce ures or ar1n
stems

Approved by the ASH RAE Standards Committee on June 28, 2014, and by the ASH RAE Board of Directors on July 2, 2014.

ASHRAE Guidelines are scheduled to be updated on a five-year cycle; the date following the guideline number is the year of
ASHRAE Board of Directors approval. The latest edition of an ASHRAE Guideline may be purchased on the ASHRAE website
(www.ashrae.org) or from ASHRAE Customer Service, 1791 Tullie Circle, NE, Atlanta, GA 30329-2305. E-mail:
orders@ashrae.org. Fax: 678-539-2129. Telephone: 404-636-8400 (worldwide) or toll free 1-800-527-4723 (for orders in US and
Canada). For reprint permission, go to www.ashrae.org/permissions.

© 2014 ASHRAE ISSN I 049-894X

American Sociely ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduciion or networking permitted wilhout license from IHS
ASHRAE Standing Guideline Project Committee 1.4
Cognizant TC: TC 7.9, Commissioning
SPLS Liaison: Janice C. Peterson
Gerald J. Kettler, Chair* Justin Foster Garner • Jean-Francois Pelletier•
Bradley A. Brooks • Richard D. Hermans Ole Teisen (consultant)
Thomas E. Cappellin • Michael Khaw Shallen Verma •
Charles E. Dorgan• Michael J. King •
Harry J. Enck • Angela M Lewis

*Denotes members of voting status when the document was approved for publication

ASHRAE STANDARDS COMMITTEE 2013-2014


William F. Walter, Chair David R. Conover Malcolm D. Knight
Richard L. Hall, Vice-Chair John F. Dunlap Rick A. Larson
Karim Amrane James W. Earley, Jr. Mark P. Madera
Joseph R. Anderson Steven J. Emmerich Cyrus H. Nasseri
James Dale Aswegan Julie M. Ferguson Janice C. Peterson
Charles S. Barnaby Krishnan Gowri Heather L. Platt
Steven F. Bruning Cecily M. Grzywacz Douglas T. Reindl
John A. Clark Rita M. Harrold Julia A. Keen, BOD ExO
Waller S. Clements Adam W. Hinge Thomas E. Werkema, Jr., CO
Debra H. Kennoy

Stephanie C. Reiniche, Manager of Standards

SPECIAL NOTE

This Guideline was developed under the auspices of ASH RAE. ASHRAE Guidelines are developed under a review process, identifying
a guideline for the design, testing, application, or evaluation of a specific product, concept, or practice. As a guideline it is not definitive but
encompasses areas where there may be a variety of approaches, none of which must be precisely correct. ASH RAE Guidelines are written
to assist professionals in the area of concern and expertise of ASHRAE's Technical Committees and Task Groups.
ASHRAE Guidelines are prepared by project committees appointed specifically for the purpose of w riting Guidelines. The project
committee chair and vice -chair must be members of ASHRAE; while other committee members may or may not be ASHRAE members, all
must be technically qualified in the subject area of the Guideline.
Development of ASHRAE Guidelines follows procedures similar to those for ASHRAE Standards except that (a) committee balance is
desired but not required, (b) an effort is made to achieve consensus but consensus is not required, (c) Guidelines are not appealable, and
(d) Guidelines are not submitted to ANSI for approval.
The Manager of Standards of ASHRAE should be contacted for:
a. interpretation of the contents of this Guideline,
b. participation in the next review of the Guideline,
c. offering constructive criticism for improving the Guideline, or
d. permission to reprint portions of the Guideline.

DISCLAIMER
ASHRAE uses its best efforts to promulgate Standards and Guidelines for the benefit o f the public in light of available information and
accepted industry practices. However, ASH RAE does not guarantee, certify, or assure the safety or performance o f any products, components,
or systems tested, installed, or operated in accordance with ASHRAE's Standards or Guidelines or that any tests conducted under its
Standards or Guidelines will be nonhazardous or free from risk.

ASHRAE INDUSTRIAL ADVERTISING POLICY ON STANDARDS


ASHRAE Standards and Guidelines are established to assist industry and the public by offering a uniform method of testing for rating
purposes, by suggesting safe practices in designing and installing equipment, by providing proper definitions of this equipment, and by providing
other information that may serve to guide the industry. The creation of ASH RAE Standards and Guidelines is determined by the need for them ,
and conformance to them is completely voluntary.
In referring to this Standard or Guideline and in marking of equipment and in advertising, no claim shall be made, either stated or implied,
that the product has been approved by ASHRAE.

American Sociely ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZ ATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduciion or networking permitted wilhout license from IHS
CONTENTS
ASHRAE Guideline 1.4-201 4,
Procedures for Preparing Facility Systems Manuals
SECTION PAGE
Foreword ......................................................................................................................................................................................... 2
1 Purpose ................................................................................................................................................................................ 2
2 Scope ................................................................................................................................................................................... 2
3 Definitions ............................................................................................................................................................................. 2
4 Systems Manual Content and Organization ......................................................................................................................... 4
5 Use of the Systems Manual ................................................................................................................................................. 6
6 Predesign- and Planning-Phase Functions .......................................................................................................................... 7
7 Design· and lnvestigation..Phase Functions ......................................................................................................................... 8
8 Construction- and Implementation-Phase Functions............................................................................................................ 9
9 Occupancy- and Operations-Phase Functions ................................................................................................................... 1O
1O Existing Building Functions ................................................................................................................................................. 11
11 Computerization and Interface with Other Programs .......................................................................................................... 12
Informative Annex A-Systems Manual Documentation Flowchart...................... .................................................................... 13
Informative Annex B-Systems Manuals Process Contract Requirements............ .................................................................. 14
Informative Annex C-Roles and Responsibilities.................................................................................................................... 15
Informative Annex D-Systems Manual Executive Summary ................................................................................................. 16
Informative Annex E-Owner's Project Requirements (OPR) and Current Facility Requirements (CFR) ................................ 17
Informative Annex F-Commissioning Plan ............................................................................................................................. 21
Informative Annex G-Basis of Design (BoD) ·························································································································· 23
Informative Annex H-Construction/Project Record Documents Process............ .................................................................... 25
Informative Annex I-Project Documents and Submittal Review Reports............ .................................................................... 26
Informative Annex J-Building and Equipment Specifications ................................................................................................. 29
Informative Annex K-Approved Submittals ............................................................................................................................. 30
Informative Annex L-Manufacturer's Operation and Maintenance (O&M) Data .. ................................................................... 31
Informative Annex M-Warranty Information···························································································································· 32
Informative Annex N-Contractor and Supplier Listing and Contact Information .. ................................................................... 33
Informative Annex 0-Facility Guide········································································································································ 34
Informative Annex P-Facility Operating Plans ........................................................................................................................ 36
Informative Annex Q-Building Operation Schedules and Setpoints ...................... ................................................................. 37
Informative Annex A-Maintenance Plan, Procedures, Checklists, Schedules, and Records················································· 43
Informative Annex S-Ongoing Commissioning and Recordkeeping with the Systems Manual. ............................................. 46
Informative Annex T-Janitorial and Cleaning Plans and Procedures ................. .................................................................... 48
Informative Annex U-Utility Measurement and Reporting, Maintenance and Verification (M&V) Plans ................................. 50
Informative Annex V-Use of Systems Manual in Training ..................................................................................................... 59
Informative Annex W-lssues and Resolution Logs ................................................................................................................. 63
Informative Annex X-Commissioning Process Progress Report and Testing Records and Reports ..................................... 64
Informative Annex Y-lndustry Resources ............................................................................................................................... 66
Informative Annex Z-References ............................................................................................................................................ 67

I
'
NOTE

Approved addenda, errata, or interpretations for th is guideline can be downloaded free of charge from the ASH RAE
Web site at www.ashrae.org/technology.

© 2014 ASHRAE
1791 Tullie Circle NE - Atlanta, GA 30329 · www.ashrae.org · All rights reserved.
ASHRAE is a registered trademark of the American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
ANSI is a registered trademark of the American National Standards Institute.

American Sociely ol Healing, Refrigeraling and Ait·Condilioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduclion or networking permitted wilhout license from IHS
(This fore\\1ord is not part of this standard. It is merely For e.xistingfacilities, the Syste,ns Manual lvill have rnul-
informative and does not contain requirements necessary tiple sections, depending on the O,,vner 's Current Facility
for conformance to the standard. It has not been pro- Requirernents and the nu111ber o_f syste,ns focused on during
cessed according to the ANSI requirements for a standard the.facility develop,nent, renovation, or repair process.
and may contain material that has not been subject to The for1nat and content ofthe Syste,ns Manual provided
public revie\\' or a consensus process. Unresolved objec- in this guideline can be effectively used in both neiv construc-
tors on informative material are not offered the right to tion and .for an existing building, even (f the building is not
appeal at ASHRAE or ANSI.) com,nissioned.

FOREWORD Systems Manual Documentation Collection


A Systerns lvfanual contains inforrnation and docurnentation Requirements
on a building 's planning, design, construction, and cornrnis- The Syste,ns Manual process captures project require,nents,
sioning, along lvith operational requirernents, rnaintenance design docu,nentation, construction details, evaluation and
inforrnation, training and testing docurnentation .for the use of testing results, and training progra,ns as the i11;for1nation
building operations, and rnaintenance and optirnization o_f the beco,nes available. Additionally, the reco1n1nended operating
facility over its useful life. and rnaintenance procedures and ongoing docu1nentation
Developing the Systems J\fanual encompasses gathering require,nents are assen1bled and included. Changes to the
if!forrnation fro,n the .facility, planning, design, construction, ,nanuals are expected as the building rnaintenance ~yste,ns
testing, comrnissioning, and training activities and adding are developed and changes to the Jysterns occur.
operations and maintenance if!for,nation to create a usable The arrangement o_f the Syste,ns Manual sholvn in Sec-
if!forrnation resource. This resource includes .final project tion 4 is based on collection o_f docu,nentation during the nor-
documentation, including 01vner's Project Require,nents 1nal construction process. It is also acceptable to arrange the
(OPR), Basis o_f Design, the final Corn,n issioning Plan, Com- documentation by syste1n if that is the 01vner's preference.
rnissioning Progress Reports, sub,nittals, ,nanufacturer instal- This systern arrange,nent ,nay require substantial additional
lation ,nanuals, 1naniifacturer Operation and Maintenance titne and docu,nentation ejfiJrt to rearrange the i11;formation
(O&J\1) ,nanuals, syste,n sche,natics, record dra,,vings, check- and should be spec(fied at the titne o_f OPR development.
lists, inspections, testing results, and training and other rele-
vant 1naterials. This infor,nation is edited and organized to 1. PURPOSE
focus on key syste,ns (roofing, ,valls,fire alarm, chilled 1vate1;
This guideline provides procedures for producing a Systems
hot 111ate1; etc.) in the .facility. Coordination 1vith O&J\1 per-
Manual as a resource for training, operations, 1naintenance,
sonnel in developing standard for,nats and divisions (shops)
and upgrading of facilities .
is accornplished to si,nplify_future Syste,ns J\1anual revisions. ·,

It is the intent that the Systems Manual be asse,nbled in 2. SCOPE


electronic .forn1at to facilitate access and reduce storage
require,nents. The electronicjor,nat also reduces the possibil- This guideline applies to information fro1n planning, co1nmis-
ity o_floss o_fparts or all ofthe information. For Systems Man- sioning, design, construction, testing, and training activities,
uals assen1bled in hardcopy_format, la,ger docu,nents such as and operations planning for new, renovated, and existing
record dra,vings, spec(fications, sub,nittals, and O&M docu- facilities, equipn1ent, and assemblies.
1nents can be stored in secure locations, 1vith these locations
referenced in the Systems Manual. 3. DEFINITIONS
Also included in the Syste,ns Manual is the develop,nent acceptance: a formal action, taken by a person \Vith appropri-
ofperiodic ,naintenance and if!for,nation for insertion into a ate authority (\vhich may or ,nay not be contractually defined)
co,nputer ,naintenance 1nanage1nent syste,n, including equip- to declare that so,ne aspect of the project ,neets defined
1nent ,nake and rnodel, checking require,nents, ,naintenance require,nents, thus permitting subsequent activities to pro-
require,nents, and troubleshooting ite,ns. ceed.
ff the Syste,ns Manual is asse,nbled during a co1n1nis- Bllsis ofDesig11 (BoD): a docu1nent that records the concepts,
sioning process, the Co1n1nissioning Authority (CxA) should calculations, decisions, and product selections used to meet
be responsible for evaluating the developrnent of· the Syste,ns the Owner's Project Requirements (OPR) and to satisfy appli-
Manual. At other ti,nes, the responsible person or agency lvill cable regulatory requiren1ents, standards, and guidelines. The
be designated by the Olvner. docu1nent includes both narrative descriptions and lists of
The entity responsible .for developing the Systerns A1an- individual items that support the design process.
ual should include all ite,ns involved in the project and cap-
checklists: project- and ele,nent-specific checklists that are
ture the systern and assernb~y data in either an electronic or
developed and used during all phases of the Co,nmissioning
printed version. In addition, printed operations, service,
Process to verify that the OPR is being achieved. Checklists
rnaintenance, spare parts lists, and repair rnanuals ,nay be
are used for general evaluation, testing, training, and other
provided. This entity (Olvner, contractor, design professional,
design and construction require,nents.
CxA, other) shall have the skills of design, construction, and
operations required to develop a cohesive Systerns Manual. co111111issio11i11g (Cx): see Co,nrnissioning Process.

American Socie~ ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS4nder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
Con1111issio11i11g Authority (CxA): an entity identified by the operated. This includes goals, 1neasurable perfonnance crite-
Owner v,,ho leads, plans, schedules, and coordinates the co1n- ria, cost considerations, bench1narks, success criteria, and
1nissioning team to i1nple1nent the Co1n1nissioning Process. supporting information to rneet the requirernents of occu-
pants, users, and owners of the facility.
Co111111issio11.ing Pl,111 (Cx Plan): a docu,nent that outlines the
organization, schedule, allocation of resources, and docwnen- design checklist: a fonn developed by the Cornrnissioning
tation require1nents of the Com1nissioning Process. Team to verify that elements of the design are in compliance
Con1111issio11i11g Process (Cx Process): a quality-focused pro- with the Owner's Project Requirements (OPR). See also,
cess for enhancing the delivery of a project. The process checklists.
focuses on verifying and docu,nenting that all of the co1nmis- design review
sioned systems and assemblies are planned, designed,
desig11 revieJv, code or regullltory: a revie,v of a docu-
installed, tested, operated, and 1naintained to 1neet the OPR or
1nent conducted by staff or designated entity of an
Cw-rent Facility Requiretnents (CFR).
Authority Having Jurisdiction (AHJ) to determine
Con1111issio11.b1g Process Activilies (Cx Process Activities): whether the content of the document complies with regu-
co1nponents of the Co1nmissioning Process. lations, codes, or other standards administered by the
Con1111issio11i11g Process Progress Report (Cx Process Prog- jurisdiction.
ress Report): a \.vritten doctunent that details activities com- design revieH', co111missio11i11g: a review of the design
pleted as part of the Co1nmissioning Process and significant docu1nents to detennine co1npliance with the Owner's
findings fro1n those activities and is continuously updated Project Requirements (OPR), including coordination
during the course of a project. between syste1ns and assernblies being co,nmissioned,
Con1111issio11i11g Tea,n (Cx Tea,n): the individuals and agen- features and access for testing, com1nissioning and main-
cies ,vho, through coordinated actions, are responsible for tenance, and other revie,vs required by the OPR and
implementing the Co1nmissioning Process. Co1n1nissioning Plan.

co111111issio11i11g testing: the evaluation and docu1nentation of design revie•v, constructability: the review of effective
the equiptnent and assemblies, delivery and condition, instal- and tirnely integration of constn1ction kno\.vledge into the
lation, proper function according to the manufacturer's speci- conceptual planning, design, constntction, and field oper-
fications, and project documentation to 1neet the criteria in the ation of a project to achieve project objectives efficiently
O,vner's Project Requirements. and accurately and at the 111ost cost-effective levels to
reduce or prevent errors, delays, and cost overruns.
co11str11ctio11 checklist: a fonn used by the comtnissioning
design revie•v, peer: an independent and objective tech-
team to verify that appropriate 1naterials and components are
nical review of the design of the project or a part thereof,
on-site, ready for installation, correctly installed, functional,
conducted at specified stages of design cornpletion by
and in con1pliance with the OPR. See also, checklists.
one or more qualified professionals for the purpose of
co11str11ctio11 docu111e11ts: includes a wide range of docu- enhancing the quality of the design.
ments, which \.viii vary frotn project to project and with the
O,vner's needs and regulations, laws, and jurisdictional evlli1tlltio11: the process by which specific docu1nents, con1po-
requirements. Construction documents usually include the nents, equiptnent, assetnblies, syste1ns, and interfaces a1nong
project 1nanual (specifications), plans (drawings), and general systems and their perfonnance are confirmed with respect to
terms and conditions of the contract. the criteria required in the Owner's Project Requirernents
(OPR).
contract doc11111e11ts: a wide range of documents, which will
vary from project to project and with the Owner's needs, reg- existing buildi11g Co111111.issio11i11g Process (existing building
ulations, laws, and jurisdictional requiretnents. Contract doc- Cx Proces!.): a quality-focused process for attaining the Cur-
tunents frequently include price agree,nents, construction rent Facility Requiren1ents (CFR) of an existing facility and
management process, subcontractor agreernents or require- its syste1ns and assetnblies being co1n1nissioned. The process
ments, requirements and procedures for submittals, changes, focuses on planning, investigating, irnplernenting, verifying,
and other construction require1nents, ti1neline for co1npletion, and documenting that the facility and/or its syste1ns and
and the construction docu1nents. assemblies are operated and 1naintained to meet the CFR,
with a program to 111aintain the enhancen1ents for the remain-
coordi11atio11 drawi11gs: drawings showing the work of all ing life of the facility.
trades to illustrate that equipment can be installed in the space
allocated ,vithout compro1nising equip1nent function or facility guide: a basic building syste1n 's description and oper-
access for 111aintenance and replace1nent. These dra,vings ating plan with general procedures and confirmed facility
graphically illustrate and di1nension 1nanufacturers' recotn- operating conditions, setpoints, schedules, and operating pro-
mended maintenance clearances. cedures for use by facility operations to properly operate the
facility.
Current Facility Req11iren1e11ts (CFR): a written docun1ent
that details the current functional requirements of an existing ji.11lll Co111n1issio11ing Report {finlll Cx Repo,1): a document
facility and the expectations of how it should be used and that records the activities and results of the Co1n1nissioning

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~~~m!#Ml-U.e I .4 -LU 14 Nol for Resale, 201515/28 09:22:15 3
No rep1oduciion or networking permitted wilhout license from IHS
Process and is developed from the final Com1nissioning Plan 111ents, and docun1entation of building design and construc-
with all of its attached appendices. tion, along with testing and training docrnnentation,
issues and resolution log: a formal and ongoing record of operational requirements, and maintenance infonnation for
proble1ns or concerns and their resolutions that have been the use of building occupants, operators, and maintenance
raised by n1en1bers of the Com1nissioning Tea1n during the staff, and for optimization of the facility perfonnance over its
course of the Co1n1nissioning Process. useful life.
The fonnat and content of the Syste,ns Manual provided
011goi11.g Co111111.issio11i11g Process (OCx Process): a continu- in this guideline can be effectively used in both new construc-
ation of the Con1n1issioning Process well into occupancy and tion and for asse1nbling a Systen1s Manual for an existing
operations to continually i1n prove the operation and perfor- building, even if the building is not con1n1issioned.
1nance of a faci lity to meet current and evolving CFR or OPR.
OCx Process activities occur throughout the life of the faci lity; 4.2 Systems Manual Content Preparation. The Syste111s
some of these will be close to continuous i1nplementation and Manual is intended to
others will be either scheduled or unscheduled as needed. a. provide necessary infonnation to the facility occupants
Opera.tiou and Mai11ten,u1ce (O&M) Manual: the doctunen- and operating staff, and the 111aintenance function to
tation, usually in generic form, that the manufacturers provide understand the design and construction of the facility
to install, operate, and/or 111aintain a specific piece of equip- (new or existing) and how to operate and ,naintain the
1nent or specific assembly. building;
b. asse111ble the facility planning, design, constn1ction, and
Owner's Project Require111e11ts (OPR): a \.Vritten docrnnent
testing results for building syste,ns in one set of docu-
that detaiIs the requirements of a project and the expectations of
1nents and provide the fonnat for the updating of this
how it will be used and operated. This includes project goals,
information;
111easurable perfonnance criteria, cost considerations,
c. provide a docun1entation source to be used in training
benchrnarks, success criteria, and supporting information.
111aterials ·, and
(The tenn prqject intent or design intent is used by some
d. provide docu1nentation for building perfonnance
Owners for their Cornmissioning Process OPR.)
improve1nent and ongoing com1nissioning.
p erfor111ance test (P1): the process used to verify that a 1nate-
rial, product, assernbly, or syste1n meets defined performance 4.3 Systems Manual Documentation Organization
criteria. The methods and conditions under which perfor- 4.3. 1 The Syste,ns Manual process captures project
1nance is verified are described in one or 111ore test protocols. requirements, design and construction documentation, evalu-
ation and testing results, and training programs as the infor-
reco111111issio11i11g: an application of the Comtnissioning Pro-
1nation bec.0111es available. Additionally, the reco111111ended
cess requirements to a project that has been delivered using the
operating and ,naintenance procedures and ongoing docu-
Com1nissioning Process. (See existing building Co1111nission-
mentation requirements are assembled and included. Changes
ing Process.)
to the manuals are expected as the building maintenance sys-
retroco111111issioni11g: the Comtn issioning Process applied to tems are developed and changes to the systen1s occur.
an existing fac ility that was not previously commissioned. 4.3.2 The Syste,ns Manual should be organized as follows.
(See e.xisting building Co1111nissioning Process.) The six major docrnnentation assembly subjects are labeled
Syste111s Manual: a system-focused co,nposite doctunent that as "Parts" of the Systems Manual in this guideline. These
includes the design and construction docrnnentation, facil ity headings may also be called sections, chapters, divisions or
guide and operation manual, 111aintenance infonnation, training another tenn that is cotnpatible with the project docu111enta-
information, Com1nissioning Process records, and additional tion requirements.
infonnation of use to the Ov;ner during occupancy and opera-
tions. Part 1. Executive Summary
Part 2. Facility Design and Construction
test procedure: a ,vritten protocol that defines 111ethods, person-
2. 1 Owner's Project Require111ents
nel, and expectations for tests conducted on components,
2.2 Basis of Design R.equire1nent
equipment, assemblies, syste,ns, and interfaces among sys-
2.3 Facility/Project Design and Record Docu1nents
te,ns to verify cornpliance with the Owner's Project Require-
(or directions to their location)
n1ents (OPR).
Part 3. Building, Systems, and Assemblies
training plan: a written docu111ent that details the expecta- Information
tions, schedule, duration, and deliverables of Com,nissioning 3.1 Facility and Equip,nent Specifications
Process activities related to training of project operating and 3.2 Approved Submittals
111aintenance personnel, users, and occupants. 3.3 Coordination Dra,vings
3.4 Manufacturer's Operation and Maintenance
4. SYSTEMS MANUAL CONTENT AND (O&M) Data
ORGANIZATION 3.5 Warranties
4.1 Introduction. The Systen1s Manual contains information 3.6 Contractor/Supplier Listing and
on the Owner's initial and current facility and project require- Contact lnfonnation

American Sociel~ ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS'f.lnder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
Part 4. Facility Operations or describe locations of record drawings and
4.1 Facility Guide (including Operating Plan; Facil- documents. Digitized Systen1s Manuals can also
ity and Equip,n ent Operating Schedules; Set- contain copies of the record documents and 111in-
points, Ranges, and Limitations; Systems imize the loss of these doctunents.
Operation Control Sequences of Operation; and Part 3. Facility, Systems, and Assemblies
E,nergency Procedures) Information
4.2 Maintenance Plans, Procedures, Checklists, and 3.1 Specifications: Insert final copy of facility and
Records equip1nent design specifications.
4.3 Maintenance Schedules 3.2 Approved Sub,nittals: Insert final copy of spe-
4.4 Ongoing Con11nissioning Operational and cific approved sub1nittals by specification sec-
Maintenance Record Keeping tion sequence, including a copy of final
4.5 Janitorial and Cleaning Plans and Procedures approved and comn1issioned sequences of oper-
4.6 Utility Measure1nent and Reporting ation for equip111ent and syste111s, along with
Part 5. Training limitations to operation.
5.1 Training Plans and Materials 3.3 Coordination Dralvings: Insert a copy, or desig-
5.2 Training Records nate the location of, the system installation
5.3 Syste1n Manual Maintenance and Documenta- coordination dra,vings and related information.
tion, including Operator's Ongoing Documenta- 3.4 Manufacturer's Operation and Maintenance
tion of Modifications and Adjust1n ents to the Data: Insert manufacturer provided installation
Facility Systems and Asse,n blies and O&M 111anuals that have been verified and
Part 6. Commissioning (Cx) Process Report localized to the installed building syste111 or
6.1 Executive Stunmary equip1nent by specification section sequence.
6.2 Cx Plan(s) 3.5 Warranties: Insert syste111 and equip111ent warran-
6.3 Cx Design and Sub,nittal Review Reports ties arranged by specification section sequence.
6.4 Testing and Start-Up Reports, Permits, Inspec-
3.6 Contractor/Supplier listing and Contact lnfor-
tions, Evaluation Checklists, and Testing
1nation: Insert a listing of all contractors and
Checklists Co1npleted for Co1n1nissioned Sys-
,najor suppliers, including address, phone, and
te1ns and Asse1nblies e-mail to facilitate repairs and replacements.
6.5 Cx Process Progress Reports Insert the design tea111 111e111bers listing along
6.6 Issues and Resolution Logs with contact infonnation to facilitate informa-
6.7 Ite1n Resolution Plan for Open Items tion transfer on original designs and mainte-
4.4 Sources and Content of the Documents nance and optimization.
in the Systems Manual Part 4. Facility Operations
Part 1. Executive Summary 4.1 Facility Guide (Operating Plan, Building and
The executive sum1na1y contains an overview of Equip,nent Operating Schedules, Setpoints and
the building design, construction, and opera- Ranges, Sequences of· Operation, Li,nitations,
tional requirements. The inforn1ation is intended and Ernergency Procedures Actions)
to provide general guidance on the intended
• Insert a copy of the completed facility operating
operation, perfonnance, and 111aintenance of the
plan v,rith explanations of the intended use and
building in confonnance to the Owner's Project
operation of the faci Iity.
R.equire111ents and/or Current Facility Require-
111ents (CFR). • Inse1t a copy of the final co1nmissioned sequences
Part 2. Facility Design and Construction of operation for all operating equip1nent.
2.1 Otvner 's Project Require,nents (OPR)/ Current • Insert a copy of final co1n1nissioned setpoints of
Facility Require,nents (CFR): Insert final copy all equip,nent with operational adjustments.
of OPR/CFR developed and revised during the Include the setpoint nonnal intended ranges and
project and Cx Process. This provides the opera- Iin1itations.
tions and 111.aintenance (O&M) staff, as well as • Insert a copy of routine 111aintenance require-
future o,vners, the inforn1ation on the original 111ents.
intent for the design and use of the facility.
• Insert a copy of e111ergency procedures and loca-
2.2 Basis o_f Design (BoD): Insert final copy of BoD
tions of applicable controls.
document and any other design information
developed during the project and Cx Process. 4.2 Maintenance Procedures, Checklists, and
This provides the O&M staff, as well as future Records: Insert procedures, fonns, and check-
owners, the infonnation on the design of the lists for facility operation and 1naintenance.
faci lity. Include updating require1nents. Describe inspec-
2.3 Construction/Project Record Docu,nents: Insert tions and testing required on a routine basis and
final progra111 and design docu111ents, and insert standard fonns required.
+4 . . . ........ .. . .• . ... . ..

