Professional Documents
Culture Documents
It should be noted that the definition of reliability may vary from different
perspectives. The two main perspectives for reliability consideration in a power
system are customer perspective of quality and continuity of service and utility
perspective of achieving an acceptable level of system reliability as shown in
Figure (1).
The customers care about quality of service and being able to use their
appliances any time needed during a day. Therefore any interruption in service is
undesirable from the customer’s perspective. The utility’s perspective of reliability
considers both the service reliability at the load points and reliability of the supply
side which may include the reliability of generation, transmission and distribution
assets.
Reliability studies and the development of reliability models and tools are
important activities in the design, operation, and planning of reliable power
systems. It is important to create ways to evaluate power system reliability in order
to minimize non-continuity in service and interruptions in the electric supply. In
field of power system, such evaluation can be defined as analyzing the ability of
the system to satisfy the load requirements.
Figure (2) shows the two main types of system reliability evaluation categories
which are related to system adequacy and system security.
Figure (4): An overall electric power system and its distribution system.
Transmission substation: A transmission substation connects two or more
transmission lines. It may have transformers to convert between two transmission
voltages, voltage control/power factor correction devices such as capacitors,
reactors or static VAR compensators and equipment such as phase shifting
transformers to control power flow between two adjacent power systems.
Distribution substations: transfer power from the transmission system to
the distribution system of an area. These substations are connected to the sub-
transmission system in order to reduce the transmission HV to medium voltage
ranging between 1 kV and 35 kV according to IEC (Hint: The standard ratings are:
11 kV and 22 kV in Egypt) with the use of transformers. Distribution substations
convert energy to lower primary system voltages for local distribution and usually
provide facilities for voltage regulation of the primary voltage.
Feeder feeds power from one point to another without being tapped from
any intermediate point. A primary distribution feeder in Egypt usually operates in
the range of 22 kV to 11 kV and supplies the load in well-defined geographical
areas. These feeders carry power from the main distribution substation to the
secondary substation.
The Higher Institute of Engineering Al-Shorouk City
A circuit breaker is usually present in the main feeder to detect the fault in
any part of the system and to protect the overall system from the damaged fault.
Manual sectionalizing equipment such as disconnects or isolators are also installed
at strategic locations on the main feeder for isolating the faulted sections and
restoring supply to the healthy sections. The time required performing isolation
and switching actions while a faulted component is being repaired is known as the
restoration time. Fuses are usually present in the lateral distributors at the junction
where they meet the main feeder to isolate the failures in the lateral sections from
rest of the main section.
It is important to note that the distribution system is a vital link between the
bulk power system and its customer. In many cases, these links are radial. A radial
distribution system consists of series components, including lines, disconnects (or
isolators) and bus bars. A radial distribution circuit generally uses main feeders
and lateral distributors to supply energy requirements. Failure of any of these
components will cause an outage of service at the load points for all the system.
The Higher Institute of Engineering Al-Shorouk City
The reliability of this system is affected by the type of protection such as the
fuse gear which install at tee-point in each lateral distributors to isolate failures on
the lateral sections from the main feeders and disconnects or isolators at judicious
points along the main feeder. The characteristics of RDS shown in Figure (5) are
series, low cost, simple design and lower reliability systems which only contain
one source of supply to feed the load points.
The load point failure rate ( λj), average outage time (𝑟j) and average
annual outage time (𝑈j) are the basic load point indices. The system reliability
indices can be obtained from the basic load point indices and information on the
number of customers and load connected at each load point in the system.
The Higher Institute of Engineering Al-Shorouk City
The component reliability data of failure rate ( λ i), outage time (𝑟i) can be
used to determine the reliability indices for the load points through Minimal Cut
Sets (MCSs). The load point reliability indices expression is given from (1-1) to (1-
3). The average failure rate indicates the number of failures a load point will
experience during a given period of time. The average outage time is the average
restoration duration of load point. The average annual outage time is the average
total duration of outage in a year experienced at the load point.
