Field Density Test

This document appears to be a density test report from an infrastructure project in Zarima-May Tsebri-Shire road. It includes details on conducting density tests using the sand replacement method according to AASHTO T-191 standards. Test results were recorded for various layers including embankment, subbase, wearing course, capping layer and base course. The document contains tables for recording station locations, mass measurements, bulk density, moisture content, dry density, optimum moisture content and degree of compaction. It appears to have spaces for contractor, consultant and approval signatures with dates.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views2 pages

Field Density Test

This document appears to be a density test report from an infrastructure project in Zarima-May Tsebri-Shire road. It includes details on conducting density tests using the sand replacement method according to AASHTO T-191 standards. Test results were recorded for various layers including embankment, subbase, wearing course, capping layer and base course. The document contains tables for recording station locations, mass measurements, bulk density, moisture content, dry density, optimum moisture content and degree of compaction. It appears to have spaces for contractor, consultant and approval signatures with dates.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

SHELADIA In ZARIMA-MAY TSEBRI -SHIRE ROAD ERA own force

association PROJECT construction


with EIE &HITCON Contract no. 2 division

In place Density Determination


Sand Replacement Method AASHTO T - 191
Test Taken on: Embankment Subbase Wearing Course
Capping Layer Base Course Bedding/Backfill
Date Of Testing _________
Station from ________ To______ Unit weight of sand,γs ________
material Source ________ Sand in cone ________

Station
Layer
Mass of wet soil from hole, Mw[gm]
Mass of sand + jar before pouring, M1
Mass of sand + jar after pouring, M2
Mass of sand in cone, M3[gm]
Mass of sand in hole, M4=M1-M2-M3
Bulk density,γwet =Mw /M4*γs[gm/cc]
Moisture Content Determination
Container No
Mass of wet soil + Container[gm]
Mass of dry soil + Container[gm]
Mass of Container[gm]
Mass of Water[gm]
Mass of dry soil[gm]
Moisture Content, ω[%]
Dry Density,γdry=γwet* 100 /(100+ω)
Optimum Moisture Content[%]
Maximum Dry density[gm/cc]
Degree of Compaction[%]
Moisture Content[%]

Remark ______________________________________________________________

CONTRACTOR: CONSULTANT
TESTED BY CHAKED BY CHAKED BY APPROVED BY
DATE DATE DATE DATE
SIGN SIGN SIGN SIGN