Provided by IHS~~~m!#Ml-U.e I .
.A14~1W1ifing
Ame~can Sociely_..o)..);le?tina.,.B~ger<11.i.rJ:9 and
:u
Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 595661 7
5
Nol for Resale, 201515/28 09:22:15
No rep1oduciion or networking permitted wilhout license from IH S
4.3 Maintenance Schedules: Include recon11nended 6.3 Cx Design and Sub,nittal Revietv Reports:
1naintenance schedules for syste1ns and equip- Insert a copy of the Cx design and submittal
1nent along ,vith update require1nents. review reports.
4.4 Ongoing Cx Operational and Maintenance 6.4 Testing Reports, Per,nits, Inspections
Record Keeping: Include ongoing Cx and opti- • Insert co1npleted Cx Process Progress R.eport
1nization procedures and documentation to with documents and verification and testing
1nonitor and in1prove the performance of facility forms and records for each building and system
syste1ns. and asse1nbly included in the Cx Process. This
4.5 Janitorial and Cleaning Plans and Procedures: creates a record of all required testing contained
Insert a copy of facility cleaning and janitorial in the com1n issioning sections of the project
plan with procedures and intended che1nicals contract documents and perfonned during the
and equip1nent. project.
4.6 Utility A1easure,nent and Reporting • Insert manufacturers', testing agencies', and
contractors' reports.
• Include description of utility mete ring and mon-
• Insert ins tallers' and Cx authorities' completed
itoring syste1ns.
checklists. This provides a record of ins tallation
• Provide docutnent fonnats and procedures for checks and observations for future reference.
tracking utility use and reporting this infonna- • Insert installers' and Cx authorities' completed
.'' tion to 1neet Owner's and jurisdictional require- performance checklists of assemblies, equip-
ments. 1nent, and integrated systems. This provides a
• Include a copy of the facility 1neasurement and record of performance checks and observations
verification (M&V) plan if available. for future reference.
' • Insert relevant co1n1nissioned syste1n and
Part 5. Training
asse1nblies test reports.
5.1 Training Plans and Materials
6.5 Cx Progress Reports: Insert a copy of all Cx
• Include instructions and procedures for the use Progress Repo1is
of appropriate sections of the Syste1ns Manual 6.6 Issue and Resolution Logs: Insert a copy of all
for training of building O&M personnel and issue and resolution logs ,vith resolution or sta-
occupants. tus of each item. This provides a record of prob-
• Insert copy of training plans used for each type lems and issues found and resolved during the
of equip1nent along with session syllabus used. design and construction process for future refer-
ence.
• lnse1i training 1naterials used, arranged in speci-
6.7 Ite,n Resolution and Open Ite,ns: Insert a list of
fication seque nce. Describe location or sources
any open ite1ns and seasonal or additional test-
of available additional training.
ing required.
5.2 Training Records: Insert records of training,
5. UTILIZATION OF THE SYSTEMS MANUAL
schedules, s ign-in sheets, etc. Include copy of
training docwnentation and training recordings 5.l Introduction. The Systems Manual is the concise collec-
on the operation of the systetns and equipment tion of design, construction, testing, and operations inforn1a-
along with appropriate trouble shooting instn1c- tion, including updates and 111odifications to systems and
tion. assemblies as they occur during construction, renovation, and
5.3 Training/or Ongoing Syste,n Manual Updating operation. For con1missioned projects, the Co1nmissioning
(Cx) Tea1n shall be responsible for updating the Syste1ns
• Include training and documentation on the updat- Manual during the Cx Process, including design construction
ing and continued use of the Systems Manual. and operation as required in the Owner's Project Require-
• Insert copy and updates of operator's ongoing 111ents (OPR)/Current Facility Requiren1ents (CFR), Cx Plan,
docu1nentation of 1nodifications and adjust- and contract docu1nents. For existing building projects that do
1nents to the facility systen1s and assemblies. not involve com1nissioning, the building operating and main-
These docu1nents are updated as changes are tenance functions (staff or contractors) are responsible for
1nade to keep the Systems Manual current and developing, utilizing, and updating the Systems Manual.
relevant. 5.2 The information contained in the Syste1ns Manual is
given by the project and Cx tea1ns to provide essential infor-
Part 6. Commissioning (Cx) Process Progress Report
1nation needed by the operation and maintenance (O&M)
6.1 Executive Surn1na1y staff to understand, operate, and maintain the building's sys-
6.2 Cx Plan(s): Insert the final Cx plan and com- te1ns and asse1nblies, opti1nally operate the building, and pro-
pleted Cx report with evaluation and testing vide a system for docu1nenting modifications. While the
forms and records for each building and syste1n. amount of documentation in the Systems Manual is extens ive,

American Socie11ot Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZATION 595661 7
Provided by IHSQnder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
1nost of it is available from the non11al planning, design, con- O,vner defines the Systems Manual forn1ats, interface
struction, and Cx processes. Collecting this information as it requirements, and responsibilities. This should include devel-
becomes available greatly facilitates the assen1bly of the Sys- op1nent, assembly, and 1naintenance budgets for the Syste1ns
tems Manual. :tvfanual for the building and includes those requiren1ents dur-
5.3 The necessary sections of the Systerns Manual are used ing the develop1nent of the Owner's Project Requirements
in the initial and subsequent training of the O&tvl staff and (OPR) or Current Facility Require1nents (CPR). This section
occupants. outlines the functions and activities required during this phase
of the project to produce an acceptable Systems Manual.
5.4 The O&M staff uses the Syste1ns Manual to docu1nent
1nodifications they i1nple1nent and the reasoning behind the 6.2 Predesign- and Planning-Phase Ob_jectives. During
1nodifications and i1nprovements. It is also an asse,nbly of this phase of Systems Manual development, objectives
needed infonnation for 1nodifications required to 1neet CFR include the follo\.ving.
that will guide 1nodifications, updated Basis of Design (BoD) 6.2.l Develop and list the require1nents for a concise col-
infonnation, and changes to equip1nent and assemblies being lection of infonnation essential for the building operators to
1nodified or replaced. understand, operate, and 1naintain the syste1ns and asse111-
5.5 The Syste1ns Manual is the assembly of institutional blies.
knowledge that records needed infonnation for present opera- 6.2.2 Develop docun1ent requirements to inform those not
tion and future modifications. It is also the history of modifi- involved in the design and construction process about the
cations by all ,vho contribute to the modifications that happen O,vner's objectives and criteria that defined building attri-
over the life of a building. butes required to support the various Owner-envisioned activ-
ities the building was designed to support.
5.6 The infonnation on the building systems as described in
this guideline assu1nes that it is gathered and assernbled as it 6.2.3 Include the Systerns Manual criteria in the current
becornes available during a constn1ction or renovation proj- facility OPR/CFR to l,'11ide building operation and cornrnuni-
ect. This infonnation may be arranged by building systern cate requirernents for future modifications.
when that is a require,nent of the Owner for the project. This 6.2.4 Develop and list the requirements for operation and
decision should be rnade at the ti1ne of OPR development. n1aintenance (0&:tvf) staff for docun1enting and tracking
The systern arrangement ,nay take longer to accomplish since infonnation on updates and modifications to syste1ns and
large amounts of data need to be rearranged and new fonnats assemblies as they occur during the Occupancy and Opera-
developed. Time should be included for these efforts where tions Phase and the reasoning for the 111odifications to the
required. building's operation.
5.7 Production of the Systen1s Manual will depend on the 6.2.5 Develop requirements, designate responsibilities, and
directives in the OPR, the process of how the project is provide contracts for the production and gathering of the Sys-
planned, designed and built, how it is to be operated, and the tems Manual documentation and for additional information to
organization and application of the n1aintenance program. be gathered during the project and Cx Process, including
The responsibilities for all of the parts and documents in the techniques for opti1nization and a syste1ns-based organization
Syste1ns Manual should be carefully considered and specific of information.
assign1nents included in the project plans, contracts, and
6.3 System Manual Structure Requirements. Dw·ing the
specifications.
Predesign or Planning Phase, the Owner should establish the
5.8 This guideline is supplemental to the Cx Process detailed structure, fonnat, and expected source of doctunents that
in AN SI/ASHRAE Standard 202-2013 and ASHRAE Guide- rneets their project or organizational require1nents.
line 0-2013 and should be used in conjunction with those and 6.3.l Establish the format and organization of the Syste1ns
other applicable docu1nents. Manual as shown in Section 4.3.
5.9 Sections 6 through 11 of this guideline provide guidance on 6.3.2 Establish fonnat for doctunents included in the Sys-
the actions necessary to assernble, produce, utilize, and update terns Manual. This should occur dw·ing the Predesign or Plan-
the information in the Systerns Manual at each stage of the proj- ning Phase so the design and construction tearns can sta1i at
ect. The annexes provide exa,nples of documentation and for- the beginning of the project with doctunent collection and
1nats that can be used in developing the Systems Manual. assernbly. These documents should be collected in electronic
5.10 To ensure co1npliance ,vith the OPR, a con1pliance and fonnat and stored in a cornputerized storage tmit until the
approval process should exist for each stage of the develop- time for final assernbly and distribution. This procedure faci 1-
1nent and revision of the Systems Manual. The O,vner is ulti- itates the collection and frequent changes to the docurnents
1nately responsible for the decisions and approvals on the before the Syste1ns Manual is issued.
for111ats, arrange1nents, and asse1nbly responsibilities. 6.3.3 Establish the procedures, fonnat, and docu1nent col-
lection syste1ns require1nents as initially set in the OPR or
6. PREDESIGN- AND PLANNING-PHASE CFR. The Syste1ns Manual contents outlined in Section 4 can
FUNCTIONS be used as the list and arrange1nent of doctunents or 1nodified
6.1 Introduction. During the new project Predesign Phase or to 1neet the Owner's needs for a specific project or existing
existing facility co1111nissioning (Cx) Planning Phase, the doc111nentation syste111.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 7
No rep1oduciion or networking permitted wilhout license from IH S
6.3.4 Additional format and content infonnation for the ing if there is a proble1n, providing detailed repair informa-
individual docun1ents in the Systems Manual are sho,vn in the tion, and detern1ine cause of a problen1.
annexes to this guideline. 6.5.1.8 The process for collecting and storing infonnation
6.4 Roles and Responsibilities for Systems Manual Initial in the Syste,ns Manual that is essential for the building opera-
Documentation tors to understand, operate, and ,naintain the syste1ns and
assemblies and to infonn those not involved in the planning,
6.4.1 The roles and responsibilities for each co,nponent of design, and implementation and construction process about
the Syste,ns Manual as well as the entity that will coordinate the Owner's objectives and criteria that defined building attri-
and assemble the initial project Syste1ns Manual are defined butes required to support the various Owner-envisioned activ-
during the develop,nent of the OPR or CFR under the direc-
ities the building was designed to support.
tion of the O,vner. These responsibilities should be defined in
6.5.1.9 The process for documenting and ,naintaining a
project require,nents, specifications, and contract require-
current version of the Syste,ns Manual for a facility or new
ments. The co1nponents that compose the Syste,ns Manual as
sho,vn in Sections 4.3 and 4.4 are to be included in the project project and updating the Owner defined requirements (CFR/
QPR.) to guide operation and co,nmunicate requirements for
Syste,ns Manual and should be designated to be pe1fonned by
future modifications needed to support changes in Owner-
specific entities. See Informative Annex C of this guideline
envisioned activities and occupants' ,nission for the life of the
for additional roles and responsibilities infonnation.
building.
6.5 Predesign- or Planning-Phase Systems Manual Con- 6.5.1.10 Defining operation and n1aintenance procedures
tent Requirements. The 0,vner documents in the OPR or for staff or contractor that docu1nents and tracks updates and
CFR and by contract the responsibilities and deliverables of 1nodifications to syste1ns and asse1nblies as they occur during
each tea,n me,nber in providing the content, documentation, the Occupancy and Operations Phase and the reasoning for
asse,nbly, training, utilization, and updating of the Syste,ns the 111odifications to the building's operation.
Maiiual. At this ti,ne, the use of an electronic or hard-copy
6.5.1.11 Process for docu1nentation of additional infor-
fonnat or a specific ,nixture of both should be determined.
mation gathered during the project.
Ovrner activities include the follo,ving.
6.5.l.1 l .l Contract docun1ents, sub1nittals, shop dra,v-
6:?.1 At the initiation of a project, the O,vner is responsible ings, requests for infonnation (RFI), architect's supple1nental
for detennining project-specific requirements. Systems Man-
instructions (ASI), coordination drawings, operation and
ual ,content must support the project-specific operation and
1naintenance manuals, warranty requirements.
,naintenance. Based on project requirements, these require-
1nents could include the following . 6.5.1.11.2 Maintenance procedures for installed sys-
te,ns and assemblies not included in the O&M ,nanuals
6.5.1.1 Docun1entation in accordance with Section 4 of needed to operate and ,naintain the facility and its petfor-
this guideline and specification of who is responsible for the mance.
contents developn1ent and assembly.
6.5.l.11.3 Recom1nissioning process, including tech-
6.5.1.2 If the Syste,ns Manual is electronic based, ,vhat niques for optimization and a systems-based organization of
syste1ns or soft\vare will be utilized? What are the co1npatibil- infonnation.
ity requiretnents for porting of infonnation? What are the
6.6 Budgets. The Owner should include sufficient project
operating systen1 require,nents? What interactive fonnat is
funding and operational budgeting in the project and building
needed for quickly finding a topic or a specific type of infor-
operations budgets to develop, i1nple1nent, and 111aintain the
1nation? Where will the Syste1ns Manual reside- the owner's
Syste,ns Manual.
IT infrastructure or ,vith an outside service?
6.5.1.3 If the Syste,ns Manual is paper based, where will 6.7 Planning- and Predesign-Phase Systems Manual
the docu,nents be stored, and for larger projects ,vhat shall be Evaluation and Acceptance Criteria
contained in each volwne to facilitate access? 6. 7 .1 The Systen1s Manual fonnat, contents, and applica-
tion, if available at this phase, should be revie,ved by the CxA,
6.5.1.4 The fonn of infonnation desired and if graphic
if comn1issioning is included in the project, and building
system diagra,ns of each system are required.
O&M staff. The OPR or CFR should include these require-
6.5.l .5 The level of information operators and 1nainte- n1ents.
nance personnel will need and the access levels for infonna-
6.7.2 The Systems Manual should be reviewed and
tion that assists the Owner's personnel in identifying whether
approved by the Owner at the time of initial completion and
there is a problem and ,vhat service contractor should be con-
periodically during the life of the building.
tacted, or very detailed information for complex repair.
6.5.1.6 General and detailed emergency procedures based 7. DESIGN- AND INVESTIGATION-PHASE
on kno,vledge and skill level of first responders. FUNCTIONS
6.5.1.7 The level ofinfonnation needed by O&M person- 7.1 Introduction. DLu-ing the Design Phase for new projects
nel to efficiently 1naintain and i1nprove the project's perfor- or the Investigation Phase of existing buildings, the Systen1s
1nance in such areas as 1nanaging occupant satisfaction, Manual require,nents are inserted and detailed in the project
1nini1nizing scheduled 1naintenance require1nents, determin- require,nents, docu,nentation, and contracts. This infonnation

American Sociel)'; ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~ nder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
provides the Cx Team, contractors, operators and 1nainte- 8.2 Construction-Phase Systems Manual Preparation
nance personnel specific instruction in the assembly and use Objectives
of the Systems Manual. 8.2.l Implement the documentation process and provide
7.2 Design-Phase Systems-Manual Preparation Objectives. necessary coordination to produce and use the Syste,ns Man-
The Design Phase and Investigation and Design Phase objec- ual.
tives include the conversion of the Systems Manual require- 8.2.2 Determine Procedures, Responsibilities, and
ments into contract requirements. This will instruct the Schedules for Documentation Production and Collection
contractors, suppliers, and building operators, as well as the 8.2.3 Ensure that the contractor is required to include per-
design and Cx teams, on their responsibilities to produce the formance and docun1entation require1nents for Systems Man-
Syste1ns Manual. ual document develop1nent and collection and Syste1ns
7.3 Design-Phase Systems Manual Documentation Require- Jvfanual assembly in subcontracts as required for the desig-
ments for S pecific Building or Pro,ject nated systems.
7.3.1 During the Design Phase, the Owner's requirements 8.2.4 Ensure that the necessary sections and documents of
are converted to specific project docu1nent require1nents. The the Systems Manual should be available and those documents
responsibility to produce the document deliverables is used in the training process and building operations.
inserted in project plans and specifications. See Informative 8.3 Construction and Implementation Phase Systems
Annexes C and J of this guideline for added roles and respon- Manual Documentation Requirements
sibilities and specification infonnation.
8.3.1 Coordinate O,vner's Systems Manual Require-
7.3.2 The schedules to provide the individual documents ments. The contractor and the project and Co1nmissioning
and the finished Systems Manual are included in the project (Cx) tea1ns work together to produce and capture the neces-
docu1nents during this phase. sary documents for the Systen1s Manual.
7.3.3 The design and Cx tea1ns will define systetn descrip- 8.3.2 Update O"•ner's Facility Project Requirements. If
tion and docutnentation requiretnents for all syste1n s as proposed changes to the facility are at variance with the
required in Owner's Project Requiretnents (OPR)/Current o,vner's Project Requirements (OPR) and C11rrent Facility
Facility Require1nents (CFR). Syste1ns requi ring comtnis- Requirements (CFR) and are approved by the design profes-
sioning will be designated and instructions will be included sionals and Owner, then the OPR/CFR and Basis of Design
for all applicable syste1ns. (BoD) must be revised and approved. This provides for con-
7.3.4 The Syste1ns Manual formats and updating require- tinuous updating of the OPR/CFR and BoD to reflect the con-
tnents should be specifically defined in the contract docu- structed project and facility.
tnents, specifications, and constn1ction plans. 8.3.3 Conduct Preconstruction Systems Manual and Cx
7.3.S The Systems Manual's use in training requiren1ents is Process Meeting. Special issues relative to installation of
defined and n1ade a require1nent for project completion in equiptnent located in litnited access areas (such as equiptnent
specifications and contract documents. to be installed in lower levels of a building) should be docu-
7.3.6 Requirements are defined for the collection of check- mented and recorded for future 1naintenance activities.
lists and other Syste1ns Manual docu1nents, including plan- 8.3.4 Coordination Dra\\'ings. Coordination dra,vings
ning and design documents, record docun1ents, approved should be retained and inserted in the Syste1ns Manual to ver-
submittals, evaluation, and performance testing records by the ify that the following require1nents have been met and con-
contractor and Cx Team. struction infonnation is transferred to the operation staff:
7.3.7 The inclusion of a facility guide and 1naintenance a. Mechanical and electrical equipment spaces sho,\1ing
checklists for equipment and syste1ns for building operation structural elements, equip1nent, piping, ductwork, and
should be defined and required. conduit
7.4 Design-Phase Systems Manual Evaluation and Accep- b. Ceiling space coordination drawings showing a consistent
tance Criteria layering for structural eletnents, ceiling grid, access doors
7.4.1 The Systen1s Manual format and application in the and panels, fire and s1noke da1npers, lighting, piping, duc-
project documents should be revie,ved by the Commissioning t\vork, conduit, and control elements
Authority (CxA) on com1nissioned projects. c. Vertical shaft coordination drav.,ings for piping and duct-
7.4.2 The Syste1ns Manual requirements in the projects work showing structural eletnents, equip1nent, piping,
should be reviewed and approved by the Owner. ductwork, and conduit
d. Specified clearances are shown for n1aintenance and oper-
8. CONSTRUCTION- AND IMPLEMENTATION-PHASE ation procedures appropriate to the accepted n1ake and
FUNCTIONS 1nodel of equip1nent
e. Coordination dra,vings detnonstrate adequate space for
8.1 Introduction. During the Construction Phase of a new
1naintenance access and installation and identify spaces
building and the linple1nentation Phase of an existing build-
reserved for maintenance and operational procedures
ing, the Syste1ns Manual require1nents are updated and i1nple-
1nented to provide the docu1n ents and asse1nble the1n for use 8.3.5 Equipment Submittals. Equip1nent and co,nponent
in training and operation and 1naintenance (O&M) functions. vendor sub1nittals shall be obtained for use by the Co1n1nis-

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~ ~ ~ m ! # Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 9
No rep1oduciion or networking permitted wilhout license from IHS
sioning Authority (CxA) and project tea,n. This inforn1ation, for the building operators to understand, operate, and main-
when confirmed and approved, shall be used in developing the tain the systems and assen1blies.
construction checklists and test procedures. These approved 9.2.2 Ensure that the operations and 1naintenance (O&M)
submittals are to be included in the Syste1ns Manual. staff effectively utilize procedures for docu111enting and track-
8.3.5. 1 Subtnittal of the control sequence of operation ing infonnation on updates and ,nodifications to syste,ns and
should be presented in the fonn of a written description and a asse,nblies as they occur during the Occupancy and Opera-
control logic diagra,n or other approved format. This allows tions Phase and the reasoning for the 111odifications to the
the building O&M staff to understand the intended functions building's operation.
and operation of the equipment. 9.2.3 Continuously and consistently update the systems'
8.3.5.2 The training-prograin submittals review includes information utilizing the prescribed update process, including
the schedule, syllabus, evaluation forms, qualifications of the techniques for opti111ization and a systerns-based organization
trainer, any video or other material that will be used, any pro- of infonnation. This \.Vottld include adding additional systerns
posed demonstration training, and recording or documenta- and assernblies that 1nay be installed or 1nodified in function
tion of the training for future use and inclusion in the Systems throughout the life of the building.
Manual (refer to Informative Annex 0). 9.2.4 Results from con11nissioning (Cx) tasks perfonned in
8.3.6 Facility Operating Procedures this phase 1nust be entered into the Systen1s Manual. This
8.3.7 The facility standard operating procedures should be would include load and perfonnance testing and building
developed for use in training and operation standardization. indoor climatic conditions of the facility in use.

8.4 Testing and Evaluation Documentation 9.3 Occupancy- and Operations-Phase Systems Manual
Documentation Requirements
8.4.1 The testing and evaluation procedures, docu1nentation,
and results should be recorded, and the results asse,nbled, for 9.3.l Continual Updating of the Systems Manual. The
the Cx Process Progress Report and Syste,ns Manual. responsibility for maintaining the accuracy and relevancy of
the Systems Manual for new construction projects is trans-
8.5 Project Record Documents ferred from the contractors to the O&tvl personnel at the start
8.5.1 The project record docwnents should be updated and of the Occupancy and Operations Phase. The Owner's per-
included in the Systen1s Manual. sonnel ,nay accept this responsibility directly, place the
8.6 Construction- and Implementation-Phase Systems responsibility on a property rnanager, or hire an outside con-
Manual Evaluation and Acceptance Criteria tractor to assist with the maintenance process.
8.6.1 The Systen1s Manual project documentation should 9.3.2 Maintaining and updating the Systems Manual is
be revie,ved by the CxA and building O&M staff, if available, required for the life of the facility and includes the following:
before the end of construction. a. Inclusion of n1aterial as the result of completing the Cx
8.6.2 Syste,ns Manual docu,nents to be included in the Process activities in the Occupancy and Operations Phase
training progra1ns should be reviewed and approved by the b. Inclusion of updated maintenance procedures and sched-
CxA and Owner in accordance with OPR and CFR require- ules, ongoing operational record keeping, bench1narking
1nents. results, and actions take n in the optirnization of the facil -
8.6.3 The complete Systems Manual should be reviewed ity systerns
and approved by the 0,\1ner c. Modifying information as changes are made to the sys-
tems, including updating the OPR/CFR. and Basis of
9. OCCUPANCY- AND OPERATIONS-PHASE Design (BoD)
FUNCTIONS d. Keeping the record documents current with changes in
9.1 Introduction. During the occupancy and operation of a progran1ming, nomenclature, equipn1ent, systen1s, and
facility, the Systerns Manual is utilized to assist in the opera- assen1blies
tion and 1naintenance of the building. The docwnents are e. Utilizing training 111echanis1ns to ensure that new person-
updated on a periodic basis and as needed to keep the Sys- nel are properly infonned to perpetuate syste1ns and pro-
terns Manual current. cedures for updating the Syste1ns Manual
f. Evaluating and recording the condition of all the 1najor
9.2 Occupancy- and Operations-Phase Systems Manual
building equipment.
Objectives
9.2.1 During the occupancy and operation of a facility, the 9.4 Occupancy- and Operations-Phase Systems Manual
Ov,ner ,nust develop and i1nple1nent processes to 1naintain the Evaluation and Acceptance Criteria
Syste1ns Manual. W11ile these processes ,vere generally 9.4.1 The Syste1ns Manual fonnat and content s hould be
defined in the Owner's Project Require,nents (OPR)/Current reviewed and approved on a periodic and scheduled basis by
Facility Require,nents (CFR), these functions should be the responsible 1ne1nber of the building Owner's staff or des-
,naintained throughout the project through the Occupancy and ignated representative of the Owner. This is especially i1npor-
Operations Phase. Changes in operational procedures, build- tant when a contracted finn or property 1nanager is in charge
ing functions, personnel or technology dictate the need for of 1naintaining the Syste1ns Manual. This process is essential
updating procedures. Maintaining the infonnation is essential to ensure effectiveness of the Syste1ns Manual as a tool for
•• • • • .. ........ + • • ... ...

American Sociely Rl Healing, Refrigeraling and Air-Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS l!W:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
efficiently 1naintaining equipment, syste1ns, and asse1nblies operation and n1aintenance (O&M) data will n1ost likely be in
over the life of the building. paper forn1at and will need to be scanned into digital format
9.4.2 The Syste,ns Manual should be reviewed by the for an electronic format Systems Manual. If the model and
building O&M staff on a monthly basis. Errors should be cor- serial nun1ber of the equipment is available, usually on a
rected and updates ,nade as they occur. na1neplate, the n1anufacturer could be contacted and the
equipment docu1nentation requested. This inforn1ation will
9.4.3 The procedures and processes for updating the Sys-
need to be arranged in a searchable format for convenient use.
tems Manual should be reviewed by the party responsible for
This arrangement could be si1nilar to the CSI MasterFonnat,
maintenance of the Syste1ns Manual as part of a continuous
or the manufacturer's O&M data 1nerged with the sub1nittals
improvement process and approved by the Owner on a peri-
and specifications so that all information on a specific piece
odic and scheduled basis.
of equipment or system is in the same location or section in
10. EXISTING BUILDING FUNCTIONS the Syste1ns Manual.

10.1 Introduction. For existing facility syste,ns and projects, 10.3.1.5 Existing and current sequences of operation are
the plans and doc1unentation sources often vary from ne\.v essential to the building operation. These can often be located
construction. The require,nents for assembling a Systems with the facility control syste1n infonnation. If the facility has
l'v1anual if it does not exist or updating an existing Syste,ns a co1nputerized energy 1nanage1nent and control syste,n, the
l'v1anual may require docu,nent gathering alternatives to docu- sequence ,nay be included in or derived fro1n the control sys-
ment gathering and asse,nbly procedures. te,n co1nputer or docuinentation. If a written sequence of
operation for the facility is not available, one should be devel-
10.2 Existing-Building Systems Manual Objectives oped with infonnation fro,n the CFR and the operating
10.2.1 For updating an existing Syste,ns Manual, if the knowledge of the building staff. This sequence of operation
building had a Systems Manual prepared at the ti,ne of con- should be in plain, understandable language and be entered
struction or renovation, those documents should be updated into the facility guide and operating plan in a standard fonnat.
and maintained as described in Section 9 of this l,TUideline. Graphical sequences of operation should also be utilized
10.2.2 When developing a Systems Manual for an existing where available.
building, the documentation should be gathered and assem-
10.3.l .6 Existing facility maintenance programs, plans,
bled in the format required by the Owner. The purpose of this
procedures, and schedules should be located fro1n building
Systeins Manual is the same as in a new building, that is to
1naintenance operation documentation. If there are no written
provide planning, design, construction, and operations infor-
plans, these should be developed and included in the Systems
mation for training of the operations and maintenance staffs
Manual to assist in the continuity of building operation and to
and to facil itate building perfonnance and future changes.
assist in building improve1nent progra1ns. Current facility
10.3 Existing-Building Systems Manual Documentation O&M personnel and maintenance contractors are usually the
Requirements "'here no Systems Manual Presently Exists best sources for this information .
10.3.l Gathering Information 10.3.1.7 Existing 1naintenance testing records separated
10.3.1.1 Original planning, design, dra,vings, and specifi- by system should be collected and entered into a records sec-
cations can be found in some facilities in the 1naintenance tion to provide a base of operating data for future n1ainte-
office or property 1nanager's area. In so1ne cases, the infonna- nance progra1ns and building i1nprovement programs.
tion may be in a storage area. If the original or remodel design
tean1 is known, they may be a source of design documents. 10.3.2 Format Development. The fonnat of the Syste,ns
Usually this information is in paper fonnat and will need to Manual and the collected infonnation should be defined in the
be scanned if the Systen1s Manual will ulti1nately be in digital CFR. This information should be arranged to best suit the
fon11at. building operating require,nents, be understandable to the
operating staff, and be easy to locate, use, and update.
10.3. 1.2 Current Facility Require,nents (CFR) should be
doc1unented. This is a funda,nental requirement for proper 10.3.3 Documentation Processing. The documentation
building operation. These require,nents should include the should be in digital format if the Systen1s Manual is assen1-
fonn and fonnat for the Syste,ns Manual. bled in that media. It is reco1nmended that the digital format
10.3.1.3 Existing submittals for equipn1ent and syste1ns be used to reduce the loss of parts of the docu,nents and to
should be located. These can often be found in the 1nainte- n1ake the information easier to find and update.
nance office or storage area. This information will assist in 10.3.4 Developing Plans, Records, and Documents that
the operation and maintenance of the building. Most likely, do not Currently Exist. A co,nplete facility Syste,ns Manual
the submittals will be in paper format and will need to be would contain all the infonnation included in the contents list
scanned into digital fonn for an electronic forn1at Syste1ns in Section 4 of this guideline. Ho~rever, in existing buildings
Manual. The sub1nittals should be arranged in a logical order, that were not co1n1nissioned and/or for which a Systen1s Man-
such as the Construction Specifications Institute (CSI) Mas- ual was not provided, this is seldo,n the case. The facility
terFormat, and include an index syste111. guide infonnation and current O&M infonnation should be
10.3.1.4 Existing equip1nent O&M doc1unents and ,nanu- developed fro1n current operations as a 1nini1nu1n for building
facturer-supplied infonnation should also be located. The operation.
.. . . . , . ...... , . .. . ... ...