These reliability indices are expected values and represent the long-run
average value.
Where λi and 𝑟i are the failure rate and the average repair time of the
component i, while 𝜆j, rj and 𝑈j are the average failure rate, repair time and
unavailability at load point j.
Where, λj is the failure rate of load point j and Nj is the number of customers at
load point j.
= 𝐸𝐸𝑁𝑆⁄
∑𝑁j (MWh /cust.yr)
The average values of these indices can be easily computed as the associated
analytical techniques are highly developed for both radial and meshed systems.
Example 1: Consider the simple radial system shown in Figure (7). The
assumed failure rates and repair times of each line A, B and C are shown in Table
1.1.
This numerical example illustrates the typical and generally accepted feature
of a radial system that the customers connected to the system farthest from the
supply point tend to suffer the greatest number of outages and the greatest
unavailability. The results for this example were evaluated using the basic concepts
of network reliability. This assumes that the failure of line elements A. B and C are
simple open circuits with no compound effects, i.e. the failure of line element C
does not effect Load_A or Load_B. This is the same as assuming perfect isolation
of faults on line elements A, B and C by the breakers shown in Figure (7). The
load point reliability indices are shown in Table 1.2.
The Higher Institute of Engineering Al-Shorouk City
The load point reliability indices have been executed by NEPLAN Software
as shown in Figure (8).
SAIFI = ∑ j 𝑁j
⁄ =
((0.2*200)+(0.3*150)+(0.45*100))
= 0.289 (int/yr)
Z 𝑁j (200+150+100)
SAIDI = ∑ Uj Nj⁄ (( ) ( ) ( ))
= 1.2*200 + 1.7*150 + 2.9*100 = 1.74 (hr/yr)
∑ Nj (200+150+100)
CAIDI = ∑ Uj Nj⁄ (( ) ( ) ( ))
= 1.2*200 + 1.7*150 + 2.9*100 = 6.04 (hr/cust.int)
∑ 𝜆j Nj ((0.2*200)+(0.3*150)+(0.45*100))
Example 2: Consider the system shown in Figure (10). This is a single line
representation of the system and the following discussion assumes that any fault,
single phase or otherwise, will trip all three phases.
In this case the reliability indices are improved for all load points although
the amount of improvement is different for each one. The most unreliable load
point is B because of the dominant effect of the failures on its lateral distributor.
The additional indices for this system are:
SAIFI = 1.153 (f/yr)
SAIDI = 3.906 (hr/yr)
CAIDI = 3.38767 (hr/f)
ASUI = 0.000044589
ASAI = 0.9995541
EENS = 54.8 MWh/yr
AENS = 18.3 kWh/cust.yr
The system reliability indices have been executed by NEPLAN Software as
shown in Figure (13).
Figure (14): Test system reinforced with disconnects and fuse gear
The reliability indices for the four load points are now modified to those
shown in Table 1.8.
Load pt C Load pt D
Component 𝑟 U 𝑟 U
Failure (𝑓⁄𝑦𝑟) (ℎ𝑟) (ℎ𝑟⁄𝑦𝑟) (𝑓⁄𝑦𝑟) (ℎ𝑟) (ℎ𝑟⁄𝑦𝑟)
Section
1 0.2 4 0.8 0.2 4 0.8
2 0.1 4 0.4 0.1 4 0.4
3 0.3 4 1.2 0.3 4 1.2
4 0.2 0.5 0.1 0.2 4 0.8
Distributor
a
b
c 0.4 2 0.8
d 0.2 2 0.4
Total 1.2 2.75 3.3 1.0 3.6 3.6
In this case, the reliability indices of load points A, B, C are improved, the
amount of improvement being greater for those near to the supply point and less
for those further from it. The indices of load point D remain unchanged because
isolation cannot remove the effect of any failure on this load point. The additional
customer- and load-orientated indices for this configuration are: