Maintenance Plan for NR4, CW3- AF

Duration Dec. 2022 Jan. 2023 Feb.2023 Mar. 2023 Remarks


Description
(Day) 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Week
Quantities as per Inventory (Sq .m) 14,858.65
Permanence Repairs
Saw Cutting
LHS ;:::==J ~ ~ ~ ==:J ~ ~ ~ ==:J ~ ::::J ;:::==J ~
90 156 Sq.m I day
RHS ~ ~ r=:=J ~ ::::J ~ ~ ~ ==:1 ;:::==J ==:J ~ p
Removal of existing AC Pavement
LHS
100
~ ~ ~ ~ ;:::==J ~ ~ ~ ~ ~ ::::J ~ ~ ~ 150 Sq.m /day
RHS ;:::==J ~ ;:::==J ~ ~ ~ ~ ~ ~ t=:J ~ ~ ~ ~
Repair of foundation
LHS
100 ~ ~ ::::J ~ ::::J ~ ~ ~ ::::J t=:J ~ ~ ~ ::::J 150 Sq .m /day after removing existing AC Pavement
RHS ;:::==J ~ ::::J ~ ==:J t=:J ~ ~ ~ ~ ;:=:1 ;:=:1 ~ ==:J
Apply Prime Coat/Tack Coat
LHS ;:::==J ~ ~ ~ ~ ~ ~ ~ ;=:J ~ ;:::==J ~ ::::J
t=:J 150 Sq.m /day, apply prime coat after repairing
100
RHS ~ ~ ~ ~ ~ ~ ~ t=:J ~ t=:J ~ ~ ~ ==:J foundation and apply tack coat prior laying AC
Sealing/AC Patching
LHS ~ ~ ~ ~ ;=:::J ==:J ~ ;:::==J :=:J ~ ::::J
;:::==J ~ r=:=J
100 150 Sq.m /day or 18 Tons of AC/day
RHS ~ ~ ~ ~ ~ ~ ::::J t=:J ==:J c===J ~ ==:J ~ ::::J
Repairing on new construction Base Course
75 2nd Team
from PK101 +000 to 143+000 (BS)
I I I I I I I I

Estimated Quantities as per Inventory 14,858.65 Sq.m Requirement Progress= 39.475Km I 100 day= 0.395Km/day
Target repair by AC per day : 18 Tons 148.59 Sq.m/day = 0.40Km/Day (BS)
Duration 100 Day
Manpower Equipment Material
Site Engineer 1 Cutting machine 2 Base Course (M30)
Foreman 1 Tamping Rammer 2 Prime Coat (CSS-1)
Cutting Team Plate Compactor 1 Tack Coat (CRS-2)
Safety and traffic control 2 Air Compressor 1 Asphalt Concrete
Saw cutter 4 Tired Excavator 1
Repairing Team Tired Roller 1
Safety and traffic control 2 Macadam Roller 1
Operators, Drivers, Skilled and Unskilled
13 Wheel loader 1
workers
Patrol team 2 Dump Truck 2
Water Truck 1
Service Truck 2
Distributor 1
Prepared by Checked by Verified by

~
MUV Poleang
11--
MOM Moniroth NITHIS Thanawich
Design Engineer Road Project Manager Acting Team Leader