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir-CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~ ~ ~ m ! # Ml-U.e I . 4 -LU 14 Nol for Resale, 201515/28 09:22:15 11
No rep1oduciion or networking permitted wilhout license from IH S
10.3.5 Information Retention and Updating. The Sys- a. Capturing all the infonnation in a con11non digital format
tems Manual should be maintained and updated ,vith avail- to make access easier
able information. Even if the 1nanual is not co1nplete or ideal, b. Reducing the loss of infonnation that can be physically
it should be treated in the same 1nanner as a document needed removed from a printed manual
to properly operate the building. The docu1nents should be c. Improving accessibility of the infonnation
reviewed on a regular and scheduled basis and updated as
d. Making the manual easier to maintain and update
required to keep them current. Any changes to equipn1ent or
facility operations should be entered into the 111anual at the 11.3 Computerization and Interface Documentation
tin1e of the change. Requirements
10.3.6 Systems Manual Usage and Access. The Syste1ns 11.3.1 The n1ost i1nportant require1nent for a digital Sys-
:tv1anual is intended to be used by building 1nanagen1ent, tems Manual is to provide a fonnat that can be stored on a
O&M personnel, 1naintenance contractors, and design and con1puter system or produced on co1npact disc or universal
co1nmissioning (Cx) tean1s for building recommissioning and serial bus (USB) drives that can be accessed and read by the
upgrading. Access to the Systems Manual infonnation in a intended users. If the intent is to 1nake the information avail-
digital format may be the 111ost convenient for all users. able on a full-time basis on 1nobile platfonns such as tablet
10.4 Existing-Building Systems Manual Evaluation and con1puters, then the system will be 1nore co1nplex.
Acceptance Criteria 11.3.2 The simplest format for a digital Syste1ns Manual is
10.4.1 The Syste1ns Manual format and application in the a spreadsheet or database program. An outline or index can be
project documents should be reviewed and accepted by the created on a con1puter or server system and the docun1ents
building O&M managen1ent and staff on a periodic basis. entered in the outline as they are collected. This method is
This review ideally should be done monthly but should an1ong the simplest, but search ability can be a challenge.
always be co1npleted annually.
11.3.3 Several 1nore con1plex database syste1ns have been
10.4.2 The Systems Manual should be reviewed and developed and have varying degrees of functionality. One
approved by the owner on a periodic and scheduled basis. such syste1n for design and construction docu1nentation, the
Construction Operations Building Information Exchange
11. COMPUTERIZATION AND INTERFACE WITH
(COBie), has been developed by the U.S. Anny Corps of
OTHER PROGRAMS
Engineers and can interface directly with some computerized
11.1 Introduction. Even though a Systems Manual can be 111aintenance programs.
assembled in a hard copy fonnat, it is usually better to digitize
the infonnation and assemble it into a co1nputerized and 11.4 Computerization and Interface Verification and
searchable format. The volume of information is much easier Acceptance Criteria
to handle and store in digital fonnat. There are several for- 11.4.1 The Systems Manual digital processes, fonnat, and
111ats available for the asse1nbly of the Syste1ns Manual, from application in the project docun1ents should be revie,ved on a
111anual paper copies, to digitized versions of the paper docu- scheduled periodic basis and accepted by the building O&M
111ents, to totally computerized systems. 111anagement.
11.2 Computerization and interface objectives include the 11.4.2 The Systems Manual should be reviewed and
follo,ving: approved by the Owner on a scheduled periodic basis.

•• • • • ., , . ., , • ., • + • ..• •••

American Sociely ,ql Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS Wder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
(This annex is not a mandatory part of this guideline. It is merely informative and does not contain requirements neces-
sary for conformance to the guideline. Unresolved objectors on informative material are not offered the right to appeal at
ASHRAE.)

INFORMATIVE ANNEX A
SYSTEMS MANUAL DOCUMENTATION FLOWCHART

[ DESIGN PHASE ]
Commissioning (CX) Team
No-------------
Owner Prqect Manag«
Owner Controls Technician
Owner HVAC&R Technician HVAC&RDP
Prepares System
System Manuel
Speclftc.tlons
Cx Team Reviews ......
Spedlclllons
,..._.em
FaciUtles Engineer Specifications
HVAC&R Design Professional (DP) Manual of
0Pft
Electrlcal Design Professional Soeclllcatlons
Archlect
Comrrisslonlng Authority (CxA) 1--------- N,r-- - - - - - - - - . Yes

CxA& CxA
HVAC&R DP Recomnends
~

[ CONSTRUCTION PHASE I
(CX) Team
Owner Project Manager Contractors Ust.-ig OwnerPrqect
Owner Controls Technician & Emergency Requirements
Executive Comrrisslonlng Flan
Owner HVAC&R Technician Summary
Information
Facill les EnglnNr
HVAC&R Design Professional
Eledtlcal Design Professional
Commissioning Authority
Operational
Recordng Basis of Design

Benchmarking
&
Organization
~
Submittals

Commissioning
Test Reports

Operation &
Maintenance
Traln.-ig Information Record Documents Requirements
& Records

[ WARRANTY & OCCUPANCY PHASE ]


(CX) Team
Owner Prqect Manager Changes to OPR OwnerO&M Staff
Owner Controls Technician AndHVAC&R l.lpdttes System - Syst«n Manuel
Owner HVAC&R Technician System Manual
Faalilles Engineer
Comrrisslonlng h.lthonty

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZATION 595661 7
Provided by IHS~ ~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 13
No rep1oduciion or networking permitted wilhout license from IH S
(This annex is not a mandatory part of this guideline. It is The o,vner shall require the update of the OPR/CFR and
merely informative and does not contain requirements Systems Manual as defined objectives and criteria contained
necessary for conformance to the guideline. Unresolved in the docu1nent are changed as the project progresses.
objectors on informative material are not offered the right The Owner shall 111ediate and provide direction to the
to appeal at ASHRAE.) project tea,n on issues identified but unresolvable by the team
as part of the issue resolution process. The Owner shall
INFORMATIVE ANNEX B approve, in ,vriting, the resolution.
SYSTEMS MANUAL CONTRACT REQUIREMENTS
B2. SETTING CONTRACTUAL REQUIREMENTS
B1. INITIATING THE PROCESS This annex provides suggested examples ofho,v to i1nple1nent
the process contracting activity. It is not intended to be a con1-
Syste1ns Manual asse1nbly is a team effort, and the entire prehensive representation or a best-practice exa,nple. Owners
project tean1 is part of the process. The Owner's Project and practitioners applying the project process should care-
Requiren1ents (OPR)/Current Facility Requiren1ents (CFR) fully follo,v ANSI/ASHRAE Standard 202-2013 and
and Co1nmissioning (Cx) Plans define project team's roles ASHRAE Guideline 0-2013 and applicable technical guide-
and responsibilities, communication protocols, asse1nbly lines tailored to their specific proj ects.
activities, and the schedule of those activities. Success is The following suggested contract language must be
dependent on each team 1nember's understanding of what is developed for each activity applicable to a specific project or
expected of the1n and obtaining their buy-in. This is ,vhy it is building:
essential that the Owner clearly define, contractually, each
tean1 me,nber's role and responsibility and their part in the Suggested Language for Systems Manuals
Syste1ns Manual assembly process and achievement of the a. Proj ect and Con1n1issioning (Cx) Teams shall include in
defined objectives and criteria as defined by the OPR or CFR. the specifications contractor deliverables defined in the
The Owner is head of the project and shall be engaged in O,vner's Proj ect Requiren1ents (OPR)/Current Facility
defining the team's goals and objectives and verifying that Requiren1ents (CFR) to be included as part of the Syste1ns
they are clearly docun1ented in the OPR/CFR documents, Manual. The specifications shall define in the submittal
contracts, and project require1nents. The Systen1s Manual the format and infonnation required.
providers use these directives to in1plen1ent the process for b. Designer shall provide Basis of Design (BoD) infonnation
the Owner's benefit. in defined fonnat for inclusion in the Systems Manual.

.. , , . .......... .. , ... ...


American Sociely gt Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS Lffder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is Subcontractors. Demonstrate proper syste1n perforn1ance
merely informative and does not contain requirements and sub1nit documentation for the Systems Manual.
necessary for conformance to the guideline. Unresolved
objectors on informative material are not offered the right Design Professional (DP). Perform construction observation,
to appeal at ASHRAE.) approve O&M and Systen1s Manuals, and assist in resolving
problen1s.
INFORMATIVE ANNEX C
ROLES AND RESPONSIBILITIES Facility Management. Facilitates 1nanagen1ent and n1ainte-
nance, supports the process, and gives final approval of the
Surnmarize project-specific responsibilities such as provided Systems Manual.
below in the appropriate contract or project docurnents.
Manufacturers. The equipn1ent rnanufacturers and vendors
Team Members for the Systems Manual provide documentation to facilitate and perfonn contracted
start-up and subrnit documentation for the Systems Manual.
The rnembers of the project and conu11issioning (Cx) teams
consist of the Owner or representative, Con1missioning Building Operator. The Owner is responsible for the activi-
Authority (CxA), design professionals, assigned n1en1bers of ties of the building operations staff. As such, periodic review
the construction n1anager/general contractor team, appropri- of the Systen1s Manual is essential to the transfer of institu-
ate subcontractor(s), and any other installing or 1naintenance tional knowledge to successors of existing staff necessary for
subcontractors or suppliers of equip1nent. The O\vner's build- efficient operation of the building. Defining these require-
ing or plant operator/engineer is also a 1nember of the project n1ents early in the project planning will allow the require-
tean1. The mernbers of the project tearns responsible for the n1ents to be included in the initial building operating
assen1bly of the Systems Manual n1ust be designated by the requirements.
O\Vner in the appropriate plans and contracts. The head of the facility's operation should either person-
ally rnaintain or ensure n1aintenance of the Systen1s Manual
General Management Plan records, including, but not limited to the following:
All n1embers \vork together to fulfill their contracted respon- • Changes in operating schedules
sibilities and 1neet the objectives of the contract documents
• Overriding controls and the associated reasoning
and assen1bly of the Systems Manual.
• Changes to building automation system (BAS) setpoints
General Descriptions of Roles and the associated reasoning
• Replacement of equipment that is not the sarne make and
General descriptions of the com1nissioning roles are as fol- n1odel
lows:
• Additions or rnodifications to the systems being rnain-
tained by operational staff
O"'•ner. Provides inforn1ation on operation and 1naintenance
(O&M) resources, including O&M staff, O&M routines, • Designed and constructed modifications, including
required tools, computer maintenance managen1ent systerns changes to floor-plan layout
(C!vlMS), etc., and the expected future role of these resources. • Documentation of repeated equipment failures or n1al-
The O\vner decides the level of decisions that are delegated to functions
the CxA and others. The owner also participates in budgeting • Updating construction record documents to reflect modi-
and provides funding for the \VOrk with the Systems Manual. fication to the building infrastructure
• Collection and inclusion of Current Facility Require-
Commissioning Authority (CxA). Coordinates the process, n1ents (CFR); Basis of Design (BoD); O&M n1anuals for
writes tests, and oversees and docun1ents perforn1ance tests ne\v or replaced con1ponents, systems, and assemblies;
and the assen1bly of the Systems Manual. The CxA also and associated Cx Process Progress Reports
assists the O\vner with setting the requirements and the bud- • Updating of optimization strategies
gets for the Co1nmissioning (Cx) Process and the Systerns
• Updating of systen1 schematics (single-line diagran1s)
Manual.
• !v1odification to operational procedures for normal,
General Contractor (GC). Facilitates the project process, abnorn1al, and emergency modes of operation
ensures that subcontractors perform their responsibilities, and • Current training record for each operation and n1ainte-
integrates the collection of documents and assen1bly of the nance staff 1nen1ber
Systen1s Manual into the construction process and schedule. • Preventive 1naintenance schedules

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS ~ ~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 15
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is construction or project documents. These provide the design
n1erely info rmative and does not contain requirements foundation for the facility and the construction dra,vings.
necessary for confor1nance to the guideline. Unresolved
objectors on informative material are not offered the right PART Ill: FACILITY SYSTEMS AND
to appeal at ASHRAE.) ASSEMBLIES INFORMATION

INFORMATIVE ANNEX D Describe the use and location of the systems and assemblies
SYSTEMS MANUAL EXECUTIVE SUMMARY information. These include the project specifications,
approved sub1nittals, manufacturer's installation instn1ctions,
The executive su1111nary contains an overview of the building
operational and maintenance information, warranties, and list-
design, construction, and operational require1nents. The infor-
ing of design team, contractors, and suppliers. This provides
rnation is intended to provide general guidance on the
specific information on the facilities systems and assemblies
intended operation, performance, and maintenance of the
that can be used for operation and maintenance (O&M) func-
building in conformance \.Vith the Owner's Project Require-
1nents (QPR) and/or Current Facility Require1nents (CFR). tions.

PART I: SYSTEMS MANUAL EXECUTIVE SUMMARY PART IV: FACILITY OPERATIONS


1. Overview of the Facility Design and Intended Use Describe the facility guide and its use in daily operation of the
Using the OPR and/or CFR as references, this section facility. If included in the owner's require1nents and the project
describes the faci lity and outlines its intended uses. The sys- contracts, include 1naintenance plans and schedules, utility
te1ns and assernblies included in the Syste1ns Manual are 1neasure1nent and reporting, 1neasure1nent and verification
listed and described along with their function in facility oper- (M&V) plans, ongoing Cx (OCx) Plans and require1nents, and
ations. janitorial plans and require1nents.
2. Facility Construction
PART V: TRAINING
This section outlines the construction process and histoty and
describes any plans or intent for future changes or expansion. Describe the training conducted during the project and the
location of the training material. Include training information
3. Operational Requirements
on requirements and procedures for updating the Systems
Provide general guidance on the intended operation, perfor-
Manual.
1nance, and n1aintenance of the facility in conformance ,vith
the OPR and/or CFR. They include a su1n1nary and direction
to the operational plans and require1nents included in the var-
PART VI: ex PROCESS PROGRESS REPORT
ious sections of the Systen1s Manual. Describe the Corn1nissioning (Cx) Process and results for the
project, and list the locations for the testing plans, checklists,
4. Systems Manual Contents Description and
and results.
Use Summary

PART II: FACILITY DESIGN AND CONSTRUCTION 5. Update and Systems Manual Maintenance
Describe the use, function, and location of the design docu- Describe the requirements, process, and responsibilities for
m.e nts, including the OPR/CFR, Basis of Design (BoD), and 1naintaining and updating the Systems Manual.

American Sociely pl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS LQJer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is • Objectives: For any proj ect, there are goals that must be
merely informative and does not contain requirements achieved for the project to be successful. Goals can
necessary for conformance to the guideline. Unresolved include first-cost, time schedule, nu,nber of change
objectors on informative material are not offered the r igh t orders, or life-cycle cost. Regardless of which goals are
to appeal at ASHRAE.) identified, they must be su1n1narized at the beginning to
ensure everyone shares a com111on understanding.
INFORMATIVE ANNEX E • Green-Building Concepts: This is an optional section for
OWNER'S PROJECT REQUIREMENTS AND Owners who wish to focus on the sustainability aspects
CURRENT FACILITY REQUIREMENTS DOCUMENTS of their building.
Follo,ving are examples of the Owner's Project Requirements • Functional Uses and Requirernents: In addition to general
(OPR) and Current Facility Requirements (CFR) require- documentation produced by the architect on functional
ments and fonnats for the docu,ne nts to be included in the uses of the building ( office, storage, kitchen, etc.), the spe-
Systems Jvfanual. This annex provides an exan1ple of how to cific require,nents for each functional area ,nust be docu-
i1n ple1n ent part of this guideline. It is not intended to be a mented. This can include ite111s such as security, safety,
comprehensive representation or a best-practice example. co,nfort, ene11,'Y, 1naintainability, and indoor air quality.
Practitioners applying the Co1nmissioning (Cx) Process • Lifespan, Cost, and Quality: It is important to clearly
should carefully fo llow ANSI/ASHRAE Standard 202-201 3 docwnent the Owner's expectations for lifespan of rnate-
and ASHRAE Guideline 0-2013 and applicable technical rials, cost of construction, and the level of quality
guidelines tailored to thei r specific projects. desired. By providing this infonnation, unrealistic expec-
tations are identified and eli,n inated.
E1 . OWNER'S PROJECT REQUIREMENTS • Perfor,nance Criteria: Often the ,nost difficult section to
The OPR is developed and defined in the beginning of the define, perfonnance criteria detail 1ninimum acceptable
proj ect delivery process. Infon11ation about the proj ect is gath- perfonnance bench1narks for various aspects of the facility.
ered, including program require,n ents, com,ntmity context, • J\1aintenance Require,nents: The maintenance require-
codes and regulations, site and cti,nate, facility context and ments are a 1n ixture of the level of knowledge of the cur-
function, facility technology, sustainability, cost, schedule, and rent O&M staff (what they can 1naintain) and the
the clients' (including 0 \.vner, occupants, operators, and 1nain- expected co1n plexity of the proposed syste1ns (what they
tenance personnel) needs and capabilities. The OPR provides can learn). If there is a significan t gap behveen the t\vo,
the basis fro,n \.vhich all design, constn1ction, acceptance, and no n1atter how well the building is constructed, it will not
operational decisions are made. An effective Cx Process be ,naintained or operated properly.
depends on a clear, concise, and co1nprehensive OPR docu- The following are exa,n ples of OPR ele1nents that are
ment, which includes information to help the project team co111mon to most of the technical Cx Process guideline topics.
properly plan, design, construct, operate, and maintain sys-
te,ns and asse,nblies. The OPR is often developed in an OPR • Benchmarks .for Pe1.for1nance: Specific crite ria for the
workshop as described in ASHR.AE Guideline 0-20 13. functional use of each space, assembly, and system must
The 0 \.vne r is encouraged to provide a mini1n u1n of five be defined. These include te1nperature, htunidity, airflow,
participants that equitably represent the various groups asso- light, noise, durability, aesthetics (materials and colors),
ciated with the existing building or future project. service life, reliability, redundancy, and the like. Typi-
cally, upper and lower litn its are provided for general
The OPR is considered the heart and soul of the Cx Pro-
spaces, ,vith exceptions noted as required.
cess. When the OPR is not developed, the Owner, designer,
contractors, and operation and maintenance (O&M) person- • Problems to Avoid: S ince occupant/user/operator com-
nel each interpret the building require1ne nts, including their plaints are co1nn1on, it is i1nportant to identify and docu-
individual responsibilities, fro,n the standpoint of their own 1nent those proble,ns that have caused complaints in the
specific needs. This often creates a range of diverse vie,vs of past. If these problen1s are not documented and the situa-
the constn1cted project's needs. Developing OPR that reflects tion recurs, the occupants often consider the entire proj-
the actual needs of the O,vner, the users or occupants, service ect a failure.
and operating un its, and so1n eti1nes the co1n1nunity is one the • 5JJectfic Occupant Requirements: Specific items that are
most difficult and itnportant aspects of successful implemen- deemed in1portant to the various occupants in a building
tation of the Cx Process. 1nust be identified and docu1n ented. In speculative-built
The following sections detail an exa,nple format to fol- bu ildings, this section would detail the limits to which
low in developing the OPR and a discussion ofho,v to obtain occupants can make use of their spaces. For exa1nple, a
the required infonn ation. Note that, historically, the OPR has che,n ical laborato1y cannot be put in a space designed
often been referred to as "design intent" or "project intent." and constructed for general office use without signifi-
cant changes to the syste1ns and possibly to the building
Format as a ,vhole.
Key sections of the OPR docwnent are as follows: Obtaining the Information
• Background: A narrative description to provide context While it ,nay be easy to obtain the basic infonnation related to
for the project. develop1nent of the OPR, it is difficult to obtain quality in for-

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZATION 595661 7
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 17
No rep1oduciion or networking permitted wilhout license from IHS
1nation that the Owner, O&M staff, service contractors, cus- d. Environmental Require1nents Construction Process if a
to1ners (i.e., students, patients, retail custo1ners, renters), project require1nent
visitors, subtenants, occupants, and the collllntmity all agree e. Maintainability and 111aintenance program requiren1ents
on. In quality-based processes, it is critical that input be f. Operations training requirernents
obtained fro1n all users (the various user groups) and that the g. Bench1narks
consensus of and differences a1nong the groups are docu- h. Docutnentation and fonnat requirements, including Sys-
1nented. There usually are require1nents on which users do not tems Manuals.
all agree. These must be docu1nented as tmresolved ite1ns.
O,vner's Pro_ject Requirements Version History. Includes a
Nonnally, the Owner will 1nake final decisions on \.vhat the
priority order of OPR ,viii be. However, the Owner and the rest sun1111ary of the changes 111ade throughout the Predesign, Design,
of the Cx Team 1nust be a,vare of all requirements so that the Constn1ction, and Occupancy and Operations Phases. This infor-
final product will include as 1nany individual group require- 1nation is critical to understand and document, the trade-offs
ments as are deerned appropriate and ,vithin the budget. 1nade over ti1ne, and the resulting i1npact on the project.
A si1nple, three-step process is recom1nended for devel-
E2. CURRENT FACILITY REQUIREMENTS
oping the OPR:
The key to a successful existing-building co1runissioning proj-
I. OPR \.VOrkshop ect is a well-defined CFR. The CFR forms the foundation of
2. QPR docurnentation (report) any design that meets the Owner expectations. When sufficient
3. Project tea1n approval of the OPR ti1ne and effo1t is given to docutnenting the Ov.rner's present
and future requirements, there is a high probability that the
OPR Document facility ,viii be effectively co1n1nissioned and that the Owner
will be satisfied.
A general format for an OPR document is presented below. For those facilities co1n1nissioned using a process si1nilar
The structure provided is intended to encon1pass the facility to that defined in ANS/ASHR.AE Standard 202-2013 and
requirements and enable the addition of sections depending ASHRAE Guideline 0-2013, the OPR becon1e the CFR for
on the syste1ns and asse1nblies to be constn1cted and co1runis- the existing facility and IS updated using the process outlined
sioned. in Infonnative Annex I. The update of the original OPR
Introduction. Includes an overview of the project and the should also focus on all 1nodifications to the facility and those
general reasons \.vhy the project is being unde1taken. A syste,ns and assemblies that are underperforming.
description of the Owner's processes (Cx Process) is typically As the existing-building co1n1nissioning proceeds during
contained in this section. through different phases, the CFR ,nay require updating or
a1nending. This 1nay occur, for example, as the budget and
Key 0\\'ner's Requirements. Includes a listing of key
costs change. No changes to the CFR will occur ,vithout the
Owner's requirements on which the Cx Process will focus
O,vner's written approval. For example, the CFR may require
and that the O,vner (Cx Team) has determined are critical to
that new windo,vs be i1npact-rated certified to Category 5 hur-
the success of the project.
ricane level. If the windo\.v replace1nent bid exceeded the bud-
General Project Description. The size and scope of the proj- get, the CFR could be changed (and approved by the Owner)
ect are included in this section. to design nonimpact-rated windo\.vs ,vith provisions for field-
Objectives. The objectives for acco,nplishing this project are installed protection during a hurricane.
detailed in this section. Developing the CFR includes contributions frotn all
stakeholders that use, occupy, operate, and maintain the facil-
Functional Uses. The expected functional uses (spaces) for ity. The CFR will contain both technical and nontechnical
the facility are detailed in this section. A short description of requirernents (e.g., a technical require1nent would be to
each functional use is included to provide the context in replace roof with an R-30 roofing assembly; a nontechnical
which it was detailed. require1nent would be to co,nply with LEED for existing
Occupancy Requirements. Includes the number of occu- buildings at gold level). The CFR contains specific and mea-
pants (users and visitors) and the schedule of occupancy, surable require1nents (e.g., instead of "the light level in offices
including all special conditions. will be adequate; ' the CFR may read, "the light level in offices
will be 40 fc (430 lux) measured at 2.5 ft (0.75 111) above the
Budget Considerations and Limitations. The expected bud-
floor level"). The CFR 1nust be concise, clear, correct, and
getary restrictions and considerations are contained in this
complete to reduce the risk for misinterpretation .
section. Some of the 1nore general require,nents for the CFR are
Pei;formance Criteria. The performance criteria on which listed below. These require1nents may expand or contract fol-
the: project will be evaluated by the Cx Tea1n are included in lowing focused discussions with the Owner.
this_section. Each syste,n and asse,nbly performance criterion Suggested CFR. contents are as follows:
shquld be 1neasurable and verifiable. Include subsections as
I. User/occupant require1nents
appropriate to organize and explain the criteria:
2. 0\vner-directed requirements
a. ;Cx
'
program require,nents
'
3. Specific facility requirernents, such as environ1nental and
b. 'Econornic and efficiency require,nents energy goals, level of systems control, and/or sustainabil-
c. Envirorunental and sustainability goals ity certification

American Sociely RI Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS Li\:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
4. Training requiren1ents and cornfort require111ents-Jpace te111perature and hu,nidity
5. Sustainability requirements for occupant com(<.Jrt. ft ,nay also include spec~fic para,neters
6. Equip1nent and syste1ns 1naintainability require1nents for critical environ111ents, such as tolerances .for minilnu,n
lighting levels, te,nperature variation, ventilation rates, roorn
7. Capabilities of operators and n1aintenance team
pressurization, noise levels, etc. All variations in occupancy
8. Doctunentation require1nents
schedules should be defined along \vith any subsequent
9. Regulatory require1nents changes in operational para,neters.
10. Ongoing com1n issioning (OCx) requirements
I. Indoor lighting require1nents: Offices 40 fc (430 lux) at
11. Bench1narks
2.5 ft (.075 m). AFF. List other areas and any specific
I 2. Financial require1nents and investn1ent criteria
nonstandard require,nents-.for exa,nple, pendant-
rnounted lighting, illu,nination requirements, special
E3. CURRENT FACILITY REQUIREMENTS
applications.
OUTLINE EXAMPLE
2. Occupant lighting control require,nents: Each office shall
The CFR is developed from all stake holders' requirements be fitted with dual technology occupancy sensors. List any
that are gathered during CFR workshop(s). Where an OPR nonstandard requiren1ents-for exa111ple, ,nultilnode con-
exists, it would be updated and rnodified. The resultant docu- trols.for assernbly spaces.
1nent will be the CFR.
3. Thermal co,nfort requirements: Maxi1nun1 temperature/
The follo\.ving exa1nple docurnent provides a ternplate for
htunidity 72°F (22°C) dry-bulb at 50% rh. list any non-
ho,v a CFR docun1ent ,nay be formatted and what types of
standard te,nperature or hu,nidity require,nents.
information should be covered in typical applications. The
document is structured as a template, given that in most cases 4. Ventilation and filtration requirements: Ventilation sha)I
any specific content fro1n exa1nple projects will serve to li1nit 1neet current ASrIRAE standard filter require1nents for
the scope to the specific issues and objectives of that applica- occupied areas and shall be a mini1ntun MERY 12. list
tion. For each section of the te1nplate, norn1al text provide any nonstandard require111ents.
exa1nple language specific to that section \.vhile italics pro- 5. Occupancy HVAC control requirements: Occupants shall
vides the reader ,vith guidance as to the type of information be able to adjust the temperature setpoint 2.0°F ( I. I °C).
that would be added to that section, specific to the facility List any nonstandard requirements-.for exa,nple, integra-
tmder consideration. tion with existing control systerns.
6. Acoustic environ1nent requirements: Office shall be maxi-
1.0. User-Occupant Requirements 1nu1n 35 roo1n coefficient (RC). list any nonstandard
This section should be used to define any specific require- require,nents-.for exa,nple, local noise sources requiring
rnents ofthe.facility occupants and users that are necessary to rnitigation and spaces such as classroo,ns that require lo1v
,neet the overall ,nission requirements. These n1ay be current background noise and short reverberation ti,nes.
facility.features that ,nust be ,naintained or those that need to 7. Other O,vner requirements (e.g., natural ventilation, oper-
be added to support.facility operation. able tvindolvs, daylight.)

I . Private offices occupants will be able to adjust the te1nper- 4.0 Training Requirements
ature setpoint in the offices.
This section should define the etpectations .for the core co,n-
2. The ground floor (Southwest quadrant) will be converted
petency level o.f the .facility personnel responsible .for operat-
to a cafeteria for users and occupants of the building.
ing the facility. This tvill serve as an evaluating rnetric to
2.0 Owner-Directed Requirements deter1nine any training require,nents necessa,y to achieve the
required comJJetency level at all necessary levels of the .facil-
This section should define any directives given that need to be ity staff:
addressed by the existing-building corn,nissioning process.
This is an interactive process to generate infor,nation I. Factory or on-site training for the Owner, whether o,vner
bettveen all o.f the stakeholders. staff, contracted staff, or users/occupants, shall include a
description and overview of systems, not just the co1npo-
I. The existing windo,vs shall be replaced with impact nents and equip1nent that co1npose each syste111.
rated ,vindows in a 150 n1ph (67.11n/s) zone.
2 . Training should include general orientation and revie,vs of
2. The roof shall be replaced with a green roof ,vith min- the written O&M instn1ctions, relevant health and safety
in1un1 R-35 (R-6. I) thern1al insulation value. issues or concerns, operation in all possible modes, pre-
3. The fire alann system shall be 1nanufactured by ventive maintenance, and co1nmon troubleshooting prob-
National Brand. lems and solutions.
4. Building shall be sprinkled. 3. Training shall be performed for the follo,~1ing building
syste1ns and assemblies:
3.0 Specific Facility Requirements 1. List all syste111s and asse,nblies that have been
This section should de.fine Jpecifzc .ft1nctional require,nents a!Jected- e.g., lighting control security syste,ns, roof
for each area o.f the.facility and space-use variation. This \Viii asse1nbly, etc.
include para,neters such as .functional uses, space needs, 11. List all Jyste,ns and asse111blies that i,vere not
occupancy requirernents, syste,ns or assernblies replacernent, affected- e.g., chiller plant.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 19
No rep1oduciion or networking permitted wilhout license from IHS
4. Building systen1s that the occupants/users shall be trained 9.0 Ongoing Commissioning (OCx) Requirements
on include:
This section should de.fine the OCx require,nents. This 1vill
t. List all syste,ns and asse,nblies that the occupant/user
include the.frequency for the OCx o_f each systern and assern-
needs to operate- e.g., lighting controls.
bly.
5. Most training shall be completed prior to the end of the
Implementation Phase and an electronic copy (DVD for- I. OCx for ,nechanical systems \.viii be perfonned every
1nat) provided for the Owner's use. three years.
2. OCx for electrical and plumbing systems will be per-
5.0 Sustainability Requirements fonned every five years.
The facilities' syste,ns and assemblies shall be renovated/
upgraded to provide long life while promoting environmental 10.0 Benchmarks
quality and resource conservation through sustainable design This section should de.fine the evaluation ,nethods that 1vill be
and constntction. used to compare e.xisting perfor,nance <~f the overall facility,
I . The Cx process shall result in a LEED-EB 2009 certifica- ~ysterns, and assernblies. There are innu111erable criteria that
tion at no lower than silver level. ,nay be e,nployed based on the type offacilities, systems, and
asse,nblies under evaluation. This n1ay involve easily quantifi-
t. List specific sustainability goals-e.g., ,vater f!f!i-
able criteria, such as indoor environ,nental quality issues
ciency, energy efficiency, etc.
(temperature, hzunidity, ventilation rates) or energy per(<Jr-
2. Ongoing commissioning shall achieve the 2030 Challenge rnance (overall or co,nponent energy usage). However, this
to result in zero possible fuel-based energy. ,nay also include more subjective criteria, such as occupant
satis_faction, irnproved occupant productivity, etc. The CFR
6.0 Equipment and Systems Maintainability should define ,vhat ~pec(fic pararneters tvill be used, ho1v they
Requirements
1vill be quantified (baseline), and 1vhat improvements can be
This section should define the mini,num requirements for the e,pected. The CFR should also d(!fine ,vhat bench,nark crite-
,naintainability ojfacility syste111s and asse,nblies. ria ,,vill be used to evaluate the baseline perforrnance. This can
be through established database injor,nationfor sirnilar/acili-
I. All equipment s hall be installed with 1nanufacturer's rec- ties (such as energy usage index [kBtu(ft2 (MJl,n 2)J). Ho1vever;
ommended clearance. this ,nay be difficult 1-vhen evaluating para,netersfor 1vhich no
2. All equiptnent shall be easily accessible to tnaintenance database exists for co111parison.
staff.
3. Adequately sized doors/access panels shall be provided 1. Temperature changes throughout each floor shall not vary
111ore that 4.0°F (2.2°C).
for equiptnent replacernent.
2. Energy consumption shall be 30°/o less than present con-
7.0 Capabilities of Operators and Maintenance Team stunption.
This section should define the capabilities o.f the operators 3. Postoccupancy surveys shall be used. Acceptable responses
and 1nai11tena11ce team, including their experience, training in for all categories shall not be less than 70% of the
specific syste,ns and asse,nblies, and level ofeducation. responses.

1. The HVAC chjllers will be 1naintained by an outside vendor. 11.0 Financial Requirements and Investment Criteria
2. The Owner fire alann technicians have been factory
This section should be used to d(!fine ho1v identified reco1n-
trained and certified in installed syste,ns.
1nendations tvill be evaluated .for irnplernentation. In 111any
3. All the Owner technicians have obtained craft certifica- cases, this rnay be so,ne n1ethod ofecono,nic evaluation (sitn-
tion from technical institutes. ple payback, life-cycle cost, return on investlnent, etc.). Hotv-
eve,; there ,nay be other cases 1-vhere monetary itnpacts o.f the
8.0 Regulatory Requirements expected i111provernents are secondary to other benefits or dif~
This section should define specific regulato,y requirernents .ficult to quantify. It should also be discussed tvhether ,nea-
placed on the operation ofthe facility and what i,npact this ,nay sures ,,vill be evaluated individually or ,,vhether bundling of
have on the ,nanner in ,vhich the facility, syste111s, and asse1n- recorn111ended rneasures can be used. Bundling ,nay allo,v for
blies are operated, 1nonitored, and ,naintained. The spec/fic high-priority itnprovernents ,vith less attractive singular eval-
require,nents ,nay vary throughout the.facility based 011 d(ffer- uation criteria to be co111bined 1-vith other higher-pe1jor1ning
ent functional requirements of specific areas of the .facility. ,neasures to provide a co,nbined project that rneets the overall
Exa,nples ,1,ould be r(!ferences to spec[fic environmental health investlnent criteria.
and safety standards such as College o,fA,nerican Pathologists
1. Project having a simple payback of less than two years
(CA P), and Clinical Laboratory J1nprove1nent Act (CLJA),fed-
will be implemented.
eral, state, and provincial civic and county requirernents.
2. For 1najor changes to systems and assemblies, life-cycle
I. Fire s prinkler systerns- NFPA 13, latest edition (even if costs determine the option to be i1nple1nented. List dis-
not adopted by the Fire Marshall) count rate, period o.f study, escalate rate criteria .for
2. Building code energy, etc.
.. . , . .. .,.,,. .. . . . ,., ...

American Socie~Rl Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS-4H:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is Accon1plish design reviews
merely informative and does not contain requirements Prebid meeting
necessary for conformance to the guideline. Unresolved
objectors on informative material are not offered the right CONSTRUCTION ACTIVITIES
to appeal at ASHRAE.) Conduct preconstruction 1neeting
Contractor submittal review
INFORMATIVE ANNEX F Construction checklists
COMMISSIONING (CX) PLAN Delivery process
The followi ng are exa,nples of the require,nents and fonnats Preinstallation checks
for the docu,nents to be included in the Syste,ns Manual. Installation and start-up checks
This annex provides an example of how to implement a Perfonnance and coordination checks
Cx Plan fron1 project initiation through occupancy. It is not Testing
intended to be a co1nprehensive representation or a best-prac- Docu,nentation
tice exan1ple. Practitioners applying the Cx Process should Systems Manual
carefully follow ANSI/ASHRAE Standard 202-2013 and Training
ASHRAE Guideline 0-2013 and applicable Cx technical Preliminary Cx Process Progress R.eport
guidelines tailored to their specific projects.
The following is an exa1nple outline for a Cx Plan. The OCCUPANCY AND OPERATIONS ACTIVITIES
basic structure of this example is such that each phase of the Seasonal testing
plan has its own section detailing what activities will be Ongoing training
accomplished and guidance on who accomplishes it and how Warranty revie\V
it is completed. The deliverables for each activity are included Lessons-learned ,neeting and report
in an appendix . Each section of the plan \viii have a descrip- Final Cx Process Progress Report
tion of the requirements for that subject. The intent of this for-
mat is for the Cx Plan to become the Final Cx Report at the CONTACT AND RESPONSIBILITY lNFORlvlATION
end of the project by updating the plan and filling in the
results for each section as the project progresses. SCHEDULE REQUIRE!VIENTS
Depending on the size and scope of the Cx Process activ- Provide a detailed description of Cx Process activities and a
ities, it ,nay be beneficial to have three Cx Plans: one for the schedule of activities. The design ,nilestones shall include the
Predesign Phase, one for the Design Phase, and one for the Cx Tea,n meetings, OPR developtnent, design revie\vs, and
Construction Phase. If separate Cx Plans are used, then care the co,npletion of the BoD and the Cx specifications. For con-
must be taken to inform those that are involved in only a por- struction and renovation activities, the additional ,nilestones
tion of the process of the previous ,n aterial. shall include the Cx Team ,neetings, sub,n ittals, installation
checklists co,npletion, start-up plan start and finish, perfor-
COMMISSIONING PLAN mance testing, Owner ,n ove- in, training, operation and ,n ain-
Table of Contents tenance (O&M) and record drawing cotnpletion, deferred
seasonal testing, \varranty review, and final Cx Process Prog-
ress Report. For co1n 1nissioning in existing buildings, ,nile-
OVERVIEW
stones shall include representative tasks from the planning,
investigation, testing, i1nple1nentation, and Hand-Off Phases.
COMMISSIONING PROCESS DESCRIPTION
Appendices in the initiation and design stages of the proj-
ect will state the requirements and responsibilities for that
PREDESIGN ACTIVITIES deliverable. The fi nal results and doctun entation for each itetn
Develop Owner's Project Requirements (OPR) wi II be inserted in the final repot1.
Develop Initial Cx Plan It is not necessary to include copies of documents
Cx Process Issues included in the Systems Manual in the final Cx Report if that
Step 1. Identify syste1ns and assemblies to be Cx Report is included in the Systems Manual, but the location
co,nmissioned. of the docu1nent(s) shall be noted.
Step 2. Record Issues, Schedules, Budgets, and
Expectations. APPENDIX A-OWNER 'S PROJECT REQUIREMENTS
Step 3. Provide docu1nentation and training (OPR)
require,nents
APPENDIX B-BASIS OF DESIGN (BoD)
DESIGN ACTIVITIES
Develop and update Basis of Design (BoD) APPENDIX C-PROJECT SPECIFICATIONS
Update Cx Plan
Develop Cx Process APPENDIX D-COMMUNICATION STRUCTURES
Develop contract documents
Develop and review project specifications APPENDIX E- ROLES AND RESPONSIBILITIES

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~ ~ ~ m ! # Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 21
No rep1oduciion or networking permitted wilhout license from IH S
APPENDIX F-COMMISSIONED SYSTEMS APPENDIX M-TESTS AND DOCUMENTATION
[listing of systems and asse1nblies]
APPENDIX N-SYSTEMS MANUALASSElvfBLY
APPENDIX G-Cx PROCESS
SCHEDULE APPENDIX 0-TRAINING

APPENDIX H-PREBID MEETING APPENDIX P-lvfEETING MINUTES

APPENDIX 1-PRECONSTRUCTION MEETING APPENDIX Q-CORRESPONDENCE

APPENDIX J-SUBMITTAL REVIEW APPENDIX R-WARRANTY REVIEW

APPENDIX K-Cx PROCESS ISSUES APPENDIX S-OPEN ISSUES

APPENDIX L-CONSTRUCTION CHECKLISTS APPENDIX T-LESSONS LEARNED

''
'

·,

'

American Socie~,ql Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IH ~er license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is 2. The design teatn shall gather and organize the information
n1erely informative and does not contain requirements during the creation of the design.
necessary for conformance to the guideline. Unresolved 3. The design team shall subrnit the BoD to the Owner and
objectors on infor1native 1naterial are not offered the right Con11nissioning Authority (CxA) for review and con1ment
to appeal at ASHRAE.) with each design docwnent subrnittal.
4. The BoD shall be updated by the design teatn to provide
INFORMATIVE ANNEX G
increasing levels of detail as the design evolves.
BASIS OF DESIGN (BoO)
5. The BoD shall be updated by the design tea1n to reflect
The following are examples of the requirements and formats changes to design criteria and systems during the subse-
for the docu1nents to be included in the Syste1ns Manual. quent phase of the project and the reason for those
This annex addresses require1nents developed and changes.
included in the BoD docun1ent and must be coordinated ,vith
6. The design team shall ,vork with the Owner and CxA to
the BoD docurnents of other technical guidelines. The BoD
resolve revie,v comn1ents.
docurnent records the major thought processes and assump-
tions behind the faci lity design decisions 1nade to rneet the 7. The BoD shall include signature blocks for acceptance by
O,vner's Project Requirernents (OPR) as they relate to the the Owner and CxA.
Syste1ns Manual. The design professional n1ust read the entire
Boo Content
OPR before starting the BoD. The BoD document captures
important information linking the ''\vhat" of the OPR and The following BoD contents will be edited for each project
"how" of the syste1n design. based on discussions bet\veen the Owner, CxA, or other par-
The objective of specifically docutnenting the Systems ties. Ideally, the requirements for the BoD, third-party Cx,
Manual requiren1ents in the BoD inforn1ation is to provide the sustainable rating certifications, tneasurement and verifica-
parties involved in a project, at each phase in the process, an tion (M&V), energy mode ling, and other nontraditional
understanding of the underlying thinking that led to the selec- design ele1nents are identified prior to receiving proposals for
tion of specific co1nponents, systeins, and syste1n integra- services frorn the design teatn.
tions. This includes documenting the type of systetn chosen, HVAC
as well as docu1nenting those rejected during the initial phase
Sche111atic Design
of the project and why they were selected or rejected. A
design narrative that provides an overview of systen1s in ver- • Occupancy schedule (ti1ne and nu1nber of
bal fonnat is us ually an integral ele1nent of the BoD. people)
The specific contents of the BoD docuinent ,viii vary • Climatic design criteria
fron1 project to project and systen1 to syste1n but in general
• Indoor design criteria, including tolerances (allowable
should address the following for the information required in tetnperatw·e and hutnidity ranges)
the Systems Manual:
• Design diversity per system
a. List s pecific codes, standards, and guidelines considered • Redundancies
during the design of the facility.
• Applicable building codes
b. List the specific building codes being utilized for the
design of the project. This should include the title of the • Additional design require,nents (LEED and energy goals,
code and the year. other special requirements)
c. List s pecific standards (including year of publication) • Sustainable code requirements
being utilized in the design of the project (e.g., ANSI/ • Design narrative, including description of how each sus-
ASHRAE Standard 62.1-2013, NFPA 45-2000). tainable design requirement is met
• Controls syste1n narrative
G1 . BASIS OF DESIGN
• Renewable energy syste1ns narrative
The BoD should be reviewed and updated as part of each
design subtnission during develop1nent of the design, after Optional
issue of supplementary instructions during the construction
• Design narrative (systern options described in sufficient
process, prior to occupancy, and after co1npletion of accep-
detail for energy 1nodeling)
tance testing.
• Ventilation calculations for each above syste1n option
Sample Boo Requirements to Be Contained in Design Develop,nent
the OPR
• Preliminary energy modeling report
Introduction. The BoD is a written docun1ent that shall detail
the design tea1n's approach to the OPR. • Ventilation opti1nization narrative
Process. The general process for producing the BoD shall be • ANSI/ASI-fRAE Standard 62.1 calculations
as follows: • Heating- and cooling-load calculations (input and output
I. The OPR shall provide a list of required infonnation and fi les)
the forn1at for the BoD to the design team prior to the start • Equip1nent cut sheets (equip1nent around which the
of design. design was based)

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 23
No rep1oduciion or networking permitted wilhout license from IHS
• Control schematics, database, points list, sequences, The fonnat and organization of the BoD shall detail the
alann conditions, and operator interface elements design response to the OPR require1nents as follows:
Construction Docu,nents I. Major sections shall include <edit as appropriate for
each project> envelope syste1ns, interior syste1ns, electri-
• Any 1nodifications to design development BoD cal and lighting syste1ns, HVAC syste1ns, renewable
Lighting energy syste1ns, and plu1nbing and service hot-water
(SI-fW) syste1ns. Within each 1najor section shall be sub-
Sche111atic Design
sections labeled for each required design sub1nittal (sche-
• Design power capacity, W/fr- (W/m2) n1atic design, design development, etc.).
• Design illumination levels, fc (lux) 2. An updated BoD shall be required to be sub1nitted with
• Lighting perfonnance goals and standards each design sub1nittal. Updates shall include descriptions
• Lighting and lighting control narrative of changes to the design since the previous sub1nittal, the
reasons for those changes, and additional detailed infor-
• Anticipated lighting power density (LPD) for each space
1nation that beco1nes available as the design progresses.
type
Design sub1nittals for this project include <edit as appro-
Design Develop,nent priate for each project> Sche1natic Design Phase,
Design Develop1nent Phase, and 50%, 95%, and I 00%
• Lighting calculations
contract docu1nents.
• Power load calculations
3. The BoD shall reflect the progression of the design within
• Lighting control zoning diagran1s
a single docu1nent. Sections previously sub1nitted shall
• Lighting systen1 control infon11ation distributed to poten- not be 1nodified but rather addressed, as necessary, in the
tial suppliers nev,r section related to the current sub1nittal.
Optional 4. Non-narrative-type infonnation shall generally be pro-
vided in a BoD appendix for each sub,nittal and be refer-
• Short-circuit study
enced in the narrative.
Construction Docu,nents 5. The main body of the BoD shall be concise, providing the
Ensure lighting controls construction documents include reader with concise descriptions of syste,ns and later
the following: ,nodifications and details on those systems.
• Finalized specification language 6. The BoD shall not duplicate infonnation provided in plans
• Din1ension locations of ceiling-1nounted sensors and specifications but shall reference that infonnation as
• Controls initial calibration criteria appropriate.
• De.finition of the timing of final calibration (for daylight- 7. The BoD shall address how the OPR is i1nple1nented in
ing controls) after partitions/furniture in place the design. For any criterion of the OPR that could not be
n1et, documentation detailing what ,vas done, its impact
• Definition of initial scheduling or tin1e clock require-
on the OPR, and how the OPR. was modified shall be
n1ents
included. It is not intended that the BoD repeat the text of
• Identification of interface coordination requirements the OPR with com1nents addressing each individual OPR
• Definition of any other progra1111ning, such as scenes, criterion but rather that the BoD remain a concise, read-
overrides, or special events able document that is useful throughout the design and
Other Systems construction processes and into occupancy.

Develop BoD requiren1ents for other systen1s as required by Acceptance


the OPR. The BoD shall include signature blocks for acceptance by the
For,nat and Organization Owner and CxA of each BoD subn1ittal.

·· · · · ········ ·· ·· ···· ···

American Socie~ gt Healing, Refrigeraling and Air-Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZATION 595661 7
Provided by IHS4ntder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
(This annex is not a mandatory part of this guideline. It is ings should be included if record dra,vings are not available.
merely informative and does not contain requirements It is also useful to initially include the design drawings in the
necessary for conformance to the guideline. Unresolved Systems Manual and later replace the1n with the record draw-
objectors on informative material are not offered the right ings that are someti111es referred to as as-builts.
to appeal at ASHRAE.) Other record documents include change orders, archi-
tect's supple1nental instructions, and additional infonnation
INFORMATIVE ANNEX H that re.fleets actual constructed conditions.
CONSTRUCTION PROJECT RECORD DOCUMENTS Documents should include all sections of the design
The following are examples of the requirements and fonnats package drawings, such as the following:
for the documents to be included in the Syste1ns Manual. • Site: Including facility location and utility connections
The collection and retention of record docun1ents is
• Civil: Including grading, paving, drainage, and constiuc-
essential to the ongoing operation of the building and can be
tion details
critical in any building upgrades and 1nodifications. These
docu1nents provide the baseline fro1n which repairs, changes, • Landscape: Including listings of plants and irrigation
and upgrades can be made. Without these records, it ,viii be systen1s and controls
1nore costly and time consuming to maintain and modify the • Architectural: Including layouts, elevations, materials,
building. and details
If the record dra,vings and documents are digitized, they • HVAC: Including equipment listing, locations, elevations,
1nay be able to be included in the Systen1s Manual computer and coordination info
file. This is highly reco,nmended. If the drawings are avail- • Plu,nbing: Including layout dra,vings, equipment list-
able in paper or transparency fonnat, the location of the docu- ings, and risers
1nents should be included in the Systen1s Manual. • Electrical: Including power and lighting layouts, risers,
An index and table of contents should be created for both and panel schedules
the digitized and hard-copy dra,ving files. This contents list
• Fire protection and alar,ns: Including piping layouts,
shows all the available drawings at the time of assen1bly. This
controls, and details
will facilitate the location of the specific information needed
and in the updating of the docu1nents. • Conununication syste111s: Including layouts, locations,
The record dra,vings should be included, as they contain and equipment listings
all the changes 1nade to the design dra,vings and documents • Coordination and interference dra,vings
during constiuction and modification. Original design draw- • Other

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~ ~ ~ m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 25
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is • schedules of equipment specific to the project,
merely informative and does not contain requirements including coordinated tag identification, location,
necessary for conformance to the guideline. Unresolved systen1(s) served, capacities, electrical characteris-
objectors on informative material are not offered the right tics coordinated \Vith electrical dra\vings, and addi-
to appeal at ASHRAE.) tional pertinent data ( accessories, special options,
weight, etc.);
INFORMATIVE ANNEX I • that all infonnation, shown on drawings, is legible
PROJECT DOCUMENTS AND SUBMITTAL REVIEW (not hidden by crossing lines or text);
REPORTS
• the design professional's Basis of Design (BoD) nar-
The following are exa1nples of the requirernents and fonnats rative; and
for the documents to be included in the Systerns Manual. A • that OPR information is included on docwnents.
copy of the final review reports are included in the Systems
3. Conduct a quick general review. The general review is
tv1anual to provide history and background on the planning,
intended to fan1iliarize the revie\ver with the sub1nis-
design, and construction of the facility.
sion. If during this review significant ite1ns are identi-
fied as poor quality then the revie\v process should be
11. DESIGN REVIEW REPORT
stopped and the design professionals contacted to dis-
This annex provides an exa1nple of how to i1nple1nent a sa1n- cuss the quality concerns. If the general quality is
pling process if directed by the Owner. It is not intended to be good, 111ove on to the coordination revie\v.
a co1nprehensive representation or a best-practice exa1nple.
Practitioners applying the Co1n1nissioning (Cx) Process Coordination Review
should carefully follow ANSI/ ASHRA E Standard 202-2013 I. If sampling review is approved, determine sa1npling areas.
and ASI-IRAE Guideline 0-2013 and applicable technical For each floor plan area (e.g., if there are five sheets for
infonnation tailored to their specific projects. each floor, then there are five floor-plan areas for each
floor), select a single building area randomly. A simple
Design Submissions
way to do this is to divide the drawing sheet into 15
A critical step in the Cx Process is the review of the design squares (5 x 3) and select square number 3 on the first
submissions from the design professionals. It is irnportant to sheet (area) and then 5, 7, etc., for each remaining area.
remember that the role of the Commissioning Authority This selection typically is conducted using the architec-
(CxA) is to verify that the Owner's Project R.equirements tural sheets. If sa1npling is not approved or is not practical,
(OPR)/Current Facility Requirements (CFR) are met and that the entire document should be reviewed.
the system is designed in a quality manner. There are three 2. Select review satnples on dra\.vings. Using the sampling
distinct reviews that are completed on a dra\ving set: general, strategy chosen in Step I, ,nark the sa1nple areas to be
coordination, and field specific. A review of the specifications reviewed in each area. This should be conducted for each
is also required. trade (landscaping, architectural, structural, plwnbing,
The use of sampling in the design review and the sarn- rnechanical, electrical, etc.).
pling process ,nust be defined in the OPR/CFR. The Cx Plan 3. Conduct coordination review. For each area, co1npare the
can also add requirements and information to the design squares between each discipline. The intent of this review
review process and procedures. is to identify coordination proble1ns with the placement
The general steps of co1npleting a drawing review are as and installation of con1ponents. Items of specific interest
follows: include the follo\ving:
• Placement of n1ultiple pieces of equipment/co1npo-
General Review
nents in the same location
I. Revie\v the OPR. Because the purpose of the drawing • Use of co1nputer-aided design (CAD) software by
review is to verify that the OPR/CFR were n1et, prior to the design tearn that readily discovers and coordi-
the review, the OPR/CFR should be reviewed to fan1iliar- nates points of collision betv.,een building co1npo-
ize the revie\ver with the key criteria of the facility. nents, pltunbing ,vork, sprinkler work, 1nechanical
2. Docun1ent the general revie\v criteria. The criteria from work, electrical work, and other components
which to conduct the general review of the subn1ission selected for the project
must be documented. The criteria should be based on gen- • Accessibility to equip1nent/components for 1nai nte-
eral quality characteristics and specific OPR//CFR crite- nance/replacen1ent
ria. The general quality characteristics should include
• Use of consistent tenninology (e.g., roorn nu1nbers)
items such as .
• Elevations provided where multiple systems are '
'
• continuation of iterns ( ductwork, pipes, \Valls, elec- placed in the same area
trical wiring, etc.) fro,n page to page;
• Other trade duties clearly identified (e.g., window
• labeling, including correct roorn numbering; asse1nblies, roof drains, electric wiring for I·IVAC
• details corresponding to actual cornponents; equip1nent, holes for sinks)

American Socie~ pl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS4JQJer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
If significant coordination proble111s are identified, stop Specification Review
the review and contact the design professionals to discuss. If 1. If sampling review is approved, detennine the review
the coordination is good, continue on \~rith the field specific srunpling procedure. The purpose of this review is to
review. detennine the general quality of the specifications. During
the field specific review, the actual details are checked.
Field Specific Review The sampling procedure should check approxi,nately I 0%
I. If sampling review is approved, detennine the review of the specifications. If sampling is not approved, the
sa,npling procedure as defined in the project OPR/CFR entire docu1nent should be reviewed.
and Cx Plan. Use random sampling that selects every xth 2. Conduct general revie\v. The review should focus on the
square on the drawings to be verified. Squares that are quality of the specification, specifically the following:
completely blank (no \~1alls, equipment, etc.) are not • Are there extraneous sections that do not pertain to
included in the counting. For example, if there are ten the project (i.e., medical gas in an office building, 15
pages of drawings, and each drawing is split into 15 grids types of valves when only two are used, etc.)?
(5 x 3), there \Viii be 150 potential grids to review. If a • If a manufacturer has been listed, has the engineer
20% sa,nple rate is desired, then 30 grids would be checked to verify that the OPR/CFR is met?
reviewed, or every five grids. The starting grid should be • Are there any "or as equals?" (As equal should
chosen using a random selection process (die, 1-6 in a ahvays be defined.)
hat, etc.). If sampling is not approved, the entire docrnnent
• Are the directions clear and concise?
should be reviewed.
2. Doc1unent review criteria. The criteria by which to review 3. Develop a s111n1nary of the review. If there are proble,ns
the drawings should be based on specific OPR criteria. with the specifications, contact the design professionals
This typically includes items such as accessibility, 111ain- and discuss.
tainability, meeting sustainability goals, comfort condi-
Design Professional Actions
tions, documentation of OPR/CFR and BoD, and
operating details. Com1nents provided by the CxA need to be formally replied
to by the design professionals. If syste,nic issues are identi-
3. Select review sa1nples on drawings. Using the sampling
fied during the CxA's review, the design process should be
strategy chosen in Step l, ,nark the sa,nple areas to be
resolved. Back-checking of the specific ite1ns may be appro-
revie\.ved.
priate, but not as the sole ,neans of verifying resolution of the
4. Conduct detailed statistical review. Using the review crite- .
issue.
ria fro,n Step 2 and the selections fro,n Step 3, conduct a
detailed revie\v of the drawings. This includes verifying Design Review Report
that the specifications 1natch those shov,,n on the drawings The design revie\v report should contain the follo\.ving infor-
(see below for specification revie\v details). For example, if 111ation:
an air tern1inal box is in the selected square, the steps in
1. Project title, number, and date of review
conducting the detailed review ,night include the follov,,ing:
2. Executive su1nmary (Include a summary of the process
a. Review design calculation inputs for 1natching archi- used for the review and for processing the co1nn1ents and
tectural assu1nptions and the OPR. responses.)
b. Compare calculation results \vith the total airtlo\v of 3. List of docu1nents reviev,,ed by title and issue nu1nber or
the diffusers downstrea,n of the air tenninal box and date (Include a list of all the docu1nents reviewed.)
v,,ith the tenninal box schedule. 4. Issues, co1n1nents, and variances fro,n OPR (Include cop-
c. Co1npare location of air terminal box with 1nainte- ies of all reviews, distribution lists, and responses.)
nance requirements of the selected make and ,node! 5. Coordination of dra\vings and systems (Include a copy of
d. Co1npare air terminal box location on dra\vings \vith the reviews on drawings and syste,ns coordination.)
require1nents in the specifications. 6. Access, constructability, and 111aintainability questions
e. Review the OPR/CFR for other issues that the air ter- and reco,nmendations (Include a copy of the reviews on
minal box could in1pact. syste1ns and assemblies access, constructability, and
,naintainability.)
5. Doc1unent concerns. During the review of the drav,,ings,
keep detailed notes of problems found or concerns \vith 12. SUBMITTAL REVIEW REPORT
certain items. Also, at the end of the review, a general
The review of the manufacturer's and contractor's submittals
summary of the quality of the drawings should be devel-
is intended to verify confonnance to the project OPR/CFR
oped. A letter detailing the quality of the drawings should and gather information for the testing and commissioning of ;
then be sent to the design professionals and the Owner the equip,nent and syste,n. :
with specific reco1111nendations and directions given. The use of sampling in the sub1nittal revie\v and the sam- :
6. Reviev,, the dra\ving review procedure. After the drawing pling process ,nust be defined in the OPR. The Cx Plan can
review is completed, this docu1nent should be reviewed also add requirements and infonnation to the review process '.
and ,nodified to i,nprove the process for the next ti,ne. and procedures.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 27
No rep1oduciion or networking permitted wilhout license from IHS
The submittal review report should contain the following 4. Issues, comments, and variances from OPR (Include cop-
infonnation: ies of all reviews, distribution lists, and responses.)
I. Project title, number, and date of revie,v
5. Coordination with project systems (Include a copy of the
2. Executive sun1mary (Include a summary of the process
reviews on submittals and systerns coordination.)
used for the review and for processing the con1ments and
responses.) 6. Conformance to functional requirements and maintain-
3. Descriptive outline of subn1ittals reviewed (Include a list ability (Include a copy of the reviews on systerns and
of all the docu1nents reviewed.) assemblies access, constructability, and maintainability.)

