Professional Documents
Culture Documents
Contracts
Course Unit 3
Leonardo, John Rick I.
02
Introduction
3.1
WHAT IS CONTRACT?
a written or spoken agreement, especially one
concerning employment, sales, or tenancy,
that is intended to be enforceable by law.
What is a Construction Contract?
PROS OF HAVING
A CONTRACT
Protects both parties
Work is detailed
Disputes will be handled
well.
CONSEQUENCES OF
NOT HAVING ONE
CONSEQUENCES OF
NOT HAVING ONE
Contract
Subcontracting Formation
Bid Project
Submission Delivery
Bidding procedure
The principal steps in the bidding procedure for a fixed-
price construction contract include solicitation, bid
preparation, bid submission, bid opening, selection of
the lowest qualified bid, and contract award.
Contract award
After the bids are opened, they are evaluated by the
owner to determine the lowest qualified bid. The
qualification of a contractor is the determination that
the contractor possesses both the technical and
financial ability to perform the work required by the
contract.
SUBCONTRACTORS
Subcontracts are contracts between a prime
contractor and secondary contractors or
suppliers.
04
Construction
Contracts
Plans and
Specifications
3.4
Plans
Specifications
Construction technical specifications provide the detailed requirements for the
materials, equipment, and workmanship to be incorporated into the project.
1 General Requirements
Table 18–1 Organization of the
2 Site Work
uniform system for building
3 Concrete
4 Masonry specifications
5 Metals
6 Wood and Plastics This format was developed by the
7 Thermal and Moisture Protection Construction Specifications
8 Doors and Windows Institute (CSI) and is usually
9 Finishes
identified as the CSI format or
10 Specialties
11 Equipment Uniform System for Building
12 Furnishings Specifications.
13 Special Construction
14 Conveying Systems
15 Mechanical
16 Electrical
08
Shop drawings are drawings, charts, and other Samples are physical examples of
equipment or show how specific structural to the owner for approval prior to
Contract
Administration
Those beyond the control of either the contractor or owner (“acts of God”) - Any
financial compensation to the contractor would be provided by the contractor’s
insurance, not by the owner.
Those under the control of the owner - the owner must compensate the contractor for
any additional costs incurred as well as provide an appropriate time extension to the
contract.
Those under the control of the contractor - the contractor is responsible for
reimbursing the owner for any damages (actual or liquidated) resulting from the
delay.
07
Acceptance and Final Upon correction of all deficiencies on the punch list
Payment of record, the contractor should notify the owner’s
representative of this fact and submit a request for
The acceptance of a completed project final payment, together with any other documents
is customarily based on a final required by the contract (such as releases of liens,
inspection performed by the owner’s an affidavit that all payrolls and bills connected with
representative and conditioned upon the project have been paid, consent of surety to final
the correction of any deficiencies payment, etc.
noted.
Final payment and its acceptance by the contractor
If the facility or a portion thereof is
usually constitute a waiver of all claims by either the
substantially complete,the owner's
owner or contractor except for unsettled liens and
representative will execute a certificate
claims and deficiencies falling under warranty
of substantial completion for the work.
provisions.
06