Professional Documents
Culture Documents
ANUGRAH RAYA
Jl. Gabus Raya No. 2, Desa Srijaya. Kec. Tambun Utara. Kab. Bekasi. West Java-Indonesia 17510
Telp. (+62) 851 0039 4472 / WhatsApp : (+62) 851 0039 4525, Facebook : Anugrah Raya
Website : www.ar-shearconnector.com, Email : arkoco@ar-shearconnector.com
AR
ANUGRAH RAYA
Composite Construction
Building
Steel beam and reinforced concrete slab joined by AR
shear connector give action as a beam structures
produce load bearing efficiently that combined
strength of steel and concrete slab. It allow longer
span with thinner and lighter floor, which provide great
cost saving in entire construction expenses. AR shear
connectors can be welded throughmetal decks, which
secure the decks to the beam and also the beam to
reinforced concrete slab with the studs producing all
three structural members act as a strong unit.
Page 2
AR
ANUGRAH RAYA
The composite beam consists of three elements : (1) steel beam, (2) reinforced concrete slab, and (3) AR shear
connector welded to the beam. The studs transfer horizontal shear from slab to beam, causing the two elememnts to
act as a unit. Thus, the strength and stiffness of the efective section can be increased without using more steel.
Specifically, composite design permits saving in steel tonnage up to 20%; reduces building height and saves on
materials because lighter beams result in shallower floor section; and provides larger rooms with fewer obstructions
because longer span may be used.
* Top flanges of beams should be unpainted. The beams should be free of heavy rust and mill scale, dirt, sand, or
other materials which will interfere with the welding operation.
* Floor sheets or deck material also should be free of dirt, sand, or other foreign materials.
* Water on the deck or between the deck and beams must be removed before welding.
* Floor sheets or deck material must rest tightly upon the top flange of the beam.
* Adequate incoming AC power must be available for power requirements of recommended power sources.
* Adequate welding power must be available to provide weld current requirements as indicated in recommended
Weld Setup.
Cable length and size have a definite effect on power source current output and become increasingly important
when dealing with high currents and high welding rates. Refer to factors affecting equipment installation for cable
recommendations.
Small cables heat up rapidly, increasing resistance and decreasing the power for the weld. ALWAYS USE #4/0
WELDING CABLE, AND USE THE SHORTEST POSSIBLE CABLE LENGTHS.
Usual maximum cable length is 200 feet. If adequate current cannot be obtained, shorten cable lengths or parallel
two #4/0 cable. Note : Cable lengths mean total cable length in the weld current including ground cable.
A clean solid ground is a must . To be certain that you have such a connection, always grind or otherwise clean the
surface where the ground with a heavy screw type clamp.
Page 3
AR
ANUGRAH RAYA
Even the best operators, however, need to follow certain practices if deck is to be installed with weld-through AR
shear connectors. Be sure to:
* Lay deck material, in dry weather, just ahead of the stud welding crew when possible. Such scheduling is the best
way to avoid problems caused by water and dirt which may collect on deck material or between deck and the
beam.
* It is best to keep the tacking or puddle welding of deck to minimum prior to stud welding.
* Remove any standing water on deck or beams before welding. Sweep and/or blow water using compressed air or
a propane torch.
* Brush and blow away from weld area any dirt, sand, concrete dust, etc. before welding studs.
* Keep studs and ferrules dry by storing them in a waterproof enclosure. Rusty studs or damp, wet ferrule will affect
weld quality. After welding, ferrule should be broken free from the stud.
* Do not lay out any more ferrules, ahead of stud welder, on deck material for welding, than can be welded in one
production period. Ferrules not used and left on the deck may absorb moisture and affect weld quality.
* Do not weld through two thicknesses of hot dipped galvanized or cellular deck. Proper fit up between sheets is
almost never obtained, and excessive gap between sheets will cause poor welds.
A minimum of two test studs should be welded. These studs should then be bent to an angle of 30° from their
original axis by either striking the studs with a hammer or by placing a pipe or other suitable hollow device over the
stud and manually or mechanically bending the stud. If failure occurs in the weld zone of either stud, correct or
adjust the setup and repeat the test. Two consecutive studs should be welded and found satisfactory before any
production studs are welded.
If visual inspection reveals studs that do not show full fusion or a full 360° flash ( wel fillet), each stud should be bent,
by striking with a hammer or by placing a pipe or other suitable hollow device over the stud and manually or
mechanically bending, approximately 15° off perpendicular in a direction opposite to the missing flash. If the weld
does not fracture, the stud should be considered accptable and left bent. Stud that fail this test should be replaced.
Page 4
AR
ANUGRAH RAYA
1. This is a typical weld through hot dipped 2. This is a good weld in which the weld flash (fillet),
galvanized deck material in which the deck was is not uniform. Absence of a uniform flash (fillet),
tight against the beam. Note the relatively uniform, does not necessarily indicate a bad weld.
clean weld metal flash (fillet), or build up of weld Questionable weld should be tested, however.
metal around the stud
1 2
Page 5
AR
ANUGRAH RAYA
Mechanical Property :
D L Reduction
Yield Strenght Elongation
Standard Tensile Strenght Of Area
Min. Min.
Min.
AWS D1.1 Min. 65.000 psi / 51.000 psi /
20% 50%
Sect.7 Min. 450 MPA 350 MPA
Material Low Carbon Steel (as cold drawn) : ASTM A29 ( A108 ) Grades 1010 – 1020
75 mm 200-019-075
90 mm 200-019-090
100 mm 200-019-100
19 mm ( 3/4 Inch ) 10 mm 32 mm 100-019-008*
125 mm 200-019-125
135 mm 200-019-135
150 mm 200-019-150
Lift 2.5 to 4 mm
Plunge 6 to 10 mm
Polarity Straight
Ferrule 100-019-008
Page 6
AR
ANUGRAH RAYA
Embedment
Concrete Shear connector studs and other various studs can be welded to steel plate, steel angle, channel steel and
other large steel weld ments to serve as for joining steel liners to concrete surroundings.
Steel Plate
Steel Beam
Page 7
AR
ANUGRAH RAYA
Composite foundation
Shear connector are welded to inside of
steel pipe piling. Which is to be used for
brige foundation.
To make complete brige foundation, shear
connector are welded to secure concrete
section of steel pipe piling and footing
column.
Shear Connector
Bridge
Modern bridge to be built requires
strong structural strength bearing load
from heavy traffic passings. Shear
connector serves for such bridge
enable to make it more strong and
economically.
Composite Beam
The structure of compositebeam
widely used for building bridge
consists of steel beam nd reinforced
concrete slab joined by AR shear
connector, so that the steel and
concrete act as a unit to bear the
bending stress.
If the same load is to be born, the
composite beam allows smaller
sectional area, the composite bem
bears heavier load than non-
composite beam. Non – composite Beam
Page 8
AR
ANUGRAH RAYA
AR Shear Connector
Page 9
AR
ANUGRAH RAYA
Page 10
AR
ANUGRAH RAYA
Page 11
AR
ANUGRAH RAYA
BENDING TEST
According standard AWS D1.1. Sect.7, No fracture in weld near stud fillet/collar remains on plate, was passed bending
test by the solid steel with double acting-hydraulic cylinder to be 30° alternately in opposite direction.
Page 12
AR
ANUGRAH RAYA
Shear Connectors Production With Standard spesification :
H 1. AWS D1.1 Section 7 – Structural Welding Code
2. AASHTO/AWS D1.5 Section 7 – Bridge Welding Code
A
3. ISO 13918
4. JIS B1198
Mechanical Property :
Reduction
L Yield Strenght Elongation
D Standard Tensile Strenght
Min. Min.
Of Area
Min.
AWS D1.1 Min. 65.000 psi / 51.000 psi /
20% 50%
Sect.7 Min. 450 MPA 350 MPA
75 mm 200-016-075
16 mm 100 mm 200-016-100 100-016-007
125 mm 200-016-125 8 mm 32 mm
( 5/8 Inch ) 150 mm 200-016-150 100-016-009**
175 mm 200-016-175
75 mm 200-019-075
90 mm 200-019-090
100-019-007
100 mm 200-019-100
19mm
115 mm 200-019-115
10 mm 32 mm 100-016-008*
125 mm 200-019-125
( 3/4 Inch )
150 mm 200-019-150
100-016-009**
175 mm 200-019-175
200 mm 200-019-200
75 mm 200-022-075
100 mm 200-022-100
22 mm
125 mm 200-022-125
10 mm 35 mm 100-022-007
150 mm 200-022-150
( 7/8 Inch )
175 mm 200-022-175
200 mm 200-022-200
75 mm 200-025-075
100 mm 200-025-100
25,4 mm
125 mm 200-025-125
12.7 mm 41 mm 100-025-007
150 mm 200-025-150
( 1 Inch )
175 mm 200-025-175
200 mm 200-025-200
Length
Flat Surface Fillet Heel Angle Bend Double Band Single Bend J Hook
Page 14
AR
ANUGRAH RAYA
ANUGRAH RAYA
Jl. Gabus Raya No. 2, Desa Srijaya. Kec. Tambun Utara. Kab. Bekasi. West Java-Indonesia 17510
Telp. (+62) 851 0039 4472 / WhatsApp : (+62) 851 0039 4525, Facebook : Anugrah Raya
Website : www.ar-shearconnector.com, Email : arkoco@ar-shearconnector.com
Page 15
AR
ANUGRAH RAYA
HARAPAN
INDAH
AQUA
KALIMALANG
EXIT
TOL BEKASI
BARAT ST.KRANJI
PARK BEKASI
SUMMARECON
BEKASI
KEC.
TAMBUN UTARA
ST.BEKASI
Page 16