American Socie~ Al Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS4Ji\:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is <lard 202-2013 and ASHRAE Guideline 0-2013 and applica-
merely informative and does not contain requirements ble technical infor111ation tailored to their specific projects.
necessary for conformance to the guideline. Unresolved
objectors on informative material are not offered the right Building and System Specifications
to appeal at ASHRAE.) All of the relevant design specifications should be retained in
the Syste1ns Manual. These are usually entered by ConstJuc-
INFORMATIVE ANNEX J tion Specification Institute (CSI) nu1nber. If parts of the Sys-
BUILDING AND EQUIPMENT SPECIFICATIONS tems Manual are in hard-copy format, a colu111n should be
The following are examples of the requirements and fonnats added for the location of those docu1nents.
for the docu1nents to be included in the Systems Manual. It is The specifications part of the Syste111s Manual should
important that the building and equipn1ent specifications are include a list of specifications and relevant inforn1ation on
be included the design drawings in the Syste1ns Manual in their contents, including the following:
order to provide co1nplete inforn1ation on the facility and the
• Specification nu111ber-usually a CSI nu111ber
syste1ns.
• Title of specification from design docun1ents
J1 . COMMISSIONING SPECIFICATIONS • Publication and changes dates
This a1111ex provides an exan1ple of how to i1nple1nent part of • Cross references for syste111s or equip111ent included with
this guideline. It is not intended to be a con1prehensive repre- necessary cross references
sentation or a best-practice example. Practitioners applying • Notes-information that is helpful to utilization of the
the Cx Process should carefully follo\v ANSI/ASHRAE Stan- infonnation

..·. . . .. .,.... .. . . . .., ...

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir,CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~ ~ ~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 29
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is This inforn1ation is essential to understanding and operating
merely informative and does not contain requirements the building, as well as for future changes and upgrades.
necessary for conformance to the guideline. Unresolved The sub1nittal part of the Syste1ns Manual should
objectors on informative material are not offered the right include a list of sub111ittals and applicable specifications and
to appeal at ASHRAE.) relevant infonnation on their contents, include the follo,ving:
INFORMATIVE ANNEX K • Submittal and related specification number-usually a
APPROVED SUBMITTAL$ Construction Specifications Institute (CSI) number
The follov,ing are examples of the requirements and forn1ats
• Title of submittal and specification-fro1n design docu-
for the documents to be included in the Systen1s Manual.
ments
Insert final copy of approved submittals by project speci-
fication section sequence. These documents provide specific • Approval and changes dates
infonnation on the exact equipment and 1naterials installed in
• Cross references for systems or equip1nent included with
the project. If the sub111ittals are in hard-copy format, a col-
necessary cross references
un1n should be added for the location of those documents.
The approved sub1nittals provide detailed inforn1ation on • Notes-infonnation that is helpful to utilization of the
the exact materials and equipn1ent installed in the facility. inforn1ation

..

American Sociel)( Rl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IH~ e r license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is tion criteria needed to operate the facility. Thus, the O&M
merely informative and does not contain requirements n1anuals are only a part of the complete Systems Manual.
necessary for conformance to the guideline. Unresolved The n1anufacturer's installation, operation, and 1nainte-
objectors on informative material are not offered the right nance part of the Systen1s Manual should include a list of the
to appeal at ASHRAE.) n1anufacturer's installation, operation, and maintenance infor-
n1ation and relevant information on their contents. The infor-
INFORMATIVE ANNEX L n1ation included should be limited to the specific equipment
MANUFACTURERS OPERATION AND installed in the building, including the follo,ving:
MAINTENANCE DOCUMENTS
The following are examples of the requirements and fonnats • Equip1nent and specification number-usually a nun1ber
for the documents to be included in the Syste1ns Manual. from the design or installations docun1ents and related
Insert 1nanufacturer-provided installation and Operation Construction Specifications Institute (CSI) number
and Maintenance (O&M) Manuals that have been verified and • Equip1nent title from design or installation documents
localized to the installed building systen1 or equipment by • Publication, approval, and changes dates
specification section sequence. They should be organized to
be easily located and updated. • Cross references for syste111s or equip1nent included with
The manufacturer's O&M docun1ents are usually not necessary cross references
project-specific and often come in catalog fonn. They do not • Notes-information that is helpful to utilization of the
contain the project-specific connection and sequence opera- infonnation

.. . . . .. ........ .·. . ... ·...


Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir,CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 31
No rep1oduciion or networking permitted wilhout license from IHS
(fhis annex is not a mandatory part of this guideline. It is The warranty part of the Systen1s Manual should include
merely informative and does not contain requirements a list of equipn1ent warranties and applicable specifications
necessary for conformance to the guideline. Unresolved and relevant information on their contents, including the fol-
objectors on informative material are not offered the right lowing:
to appeal at ASHRAE.)
• Warranty and related equiprn ent and specification nu1n -
INFORMATIVE ANNEX M ber- usually a Construction Specifications Institute
WARRANTY INFORMATION (CSI) ntunber
The following are examples of the requirements and fonnats • Title of warranty and related equi prnent and specification
for the docu1nents to be included in the Systems Manual. fro,n design docwne nts
These warranty documents can be retained with the equip- • Approval and changes dates
n1ent operating inforn1ation or kept in a separate section for • Expiration dates
ease of use and updating.
The warranty infonnation and copy of the warranty doc- • Cross references for systerns or equiprnent included w ith
u1nents are provided along with the e.ffective and expiration necessary cross references
date to facilitate building operation and expedite repairs of • Notes-information that is helpful to utilization of the
any defective syste1ns or equipment. inforn1ation

.
..

Am erican Sociel)(,ql Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZ ATION 5956617
Provided by IH ~er license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted w ilhout license from IHS
(This annex is not a mandatory part of this guideline. It is The contractor and supplier part of the Syste1ns Manual
merely informative and does not contain requirements should include a list of installing contractors and suppliers of
necessary for conformance to the guideline. Unresolved equipment and materials and applicable specifications and
objectors on informative material are not offered the right relevant information on their contents, including the follow-
to appeal at ASHRAE.) 1ng:

INFORMATIVE ANNEX N • Contractor and supplier name, address, phone numbers,


CONTRACTOR AND SUPPLIER LISTING AND and e-mail contacts and related specification number-
CONTACT INFORMATION usually a Construction Specifications Institute (CSI)
number
The following are examples of the requirements and fonnats
for the documents to be included in the Syste1ns Manual. • Alternate sources and cross references for syste1ns or
Contractor listing and contact inforn1ation are provided equip1nent included with necessary contact information
for emergency operations, maintenance, and 1naterials • Notes-information that is helpful to utilization of the
replacement information. infonnation

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 33
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is 02. SOURCES AND CONTENT OF THE
merely informative and does not contain requirements DOCUMENTS IN THE FACILITY GUIDE
necessary for conformance to the guideline. Unresolved
objectors on informative material are not offered the right Executive Summary
to appeal at ASHRAE.) a The executive sum1nary contains an overview of the building
design, construction, and operational requirements. The infor-
INFORMATIVE ANNEX 0 rnation is intended to provide general guidance on the
FACILITY GUIDE intended operation of the building in conformance to the
Owner's Project Requiretnents (OPR) and Current Facility
The following are examples of the requirements and fonnats
Requirernents (CFR) . In the outline belo\.v, italics provides
for the docu1n ents to be included in the Syste1ns Manual.
the reader ,vith guidance as to the type of infonnation that
This annex provides an example of how to implement a would be added to that section, specific to the facility tmder
faci lity guide. It is not intended to be a co1n prehensive repre- consideration.
sentation or a best-practice exatn ple.
The facility guide is sin1ilar to an operator's 1nanual. It is A. Facility Operations Instructions
intended to provide the basic information needed for the 1. Operating Plan
building operations staff to operate the building on a day-to-
day basis. It includes a si1n ple description of the buildi ng sys- Insert a copy ofthe completed.facility operating plan
tems and their normal operation, schedules, setpoints, and l-vith explanations of the intended use and operation
litnitations. Also included is routine 1naintenance for the sys- o.fthe .facility.
terns to keep them in good condition but not major mainte-
nance or repair functions. Scheduled start-up and shutdown Included in ''General Building /nfor,nation."
functions should be included. 2. Building and Equipment Operating
Developing the facility guide encompasses gathering all Schedules, Setpoints, and Ranges
of the infonnation related to the syste1ns and asse1n blies that Insert a copy o.fsetpoints o.f all equipment lvith oper-
require regular attention and incorporating it into a usable ational adjustrnents. Include the setpoint nor,nal
infonnation resource, with indexes and cross references. This intended ranges and li111itations.
information is edited and organized to focus on the key sys-
tems (HVAC, plu1nbing, electrical, vertical transportation, fire Included in "System Setpoint Require,nents."
alann, security syste1n s, etc.) in the building. Coordi nation
w ith maintenance personnel in developing building standard 3. Sequences of Operation and Limitations
fpnnats and reporting procedures is necessary for the long- Insert a copy o.f the sequences of' operation .for all
t~rm
. operation of the facility. The facility guide is usually
. operating equip,nent in language and.format that is
located in the operations section of the Systems Manual, but it understandable to the property ,nanagers.
d,a n be developed independently if needed.
Based on the needs of the O,vner and building opera- Included in "Building Energy Syste111 Descriptions
tions, the facility guide and Syste1ns Manual could also and Sequence ofOperations."
include infonnation for insertion into a computer mainte-
4. Start-Up and Shutdown Actions
nance n1anage1nent syste1n (CMMS), including equipn1ent
1nake and 1n odel infonn ation, checking require1nents, 1nainte- Insert a copy of routine sy ste,n start-up and shut-
nance requirements, and troubleshooting items. The Commis- dol-vn procedures and locations of applicable con-
sioning Authority (CxA) should be responsible for verifying trols.
the development of the faci lity guide on comrn issioned proj-
ects. The Owner should designate a specific entity to develop Included in "Building Energy Syste111 Descriptions
the facility guide for existing buildings and for the 1nainte- and Sequence ofOperations. "
nance and updating of the facility guide. B. Maintenance Procedures, Checklists,
The entity responsible for developing the facility guide and Records
shall include all iterns involved in the building operation in Insert procedures, for,ns, and checklistsf'or.facility oper-
either an electronic or printed version. This entity (Owner,
ation and maintenance. Include updating requirements.
CxA, contractor, design professional, mai ntenance rnanager, Describe inspections and testing required on a routine
or other) shall have the skills of design, construction, and
basis and standard.for,ns required.
operations required to develop a cotn prehensive faci lity
guide.
Checklists included in "Key Elements to Monitor."
It should be noted that some projects 1nay not include all
of the infonnation outlined in this annex. The outline is pro- C. Maintenance Schedules
vided to supply organization and sources for information Include reco1nn1ended ,naintenance schedules .for sys-
available for the building or project. te,ns and equip111ent along ,,vith update require,nents.

American Sociel)( gt Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZATION 595661 7
Provided by IHS-!lffder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
D. Utility Measurement and Reporting Include OCx and opti111ization procedures and docu,nen-
include description o_f utility tnetering and 1nonitoring tation to 1nonitor and i,nprove the p erfor1nance o.ffacility
systems if that is included in the property 1nanage1nent ~yste,ns.
_functions.
F. Janitorial and Cleaning Plans and Procedures
Provide docu,nent .for1nats and procedures for tracking
utility use and reporting this information to ,neet insert a copy o_ffacility cleaning andjanitorial plan 1vith
o~vner 's andjurisdictional require,nents. procedures and intended chemicals and equiptnent if this
is a .function of the building property ,nanage,nent. These
E. Ongoing Commissioning (OCx) Operational and janitorial plans could also be used to contract .for those
Maintenance Record Keeping services.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS ~ ~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 35
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is 2. Facility Layouts
merely informative and does not contain requirements
necessary for conformance to the guideline. Unresolved Include sirnplified line dra,vings sho,vingfacility site
objectors on informative material are not offered the right plan, floor layouts, and locations of ,najor Jystems,
to appeal at ASHRAE.) control centers. and utility shut-offpoints. This assists
in the orientation ofoperating staff and othe,~~-
INFORMATIVE ANNEX P
FACILITY OPERATING PLAN 3. Operating Schedules
The following are examples of the requirements and fonnats Describe and list planned operating hours .for the
for the doctunents to be included in the Systems Manual. In facility. This is the basis for the more detailed sched-
the sections below, italics provides the reader with guidance ules and sequences o.f operation.
as to the type of infonnation that would be added to that sec-
tion, specific to the facility under consideration. 4. Roles and Responsibilities
A. Facility Operations Instructions Describe the facility rnanagernent organization and
staff and their reJponsibilities. Include the planned
1. Operating Plan use of·contractors and consultants in building opera-
Describe the intended use and operation o.fthe.facility. tion, such as security and janitorial functions.

.. . . . .. ........ . . .
- ... ·...
American Sociel)( pl Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHs.iQJer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is 2. Facility Owner or operator defines the initial desired ten1-
merely informative and does not contain requirements perature for each roo1n or space and any hu1nidity, airflow,
necessary for conformance to the guideline. Unresolved and pressure require1nents.
objectors on informative material are not offered the right 3. Design team for new buildings, or Comn1issioning (Cx)
to appeal at ASHRAE.) Tean1 for existing buildings, sets initial tolerances and
1naxi1num functional ranges for te1nperatures, humidity,
INFORMATIVE ANNEX Q air flow, and pressure require1nents.
BUILDING OPERATING SEQUENCES AND 4. Design tea1n for new buildings, or Cx Team for existing
SETPOINTS buildings, using the Basis of Design (BoD), defines the
The following are exa1nples of the require1nents and fonnats equipment and sequences of operation necessary to
for the docu1nents to be included in the Syste1ns Manual. accomplish the require1nents above.
5. Contractors or building operations personnel for existing
PROJECT: _ _ _ _ _ _ _ _ _ _ _ _ __ buildings provide and install systems to accon1plish the
DATE_ _ _ _ _ REVISION _ __ defined requiren1ents.
ADDRESS: _ _ _ _ _ _ _ _ _ _ _ _ _ __ 6. Cx Tean1 tests and validates the syste1ns performance to
OWNER:_ _ _ _ _ _ _ _ _ _ _ _ _ _ __ the requirements and updates the require1nents and
sequence docu,nents to reflect final conditions.
INSTRUCTIONS: 7. Docun1entation fro1n the above iten1s is entered in the
facility guide and Syste1ns Manual.
1. Facility Owner or operator de.fines the initial operating 8. Building operators are trained and operate the building
schedules, anticipated occupancy, and outdoor air require- based on the docun1entation, which is updated as changes
ments for each roon1 or area. occur.

.. . . . .. ..,.,, .. . . . ... ...


-

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir.Cg__ll(t!iqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 4 Nol for Resale, 201515/28 09:22:15 37
No rep1oduciion or networking permitted wilhout license from IHS
a: a~
" < •
~ i1 ::,,
8. a. :sg
" m
?; ~ (I)
~- g
:c
g~
·· ··· ;;"~ ······ I. ·· SCHEDULES
m m :c
I~ i PROJECT: Example Building EXAMPLE ROOJ\1100,
!!i
!ll ;:; :::-
3 :r 10·
SPACE OCCUPANCY SCHEDULE Office Area
::; > fD
iii (I) w Number of
0. ~ =:
• lJ. Morning
-· > IQni
:Tm Day of Occupied Unoccupied Special Number of Occupants Occupants
0
C
,
0. State Warm-Up/ Outdoor Air Required Notes
i.• ~ Week Time Time Events Time (Min/Max) (Min/Max
g, Cool-Do,vn
,
c.
Special Event)
am3 a:
g
- 5' Ivlonday- ASHRAE Standard 62.1
::c "'m On 6:00 a.in. 7:00 a.m. 6:00pm 6:00pm 6/ 50 6/80
rt>
~
Friday \Vhen Occupied
ar - -
J Off 7:00 a.m. 6:00 p.tn. 6:00 a.m. 10:00 p.m.
~ Saturday On NIA 9:00 a.m. I :00 p.m. 1:00 p.m. 0/20 0/100 ASH RAE Standard 62.1
Oft' NIA 1:00 p.m. 6:00 a.m. Midnight - - Min
Sunday On NIA NIA All 1:00 p.m. - 0/100 ASHRAE Standard 62.1
Off NIA NIA All Midnight - - Min
Holiday On NIA NIA AJI All - - Min
Oft' N/A N/A All All - - Min
Special
Conditions:
~~

.,, .
-m
-,
Q ~
"
• N
!!. ::c
.m m ~
II. SETPOINTS (1-P) Approval_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ Date_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
~;.
-z
2' G) Project~ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
~~
o-i System System
~~"' Temperature Temperature
.. Temp Temperature Pressure Pressure Pressure
;i Room or Occupied- Unoccupied-
Range, Limits- Occupied, Unoccupied,
Pressure Range,
Limits-
~
0
Area Summer/Winter, Summer/Winter, ::1:oF l\1in/max, •
ID. \Vg

ID. \Vg
±in. "'g Min/Max,
OF OF
! fli
OF
68 Sum111er/78

ID. wg

~ Building 75/72 82/68 2.0 +0.05 +0.03 +0.02 0.01/0.1


-
.... Winter

)>
(/l

~
)>
en
Cl
C:
c.:
-
~
:::,

-"
:,,._
rG
-
0
-I'-
ii', '.I'
o 3
:,,
ell s. (II
,:, 0. 5'
" m •
8. a. :s
a~
a· - 8
Cl)

.
:s J: - ·

,Q

•-
"
g'l 0

II. SETPOINTS (SI) Approval_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ Date_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

~-
j B>
"C

g
~
!t.g.
Project._ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

~-
ii; ~
~~
g ~ ni
!i
[~
5. Room or
Temperature
Occupied-
Temperature
Unoccupied-
Temp
Range,
System
Temperature
Limits-
Pressure
Occupied,
Pressure
Unoccupied,
Pressure Range,
System
Pressure
Limits-
~ Area Summer/Winter, Summer/\Vinter, ±Pa
~
-
0
3
j:
-
t!.I1
ea
.J:i.Q.
,
5'
oc oc :1: oc Minimax,
oc
Pa Pa Min/Max,
Pa
(I> "'

:i 20 Sumn1er/
j Building 24/22 28/20 1.1 +12 +7.5 5.0 2.5/25
26 Winter
~


~~

.,, .
-,
Q ~
"
• :,::
!!. N
.m m ~

~ ;.
-z
2' G)
~~
o-i

~~
;i
" (I>

~
0

!
fli
.~-..

"''
""
.. .. ....,. .. .·. ... ...
Ill. SEQUENCES OF OPERATION below setpoint, the unit shall wann the space to setpoint
Approval: _ _ _ _ _ _ _ _ _ _ _Date: _ _ __ by raising the unit supply temperature to 95°F (35°C)
Project_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ (adjustable) until the space te,nperature equals the occu-
AHU#______ Location: _ _ _ _ _ _ _ __ pied space temperature setpoint. If the space reaches the
occupied space temperature setpoint before occupancy,
1. Constant-Volume Air Handler with the syste1n shuts off. If occupancy occurs before the
Supply Fan, Chilled-Water Coil, How-Water Coil, space reaches the heating setpoint, the system switches to
Demand-Controlled Ventilation occupied ,node. Morning wann-up shall occur only once
in a day.
SEQUENCE OF OPERATION 5. Morning Precooling_for Space Te,nperature: If the space
A. OCCUPIED MODE te,nperatw·e is above the occupied space temperature set-
point and the outdoor air te1nperature is above 70°F
I. The supply fan shall be energized by (21 °C), morning precooling shall be initiated by the opti-
n1tun start progra1n. The outdoor air and exhaust air
2. The space te,nperature shall be controlled by da1npers shall be closed during the morning precool
cycle. The unit shall cool the space to setpoint by lower-
3. Heating and cooling space temperature setpoints shall ing the unit supply air ten1perature setpoint to 55°F
have a _ 5°F (_ 3°C) deadband bet\.v een the heating and (13°C) until the space temperature equals the occupied
cooling. space te1nperature setpoint. If the space reaches the occu-
4. The heating-coil valve and cooling-coil valve shall pied space te1nperature setpoint before occupancy, the
1nodulate in sequence to maintain supply air temperature system shuts off. If occupancy occurs before the space
setpoint and space temperature. temperature reaches the occupied space temperature set-
5. Outdoor air shall be provided by point, the system switches to occupied mode. Morning
precool shall occur only once per day.
Mini1nu1n!tnaxi1nu1n outdoor air shall be controlled by
C. SAFETY SHUTDOWNS
Demand-controlled ventilation shall be provided by I. Duct s,noke detection, space smoke detection, and low-
temperature limit trips shall de-energize the supply fan
6. Supply air temperature setpoint shall be reset based on and close the outdoor air dampers. Manual reset of the
space ten1perature. tripped device shall be required to restart the syste,n.
B. UNOCCUPIED MODE 2. When the outdoor air te,nperature is below the outdoor
air low-te1nperature protection setpoint of 35°F ( 1. 7°C)
I. Unoccupied qff:· The supply fan shall be de-energized (adjustable) and the air handler has shut down in alarm,
except when operation is called for as described below. the heating and cooling valves shall cycle as described
Outdoor air da,npers and exhaust da,npers shall be closed previously in the unoccupied off coil protection 111ode.
and return air da111per shall be open. Heating and cooling
valves shall be closed. 2. Fan-Coil Unit with Chilled-Water Coil,
2. Unoccupied Off Coil Protection: When the supply fan is Hot-Water Coil
de-energized and the outdoor air te,nperature is belov.r the
outdoor air low-te1nperature protection setpoint of 35°F SEQUENCE OF OPERATION
(1.7°C) (adjustable) and the mjxed-air te111perature is less A. OCCUPIED MODE
than the ,nixed-air low-te,nperature protection setpoint of
45°F (7.2°C) (adjustable), or the low-temperarure li1nit 1. The unit fan shall be energized by
trips, then the heating-coil valve shall cycle to maintain
1nixed-air temperature protection setpoint of 45°F (7 .2°C). 2. The heating-coil valve shall ,nodulate in sequence to
n1aintain a 70°F (21 °C) space heating setpoint.
3. Unoccupied Setback/or Space Temperature: The supply
fan shall cycle on with the outdoor and exhaust da1npers 3. The cooling-coil valve shall ,nodulate in sequence to
closed when the space temperature drops below the 111aintain a 75°F (24°C) space cooling setpoint.
unoccupied space te,nperature setpoint of 65°F (18°C)
B. UNOCCUPIED MODE
(adjustable). When the fan is energized, the heating shall
1nodulate to ,naintain supply air te,nperatw·e setpoint of l. Unoccupied Qff: The supply fan shall be de-energized
95°F (35°C) (adjustable). except when operation is called for as described below.
4. Morning Warm-Up .for Space Te,nperature: If the space Heating and cooling valves shall be closed.
te,nperature is below the occupied te,nperature setpoint 2. Unoccupied Setback for Space Ternperature: The supply
and the outdoor air te1nperature is below 40°F (4.4°C), fan shall cycle on when the space te1nperature drops
morning wann-up shall be initiated by the optimu,n start below the unoccupied setpoint of 65°F ( I 8°C) (adjust-
progran1. The outdoor air and exhaust air dampers shall able) and shall operate until the space is 4°F (2°C)
be closed and return air da111per shall be open during the (adjustable) above the unoccupied setpoint. Cooling shall
,norning wann-up cycle. If the space te,nperature ,s be locked out. When the fan is energized, the heating

American Sociel~ Rl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS'tH:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
shall modulate to n1aintain 95°F (35°C) adjustable dis- 9. In de1nand control ventilation, the zones with C0 2 sen-
charge temperature. sors shall send the air-handler outdoor air controller a
3. Morning War,n-Up ,for Space Temperature: If the space %C02 signal varying frorn Oo/o -100%. As the largest
is belo,v the occupied temperature setpoint, morning %C02 signal from the zones served by the syste1n varies
wann-up shall be initiated by the optimutn stati progratn. fro1n 50% to I 00%, the outdoor airflow setpoint shall
If the space tetnperature is below setpoint, the unit shall vary from V01 .,n;,, (the unoccupied design n1inimu1n out-
warm the space to setpoint by raising the unit supply door air quantity) to V01 (the occupied design outdoor air
temperature to 95°F (35°C) (adjustable) until the space is quantity).
satisfied. When the space has reached setpoint, the unit I 0. Econornizer cooling is enabled ,vhenever the outdoor air
shall operate in the occupied tnode. If the space reaches temperature is less than 55°F (13°C). When the outdoor
the heating setpoint before occupancy, the system shuts air te1nperature is greater than the supply air te1nperature
off. If occupancy occurs before the space reaches the setpoint, econo1nizer cooling is disabled.
heating setpoint, the systetn switches to occupied tnode.
Morning warm-up shall occur only once per day. B. UNOCCUPIED MODE
I, Unoccupied Off: The supply fan shall be de-energized
C. SAFETY SHUTDOWNS except when operation is called for as described below.
I. Duct smoke detection or space smoke detection shall de- Outdoor air datnpers and exhaust dampers shall be closed
energize the supply fan . Manual reset of the tripped and return air damper shall be open. Heating and cooling .
'
'
device sha11 be required to restart the system. control valves shall be closed.
2. Unoccupied Off Coil Protection: When the supply fan is
3. Variable-Air-Volume (VAV) Air-Handling Units de-energized and the outdoor air temperature is below the
with Supply Fan, Relief Fan, Chilled-Water Coil, outdoor air low-te1nperature protection setpoint of 35°F
Economizer, Hot-Water Outdoor Air Preheat (l.7°C) (adjustable) and the mixed-air temperature is less
than the tnixed-air low-te1nperature protection setpoint of
..
'
SEQUENCE OF OPERATION 45°F (7.2°C) (adjustable) or the low-temperature limit
A. OCCUPIED MODE trips, then the heating-coil valve shall cycle to maintain
1nixed-air te1nperature of 45°F (7.2°C) (adjustable), and
I. The supply fan shall be energized by
the cooling valve shall be open.
4. Morning Warm -up: The opti1nu1n start progra1n shall
2. The supply air duct static pressure setpoint shall be
start the zone heating tenninal boxes, or the unit if reheat
slowly ra1nped fro1n zero to the final setpoint value after
is the heating source, at the latest possible titne to reach
the supply fan is started.
the desired occupied space temperature setpoint at occu-
3. The air-handling unit supply fan speed sha11 modulate to pancy ti me. Tfthe average space temperature is below the
1naintain duct static pressure setpoint of 1.5 in, wg (370 occupied space te1nperature setpoint, the zone fan or sup-
Pa) (adjustable). ply fan shall energize, and the outside and exhaust dan1p-
4. The static pressure setpoint shall be reset so that at least ers shall retnain closed and the return darnper shall be
one of the VAY boxes is at 90% (adjustable) open. open. The heating-coil valve shall 1nodulate to maintain
5. A high li1nit duct pressure function shall reduce the sup- supply air temperatt1re setpoint of 95°F (35°C) (adjust-
ply fan speed to keep the supply duct pressure from able) until the average space te1nperature equals the
exceeding 2.5 in. \.vg (620 Pa) regardless of the de1nand occupied space temperature setpoint. The supply fan
fro1n the VAY boxes. speed shall be controlled as described in the occupied
6. The preheating-coil valve, mixed-air dampers, and cool- n1ode. The VAY boxes shall 1nodulate to rnaintain the
ing-coil valve shall 1nodulate in sequence to maintain occupied space temperature ,vhile the unit is delivering
supply air temperature setpoint. Provide a deadband of wann air. When the occupied space te1nperature setpoint
5°F between heating and econo1nizer cooling. is reached, the unit shall operate in the occupied 1node.
Morning warm-up shall occur only once per day.
7. The supply air temperature setpoint shall be reset from T-
inin (53°F [12°C]) ,vhen the outdoor air temperature is 5. Morning Precooling: If the n1onth falls bet,veen May and
70°F (21 °C) and above, up to T-tnax when the outdoor October (adjustable), the outdoor air te1nperature 1s
air te1nperattu·e is 65°F (l 8°C) and below. T-1nax shall below 55°F (13°C) (adjustable), and the average of the
range fron1 55°F to 65°F (l3°C to l 8°C). T-max shall three highest space ten1peratures exceeds precool space
va1y such that the VAY box with the highest cooling te1nperature setpoint, 1non1ing precooling rnay begin.
de1nand is at 90% of its cooling n1ax setpoint. The unit shall start in the precool mode as detem1ined by
an optirnwn start prograrn at the latest possible time to
8. Outdoor air shall be provided by
have the space at the occupied setpoint at occupancy
time. The econon1izer cooling ,node shall 1nodulate the
Mini1nu1n/1naxi1nu1n outdoor air shall be controlled by outdoor air and return air da1npers to provide 55°F
(l 3°C) (adjustable) supply air. The heating and cooling
De1nand-controlled ventilation shall be provided by valves shall be closed. The supply fan speed shall be con-
trolled as described in the occupied n1ode. When the

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 41
No rep1oduciion or networking permitted wilhout license from IHS
average of the three highest space temperatures falls gize the supply fan and close the outdoor air and exhaust
below the occupied space temperature setpoint, the unit air dampers. Manual reset of the tripped device shall be
shall return to unoccupied 1node. When the space has required to restart the system.
reached this setpoint, the unit shall operate in the occu- 2. When the outdoor air temperature is below the outdoor
pied mode. Morning cool-dov.rn shall occur only once per air lo,v-te1nperature protection setpoint 35°F (I. 7°C)
day. (adjustable) and the air handler has shut down in alann,
the heating and cooling valves shall cycle as described in
C. SAFETY SHUTDOWNS
unoccupied mode.
I. Duct smoke detection, space s1noke detection, duct pres-
sure safety, and low tetnperature litnit trips shall de-ener-

American Sociel~,q(Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IH~er license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
.
No rep1oduciion or ~etwotking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is An HVAC example is used in this annex, but similar list-
n1erely inforn1ative and does not contain requirements neces- ings can be prepared for all syste1ns. ANSI/ ASHRAE/ACCA
sary for conformance to the guideline. Unresolved objectors Standard 180-2012 should also be used for 111echanical main-
on informative material are not offered the right to appeal tenance infonnation.
atAS HRAE.) Inspections/111aintenance documentation shall be placed
in a con1puter-based 111aintenance system. The checklist in
INFORMATIVE ANNEX R Table R-1 details items that are included in inspections as an
MAINTENANCE PLAN, PROCEDURES, example. Specific facility and equipn1ent inspections are
CHECKLISTS, SCHEDULES, ANO RECORDS sho\vn in Table R-2.
The fo llowing are examples of the require1nents and fonnats
for the docu1nents to be included in the Syste1ns Manual.

TABLE R-1 Example Building Systems List and Schedule

Frequency,
Co,npulsory Service Contract
l\.'lonths
Building-Related Installations
Autornatic fire alarrn l X X

Autornatic fire-alarn1 routing to fire brigade X

Autornatic fire-alann certificate rene,va.1 I X X

Autornatic fire doors inspection I X

Autornatic fire doors test \Veekly X

Fire da,n_pers test according to fire instal.lations operation and rnaintenance (O&M) 1 X

Fire hoses/portable fire extinguishers inspection I X X

Fi re hose pressure test 60 X X

Portable fire extinguishers pressure test/renewal 60 X X

Srnoke ventilation test according to fire installations O&M 1 X

Stand pipes test according to fire installations O&M I X

Short-break systern service including diesel generators 12 X X

Short-break systern test \Veekly X X

Ernergency Iighti ng service 12 X X

E,nergency lighting test I X X

Cooling plant inspection 2 X

Cooling plant service according to rnanufacn1rers requirernents l X X

Elevator service 6 X X

Elevator fal I test 36 X X

Fan coils fi lters 2


Heat exchangers district heating fi lter exchange l
Heat exchangers district heating inspection and service 12 X X

Natural gas boilers inspection and service 12 X

Ventilation plant fi lters I


Ventilation syste,n inspection and service 12 X X

Freshwater distribution systern service 1


\\later analys is, including legionellosis X

Cleaning of fi lters and change of batteries in nontouch ,vater faucets I


Autornatic doors l X

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 43
No rep1oduciion or networking permitted wilhout license from IHS
TABLE R-1 Example Building Systems List and Schedule (Continued)

Frequency,
Compulsory Service Contract
Months
Building-Related Installations (contd.)
External rnechanical solar shading 1

Change of light bulbs, etc. 48


Access control systern, locks, and electronic substations inspection and service 12 X

Paging systen1 12 X

Burglar alarn1 syste111 12 X

Internal TV syste111 12
Cornpressed-air syste111 12 X

Vacuun1 systern 12 X

S,.vitchboard thennography 12 X

Building n1anagen1ent systern (BMS)-control of alanns or functions 1 X

1\1edicotechnica/ Installations
Linear accelerator 1 X

MR scanner 1 X

CTscanner 1 X

Patient lifts 6 X

IndoorO&M

Exchange of door rnats Twice weekly X

Window cleaning 2 X

Outdoor O&M

Roof sv,eep and cleaning of leaf grate 2 X

Cleaning sand h·ash rack 1 X

Window cleaning 2 X

Graffi ti rernova l 12 X

TABLE R-2 Example for Building and HVAC Equipment Inspections

System Function Cycle Corrective Action

I. Air filters Inspect filters for use of specified type, function, pressure Monthly Replace fi lters that exceed allo\ved
drop, dirt loading, contan1ination, installation with tight fit pressure drop, are loaded with dirt,
to eli111inate air bypass. or have becorne \Vet or
contan1inated. Ensure proper
installation.

2. Dampers Inspect darnpers for proper function and adjustn1ent. Verify Monthly Repair dan1pers and seals and
airflow rates; include a visual check n1ark on dan1per handle ensure they operdte as required.
to verify it has not been tarnpered \vith since balancing. Exercise darnper operdtion frorn
stop to stop (full open, full closed).

3. Drain pans Inspect drain pans and adjacent surfaces. Test drdin function Monthly Clean if dirty or if there is evidence
by pouring water or le.aning agent into pan and observing of growth or dirt.
enti re drainage cycle. All antifungal chen1icals shall be in
place where biofiln1s, slirnes, or fungi grow.

.. . .. .. ...... , . .-. . ... ·...


American Sociel~ gt Healing, Refrigeraling and Air-Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS'tritder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
TABLE R-2 Example for Building and HVAC Equipment Inspections (Continued)

System Function Cycle Corrective Action

4. Air plentuns Inspect for cleanliness, blockage, in1proper n1aterials in Sen1iannually Clean out dirt and 1nicrobial
plenun1, n1icrobial growth, or hazardous n1aterials. growth. Remove contan1inated
insulation. Coat/paint with
anti1nicrobial coatings.

5. Coils Inspect coils for cleanliness, n1icrobial growth, and pressure Sen1iannually Degrease, sanitize, and clean dirty
drop. coils.

6. Major air-handling Inspect for cleanliness and dan1age. Sen1iannually Clean dirt and dust with HEPA
con1ponents vacuun1. Clean grease and oi I
con1ponents with degreaser
chen1icals. Ren1ove and replace or
repair dan1aged areas with like
n1aterials.

7. Intake louvers Inspect louvers, adjacent areas, and bird screens for Se1niannually Repair as required.
cleanliness and functionality.

8. Trap prin1ers Inspect for proper function. Sen1iannually Repair or replace if not operational.

9. Access panels Inspect for function and condition. Sen1iannually Repair defective panels and
equipn1ent.

I 0. Outdoor air Test, adj ust, and balance outdoor air supply flov" to design Annually Repair equipn1ent as required.
rate and n1ark da1nper or control position.

11. Zone box controls Verify control operation and setpoints. Annually Correct setpoints and n1ake
necessary repairs.

12. Lighting Verify operation of lighting controls and dimn1ing. Annually Readj ust or replace defective
controls.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 5956617
Provided by IHS~ ~ ~ m ! # Ml-U.e I . 4 -LU 14 Nol for Resale, 201515/28 09:22:15 45
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is • Reporting to the facilities 1nanager
merely informative and does not contain requirements • Servicing the facility after special events according to the
necessary for conformance to the guideline. Unresolved environ1nental and maintenance quality plan
objectors on informative material are not offered the right • Ensuring that noisy custodial work, such as vacuu1ning
to appeal at ASHRAE.) or floor polishing, is perfonned at night

INFORMATIVE ANNEX S • Maintaining records as required


ONGOING COMMISSIONING (OCX) AND • Having a 1nini1nu111 of one qualified custodial technician
RECORDKEEPING on site during the work hours of 8 a.111. to 5 p.111., Mon-
day through Saturday, who will respond quickly when
The following are examples of the requirements and formats
called to perfonn specific tasks as needed.
for the documents to be included in the Systems Manual.
These provisions apply to the entire building. The occu-
S1. GENERAL REQUIREMENTS- pants of the building have the authority to ca11 on-site contrac-
SCOPE, PURPOSE, RESPONSIBILITY, tor perso1u1el for specific and in11nediate housekeeping issues
TRAINING, SECURITY that 1nay arise.
The contracted custodial 1n anager is responsible for the
Scope training of personnel and the supervision of the green custo-
This doctunent provides the facility description and opera- dial functions in execution of this plan.
tional require1nents to i1nple1nent an environ1nental and 1nain- The contracted custodial technicians are responsible for
tenance quality plan for the title facility after construction. the execution of the green custodial plan.

Purpose Training

The purpose of this plan is to provide a su1nmary of the infor- Training of the indoor air quality tea1n is essential in the oper-
1nation needed to understand and operate the title facility in a ation of an environ1nental quality progra1n. All persons in the
1nanner that provides an acceptable indoor environn1ent. The facility have an i1npact on the quality of the indoor environ-
training and procedures as ,ve11 as the materials used by the 1nent. Each group of building operators and occupants should
custodial and n1aintenance staffs are of particular importance. have a training progra1n appropriate to their involve1nent.
Included in this infonnation are a facility description; build- These groups could include the following:
ing function and uses; custodial and maintenance che1nicals, • Building 1nanagement and operations
custodial procedures, training requiren1ents, the location and
• Sectu-ity
use of record docun1ents; syste1ns modification criteria; oper-
• l'vfaintenance
ating and 1naintenance schedules, ventilation standards, and
outdoor airflow rates; environmental inspection checklists; • Custodial
and an environ1nental complaint procedure. • Occupants

All of these groups receive safety training. It is equa11y


Key Players and Responsibilities
important to require environmental training to 1naintain the
The faci lities manager has the primary responsibility to building environment.
ensure that the appropriate facility standards are used and that A training progra1n ,viii be developed for each group
confonnance is 1naintained to provide acceptable indoor envi- based on its specific function and the chemicals used. Each
ronmental quality to the faci lity occupants. He or she is also progra1n ,viii include basic understanding of building function
responsible for ensuring that service contractors are con- and operation; location and use of ,vritten procedtu-es, stan-
tracted and trained to confonn to the green requirements. The dards, and record docu1nents, specifically including 1naterial
facilities manager is tasked with coordination and communi- safety data sheets (MSDS) for all chetnicals; basic under-
cation ,vith the necessary departments affected by this plan standing of the building environ1n ental prograrns; and proce-
and has the primary responsibi lity for the plan updates. He or dures and standards for the group's job function.
she is also responsible for training of personnel and for super- In addition to the basics above, each group wi11 have spe-
vision of the green facil ity maintenance function. cific training as fo11o,vs:
The contracted service provider has the overall manage-
ment oversight for the prograrn and provides the 1notivation 1. Building 1nanagement will have training in environmental
for plan accornplish1nent. The contracted service provider is manage1nent procedures and plans, including EPA, ISO,
responsible for the following: and industry standards; chemical and materials procure-
ment; chemical and materials manage1nent and storage
• Providing research and acquisition of materials and ser- requirements; building occupant complaint procedures
vices to Green Seal Standards to acco1nplish the plan ele- and record keeping; and the review and updating of this
ments plan.
• Enstu-ing that custodial 1nanager and custodial techni- 2. Sectu-ity personnel training will include environ1nental
cians are trained to confonn to the Green Seal require- and safety building require1nents; general overview of
1nents custodial and 1naintenance functions; che1nical storage

American Sociel~ pl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZATION 595661 7
Provided by IHS'f.lQJer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IH S
requirements; and emergency chen1ical and environ1nental che1nical storage requirements; and e1nergency proce-
procedures. dures.
3. Maintenance personnel training will include environ1nen-
tal factors in facility and equipn1ent 1naintenance; equip- Special Security Requirements
1nent operations and schedules; chemical and 1naterials All personnel and contractors entering the building to perfonn
procure1nent and storage requirements; record-keeping housekeeping or maintenance n1ust be authorized by the
requirements; and emergency operating procedures. Owner and facility n1anager. Persons 1nay be subject to back-
4. Custodial personnel training will include effective clean- ground checks and training to comply ,vith current NERC
ing procedures; pennitted chemicals; use and 1nixing of standards CIP-004 and CIP-006. This n1ay include passing a
cleaning che1nicals used in the building; chemical storage seven-year critninal background check, co1npletion of annual
requirements; and emergency environn1ental procedures. training, and attendance at a quarterly Awareness Progra1n
5. Building resident training ,viii include chen1ical and 1nate- meeting. Authorized persons will be revie,ved and reapproved
rials allowed and specifically excluded in the building; quarterly by the O,vner and facility manager.

BUILDING AND EQUIPMENT CHECKLISTS


(Select specific items for each area/systen1/unit fron1 master inspection list.)
Inspector: _________________________ Date: ______________
Equipment/System Name: _________________ Designation: ____________
Location: - - - - - - - - - - - - - - - - - - - - - - - - - System Associated: _________
Man ufacture r: - - - - - - - - - - - - - - - - - - - - - - - Model #: _ _ _ _ _ _ _ _ _ _ __
SeriaI #: - - - - - - - - - - - - - - - - - - - - - - - - - - Date of Mfg: _ _ _ _ _ _ _ _ _ __

Item Component OK/NA Needs/Results Comments Follo,v-Up

Notes:

+4 . • • • • , . , • •, • • • + ' . , • •••

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir-~!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZATION 595661 7
Provided by IHS~ ~ ~ m ! # Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 47
No rep1oduciion or networking permitted wilhout license from IH S
(fhis annex is not a mandatory part of this guideline. It is be placed at all entries to carpeted areas, including outside
merely informative and does not contain requirements entries, stairwells, and entries to all other surfaces.
necessary for conformance to the guideline. Unresolved a. If walk-off n1ats are used, they should be vacuwned
objectors on informative material are not offered the right according to the following schedule:
to appeal at ASHRAE.)

INFORMATIVE ANNEX T Building Area Vacu umed


JANITORIAL AND CLEANING PLANS AND Private areas I ti,ne dai ly, 4 passes
PROCEDURES
Public or se,nipublic 2 ti1nes daily, 4 passes
The following are examples of the requirements and formats
for the docu1nents to be included in the Syste1ns Manual.
b. If a carpet surface is used, it should be vacuun1ed daily
T 1. CUSTODIAL PROCEDURES using the schedule above. Carpets should also be
General Procedures Overview extracted according to the following schedule:
All offices, classroo1ns, and building service areas shall be
operated and rnaintained in an environrnentally responsible Building Use Extract
n1anner, with the follo,ving being addressed:
Private areas Once ,veekly
I. An effective recycling program exists for paper and other
Public or sernipublic T,vice week ly
com1nodities (cardboard, glass, plastic, and alumintun)
that can be recycled, through progra1ns that ernphasize
reuse and waste rninin1ization. 2. Vacuu,ning: Daily vacuuming is the most i1nportant part
2. There is a 1nini1nization of waste paper and other dispos- of the total carpet care program. Improper or ineffective
ables. vacuu1ning will accelerate wear and allow dirt and grit to
3. Substantial compliance with the procedures and products penetrate surfaces.
recomn1ended in the Pennsylvania Green Building Opera- a. Vacuum. specifications: All areas should be vacuwned
tions and Maintenance Manual is reco1n1nended ,vherever with a dual- (2) rnotor vacuurn \Vith an internal filter-
applicable, with respect to the following: ing systern for cleaner discharge of 3 1nicrons or less.
• Custodial services The vacuurn should have a 3500-rpin chevron brush
• Landscaping with pile height adjustrnent, bn1sh wear adjustrnent,
and top loading bag. No single-rnotor, cloth-bag vacu-
• Roofing and parking
ums, or backpack vacuurns will be used.
"Substantial compliance" \.vith the rnanual means that b. Vacuu,n .frequency : All areas classified as "heavy" and
the facility 1nust dernonstrate for each area covered in the "rnoderate" traffic should be vacuwned daily. Low-
manual that it complies with 80% of the procedural guide- traffic areas should be vacuwned two (2) ti1nes
lines (action ite1ns or key points or equivalent, in bold) weekly. Heavy-traffic areas are typically classified as
and is using products that conform with recon11nended lobbies, traffic lanes, interior aisles, entrances, eleva-
criteria for at least 50% of custodial products and at least tors, and break rooms. Moderate-traffic areas are clas-
75% of other products. sified as interior aisles and conference roo1ns. Low-
4. Renovations or new buildouts use environ1nentally prefer- traffic areas are typically classified as cubicles and
able 1naterials and syste1ns. general office space.
The facility will have policies and procedures ensuring 3. Spots and Stains: Spots and stains are a detriment to an
that green faci lities' operation and 1naintenance (O&M) expected high appearance level. These should be attended
are applied on a continual basis. In particular, the building to on a daily basis.
a. provides training to all relevant staff on enviro111nen- a. Pretreatment: Prespray the spot \.Vith a water-based
tally responsible products and practices for green solvent (pH 8.5 to 9.5), and allo,v 10 rninutes of dwell
facilities ' operation and n1aintenance and
time. Agitate soiled area with a soft-bristled nylon
b. routinely 1nonitors its perforn1ance by conducting an
brush and extract residue with wann water.
internal audit at least every six months that involves
b. Coffee spills: If the water extraction stain is a coffee
periodic collection and tracking of data on perfor-
spill, use coffee spot re1nover and follow 1nanufac-
mance in green facilities' O&M, evaluation against
turer's reco1111nended procedures. Do not extract or
explicit perfonnance targets, and 1nanage1nent review
blot. Sirnply spray affected area.
for improven1ent or realign1nent.
4. Extraction: I-lot-water extraction provides rapid soil ernul-
Specific Custodial Procedures sification, as 1nost of the cleaners used for extraction are
low foarning and noncorrosive. They penetrate into the
Housekeeping Guidelines
carpeting and loosen the soil for easy re1noval while
I. Soil Control Syste,ns: Soil control syste1ns are the first extracting. The pH of the detergent used should not
defense against surface soil and grit. Walk-off 1nats shall exceed I 0.5.

American Sociel~ gt Healing, Refrigeraling and Air·Conditioning Engineers, Inc . licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS'f.li\:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
a. Extractor spec(fication: Equip1nent perforn1ance char- gallon or litre of hot ,vater. Extract the carpet. If there
acteristics are critical to ensure effective and co,nplete are any large stains, it is advisable to prespray the1n
extraction. Use a self-contained hot-,vater extractor prior to extracting. (See IICRC SOO 1-1994, Carpet
with a minin1um of 100 psi (690 kPa) water pressure Cleaning Standard, Section 3, "Spots and Stains.")
through the injection nozzles, a reel-type soft-bristled
6. Vinyl Co,nposition and Concrete Floors: Vinyl tile, com-
agitation brush, and water lift of 130 in. (330 cm).
position, and concrete floors shall be swept daily with an
b. Schedule: Schedule ofhot-,vater extraction cleaning.
oil-free dust mop or vacuum cleaner. Dan1p 1nopping n1ay
i. High traffic: Heavy and high-traffic areas shall be
be necessary to re1nove dried liquids or 1naterials.
extracted on monthly basis.
ii. Afediu,n traffic: Moderate-traffic areas shall be a. Schedule: Floor scrubbing shall be performed quar-
extracted every three 1nonths. terly in high- and moderate-traffic areas and annually
iii. Lo1,v traffic: Low-traffic areas shall be extracted in light-traffic areas.
every six months. b. Scrubbing: Scrubbing shall be preceded by a nonoily
1v. Special areas: Heaviest traffic areas n1ay require dust mop. Using a neutral liquid floor cleaner recom-
additional attention once traffic patterns have been 1nended by the flooring manufacturer, scrub the floor
established within the buildings. These areas very with a con11nercial scrubbing machine of 170 to 250
often include entrances, lobbies, and aisles directly rpm capability and equipped with a moderately abra-
adjacent to entries. sive scrubbing pad (blue or green pad). Keep the floor-
5. Carpet Cleaning Che,nicals: Only preapproved carpet ing wet at all times during the procedure but do not
cleaning che1nicals ,viii be used. Ensure fuat the che1nical flood the floor. Absorb the cleaning solution with a
1nanufacturer's recomn1endations and safety procedures 1nop or ,vet vacuu,n. Rinse the floor with clean ,vater
are followed. Do not exceed the recommended dilution after washing, follo,ved by a wet pickup vacuun1 or
ratios for any cleaning product. Chemical use should con- da1np mop.
fonn to all regulatory guidelines.
c. Finishing: After the floor has been cleaned, apply
a. PreJpray spotter (pH 8.5 to JO): Prespray the area to
three to five coats of a good metal cross-linked liquid
be cleaned. Allow the prespray eight to ten (8 to 10)
acrylic finish that is resistant to water spills and is non-
minutes of dwell tin1e. Extract the presprayed area
removable by a neutral floor cleaner.
with hot ,vater only. Note: do not prespray too large an
area. If the prespray is allowed to dry prior to extrac- 7. Mold Re,noval: All 1nold in the building or building sys-
tion, it is ineffective. tems shall be professionally re1noved according to IICRC
:_b. Detergent (pH not to e,-..:ceed 10.5): Dilute the deter- Standard S520, Standard and Reference Guide.for Profes-
gent to the che1nical manufacturer's specified ratio per sional Mold Ren1ediation.

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 49
No rep1oduciion or networking permitted wilhout license from IHS
(fhis annex is not a mandatory part of this guideline. It is Tenants will rent space with Green lease prov1s1ons,
merely informative and does not contain requirements including owner access to utility use infonnation, n1easure-
necessary for conformance to the guideline. Unresolved n1ent and verification (M&V) reporting requiren1ents, and
objectors on informative material are not offered the right Green equipn1ent procuren1ent standards. The building and
to appeal at ASHRAE.) lease are intended to help tenants achieve LEED Cl certifica-
tion. Tenants will be responsible for purchasing and installing
INFORMATIVE ANNEX U their O\vn rooftop units to provide heating and cooling.
UTILITY MEASUREMENT AND REPORTING
The following are exa1nples of the require1nents and fonnats Section 2: Intent
for the docu1nents to be included in the Syste1ns Manual. The purpose of this M&V plan is to describe the methodology
Include description of utility 1netering and n1onitoring to measure building performance and compare it to the base
syste1ns, including type and 1nodel nu1nber, and location for year of the as-designed/as-built and to the ANSI/ ASHRAE/
each meter and submeter (see Table U-1 ). IES Standard 90.1-2010 code baseline facility. This allows
Provide docu1nent formats and procedures for tracking the building owner/operator to determine if the facility is
utility usage and reporting this information to 1neet Owner's n1aintaining its planned level of use and ultimately whether it
and jurisdictional require1nents (see Table U-2). is i1nproving or deteriorating. The intent for in1plen1enting
The following plan exa1nple is provided for use in cases this M&V plan is to
where a rnore detailed 1neasurement and verification plan is l . increase energy savings by giving feedback on the opera-
needed. tion of the building, allowing the operator to adjust facility
1nanage1nent to deliver higher levels of energy savings,
MEASUREMENT AND VERIFICATION PLAN
greater persistence of savings, and reduced variability of
PROJECT NAME .
savings;
PROJECT ADDRESS
2. facilitate operation and 1naintenance (O&M) trouble-
Table of Contents shooting by providing feedback, which should facilitate
improve1nents in the O&M process and i1nprove training
Section Content Description and building perfonnance;
Section 1: Building Description 3. provide continued docu,nentation of the performance of
Section 2: Intent the building for owners, investors, tenants, designers, and
potentially, governtnent agencies, when required; and
Section 3: tvleasurernent and Verification Option and
4. to satisfy the requirements of LEED.
Botmdary
Section 4: Baseline Section 3: Approach
Section 5: Reporting Period 3.a. Summary of Approach
Section 6: Adjustments The various options and boundary to the M&V process are
shown on the following pages. These options \.Vere developed
Section 7: Analysis
by the U.S. Departtnent of Energy and other organizations as
Section 8: Energy P1ices the International Perfonnance M:easuretnent and Verification
Protocol (IPMVP) to provide an overview of current best prac-
Section 9: Meter Specifications
tice techniques available for verifying results of energy effi-
Section 10: tvlonitoring Responsibilities ciency, water efficiency, and renewable energy projects. More
Section 11: Accuracy infonnation on this process can be found on the Efficiency
Valuation Organization \.vebsite at www.evo-central.org.
Section 12: Budget
The option used in this plan and facility is Option D, cal-
Section 13: Satnple Report ibrated si1nulation. Building syste1ns that operate with energy
Section 14: Quality (natural gas, electricity, etc.) shall be 1nonitored on a relevant
ti1ne fra1ne. This 1nonitoring system will be as sophisticated as
NEW CONSTRUCTION BUILDING required to accurately deliver pertinent building perfonnance
data to the M&V tea1n.
Section 1: Building Description The base year enerf:,>y utility use will be developed with
The Seven office building is a 236,000 ft2 (2 1.9 1112), two- co1nputerized 1nodeling. This building 1nodel has been devel-
story structure recently built and currently unoccupied. Ten- oped using the Ac1ne software. The options of use of the
ants are being sought, and lease negotiations are cu1Tently 1nodel for the building are included in Section 5 of this plan.
underway with at least one potential tenant. The building is After a year of building data has been recorded, the base year
expected to be fully occupied by the third quarter of 2010 can be established, once the model has been calibrated and its
with two to six tenants. The Seven was constructed as a core accuracy verified by recording building 1nonthly 1neter read-
and shell building on its own site in any city, with adjacent ings over the first year of full occupancy operation. Fonns are
ground-level parking. included in Appendix A for this purpose. These are available

American Sociel}! Rl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IH~ e r license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
TABLE U-1 Description of Utility Metering and Monitoring Systems

l\1eter Type Brand & l\1odel N umber Location Notes

\\later

Electric

Natura l Gas

TABLE U-2 Document Formats and Procedures for Tracking and Reporting Utility Use

\Vater \Vater Electrical Electrical Fuel F uel


l\1onth Usage K, Cost, Usage K, Cost, Use, Cost,
gal U.S. dot \ Vhr U.S. dot therms U.S. dot

January
February
March
April
May
June
July
August
September
October
Novernber
Decernber
TOTAL

as spreadsheet fonns and can be used to produce co1nparative Syste1ns Manuals. Future tenant electrical and lighting
graphs for better visualization. syste1ns will be shov.,n on future lease finish drawings.
Accurate utility rates will also need to be acquired before
the calibrated 1nodel can be co1npleted and the base year val- These building plans and the desired rigor to be used in
ues docu1nented. 1neasuring performance should guide the building operator in
The reporting period for the initial co1nparison with the the selection of the type of measurement and comparison
1nodel provided should start at the beginning of the first 111ethods. The specific equip,nent installed may also allo\~' the
1nonth 1neter start schedule that is 60 to 90 days after the syste111 to be used for short term and spot-check testing, such
building reaches full occupancy. This will allow for syste1n as before and after equipment replacement.
and operational stabilization before a co1nparison is 1nade. Since this is a new building, the as-designed/as-built util-
The person responsible for i1nple1nenting and 1nonitoring ity use is developed by the energy 1nodel described above with
this plan is the facility 1nanager. assu,ned loads and schedules. Water use has not been 1nodeled
The plan assu1nes that the basic building uses and the and is detennined by recording the 1nonthly water use fro111 the
facility constn1ction and syste1ns will stay relatively constant. building n1eter. Fonns are included in Appendix A for this pur-
pose. These fonns are available and can be used to produce
I . Building configurations and construction details can be
co1nparative graphs for better visualization. Initial energy
reviewed on the construction record doctunents.
computer simulations are available that show estimated
2. Air-conditioning syste1ns are shown on the 1nechanical 1nonthly use. As noted above, these ener1:,,y 1nodels need to be
record docwnents supple1nented by the Syste1ns Manuals. calibrated to actual energy utility costs and current weather
Future tenant 1nechanical syste1ns will be shown on future conditions in order to compare the111 with actual use. For the
lease finish drawings. first co1nplete perfonnance year, the as-designed 1nodel will
3. Plu1nbing systen1s and 1netering are shown on the plu1nb- be calibrated such that the actual and the n1odeled monthly
ing record docu1nents and risers, supple1nented by the electricity and gas use agree to ±20% on a 1nonthly basis and
Syste1ns Manuals. ±10% on an annual basis. The n1odel will not be calibrated to
4. Electrical syste1ns and 1netering are shown on the electri- electrical de1nand. (Computer rnodels esti1nate hourly demand
cal record docu1nents and risers, supple1nented by the while buildings 1neasure demand on a 15-,ninute basis, render-

