Professional Documents
Culture Documents
Conclusion
For analyzing the failure effects of Power system components such as Power
Transformers, Circuit Breakers, etc., statistical failure data is collected from
the field, i.e., Nellore district sub-stations of APTRANSCO. It is substantiated
with practical case studies that failure of components does affect the system
adequacy and system security. To improve Reliability of EHT transmission
system, preventive efforts are to be taken such as replacement of worn out
equipment, installation of redundant arrangements etc. Component-wise
effect on overall system based on failure criticality index is also computed
for two sample systems based on Birnbaum’s measure.
EHT feeder interruptions are forecasted for two feeders of Nellore 220 kV
sub-station of APTRANSCO using regression-based approach, taking the
past trippings quarter-wise data into consideration. The discrepancy between
actual and predicted data may be attributable to varying climatic conditions.
The predicted data gives an idea over probable trippings in advance for
effective preventive maintenance follow up. Computation of main indices such
as availability, failure rate and repair time are carried out based on Markov
approach for 132 and 220 kV feeders of Chittoor district of APTRANSCO.
The availabilities of 132 and 220 kV feeder networks work out to be 99.014
and 99.559 respectively. These values are essential for Reliability and risk
assessment of EHT Transmission network. These values need to be tabulated
and preserved for future analysis as the frequency and duration of interruptions
need to be reduced progressively for improved Reliability.
Conclusion
Load Forecasting
Load forecasting has always been important for planning and operational
decisions conducted by utility companies. However, with the deregulation of
the energy industries, load forecasting is even more important. With supply
and demand fluctuating and the changes of weather conditions and energy
prices increasing by a factor of ten or more during peak situations, load
forecasting is vital for utilities.
ANN based approach was applied to short term load forecasting on
Chittoor district consumption collected on daily basis. Load forecasting is
carried out with acceptable level of accuracy as the error was in the range
of .04944 – 0.55109% only. This forecasting helps to plan augmentation of
power components, EHT Transmission lines and sub-stations in advance for
improved availability.
113
Conclusion
system. Instead, utilities are installing site specific systems at critical locations
throughout their networks, or more specifically, on key pieces of electrical
equipment within the substation.
Utilities have a myriad of choices in their maintenance approaches.
The terms used for these approaches; preventive maintenance, corrective
maintenance, time-based maintenance, condition-based maintenance and
reliability-centered maintenance, etc. need to be followed for improved
availability of power components. Utility personnel perform both preventive
maintenance (PM) as well as corrective maintenance (CM). PM is the scheduled
inspection or servicing of equipment at specific points in time to retain the
functional capabilities of the unit. CM is the unscheduled repair of failed
equipment to restore its functional capabilities. Generally, CM is more costly
and time consuming than PM. Therefore, the goal is to statistically develop
a maintenance plan that meets reliability and budget goals.
Utility maintenance programs have historically been based on maintenance
schedules recommended by original equipment manufacturers. As utilities
develop loading histories and maintenance logs for substation equipment, they
adjust maintenance schedules to more accurately reflect the true operating
condition of the devices. By tracking maintenance histories and measuring
critical indicators of wear or deterioration, utilities can lengthen the life span
of existing network systems without adversely affecting reliability. Utilities
now use condition-based monitoring techniques as well as traditional time-
based maintenance (another term to describe PM) schedules. As the industry
continues to restructure and evolve, utility personnel will continue to use
advanced technologies to deliver reliable power to their customers
114
Conclusion
expansion. But the possibility to build merchant lines raises new technical
and economical problems. From technical point of view, it is necessary to
compute the amount of transmission capacity to be assigned to every new
facility coming from time to time. It also requires the market forces to adopt
Flexible AC Transmission (FACTs) for controlling the power flows across
different nodes.
In order to avert a lack of adequate transmission to serve future demand,
many transmission system operators have to develop a planning process that
identifies reliability deficiencies say five to ten years in future. Apart from the
planning, the transmission system operator is expected to develop its own set
of projects to address the deficiencies along with private investments in the
form of merchant projects. This is essential because a critical transmission
line may cause grid congestion and related network violations.
A power exchange needed to be formed where producers and buyers can
bid for selling and purchase of energy conceptualizing the day-ahead energy
market. In the new liberalized environment, the secure planning and operation
is actually possible with a coordinated development of market rules aimed
at guaranteeing both competition and transparency.
115
Conclusion
Load Forecasting
Reliable power system operation requires far more than monitoring and
controlling the system in real-time. Thorough planning, design, maintenance,
116
Conclusion
and analysis are required to ensure that the system can be operated reliably
and within safe limits. Short-term planning addresses day-ahead and week-
ahead operations planning; long-term planning focuses on providing adequate
generation resources and transmission capacity. Load forecasting is required
to ensure that in the future, the system will be able to withstand severe
contingencies without experiencing widespread, uncontrolled cascading
outages.
117