Professional Documents
Culture Documents
LEO Chapter 4
LEO Chapter 4
Table 4.1. Average Daily Traffic Volumes of Different Axles (According to Htun Nyo
Lu Co., Ltd)
Table 4.2. Total Traffic Volume (According to Htun Nyo Lu Co., Ltd)
Total Cars
Date X Y
Total
(Mahlaing to Taungtha) (Taungtha to Mahlaing)
Table 4.2. Total Traffic Volume (According to Htun Nyo Lu Co., Ltd) (Continued)
Total Cars
Date
X Y
Total
(Mahlaing to Taungtha) (Taungtha to Mahlaing)
Table 4.2. Total Traffic Volume (According to Htun Nyo Lu Co., Ltd) (Continued)
Total Cars
Date
X Y
Total
(Mahlaing to Taungtha) (Taungtha to Mahlaing)
Table 4.3. Total Traffic Volume for Difference Axle of Traffic (According to Htun Nyo
Lu Co., Ltd)
Date A B C D E F G H
1.12.2019 53 82 12 52 1 60 3 18
2.12.2019 51 83 10 50 2 51 4 19
3.12.2019 52 84 12 49 3 57 2 18
4.12.2019 56 82 10 51 1 58 5 19
5.12.2019 54 80 11 48 2 53 3 18
6.12.2019 55 86 8 49 3 53 4 19
7.12.2019 124 31 43 56 5 41 10 11
8.12.2019 56 82 12 48 1 56 3 16
9.12.2019 59 83 10 49 2 58 5 17
10.12.2019 57 81 10 52 1 57 4 18
11.12.2019 56 80 12 50 2 52 2 19
12.12.2019 58 82 10 49 3 59 3 15
13.12.2019 59 83 12 52 1 59 2 18
34
Table 4.3. Total Traffic Volume for Difference Axle of Traffic (According to Htun Nyo
Lu Co., Ltd) (Continued)
Date A B C D E F G H
14.12.2019 60 86 9 50 2 28 4 16
15.12.2019 69 81 10 53 1 51 5 19
16.12.2019 67 82 12 50 2 57 2 18
17.12.2019 50 81 10 51 3 56 3 18
18.12.2019 58 82 11 50 2 53 2 17
19.12.2019 49 80 12 49 1 57 4 19
20.12.2019 50 81 10 52 2 58 2 16
21.12.2019 59 82 9 49 3 56 3 19
22.12.2019 68 90 8 50 2 50 2 18
23.12.2019 50 89 9 51 1 59 4 16
24.12.2019 70 86 12 53 2 57 2 18
25.12.2019 69 90 10 52 3 51 3 19
26.12.2019 58 88 10 50 2 52 2 18
27.12.2019 54 87 12 49 1 56 4 19
28.12.2019 57 86 10 51 2 54 2 18
29.12.2019 59 80 9 50 3 58 3 19
30.12.2019 68 89 10 49 2 49 2 18
31.12.2019 58 88 8 52 0 53 4 19
ADT = 282
35
6.30%
1.18%
21.31%
19.44%
0.70%
29.13%
17.90%
4.04%
A B C D E F G H
A 4409.25 (4.41)
B 11023.11 (11.02)
C 28660.09 (28.66)
D 37478.58 (37.48)
E 52910.94 (52.91)
F 61729.43 (61.73)
G 108026.51 (108.03)
H 112435.75 (112.44)
A = Under 2 tons
B = 2 axle 4 tire (5 tons)
C = 2 axle 6 tire (13 tons)
D = 3 axle 6 tire (17 tons)
E = 3 axle 10 tire (24 tons)
36
Determination No; 1 2 3 4 5
Container No; 1 2 3 4 5
Container No; 1 2 3 4 5
γ
Dry density, γ d (g/cm3) 1.71 1.79 1.76 1.7 1.63
1 ω
(12.4,1.79)
2
1.5
0.5
Water Content, ω (%)
0 6 12 18 24 30
Figure 4.2. Graph for Optimum Moisture Content
0 0 0
0.5 32 93.89
1 72 211.27
2 188 551.66
3 372 1091.58
4 524 1537.61
5 737 2162.63
38
10 1682 4935.61
Table 4.3. Traffic (total axle accumulations) 10 years design period will be calculated
and the structural number (SN) is assumed. In this study, the initial serviceability P i is
used 4.2 and terminal serviceability Pt is 2.5.
Let SN = 6
For A = under (2 tons)
2.205-kip single axle = 0.0004 (Table A.1)
2.205-kip single axle = 0.0004 (Table A.1)
Total 18-kip ESAL = 0.0008
For B = 2 axle 4 tire (5 tons)
2.204-kip single axle = 0.0004 (Table A.1)
8.816-kip single axle = 0.0509 (Table A.1)
Total 18-kip ESAL = 0.0513
For C = 2 axle 6 tire (16 tons)
5.732-kip single axle = 0.0081 (Table A.1)
22.928-kip single axle = 2.7501 (Table A.1)
Total 18-kip ESAL = 2.7582
For D = 3 axle 6 tire (17 tons)
7.496-kip single axle = 0.0255 (Table A.1)
29.984-kip tandem axle = 0.6317 (Table A.2)
Total 18-kip ESAL = 0.6572
For E = 3 axle 10 tire (24 tons)
5.926-kip single axle = 0.0087 (Table A.1)
23.492-kip single axle = 3.0236 (Table A.1)
23.492-kip single axle = 3.0236 (Table A.1)
Total 18-kip ESAL = 6.0559
For F = 4 axle 12 tire (28 tons)
10.42-kip single axle = 0.1002 (Table A.1)
18.402-kip single axle = 1.1106 (Table A.1)
32.908-kip tandem axle = 0.9457 (Table A.2)
Total 18-kip ESAL = 2.1565
For G = 5 axle 18 tire (49 tons)
16.745-kip single axle = 0.7528 (Table A.1)
21.282-kip single axle = 2.0308 (Table A.1)
70-kip triple axle = 4.84 (Table A.3)
42
D2 5 in
Use the thickness of untreated granular base course = 5 in
SN 2 = SN1 + a 2 m2 D2
SN 2 = 2.2+0.14x1x5 = 2.9 in
SN 3 SN 2
D 3 =
a 3m3
2 . 8 2 .9
D3 = = 0.9 in (The negative value is impossible.)
0.11 1
The thickness of asphalt concrete sub-base course is omitted.
SN 3 = SN 2 + a 3 m 3 D3
SN 3 = 2.801 SN 3
Formation Width
3 ft 18 ft 3 ft
Pavement Width
Shoulder Shoulder
Figure 4.3. Typical Design Cross Section of Mahlaing-Taungtha Road Section for the
Testing CBR Value of 11.5%
48
Measurement
Item Particular No Content Unit Total
L B H
Construction of
2 Base Layer with 3" 1 1 5280 20 0.42 44352 cu-ft 44352
Down Crushed Rock
Construction of
Wearing Surface
3 1 1 5280 18 0.42 39916.8 cu-ft 39916.8
with 1.5" to 2"
Crushed Rock
Measurement
Item Particular No Content Unit Total
L B H
Construction of
6 Shoulders with
Gravelly Soil
Labour
Construction of
Base Course 5"
Depth
2 44352 cu-ft
(Compacted)
Using 3" Down
Crushed Rock
Material
3" Down
Crushed Rock 266.11 Sud 55000 Sud 14636050
(48%)
1"x2" Crushed
232.8 Sud 60000 Sud 13968000 31168750
Rock (42%)
3/4" Chipping
27.74 Sud 65000 Sud 1803100
(5%)
50
Rate Amount
Item Particular Quantity Unit Per Total
(Kyats) (Kyats)
3/8" Chipping
6.91 Sud 65000 Sud 449150
(25% of 5%)
Coarse Sand
20.83 Sud 15000 Sud 312450
(75% of 5%)
For Operation
Machine
Smooth-wheel
355.2 Hr 20000 Hr 7104000 7104000
Roller
Labour
Material
1"x2" Crushed
611.92 Sud 60000 Sud 36715200
Rock (73.6%)
51
Rate Amount
Item Particular Quantity Unit Per Total
(Kyats) (Kyats)
1/2" Crushed
36.72 Sud 65000 Sud 2386800
Rock (4.4%)
3/8"-3/4"
Chipping 122.94 Sud 65000 Sud 7991100
(14.8%)
50745800
<3/8" Chipping
55.093 Sud 65000 Sud 3580850
(6.6%)
Coarse Sand
4.79 Sud 15000 Sud 71850
(0.6%)
For Operation
Machine
Smooth-wheel
831.47 Hr 20000 Hr 16629400 16629400
Roller
Labour
Rate Amount
Item Particular Quantity Unit Per Total
(Kyats) (Kyats)
Hot Bitumen
2.5" Depth
Grouting
(Semi-Grout)
4 95040 sq-ft
Over Crushed
Rock Surface
with 1/4" to
3/4" Chipping
Material
For Operation
Machine
Smooth-wheel
191.25 Hr 20000 Hr 3825000 3825000
Roller
Labour
Rate Amount
Item Particular Quantity Unit Per Total
(Kyats) (Kyats)
Hot Bitumen
Surface
Dressing Over
Crushed Rock
5 95040 sq-ft
Surface with
1/4" to 3/4"
Chipping
(First Seal)
Material
For Operation
Machine
Smooth-wheel
153 Hr 20000 Hr 3060000 3060000
Roller
Labour
Material
For Operation
Machine
Smooth-
21.12 Hr 20000 Hr 422400 422400
wheel Roller
Labour
Total 216029341
Rate Amount
Item Particular Quantity Unit Per
(Kyats) (Kyats)
1 Material
Rate Amount
Item Particular Quantity Unit Per
(Kyats) (Kyats)
2 For Operation
3 Machine
4 Labour
Rate Amount
Item Particular Quantity Unit Per
(Kyats) (Kyats)
Total 216029341
Rate Amount
Item Particular Quantity Unit Per
(Kyats) (Kyats)
Construction of Base
2 Layer with 3" Down 44352 cu-ft 1121.826 cu-ft 49755226.75
Crushed Rock
Rate Amount
Item Particular Quantity Unit Per
(Kyats) (Kyats)
Construction of
6 Shoulders with 22176 cu-ft 302.39 cu-ft 6705800.64
Gravelly Soil
Total 216029468.2