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~ ~ ~ m ! # Ml-U.e I . 4 -LU 14 Nol for Resale, 201515/28 09:22:15 51
No rep1oduciion or networking permitted wilhout license from IHS
ing comparisons unfair.) This calibrated 1nodel will be referred • Facility Manager will 1nanage the process and hire the
to as the as-operated model. other participants, including the energy tnodeling profes-
Subsequent year utility use variation of greater than I 0% sionals.
fron1 the previous year (the first year will co1npare to the cali- Engineer Associates developed the original energy
brated model) will trigger an analysis of building and equip- model at a cost of $5000. Engineer Associates \.viii con-
1nent operation to detennine the cause and re1nediation tract to calibrate the model using the first year's full occu-
actions. If significant deviations in operating or occupancy pancy stabilized energy use data for the additional fee of
characteristics are noted, the as-operated model \.viii be recali- $3500.
brated to reflect actual conditions. Budgeted cost for the management process is $10,000
The accuracy of the readings and the calculations is for the first year, then $6500 per year thereafter.
determined by the meters and test instruments used. This • Building Manager of Real Estate Management, LLC,
accuracy must be considered when evaluating both the results wi II tnanage the bui Iding, data collection process, the
of the readings and potential equip1nent changes. analysis of data, report generation, and potential building
Maintenance of the installed equip1nent is the 1nost syste1n re1nediation when necessary.
important factor in maintaining building efficiency. Adequate The building 1nanager's ftmction includes this data
manpower and budgets are necessary to perform inspections 1nanagen1ent process, but the budgeted cost for this local
and routine maintenance. Inspection fonns and additional building 1nanagement of the process is approximately
instructions are provided in the Recom1nissioning Manage- $5000 per year.
ment Manual to facilitate that process. • Building operating and 1naintenance personnel (nan1es
There are 1nany different types of equip1nent in 1nechani- TBD) will maintain the building systetns, read the build-
cal and electrical systen1s. So1ne of these are listed in Section ing meters, obtain weather data, and assist in the analysis
8 of this plan along with energy efficiency considerations and and potential remediation efforts.
1neasure1nents. See the 1nechanical drawings for current Budgeted cost for the M&V process by tnaintenance
installations. operations is $20,000 per year.
The level of accuracy in the M&V process depends on • Building tnaintenance and construction contractors
the type of equip1nent and training of the testing and 1nainte- (nan1es TBD) will provide construction and n1aintenance
nance staff. Care should be taken to select the compatible new assistance.
or replace1nent equipment and to continually train the staff on Budgeted cost for contractor operations is TBD at a
1naintenance and energy efficiency practices. later date.
Reports can be produced 1nonthly and yearly by using the • Sustainability consultant will assist in analysis and reso-
utility meters. If one of the syste1ns is suspected of not 1nain- lution of sustainability issues.
taining its efficiency, temporary meters or data loggers should Budgeted cost for sustainability consulting is $12,000
be installed for verification. The building energy manage.1nent per year.
syste1n can also be used for trending, 1neasure1nents, and cal- The validation and adjustn1ent of the energy 1nodel
culations. Equip1nent that can be used for this temporary will require a modeling professional fatniliar with the
metering purpose can be developed as needed. The utility 1nodeling prognun.
1neters for this building are sho,vn in separate attachn1ents. • Energy modeling professional and his team will provide
Ren1edial or corrective action would depend on the ele- tnodel calibration, energy use trend analysis, and solu-
ments of the building systetns that are causing the perfor- tions to utility issues and improve1nents.
1nance proble1ns. Some of these 1night include Budgeted cost for 1nodel calibration is $3500 per cali-
bration cycle.
I. adjustment of building operating schedules to 1neet actual
schedules; • Com1nissioning Authority (CxA) will assist in the cali-
bration and functional testing of systems.
2. deterioration of fluorescent lamp efficiencies requiring
bulb replacen1ent; 3.c M&V Approach: Systems and Monitoring Criteria
3. deterioration of HVAC equip1nent~.g., fans , co1npres- This section is used to describe the measure.1nent approach to
sors, zone boxes, etc.- requiring cleaning, adjustrnent, and/ building energy-using syste1ns. Each syste1n has the follow-
or replace1nent. Monitoring of temperature, airflow, hu1nid- ing detail structure:
ity, fan speed, and amperage is of special importance; I. Description of item to be monitored
4. HVAC and lighting control systetn operation or schedul- 2. What criteria will be used to 1nonitor it
ing proble1ns requiring reprogra1nming, adjusting, or 3. Frequency of monitoring.
upgrading systems.
These details will be monitored and provided to the
3.b. Energy Team ener1,,y teatn. Examples include the following:

The 0\.vner's energy teatn \.viii assist the property manager in • Building chilled-water use (gallons [litres]) will be
these M&V activities. Son1e of these individuals/functions are n1etered by the mag 1neter located in the base1nent fron1
as follows (Since the building is no,v vacant, some of these the central plant chilled-water distribution system. The
positions have not been filled.): 1neter ,viii be installed in the rettu-n chilled-water line
·· · · · .. ...., ... .. . , .. ...

American Sociel}!,ql Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHs:Mder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
TABLE U-3 Sample Building-1-P Units

Baseline
Assun1ptions to Be
(ASHRAE
Item As-Designed Model Units Updated During
Standard 90.1)
Calibration
l\1odel
Building Physical lnfonnation
Size 236,000 236,000 ft2

Stories 2 2
Wall insulation R-20 R-13 (ft2·h· °F}/BtU
Roof insulation R-35 R-20 (ft2·h· °F}/BtU
Co111111on area 23,600 23,600 rt2

Window area (overall) 23,600 23,600 ft2

Window U-factor 0.40 0.60 Btu/ft2·h·°F


WindowSHGC 0.40 0.80
Infi ltration 0.20 0.40 ach X

Equip111ent lnfonnation
Lighting power density 1.0 1.2 v.11ft2 .•
Equip111en t power density 2.0 1.2 w1ft2 X

Process load densi ty 0.5 0.5 v.11ft2 X

HVAC lnfon11ation-Co111111on Area


HVACtype DX air-cooled DX air-cooled
HVAC capacity 6 6 tons
HVAC perfonnance rating 13 10 EER
Fan type VAY CV
Heating Gas Gas
Outdoor air 20 20 cfnlfperson
HVAC lnfonnation-Tenant Area
HVACtype DX air-cooled DX air-cooled X

HVAC capacity 60 60 tons


HVAC perfonnance rating 13 10 EER X

Fan type VAY VAY X

Heating Electric Electric


Outdoor air 20 20 cfnlfperson X

Operating Characteristics
Occupancy (leased space) 100% 100% X

Occupancy(# tenants/111eters) 3 3 X

Occupan ts(# people) 66 66 X

Heating setpoint, occupied 70 70 Of X

Heating setpoint, unoccupied 60 60 Of X

Cooling setpoint, occupied 74 74 Of X

Cooling setpoint, unoccupied 80 80 Of X

Schedule 8 a.m.-5 p.111., M-F 8 a.111.-5 p.111., M-F X

Weather, Dallas, TX TMY TMY X

HOD, base 65 2407 2407 °F-days X

COD, base 65 2603 2603 °F-days X

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 53
No rep1oduciion or networking permitted wilhout license from IHS
TABLE U-3 Sample Building-1-P Units (Continued)

Baseline
Assumptions to Be
(ASHRAE
Item As-Designed Model Units Updated During
Standard 90.1)
Calibration
lVIodel
Results
E lectricity use 3,307,443 kVlh X

Gas use 3536 thenns X

Total energy use 11,642 MMBtu X

Energy use intensity 49.3 kBtu/ft2 X

TABLE U-3 Sample Building-SI Units

Baseline
Assumptions to Be
(ASHRAE
Item As-Designed Model Units Updated During
Standard 90.1)
Calibration
lVIodel
Building Physical lnfonnation
Size 21,900 21,900 m2

S to ries 2 2
Wall insulation R-3.5 R-2.3 (m 2·K)/\V

Roof insulation R-6.1 R-3.5 (1112·K)/W

Common area 2190 2190 m2

Window area (overall) 2190 2190 ,112

Windo,v U-factor 2.3 3.4 W/(m 2·K)

Windo,v SHGC 2.3 4.6


Infiltration 0.2 0.4 ach X

Equip,nent lnfonnation
Lighting po,ver density II 13 W/m2

Equipmen t power density 22 13 W/tn 2 X

Process load density 5.4 5.4 W/m2 X

HVAC Infon11ation-Co111111on Area


HVACtype DX air-cooled DX air-cooled

HVAC capacity 21 21 kW
HVAC performance rating 3.8 I 2.93 COP

Fan type VAV CV

Heating Gas Gas


O utdoor air 10 10 Lis/person
HVAC Infonna/ion- Tenant Area
HVACtype DX air-cooled DX air-cooled X

HVAC capacity 210 210 kW

HVAC perforn1ance rating 3.81 2.93 COP X

Fan type VAV VAV X

Heating Electric Electric


Outdoor air 10 10 Lis/person X

.. . , . ..,, ,,. .. . . .
. ,., · ...
American Sociel}! gt Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHs:Mtder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
TABLE U-3 Sample Building-SI Units (Continued)

Baseline
Assumptions to Be
(ASHRAE
Item As-Designed J\ilodel Units Updated During
Standard 90.1)
Calibration
Model
Operating Characteristics
Occupancy (leased space) 100% 100% X

Occupancy(# tenants/meters) 3 3 X

Occupants(# people) 66 66 X

Heating setpoint, occupied 21 21 oc )<

Heating setpoint, unoccupied 16 16 oc X

Cooling setpoint, occupied 23 23 oc X

Cooling setpoint, unoccupied 27 27 oc X

Schedule 8 a.in.- 5 p.m., M- F 8 a.m.- 5 p.m., tv-1- F X

We.ather, Dallas, TX TMY TMY X

HDD, base 18.3 1337 1337 °ዻC-days X

COD, base 18.3 .1446 1446 °ዻC-days X

Resulls
Electricity use 3,307,443 kWh X

Gas use 373,000 MJ X

Total energy use 12.283 G.T X

Energy use intensity 559 MJ/Jn 2 X

and \viii be sending pulse signals to the building 1nan- • The building also plans on using so rnany kilo\.vatts of
age1nent system (BMS). Chilled-\vater supply and return photovoltaic cells to supplen1ent its energy use and,
temperature will be measured by the water te1nperature therefore, reduce energy costs. Give so1ne data on the
sensors installed on the chilled-water lines in the attic, photovoltaic panels.
and the signal ,viii be sent to the BMS. Building chilled- • Solar water heating will also be used, which will help
water use and temperature difference between supply reduce energy required to heat \.Yater and reduce electric
and return lines will be recorded by the BMS and load in the building. Provide some specific data.
charted on an hourly basis ,vith reports generated by the • The building envelope has increased insulation levels and
BMS for hourly, daily, weekly, 1nonthly, and yearly windows with low solar heat gain coefficients to reduce
energy use in gallons (litres). heating and cooling energy use.
• The air-handling tmits (A.HU- I, 2, and 3) use ternpera- • Lighting fixtures are high-efficiency T-8/T-5 with elec-
ture sensors to control the econo1nizer da1npers. The tronic ballasts to achieve adequate illumination levels
economizer dampers are also controlled by the carbon with a 1.0 W/ft.2 (11 W/in 2 ) lighting power density.
dioxide sensors that are located in each classroo1n. These • The building is designed to achieve an energy use inten-
C0 2 sensors override the n1ini1num outdoor position sity of 49.3 kBtu/ft2 (559 MJ/m2), which is less than that
when Co 2 level is exceeded in any classroom. prescribed by ASH RAE Standard 90.1 -20 IO to satisfy
LEED-CS.
• The chilled \vater to the air-handling units is controlled
• The HVA.C system for the building core areas are pack-
by the chiHer plant and is not reset locally
aged roof-rnounted cooling systerns using air-cooled
condensers. Heating is provided by natural gas.
3.d. Pro_ject Energy Reduction Devices
• For tenant areas to be finished out, HVAC and air distri-
This section should provide fairly detailed inforn1ation bution is expected to be fron1 roof-mounted variable-air-
describing the systerns which are expected to reduce energy volume (VAY) air-handlers \\rith VAY and fan-powered
use and therefore costs in the building. zone boxes. Controls are electronic/direct digital con-
The building is using ground-loop heat pumps to reduce trol (DDC). Unit heaters and roof-mounted solar domes-
ener1,,y costs. This is in part due to the high efficiency con- tic \Vater heaters are included for the leased spaces.
denser that is located underground. It would be a good idea to • Outdoor air is brought into the building through the roof-
give a couple examples of efficiencies and capacities of the top packaged units. The building uses no natural ventila-
syste1n described. Sorne exa111ples include the following: tion.
.. . . . ,. ..... , .. .. , .,. ...
Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 55
No rep1oduciion or networking permitted wilhout license from IHS
TABLE U-4 Application of IPMVP

l\1& V Option Description Ho\\' Baseline Is Determined Typical Application Savings Calculations
B. Energy Conservation l\1easure Isolation
Savings are detern1ined after project Projected baseline energy use is Variable speed control of a fan Engineering calculations Ltsing
co1npleti on by short-tern, or detennined by calculating the n1otor. Electricity needed by 1netered data.
continuoLtS n1easurements taken hypothetical energy perfonnance of the 1notor is 1neasured on a
throughout the tenn of the contract the base) ine systen1 under n1easured continuous basis throughout
at the device or system level. Both postconstruction operating the M&V period.
the perforn1ance and operations conditions.
factors are 1nonitored.
D. Whole Building Calibrated Sin1ulation
Savings are detern1ined at the Projected baseline energy use is Savings detennination for the Calibrate energy sin1ulation
whole-building or systen1 level by detennined by energy sinu1lation of purposes of a ne,.v building and n1odeling: calibrated with
n1easuring energy use at n1ain the baseline under the operation perforn1ance contract, with the hourly or 1nonthly utility
n1eters or subn1eters or Ltsing a conditions of the M&V period. local energy code defining the billing data and/or end-use
whole-building sin1ulation baseline. 1netering.
calibrated to n1easured energy use
data .

Section 4: Commissioning (Cx) • base year: a defined period of any length before con1par-
This section \viii describe ho\v the com,nissioning (Cx) \.viii ison of subsequent data.
progress and how it will help the M&V plan fulfill its use. • base year conditions: the set of conditions that give rise
This section will also describe the Cx procedures. to the energy use/demand of the base year.
• base yetu· e11ergy data: the energy consumption or
Definition of "Commissioning" de1uand during the base year.
Co11unissioning is a quality process for achieving, verifying, • degree day: the difference in ten1perature between the
and documenting the performance of equipment to meet the outdoor mean te1nperature over a twenty-four-hour
operational needs of the facility within the capabilities of the period and a given base temperature.
design and to ,neet the design docu,nentation and the Owner's
• energy 111a11age111e11t syste111 (EMS): a cornputer that can
functional criteria, including training of operator personnel be progra1nmed to control and/or ,nonitor the operations
and docu,nentation.
of energy-consuming equiptnent in a facility or group of
Co1nmissioning is a process, a combined effort between facilities.
all the 1ne1nbers of the design and construction tea1n to ensure
• energy Sllvb,gs: actual reduction in electricity use
quality and efficiency \.vhen building a building for the
(kWh), electric de1nand (kW), or thermal units (Btu).
0\vner. The job of a Cx provider is to ensure that the build-
ing's systems are \.vell coordinated and operating properly. A • 111eas11re111e11t a11d verificatio11 (M& J,J: the process of
check on the systems is used to provide the O\vner with a detennining savings using one of the four IPMVP
docu1nent and, therefore, expertise describing that the sys- Options.
te,ns of the building have been installed and started within the • n1eteri11g: collection of energy and \.Vater-consumption
standard required by code. data over tirne at a facility through the use of measw·e-
ment devices.
Section 5: M&V Options and Project Boundary • n1011itori11g: the collection of data at a facility over tin1e
S.a. M&V Options and LEED® for the purpose of savings analysis.
The USGBC cites the standard i,nplernentation methods for • postco11struction period: any period of tirne follov,,ing
th_e M&V process in the International Perfonnance Measure- co1n1nissioning of the facility.
rnent and Verification Protocol (IPMVP) Volu1ne III using • verification: the process of exa,nining the report of oth-
eiJher Options B or D. Table U-4 gives an overview of the ers to co1n1nent on its suitability for the intended pur-
al?propriate methods (go to WW\V.ipn1vp.org for more infor- pose.
,n_ation).
S.b. Measurement and Verification Boundary
.
Standard Definitions The M&V boundary will typically coincide with the project
scope. Certain buildings ,night be attached to carnpuses or
• baseline: the base period that is used to co1npare subse- si,nilar areas where energy/heating/chilled-water are deliv-
quent building perfonnance using sirnilar conditions. ered from outside the scope of work and ,nay or ,nay not be
• baseline adjust111ents: the nonroutine adjustJnents arising available for rnonitoring. Issues such as this will need to be
during the post construction period that cannot be antici- addressed here to provide infonnation pertaining to the indi-
pated and that require custorn engineering analysis. vidual project.

American Sociel}! pl Healing, Refrigeraling and Air·Conditioning Engineers, Inc . licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IH~er license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
• Extraboundary Devices Interacting lvith energy use and need to be considered when co1nparing energy
Building Syste,ns use and revising the baselines for co1nparison.
• Systems outside the scope of the project boundary Base building meter syste1ns are available. These can be
and the M&V boundaty should be addressed here to read by the local utility and/or maintenance staff and recorded
ensure the total collection of data. for comparison and/or analysis (for example, comparing the
energy use of the heating syste1n to the air-conditioning sys-
• Standards and Versions
tem).
• International Perfonnance Measure,nent and Verifi-
cation Protocol, Concepts and Options .for Deter- Section 8: Adjustments
rnining Energy and /,Vater Savings, Volume 1
If the actual building perfonnance does not track the initial
(Septe,nber 2009)
perfonnance year 1nodeling, analysis and possibly additional
Section 6: Baseline spot 1netering and added energy 1nanage1nent syste,ns should
be added. Other areas of concern in the yearly adjust,nent
6.a. Baseline Information include the following:
The building's baseline ,nay be derived fro,n two sources.
First, a calibrated energy ,nodel that has a year's worth of data • Changes in equip,nent efficiencies or replace,nent of
that replaces a baseline period. Second, as 1nentioned, a base- equip,nent
line period of energy use of an existing building will give data • Installation and use of spot metering to determine spe-
previous to energy conservation 1neasure installation. cific equipment efficiencies
These data, taken from either of the above two methods, • Calibration of sensors and control for ongoing perfor-
will be used to generate a base year. This will describe all the 1nance
conditions for the building before extra ECMs have been
• Variation in the utility charges, particularly for fuel
installed and will show how they affect the cost of energy dur-
charges
ing the following year.
The building is one-story, totaling 2500 ft2 (230 ,n2) . It is • Changes to building use and operation schedules
located in Piano, TX. The expected occupancy is nearly ten Finally, if the building changes or the use (occupancy,
people. schedules, etc.) changes, these vanauons need to be
A. description of the A.SHRAE Standard 90.l baseline accounted for in the comparison of current and baseline
1nodel, combined ,~1ith the IPMVP protocol, should be written energy and water use.
here to further describe what will be done to the building and
also be used to help quantify the results of the M&V process. Section 9: Analysis

Section 7: Reporting Period 9.a. End of Year, Cost Savings Equation:

One of the key aspects of LEED is sustainability. Recording Cost Savings= Cb - Cr


and watching a building's energy use monthly will greatly
anticipate problems ,vith maintenance and energy use. cost of the baseline energy plus any adjustments.*
Reports fro,n the metering devices \.viii be delivered and cost of the repo,ting period energy plus any
reviewed by the O,vner and any maintenance staff, and the Cx adjustments.
agent, should they choose.
The following reports should be produced to 1naintain * Adjustments:
building efficiency (obtain the data fro1n the utility bills in Routine adjust,nents: For energy-governing factors expected
n1ost cases to provide consistency and ease of entry): to change routinely during the reporting period, such as
weather or production volume, a variety of techniques can be
• Electricity kWh and cost on a monthly basis used to define the adjust1nent methodology. Teclu1iques 1nay
• Natural gas or other fuel gas Mcf and cost on a n1onthly be as sin1ple as a constant value (no adjustments) or as con1-
basis plex as several multiple-paran1eter, nonlinear equations, each
• Do,nestic ,vater gallons (litres) and cost on a ,nonthly correlating energy with one or 1nore independent variables.
basis Valid mathematical techniques must be used to derive the
• Landscape irrigation water gallons (litres) and cost on a adjust1nent 1nethod for each M&V plan.
1nonthly basis Nonroutine adjust,nents: Static energy-governing factors that
This data can be recorded, compared, and analyzed using are not usually expected to change, such as facility size,
the data tables. design and operation of installed equipment, number of
A degree day table facilitates the recording of weather weekly production shifts, or type of occupants, must be moni-
variations fro,n ,nonth to ,nonth and year to year. Degree day tored for change throughout the reporting period.
data can be obtained fro,n the national weather service. The
Section 10: Energy Prices
change in building energy use is caused by internal building
loads (people and process) and external loads due the weather. Energy prices and expected energy seller should be described
The latter loads are usually ,nore variable than the building in detail here.
.. , . , ., ...,.. ., ·.. . ...·...
·

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STAN DARDIZ ATION 5956617
Provided by IHS~ ~ ~ m ! # Ml-U.e I . 4 -LU 14 Nol for Resale, 201515/28 09:22:15 57
No rep1oduciion or networking permitted wilhout license from IHS
Section 11 : Meter Specifications The level of accuracy in the M&V process depends on the
type of equip1nent and training of the testing and 111aintenance
The following 1netering and analysis systems can be used for
staff.
temporary and/or pem1anent 1netering. The equip1nent shown
Care should be taken to select the co1npatible new or
is an exa1nple of available equip1nent for pennanent 1netering.
replace1nent equip1nent and to continually train the staff on
Included are water 1neters for totalizing water flow and
111aintenance and energy efficiency practices.
individual equip1nent analysis.
Efficiencies of existing equipn1ent are shown on the
For various power and environmental measurements, equipment submittals and the Systems Manuals.
infonnation on controllers is included. The electric and water utility meter accuracy is deter-
For power quality monitoring equip1nent and building 111ined and can be obtained from the respective utility. Utility-
control syste1ns, infonnation is available fro1n the Syste1ns grade electrical meters are required to have an overall accu-
Manuals. racy of 0.5% of registration as set by ANSI Standard C-12.
l nfor111ative Note: Please see Meter Data Sheet and Further, the IPMVP (2007, Section 4.9.5) states "Utility-
Appendix BI , "Metering Devices." 111eter data is considered I 00% accurate for determining sav-
ings because this data defines the pay1nent for energy."
Section 12: Monitoring Responsibilities/M&V Team Although this section is from Option C, the Option D 111ethod
The responsibility for i1nple1nenting and maintaining the being used de.fines savings as the difference between the cali-
l'v1&Y Plan rests \.Vith the property ,nanager and the Owner. brated baseline model and the actual (measured) energy use.
l'v1any others will share in the installation, maintenance, and
Section 14: Quality
1nonitoring of the facility and its systems. The organization of
these functions re,nains the overall responsibility of the Quality assurance 1neasures can consist of the following:
Owner and the Owner's organizational management listed • Ensure that all equip1nent purchased has been analyzed
below. for proper use, application quality, and accuracy.
Program l'vfanager: • Train all 1naintenance personnel on the proper 111ethods
Na,ne and schedules for 111aintenance and operation of the sys-
Address tems.
Contact Inforn1ation • Review program application and results on a quarterly
Owner: basis.
Name • Complete routine equip1nent 1naintenance on a monthly
Address basis.
Contact lnfonnation • Complete a recalibration and total inspection on an
annual basis.
Section 13: Accuracy • Make repairs as necessary.

American Sociel}! gt Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZATION 595661 7
Provided by IH~i\:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is <lures as facility systems and components age and
merely informative and does not contain requirements degrade in performance levels
necessary for conformance to the guideline. Unresolved • Providing clear understanding of the OPR for training
objectors on informative material are not offered the right 111aterial, training sessions (schedule), and trained per-
to appeal at ASHRAE.) sonnel necessary, prior to and after occupancy by the
o,vner
INFORMATIVE ANNEX V
USE OF SYSTEMS MANUAL IN TRAINING Training respons ibilities and the pos1t1on or person
The follo,ving are exan1ples of the requiren1ents and for- assigned these responsibilities ,nust be clearly defined in the
1nats for the docu1nents to be included in the Systen1s Manual. OPR and reviewed before moving into the Design Phase. This
is of extreme importance when essential equipment or sys-
Predesign Phase tems are provided by the Owner.
The HVAC and refrigeration design needs to satisfy the
Training require1nents and implementation begin at project
operating personnel for the following OPR topic areas,
conception and are part of the Owner's Project Requirements
including consideration of training required to continuously
(OPR). At the Itnple1nentation Phase, the O,vner needs to
achieve the benefits of designs that optitnize each require-
address the source of operating personnel, in-house or out-
1nent:
sourced labor and services, and the level of responsibility
assigned to the facilities/project manager for the site. OPR • Reparability
requirements and Current Facility Requirements (CFR) for
• Interchangeability
extended ,varranty and service agreen1ents with the contractor
or original equip1nent manufacturer (OEM) need to be • Accessibility
addressed at the time of project inception. • Replaceability
ln the i1nple1nentation stage, beginning with assigned • Maintainability
individual roles and responsibilities, the OPR for training are
• Extendability
considered in a 1nanner sitnilar to choosing any of the varied
systerns, components, and assernbl ies that establish the level • Adaptability
of quality and perfonnance expectations expressed by the • Lifecycle replace,nent sequence
o,vner in the OPR. • Cost analysis of component servicing and 1naintenance
The criteria used to determine the 1ninimum level of cycles
acceptance required by the training OPR ,viii guide the devel-
• Cotnplexity of the OEM and systerns in day-to-day oper-
opn1ent and coordination of the training of personnel who are
ation
assigned responsibilities of maintaining the HVAC&R sys-
tem's perfonnance in the OPR/CFR. This includes energy, Controls at the systen1 and co1nponent level are essential
fire and safety, indoor environment, and occupant comfort for all HVAC&R systems and assemblies. Special effort must
requirements related to the HVAC&R systems. During the be directed at the training require1nents as the design develops
Predesign Phase, the initial training agenda needs to be devel- versus considering the training afterward as a result of the
oped to a level that reflects the training required to meet the controls design.
OPR/CFR. The initial training agenda provides the initial Beyond 111echanical 1naintenance, the skill set required at
guidance to the design team and includes the follo,ving: each level of the operating hierarchy for direct-digital-control
• Establishing developrnent requirernents for the training (DDC) systems needs to be defined in the OPR. These DDC
plan syste,ns have various levels of control hierarchy; so,ne levels
require computer progra111ming skills that are beyond the
• Identifying essential components or systems requiring
tneans of an Owner to support. At a minimum, the OPR
fonnal training and the estimated time designated for
should define the responsibilities and training necessary for
training by hours (unit cost)
in-house and outsow·ced contractors (service plan) of site
• Determining skill-level requirernents for operating staff DDC systems. The level of interoperability and any additions
1neeting the OPR/CFR levels ofperfonnance to interoperability not currently used at the site or organiza-
• Creating a checklist of training require,nents necessary to tion requires additional training for the systerns to be success-
maintain warranty conditions and service life ful. Issues addressed in the OPR/CFR should include the
• Specifying require1nents for acceptable organization and following:
i1nple1nentation of the OEM training requirernents prior
• DDC in-house engineering, operations, and n1aintenance
to occupancy
(EOM) requirements
• Clearly identifying the training requirements of contrac-
tor's workforce for the equipment maintaining the inte- • DDC service plans and warranty requirernents
rior environ,nent during the Construction Phase • Procedures for n1aintaining record documents and ser-
• Developing training 1nethods that 1neet the OPR, includ- vice records ofDDC Systems
ing incorporating OEM training with service bulletins, • Training and certifications requirernents for in-house and
recalls, and i111plantation of changes in operating proce-
.. . . . .. ...... .. . . . ., ...'
service contractor personnel

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 59
No rep1oduciion or networking permitted wilhout license from IHS
• Written training 1natrix updated to each level in the DDC Certification training for procedures in the use of unique
hierarchy equipment or assen1blies should be required at locations other
than the actual job site. In such cases, the design professional
Design Phase 111ay require verification of current and up-to-date certifica-
tion and valid accreditation documents for the organization or
During the Design Phase, the design professional, following individual issuing the certification. The role of the CxA in
the OPR/CFR, will define the training require1nents and verification of proper training for certification is to rando111ly
imple1nentation schedule for the project in the contract docu- check the documentation necessary to de1nonstrate co1npli-
1nents. Someti1nes this may require specific needs for each ance with the OPR/CFR. The requirement for ensuring that
installing contractor, for in-house n1aintenance, and for out- the proper documentation is valid remains with either the
sourced service personnel. The perfom1ance of these training design team or O,vner's project or construction manager.
services is verified both as part of the submittal review process
and as the training sessions occur. Additional training require- Construction-Phase Training
1nents will continue to evolve during the Design and Construc-
tion Phases of the project. It is recon1mended to hold needs- The design should hold an initial training session, during the
development workshops or sessions during design and con- constn1ction period and prior to contractor training for the
struction. These need to be defined in the specifications. Spe- Owner's EOM and users, on the OPR/CFR and Basis of
cial note should be given to the training and service Design (BoD), including syste,n litnitations. This is espe-
require1nents of equipment and syste1ns not provided by the cially required for all HYAC&R systems that are critical to
project contractor. This is usually owner-provided equipment the success of the facility.
or systems that occur outside the project submittal revie,v. In The CxA should hold a training developtnent workshop
some cases, there 1nay be two or 1nore construction projects, with the EOM (including any service contractors), several
with separate contractors or in-house construction, in which 1nonths before the final training sessions are scheduled and
case coordination of training needs is required to prevent the scope of training-sessions content is set, to gather infor-
duplication and acceptable scheduling of trainers and trainees. tnation from the EOM staff to detennine the actual training
require,nents based on the approved equip,nent, assemblies,
Procedure training on spare parts availability and service
and syste,ns for the building, on a walk-through of the build-
response times should be clearly defined by the design profes-
ing, and on the review of final plans and specifications. This
sional and verified in the sub1nittal process.
,nay require an increase or decrease in actual training require-
During the Design Phase, the design professional should 1nents, as compared to the require,nents included in the con-
clearly define. all special requirements for storage of equip- tract docu1nents, related to the final equip,nent, co,nponents,
1nent or systems prior to installation. Training necessary to and HYAC&R systems selected by the Owner, design tea,n,
1naintain the equip1nent prior to Owner acceptance is identi- and Contractor.
fied and 1nonitored by proper application of the contractor's Syste1ns Manuals need to be co1nplete before Owner's
quality assurance/quality control (QA/QC) progra1n. Special personnel are provided training and the 1nanuals are used in
training of contractor personnel handling equip1nent with spe- the training sessions.
cial require1nents should be 1nonitored by the Co1nmissioning
Training on the use of the Systems Manuals should be a
Authority (CxA). Contractor personnel should de111onstrate
co1nbined effort of the design tea1n, the Cx Tea1n, and the
co1npetence 1neeting the OPR during all periods that the
contractor.
I-IVAC&R equip1nent and syste1ns are operated during con-
The CxA should revie,v the contractor's schedule for all
stn1ction and warranty. Equip1nent 1nust be 1naintained to pre-
I-IVAC&R-related training. Resources and tin1e for HVAC&R
vent any degradation prior to turnover to the Owner for
training can place great den1and on both the contractor and
operations.
the EOM and service-firn1 personnel at the end of the Con-
struction Phase. HVAC&R syste1ns are especially impacted
Contractor Special Training, Licensing, Certification
because of a high level of training required and because the
(Construction Phase)
I-IVAC&R systems are some of the last syste1ns installed in
After the notice to proceed, the contractor is required to pro- the construction process. Early training 1nust be scheduled for
~ide initial sub1nittals in the stated period of ti1ne. One of the project success. The CxA must document that training and the
)nitial sub1nittals usually required is the contractor's QA/QC required level of co1npetence learned in the training meets the
[Progra1n. This progra1n outlines the 1nethods used by the con- OPR.
tractor to ensure his personnel have the proper training, The contractor is responsible for the start-up, testing,
{icensing, and certifications to perfonn assigned tasks. In adjusting, balancing, Systems Manual, and training for all
'~ddition, the criteria necessary to 1naintaining the project-spe- syste1ns and equipment prior to the functional testing or
cific OPR is identified in the Contractor QA/QC progra1n. On n1aintenance and verification (M&V) of these systems and
a frequent basis, the CxA should verify and note co1npliance equipment. The Cx Tea1n must verify through assembled doc-
by the contractor with required training, licensing, and certifi- u111entation that the contractor personnel are trained and co1n-
cation require1nents or activities and other quality checks petent to perform these activities.
identified in the contractor's QA/QC progra1n or required by The contractor 1nust begin early training on any major
the contract. changes in the auto1nated preventive 1naintenance and service

American Sociel1 Rl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHSQM:Jer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
progran1 that is included by syste1ns installed and required by nated by the CxA before the Owner assun1es these responsi-
the contract. bilities.
Testing and verification for co,npliance of syste,ns and
equipment to the OPR/CFR should be witnessed by the Occupancy and Occupancy Phase
o,vner's O&M staff as part of the contractor's training plan. At substantial completion and Owner operations and occu-
The CxA facilitates the ,nonitoring of functional and Cx tests pancy, the 1najor training responsibilities beco1ne the responsi-
by designated O,vner personnel performed as part of the gen- bility of the O,vner. Specifically, they beco,ne the responsibility
eral contractor's acceptance plan. The benefits to the Owner of the Owner's facility chief engineer and building ,nanager.
in monitoring these tests are lessons learned and a corrective The CxA will coordinate this shift in responsibilities until final
review of O&M procedures prior to substantial completion acceptance or beyond as required by the 0\.vner's ongoing and
and operation of the syste,ns by the Owner. Using the infor- continuous co1nmissioning process activities. The CxNchief
1nation developed in this Start-Up Phase, the Owner and the engineer/building ,nanager relationship in this phase will coor-
CxA should evaluate the abilities of in-house personnel to dinate the training require,nents to i1nple1nent and optunize the
perfonn the O&M necessary for successful operation of vari- performance of the following
ous systems and to prevent future warranty issues. A. value
analysis of OEM service progra,ns and ,naintenance by the • Existing service and outsourcing of service plans and
CxA during this period is useful infonnation for the Owner's programs
consideration. Doctunentation gathered by the CxA during • Organization and training of O&M staff
this Monitoring Phase is useful to the training progran1 and in • Qualification of training requirements of staff positions
the Acceptance Phase.
• Warranty/guaranty implementation and enforcement
The majority ofHVAC&R systems and assemblies train-
ing should occur in the Construction Phase, prior to substan- • Service call-up or call-back tracking and evaluation
tial completion. The initial training is developed at a level to • Systems and equip1nent performance in
ensure that the Owner's O&M personnel are co,npetent in the • :tvleasure1nent
proper operation of the systems and equipment during occu-
• Verification
pancy. The training prior to final acceptance takes place after
the facility has been occupied during the warranty period • Analysis (benchmarking and life cycle)
bet\veen substantial completion and final acceptance. This • Opti,nization
allows for training in seasonal operation and site-specific • Reco1nmissioning cycle
issues to be addressed in the training progran1. Using a two-
• Optimization
step training program, the CxA will facilitate the coordination
of site-specific issues: • Seasonal transition of equip,nent and tracking itnpact of
weather cycles and syste1ns perfon11ance
• Warranty/guaranty • Spare parts inventory and response times for service
• Service call-up or call-back • Equip1nent or syste1ns service bulletins and training
• Systen1s and equip1nent perfonnance updating
• Seasonal transition of equipn1ent • Life-cycle and 1naintenance budget planning
• Spare parts inventory • Modification of preventative and predictive ,naintenance
• Equipment or systems service bulletins procedures to meet site-specific conditions.

• Life-cycle analysis The facility/building ,nanager will assess the benefits and
• Modified preventative and predictive 1naintenance proce- costs of 1naintaining a training cycle that represents the inter-
dures ests of the Owner. The CxA can be of great benefit to the
building manager in the initial organization of construction
Construction-Phase Close Out documents by providing a method to keep training up-to-date
with the cycle of changes in equip111ent and use of the build-
As syste,ns are completed, the contractor ,nay be required to ing throughout the lifecycle.
or 1nay elect to use these syste1ns to maintain an environn1ent
iit the ,vorksite, meeting specified require,nents in executing Summary
:the constn1ction process. Prior to turnover, these syste,ns
operated by the contractor need to be validated for proper The processes of tra1n1ng and syste,ns opt1m1zation will
O&tv1 by contractor personnel. The validation of operating re111ain a responsibility of the chief engineer and facility/
equipment at turnover 1nust include documentation that the building manager for the life of the facility. To ensure the con-
contractor personnel were properly trained in both operation tinuing need for training and understanding of systems to
and ,naintenance of the syste,n and that the equip,nent ,nain- ensure success of site O&M, a paper trail of the learning pro-
tenance schedule was 1naintained during the period of con- cess is essential. The CxA is essential to initiating this process
tractor operation. Lessons learned and infonnation gathered and, ,vith continuing Cx efforts, provides the guidelines to
on the operations of the systems during start-up and opera- optimize the training process through the life of the building.
tions are valuable to the Owner and must be included in the The documentation of the training process coordinates the
turnover training of the Owner's operating staff and coordi- follov.,ing:

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and /4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 595661 7
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 61
No rep1oduciion or networking permitted wilhout license from IHS
• Organization of responsibilities for training assigned to a • Organization of application of service bulletins and OEM
position call-backs
• Clear application of system performance and degradation
• Verification of understanding and co1npetence in what
infonnation
was learned in training and O&M
• Opti1n al benefits frotn lessons learned
• Proper application of preventative and predictive 1nainte- • Coordination of personnel changes and mentoring for a
nance of systems position

American Sociel1 Al Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STAN DARDIZ ATION 5956617
Provided by IHS~er license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is The following ite1ns can be included 111 an effective
merely informative and does not contain requirements issues and resolutions log:
necessary for conformance to the guideline. Unresolved
• Project title
objectors on informative material are not offered the right
to appeal at ASHRAE.) • Project location
• Na1ne of co1n1nissioning authority (CxA) 1nanaging the
INFORMATIVE ANNEX W issues and resolution log with e-1nail address and phone
ISSUES AND RESOLUTION LOGS ntunber
The following are examples of the requirements and fonnats • Issue nun1ber, usually sequential
for the documents to be included in the Syste1ns Manual. • Issue description sufficient to describe item for all to
understand
W1. ISSUES AND RESOLUTIONS LOG
• Pictures of iten, if available and appropriate
The issues and resolutions log is the ongoing listing of issues • Date issue discovered
and questions on a project that need to be co1nmunicated to
the project tean1 for resolution or action. These are often • Issue fotu1d by na1ne
shown in table forn1at and supplemented with pictures and • Effects of issue on project or building operation to relate
drawings where necessary. importance of issue
It is in1portant to include a copy of all the issues and res- • Possible cause of issue or problem
olutions logs in the Systen1s Manual to provide a history of • Recornmendation for resolution if available
and information on the ite1ns of conce1n and problems found • Person(s) assigned to resolve issue
during design, construction, testing and co1nmissioning of the
facility. This infonnation can be used in operation and main- • Actions taken
tenance (O&M) training and to resolve similar problems in • Iten1 disposition
the operating building. • Approvals of issue resolution .

.. ...., .. ..
, , .,, ...

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS ~ ~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 63
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is 3. Section 2-Preinstallation checks just pnor to initial
n1erely info rmative and does not contain requirements installation
necessary for conformance to the guideline. Unresolved 4. Section 3- lnstallation as installation progresses
objectors on infor1native 1naterial are not offered the right
to appeal at ASHRAE.) 5. Section 4- Co,npletion and initiating of perfonnance data
There are a nu1nber of websites of testing and co1nmis-
INFORMATIVE ANNEX X sioning (Cx) organizations and agencies that have inspection
COMMISSIONING PROCESS REPORTS AND and testing fonns that can be adapted for specific needs and
TESTING RECORDS projects.
The following are examples of the requirements and fonnats
for the docurnents to be included in the Systems Manual. X2. COMMISSIONING REPORT

X1. CONSTRUCTION OBSERVATION AND The Cx Process Progress Report is the docu1nentation of the
TESTING CHECKLISTS AND REPORT Cx work and results accornplished dLu·ing construction. The
Cx Process Progress Report contains the following:
Overview
Construction checklists consist of two general types: I. Identification of any systems or assemblies that do not
perform in accordance ,vith the Owners Project Require-
• Component/Equipment Based: These construction ments (OPR)/Current Facility Requirements (CFR). For
checklists are utilized for cotnponents and pieces of various reasons, the Owner may choose to accept perfor-
equipment that are delivered, installed, and started during mance that is at variance with the OPR/CFR, either per-
construction. There is an individual checklist for each manently or until schedule and budget constraints allow
individual cotnponent or piece of equiptnent. for correction . The Owner's acceptance of these condi-
• System/Assembly Based: These constn1ction checklists tions should be documented along with the environn1ental,
are utilized for systems and assemblies where separate health, safety, co1nfort, energy, and operating and 1nainte-
checklists cannot be applied to subco,nponents of the nance cost i1npacts. The OPR/CFR must be updated to
system or asse,nbly. There is a single checklist for the match the revised expectations.
entire system, often assen1bled around the sequence of
2. Evaluations of the operating condition of the systerns at
operation.
the time of test cotnpletion
For each test procedure, test data records shall be devel- 3. Construction checklist completion and evaluation sun1-
oped. Test data records capture test data, observations, and 1nary
1neasurements. Data may be recorded on photographs, fonns,
or other ,neans appropriate for the application. The following 4. Results from the issues log, including the descriptions of
information shall be recorded: issues and the 1neasures taken to correct them. The
description should assess the importance of the issues and
I . Test nu,nber estimate the value of their correction in terms of environ-
2. Date and time of the test mental in1pact, improved health, safety, comfort, energy,
3. Indication of whether the record is for a first test or retest operating and maintenance costs, and the ability of the
following correction of a probletn or issue facility to support its mission .
4. Identification of the syste,n, equipment, or assembly 5. Test procedures and data. This section should incorporate
under test (List the location and the construction docu- the original test procedures and signed data fonns, includ-
1nent designation.) ing additional data such as photos, co,nputerized docu-
5. Conditions under which the test was conducted rnentation, and other records of the tests. Data should
6. Expected performance of the systems and assemblies at include the final accepted test, as \veil as earlier tests that
each step of the test failed to rneet the specified criteria. This section should
7. Observed perforn1ance of the syste1n, equipn1ent, or also include a set of blank data fonns for future use in the
assembly at each step of the test ongoing Cx Process and reco1111nissioning.
8. Issue nLunber, if any, generated as a result of the test 6. Cx Process Progress Reports-copies of progress reports
9. Dated signatures of the person performing the test and of generated throughout the Cx Process
the witness, if applicable 7. Deferred tests--execution of some tests rnay be deferred
tmtil appropriate natural loads, such as occupancy or
SAMPLE [insert equipment/component name)
design \veather conditions, are available. For these
CHECKLIST
deferred tests, the prerequisite conditions and an esti-
Tag ID: Location: Date: tnated schedule for their cornpletion should be included.
8. Lessons learned--evaluation of the Cx Process used and
General Instructions
changes that will i,nprove the delivered project and fonn
I. This fon11 is to be completed as the work is con1pleted. the basis for the Final Cx Process Progress Report devel-
2. Section I-Model verification on delivery of equipment/ oped during occupancy and operations. This is essential to
co,nponent to either the job site or storage location ensure that issues, benefits, and reco1n1nendations are cap-
•• • • • .. ........ . + • • .. ...

American Socie11gt Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHSQffder license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
tured in a written document while all tean1 me1nbers are 6. Issue and Resolution Logs
available and infonnation is fresh.
Insert a copy of all issue and resolution logs 1,vith resolution
A prelirninary Cx Process Progress Report should be or status of each itern in the appropriate appendix. This pro-
submitted for 0\.vner review. Subrnittal of the prelirninary Cx vides a record ofproblerns and issues found and resolved dur-
Report to other Cx Tearn 1ne1nbers or for jurisdictional ing the design and construction process for future reference.
require,nents rnay also be appropriate.
The final Cx Process Progress Report should incorporate 7. Item Resolution and Open Items
review comn1ents from the Owner and, optionally, from other
Insert a list o_fany open ite,ns and seasonal or additional test-
Cx Team n1embers.
ing required.
The following is an example outline for a Cx Process
Progress Report. The basic structure of this exa1nple is such
8. Contact Information
that each phase of the plan has its own section detailing what
activities were accomplished, ,vho accomplished them, and Appendices in the Initiation and Design Phases ofthe project
how they were completed. The deliverables for each activity ivill state the requirernents and re:,ponsibilities for that deliv-
are included in an appendix. Each section of the report will erable. The.final results and docu,nentation for each itern ivill
have a description of the results for that subject. The intent of be inserted in thejinal report.
this format is for the Cx Plan to becorne the fi nal Cx Process It is not necessary to include copies of docurnents
Progress Report at the end of the project by updating the plan included in the Systerns Manual in the.final Cx Process Prog-
and filling in the results for each section as the project pro- ress Report(/ that report is included in the Systerns Manual.
gresses. Text in italics provides the reader with guidance as to
the type of information that would be added to that section, APPENDIX A-OWNER'S PROJECT REQUIREMENTS
specific to the faci lity under consideration. (OPR)
Commissioning Process Progress Report APPENDIX B-BASIS OF DESIGN (BoD)
TABLE OF CONTENTS APPENDIX C-FINAL PROJECT SPECIFICATIONS

1. Executive Summary
APPENDIX D-COMMUNICATION STRUCTURES
APPENDIX E-ROLES AND RESPONSIBILITIES
2. Commissioning (Cx) Process Description
and Plan(s) APPENDIX F-COMMISSIONED SYSTEMS
[listing of systems and assen1blies]
Insert the final Cx Plan.
APPENDIX G-COMlvfISSIONING PROCESS
3. Commissioning Design Summary and Design SCHEDULE RESULTS
and Submittal Review Reports APPENDIX H-PREBID MEETING RECORDS
Insert a copy o_f the Cx design and sub,nittal reports.
APPENDIX I-PRECCONSTRUCTION MEETING
4. Testing Reports RECORDS

Insert cornpleted Cx Process Progress Report ivith docurnents APPENDIX J-SUBMITTAL REVIEW RECORDS
and testing .forrns and records for each building, :,ystern, and APPENDIX K- COMMISSIONING PROCESS ISSUES
asse,nbly included in the Cx Process in the fo/lo1,ving appen- AND RESOLUTION RESULTS
dices.
Insert copies o_f all relevant ,nanufacturers ' and installers '
APPENDIX L-CONSTRUCTION CHECKLISTS
testing reports in the appropriate appendix. This creates a uni- COMPLETED
fied record of.all required testing pe1for,ned during purchasing APPENDIX M- TESTS AND DOCUMENTATION
and installation. COMPLETED
Insert copies ofinstallers' and Cx authorities' completed
APPENDIX N- SYSTEMS MANUAL ASSEMBLY
validation checklists in the appropriate appendix. This pro-
PROCESS
vides a record o_f installation checks and observations for
future reference. APPENDIX 0-TRAINING RECORDS
Insert copies ofinstallers ' and Cx authorities ' cornpleted APPENDIX P- MEETING MINUTES AND
functional per_for,nance checklists of assernblies, equip,nent,
CORRESPONDENCE
and integrated :,yste,n in the appropriate appendix. This pro-
vides a record of per_forrnance checks· and observations for APPENDIX Q-COMMISSIONING (Cx) PROGRESS
future reference. REPORTS
APPENDIX R- WARRANTY REVIEW AND STATUS
5. Cx Progress Reports
APPENDIX S-OPEN ISSUES
Insert a copy of all Cx progress reports in the appropriate
appendix. APPENDIX T- LESSONS-LEARNED REPORT
.. ... , ....... .. .. . ., , ...
Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 65
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is International Code Council (ICC)
merely informative and does not contain requirements 500 New Jersey Ave. NW, 6th Floor, Washington, DC 20001
necessary for conformance to the guideline. Unresolved W\VW. shop. iccsafe.org/icc-G4-2012-guideline-for-comn1is-
objectors on informative material are not offered the right sioning- I .htn1l
to appeal at ASHRAE.)
International Energy Agency (IES) Energy Conservation
in Buildings and Community Systems (ECBCS)
INFORMATIVE ANNEX Y
Progranune, 9, rue de la Federation
INDUSTRY RESOURCES
75739 Paris Cedex 15, France
The following organizations and agencies have produced pub- W\Vw.ecbcs.org/annexes/annex40.htm, and www.ecbcs.org/
1ications and resources relating to the cotntnissioning (Cx) annexes/annex4 7 .htm
Process and Systerns Manuals that are available fro1n the pub-
National Environmental Balance Bureau (NEBB)
lishing organization. These publications and resources 1nay or
8575 Grovemont Circle, Gaithersburg, MD 20877
,nay not confonn to the requirernents of ANSI/ ASHRAE
W\Vw.nebb.org/resources/standards
Standard 202-20 I 3 or this guideline. This list is provided as a
resource for those using and providing Cx services. Since National Fire Protection Association (NFPA)
publications can change frequently, the organization websites I Batteryinarch Park, Quincy, MA 82169
are the best source of current doctunents. nfpa.org/codes
AABC Commissioning Group (ACG) National Institute of Building Science (NIBS)
1518 K Street, NW, Suite 503, Washington DC I 090 Vennont Ave, Suite 700, Washington, DC, 20005
W\Vw.com1nissioning.org/co1n1nissioningguideline W\Vw.nibs.org and WW\v.wbdg.org/project/building-
co1run.php
ASTM International
100 Bar Harbor Drive, PO Box C700 Portland Energy Conservation Incorporated (PECI)
West Conshohocken, PA, 19428-2959 E2813-12 I 00 SW Main Street, Suite 1600, Portland, OR 97204
W\Vw.ast1n.org/DIGITAL_LIBRARY/index.sht1nl peci.org/resources
.
Building Commissioning Association (BCA) Sheet Metal and Air Conditioning Contractors National
1600 NW Con1pton Drive, Suite 200, Beaverton, OR 97006 Association (SMACNA)
W\Vw.bcxa.org/knowledge-center 4201 Lafayette Center Drive, Chantilly, VA, 20151
W\VW. s1nacna. org/techni ea!
California Commissioning Collaborative (CCC)
The State of Minnesota, Sustainable Building Guidelines
W\VW. cacx.org/resources/index. htin 1
Design and Construction Phase
Canadian Standards Association (CSA) Com1nissioning Plan Template
Group Head Office, 178 Rexdale Blvd. W\Vw.n1sbg.umn.edu
Toronto, Ontario, Canada M9W IR3 University of Michigan
W\Vw.csa.ca/cm/ca/en/standards (search for Z320- I I Building W\Vw.plantext.bf.u1nich.edu/forarchs/com.html
Co1n1nissioning)
University of Wisconsin- Madison
Chartered Institution of Building Services Engineers W\Vw.epdweb.engr.wisc.edu
(CIBSE)
222 Balhatn High Road, London, SW 12 9BS United States Department of Veterans Affairs (VA)
www.cibsekno\vledgepo1tal.c0.uk/cibse-co1nmissioning- W\Vw.cfm.va.gov/til/co1mnissioning/CxManual.PDF and
codes W\Vw.virtualcx.convblog/2011/3/17/whole-building-com1nis-
sioning-process-manual-departtnent-of-ve.httnl
Energy Systems Laboratory
TAMU, College Station, Texas United States Army Corps of Engineers
W\vw.esl.tamu.edu/continuous-commissioning W\Vw.wbdg.org/project/buildingconu11.php
United States Department of Energy (USDOE)
Illuminating Engineering Society of North America
W\Vw.eere.energy.gov/fe1np/reconstructionguide/
(IESNA)
co1run_process.htn1l
120 Wall Street, 17th floor, New York, NY, I 0005
W\vw.iesna.org/store/product/the-co1runissioning-process- United States General Services Administration (GSA)
applied-to-lighting-and-control-systems- I 251.cfin W\Vw.gsa.gov/portal/category/21064

American Sociel1 pl Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHSQQJer license with ASH RAE Nol for Resale, 201515/28 09:22:15 ASHRAE Guideline 1.4-2014
No rep1oduciion or networking permitted wilhout license from IHS
(This annex is not a mandatory part of this guideline. It is ASHRAE. 2013. ANSI/ASHRAE Standard 62.1, Ventilation
merely informative and does not contain requirements for Acceptable Indoor Air Quality. Atlanta: ASHRAE.
necessary for conformance to the guideline. Unresolved EVO. 2007. International Perjor,nance Measure,nent and
objectors on informative material are not offered the right Ver(/ication Protocol. Efficiency Valuation Organization.
to appeal at ASHRAE.) IICRC. 1994. SOO!, Standard and Reference Guide.for Pro-
fessional Carpet Cleaning. Vancouver, WA: Institute of
INFORMATIVE ANNEX Z Inspection, Cleaning, and Restoration Certification.
REFERENCES IICRC. 2008. Standard S520, Standard and Reference Guide
for Professional Mold Re,nediation. Vancouver, WA:
ASHRAE. 2010. ANSI/ASHRAE/IES Standard 90.1 , Energy
Institute of Inspection, Cleaning, and Restoration Certifi-
Standard .for Buildings Except Lo1-v-Rise Residential
cation.
Buildings. Atlanta: ASHRAE.
NERC. n/d. NERC CIP-004, Personnel and Training. Wash-
ASHRAE. 2012. ANSI/ASHRAE/ACCA Standard 180, Stan- ington, D.C.: North An1erican Electric Reliability Corpo-
dard Practice for Inspection and Maintenance o,f Co,n- ration.
1nercial Building HVAC Syste,ns. Atlanta: ASHRAE. NERC. n/d. NERC CIP-006, Physical Security of· Critical
ASHRAE. 2013. ASHRAE Guideline 0, The Co1n111issioning Cyber Assets. Washington, D.C.: North American Elec-
Process. Atlanta: ASHRAE. tric Reliability Corporation.
ASHRAE. 2013. ANSI/ASHRAE Standard 202, The Co,n- NFPA. 2000. NFPA 45, Standard on Fire Protection for Lab-
1nissioning Process .for Buildings and Syste,ns. Atlanta: oratories Using Chen1icals. Quincy, MA: National Fire
ASHRAE. Protection Association.

..

Ame~can Sociely_..o)..);le?tina.,.B~ger<1l.i.rJ:9 and/4ir·CQ!'Kiijiqning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617


Provided by IHS~~~m!#Ml-U.e I.4 -LU 14 Nol for Resale, 201515/28 09:22:15 67
No rep1oduciion or networking permitted wilhout license from IHS
American Sociely ol Healing, Refrigeraling and Ait·Condilioning Engineers, Inc. licensee=ZHEJ IANG INST OF STANDARDIZATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduclion or networking permitted wilhout license from IHS
POLICY STATEMENT DEFINING ASHRAE'S CONCERN
FOR THE ENVIRONMENTAL IMPACT OF ITS ACTIVITIES

ASHRAE is concerned with the impact of its members' activities on both the indoor and outdoor environment. ASHRAE's
members will strive to minimize any possible deleterious effect on the indoor and outdoor environment of the systems and
components in their responsibility while maximizing the beneficial effects these systems provide, consistent with accepted
standards and the practical state of the art.
ASHRAE's short-range goal is to ensure that the systems and components within its scope do not impact the indoor and
outdoor environment to a greater extent than specified by the standards and guidelines as established by itself and other
responsible bodies.
As an ongoing goal, ASHRAE will, through its Standards Committee and extensive technical committee structure,
continue to generate up-to-date standards and guidelines where appropriate and adopt, recommend, and promote those new
and revised standards developed by other responsible organizations.
Through its Handbook, appropriate chapters will contain up-to-date standards and design considerations as the material is
systematically revised.
ASHRAE will take the lead with respect to dissemination of environmental information of its primary interest and will seek
out and disseminate information from other responsible organizations that is pertinent, as guides to updating standards and .
'
guidelines. '
The effects of the design and selection of equipment and systems will be considered within the scope of the system's
intended use and expected misuse. The disposal of hazardous materials, if any, will also be considered.
ASHRAE's primary concern for environmental impact will be at the site where equipment within ASHRAE's scope
operates. However, energy source selection and the possible environmental impact due to the energy source and energy
transportation will be considered where possible. Recommendations concerning energy source selection should be made by
its members.

American Sociely ol Healing, Refrigeraling and Air·Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduciion or networking permitted wilhout license from IHS
ASHRAE · 1791 Tullie Circle NE· Atlanta, GA 30329 · www.ashrae.org

About ASHRAE
ASHRAE, founded in 1894, is a global society advancing human well-being through sustainable technology for the built
environment. The Society and its members focus on building systems, energy efficiency, indoor air quality, refrigeration,
and sustainability. Through research, standards writing, publishing, certification and continuing education, ASHRAE
shapes tomorrow's built environment today.

For more information or to become a member of ASHRAE, visit www.ashrae.org.

To stay current with this and other ASHRAE standards and guidelines, visit www.ashrae.org/standards.

Visit the ASHRAE Bookstore


ASHRAE offers its standards and guidelines in print, as immediately downloadable PDFs, on CD-ROM, and via ASHRAE
Digital Collections, which provides online access with automatic updates as well as historical versions of publications.
Selected standards are also offered in redline versions that indicate the changes made between the active standard and
its previous version. For more information, visit the Standards and Guidelines section of the ASHRAE Bookstore at
www.ash rae.org/bookstore.

IMPORTANT NOTICES ABOUTTHIS STANDARD

To ensure that you have all of the approved addenda, errata, and interpretations for this
standard, visit www.ashrae.org/standards to download them free of charge.

Addenda, errata, and interpretations for ASHRAE standards and guidelines are no
longer distributed with copies of the standards and guidelines. ASHRAE provides
these addenda, errata, and interpretations only in electronic form to promote
more sustainable use of resources.

Productcode:86820 7/14
..· ... ,..,,.,.,. .. . ,., ...
American Sociely ol Healing, Refrigeraling and Air,Conditioning Engineers, Inc. licensee=ZHEJIANG INST OF STANDARDIZATION 5956617
Provided by IHS under license with ASH RAE Nol for Resale, 201515/28 09:22:15
No rep1oduciion or networking permitted wilhout license from IHS